7. Marke)ng has asked for a copy of the plan for your agile project, including the release
dates and the key features to be included in each release. What will you send them?
A. The teams product roadmap
B. A photo of the teams Kanban board
C. The first page of the product backlog
D. The product owner s requirements hierarchy
10. To manage a project effec)vely, work should be broken down into small pieces. Which of
the following does not describe how far to decompose the work?
A. Un)l it has a meaningful conclusion
B. Un)l it cannot be logically subdivided further
C. Un)l it can be done by one person
D. Un)l it can be realis)cally es)mated
13. On an agile soNware development project, the project manager asks business
stakeholders to create user stories, which will be used in the development and tes)ng of the
new applica)on. The main purpose of a user story is:
A. To document features or func)ons required by stakeholders
B. To create a record of issues encountered on the project
C. To perform what-if analysis
D. To communicate progress
26. It s Monday morning, and you just found out that the lead developer on your agile team
has broken his leg and will be out for six weeks. The team is in the middle of a two-week
itera)on that ends in four days, on Thursday. What should you do?
A. Explain that everyone will need to work over)me to complete their agreed-upon itera)on
goal.
B. Postpone all the upcoming itera)on deadlines and the next release date.
C. Ask the team how much of the itera)on plan can be completed by Thursday.
D. Ask HR to find a temporary replacement on a rush basis from another team.
Page 1 of 2
Project Schedule Management
8. The agile project team you are managing is responsible for developing one of the five different
components of a complex enterprise solution. Your PMO representative tells you she’s concerned
because your team is using a larger story point unit than the other four teams. What should you do?
A. Tell the PMO that this is the story point your team has chosen, and it doesn’t matter how large it
is relative to the other teams.
B. Ask your team lead to coordinate their story point metric with the other teams to ensure that the
different components interface smoothly.
C. Explain to the PMO that the size of each team’s story point doesn’t matter since this is just a
theoretical concept, not a real-world metric.
D. Show the PMO why your story point has to be larger, since your part of the solution has more
complex requirements than the others.
9. A new project manager is walking you through the schedule she has created for her project. She
asks you about the duration of a particular milestone, so she knows how to properly schedule it. What
will you tell her about a milestone’s duration?
15. A project manager is in the middle of executing a large construction project when he discovers the
time needed to complete the project is longer than the time available .What is the best thing to do?
23. Your agile project team is updating a mobile alert aggregator for social media updates and
trending news items. The team lead tells you that this week they plan to hold a planning poker
session for the user stories in the upcoming release. What does this tell you?
A. They are trying to find out how long it will take to complete the first iteration.
B. They are determining when this release will be ready to deploy.
C. They are estimating how long it will take to develop and test this release.
D. They are evaluating the relative size in story points of the stories for this release.
28. The project is calculated to be completed four days after the desired completion date. You do not
have access to additional resources. The project is low risk, the benefit-cost ratio is expected to be 1.6,
and the dependencies are preferential. Under these circumstances, what is the best thing to do?