0% found this document useful (0 votes)
6 views5 pages

Document 1

software project management

Uploaded by

ryashwanth997
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views5 pages

Document 1

software project management

Uploaded by

ryashwanth997
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

R20

Course Code: 20CS0544

SIDDHARTH INSTITUTE OF ENGINEERING & TECHNOLOGY:: PUTTUR


(AUTONOMOUS) Siddharth Nagar, Narayanavanam Road – 517583

QUESTION BANK (DESCRIPTIVE)

Subject with Code: Software Project Management (20CS0544) Course & Branch: B.Tech / CAD)
Year & Sem: IV/I Regulation: R20

UNIT –I
PROJECT EVALUATION AND PROJECT PLANNING

1 What is the importance of software project management and explain different [L2][CO1] [12M]
activities methodologies, setting objectives covered by software project
management?
2 Draw the architecture of SDLC explain it in detail? [L3][CO1] [12M]

3 Explain the following:


[L2][CO1] [6M]
a) Categorization of software projects
b) Setting objectives in software projects [L2][CO1] [6M]

4 Define management. Explain project management principles along with [L1][CO1] [12M]
management control life cycle in detail.
5 Describe Project Portfolio Management in brief with suitable examples. [L2][CO1] [12M]
6 State and explain the different types of cost benefit evaluation techniques with [L2][CO1] [12M]
suitable examples?
7 Outline the Evaluation of the Risk Process in detail. [L2][CO1] [12M]

8 Explain briefly strategic program management. [L2][CO1] [12M]

9 Illustrate Stepwise project planning with a neat diagram. [L2][CO1] [12M]

10 Explain the following terms:


a) Activities & methodologies [L2][CO1] [6M]
b) Management control [L2][CO1] [6M]
R20
Course Code: 20CS0544

UNIT –II PROJECT LIFE CYCLE AND EFFORT


ESTIMATION

1 List out the different Software process models? Explain with a neat diagram the [L2][CO2] [12M]
various stages involved in the waterfall model?
2 Demonstrate the following process models
a. The Spiral Model [L2][CO2] [6 M]
b. Rapid Application Development [L2][CO2] [6 M]
3 Explain various approaches involved in Agile Methods of process model. [L2][CO2] [12M]

4 Describe incremental delivery Plan model along with iterative process model? [L3][CO2] [12M]

5 What is software prototyping and explain it in detail with suitable examples? [L1][CO2] [12M]

6 Define SCRUM. Discuss with a neat diagram macro and micro processes that you [L1][CO2] [12M]
observed in managing iterative processes.
7 Describe various software effort and cost estimation techniques including examples. [L3][CO2] [12M]

8 Explain in brief bottom-up and top-down approaches in software effort estimation? [L2][CO2] [12M]

9 How the COSMIC full function point can be explore based on effort estimation [L1][CO2] [12M]
techniques?
10 Illustrate the following:
a. Staffing pattern with Norden’s work and Putnam’s works. [L2][CO2] [6M]
b. Basics of Software Estimation [L2][CO2] [6M]
R20
Course Code: 20CS0544

UNIT –III
ACTIVITY PLANNING AND RISK MANAGEMENT

1 List out the objectives of activity planning? Draw with a neat sketch of Sequencing [L1][CO3] [12M]
and scheduling.
2 Illustrate different activity based approaches involved in Activity Planning? [L2][CO3] [12M]

3 Define critical path method. Evaluate the critical path based on forward pass and [L1][CO3] [12M]
backward pass techniques?
4 Explain in brief a framework for dealing with risk. [L2][CO3] [12M]

5 Summarize the following:


a. Risk Identification [L2][CO3] [6M]
b. Risk Assessment [L2][CO3] [6M]

6 Describe Two Network Planning models in Activity Planning in brief. [L3][CO4] [12M]

7 Explain about the PERT technique. What are the advantages & disadvantages observed in [L2][CO4] [12M]
PERT Technique ?

8 Explain seven categories of the nature of resources. How can you identify resource [L2][CO4] [12M]
requirements in producing a project?

9 Explain various activities involved in creating critical paths or critical patterns? [L2][CO4] [12M]

10 Describe in detail about cost scheduling impact would be there on a project. [L3][CO4] [12M]
R20
Course Code: 20CS0544
UNIT –IV
PROJECT MANAGEMENT AND CONTROL

1 Explain Creation of Framework for Project Management and Control? [L2][CO5] [12M]

2 Demonstrate the Collection of Data Project Termination with suitable examples. [L2][CO5] [12M]

3 Explain the following terms in brief


i) Review [L2][CO5] [6M]
ii) Project Termination Review [L2][CO5] [6 M]
4 Illustrate the visualizing progress in Project Management and Control? [L2][CO5] [12M]

5 Explain Cost Monitoring in Project Control with simple examples? [L2][CO5] [12M]

6 Illustrate the Earned Value Analysis in project management control? [L2][CO5] [12M]

7 What is meant by project Monitoring explain it in detail? [L1][CO5] [12M]

8 Write short notes on


i) Project Tracking ii) [L2][CO5] [6M]
Change Control [L2][CO5] [6M]
9 Explain about Software Configuration Management Control in detail? [L2][CO5] [12M]

10 List out the various types of Contracts in contract management explain in detail. [L1][CO5] [12M]
Course Code:20CS0544 R20

UNIT –V
STAFFING IN SOFTWARE PROJECTS

1 Describe in detail about Managing People in Software Environment. [L3][CO6] [12M]

2 Explain the organizational Behavior of staffing in software projects? [L2][CO6] [12M]

3 List out the methods of Staff Selection among those methods which are best methods [L1][CO6] [12M]
explain it?

4 Explain in detail the Old Hackman Job Characteristic Model in software projects? [L2][CO6] [12M]

5 Discuss Ethical and Programmed concerns in briefly? [L6][CO6] [12M]

6 Write short notes on


i) Stress, Health and safety [L1][CO6] [6M]
ii) Motivations [L1][CO6] [6M]
7 What is the role of decision making in software projects and explain in detail? [L1][CO6] [12M]

8 Illustrate the following:


i) Team Structure ii) [L2][CO6] [6M]
Virtual Teams [L2][CO6] [6M]
9 Illustrate the Communication Genres with simple examples. [L2][CO6] [12M]

10 Define Communication Plan. Write down the results of communication plan in [L1][CO6] [12M]
projects.