Method Statement For Heavy Lifting
Method Statement For Heavy Lifting
REF # CFB-REG-
0020-13
HEAVY LIFTING
REF # CFB-REG-
0020-13
TABLE OF CONTENTS
1.0 SCOPE
2.0 DEFINITIONS
3.0 RESPONSABILITY
4.0 SPECIALIZED TOOLING/EQUIPMENT
5.0 SAFETY
6.0 INSTRUCTIONS
7.0 PRELIMINARY HEAVY LIFT LIST
8.0 ATTACHMENT
REF # CFB-REG-
0020-13
1.0 SCOPE
This Plan covers the requirements for the supervision of activities for lifting
including:
Review and preparation of lift data sheets
Rewiew of rigging equipment register
Requirements for and review of rigging studies and rigging sketches.
This procedure further lays out the format to be followed in the planning,
design and safe execution of the rigging program to meet the Project
requirements.
2.0 DEFINITIONS
For the purpose of this Procedure, the following terms are defined:
Lifting Data Sheet: Is a listing of all lifts to be made on the Project. This
list is primarlily a planning toll, CONTRACTOR shall
clearly demonstrate understanding of lifts to be
made and an understanding of the lift classification
for each of these lifts.
REF # CFB-REG-
0020-13
Routine: up to 20 tons
Medium lift: from 20 to 30 tons (Lifting sketch are required)
Heavy Lift: over 30 tons (Lifting study are required)
Critical lift: are those that meet any of the following criteria (Lifting
study are required):
All lift in which are utilized the tailing crane
Are located such that the load, crane boom or
rigging are near to electrical life lines
All prefabbricated flare stacks
3.0 RESPONSIBILITIES:
CONTRACTOR is responsible for ensuring that the preparation of all lifting studies,
lifting sketches, lifting equipment register, lift data sheet for all applicable lifts.
CONTRACTOR is further responsible to ensure that all lifting equipment and all
lifting tackle used in the Project have the correct test certification, and that all lifting
devices are NOT used beyond the safe limits imposed by the manufacturers
requirements and/or applicable standards.
REF # CFB-REG-
0020-13
5.0 SAFETY
5.2 Where required WORK PERMITS are obtained work can commence in
accordance with the specific measures itemized on the WORK PERMIT
5.4 A pre-work safety briefing shall be held just before any Heavy or
Critical Lift, whith all personnel involved with the lift to review the
requirements.
6.0 INSTRUCTION
6.1 Planning
Before installing the equipment, the job site shall be thoroughly
surveyed and installation carefully planned, taking into consideration
the following:
Lifting studies are required for all Heavy and Critical Lift as defined in
section 2.0 (DEFINITIONS), and as minimum, lifting drawings shall
include:
REF # CFB-REG-
0020-13
Plans, elevation and details in sufficient detail that the lift can be
executed safely
All crane, spreader bars, lift beams and rigging tackle are to be
shown
Prior the lifting CONTRACTOR shall check and confirm that no internals
ship loose items are stored inside the equipment that should be
removed prior to making the lift.
6.4.1 Rigging
All rigger shall be skilled
REF # CFB-REG-
0020-13
REF # CFB-REG-
0020-13
REF # CFB-REG-
0020-13
STATIC EQUIPMENT
Erectio
Equipme Qt SIZE per Item n
Equipment Description T
nt No. y (mm) Weight
/ Item
1412-T- 21.90
Amine Contactor 1 V 3.300 25.980 239,9
101 0
1411-V- 12.25
HP Slugcatcher 1 H 3.500 4.000 201,0
101 0
1411-V- 14.00
LP Slugcatcher 1 H 4.000 4.500 128,3
102 0
1417-V- 11.25
HP Flare Drum 1 H 4.500 5.000 107,0
103 0
1412-V-
Amine Outlet Separator 1 V 2.700 8.300 11.730 103,7
103
1412-V- 13.40
Rich Amine Flash Drum 1 H 4.600 5.100 99,8
201 0
1414-V-
Low Temperature Separator 1 V 2.900 4.100 7.080 91,2
202
1412-T- 29.90
Amine Regeneration Column 1 V 2.800 38.950 78,0
201 0
1412-V-
Amine Inlet Separator 1 V 2.800 4.000 6.950 74,3
101
1414-V- Turbo Expander Inlet
1 V 2.700 3.900 7.580 63,5
201 Separator
PACKAGES
QT WEIGH
TAG DESCRIPTION P TYPE DIMENSIONS
Y T
1414-V- 380 11.90
Molecular Sieve Vessels 3 V Vessel 8100 196,0
102 A/B/C 0 0
Dehydration Regenration
1414-H- Package 3.70 10.00 40.00
Gas Heater consists of 1 V 127,0
101 skid 0 0 0
Following
141A-H- Heating Medium Fired Heater Package 3.70 10.00
1 V 9.000 127,0
101 consists of following Skid 0 0
ROTATING EQUIPMENTS
QT WEIGHT
TAG DESCRIPTION
Y (TON)
BOOSTER
1460-Booster COMPRESSION
2,0 131.5
Compression (14601) -EPCSS
1b
REF # CFB-REG-
0020-13