Process Subcontracting
Process Subcontracting
1. Input checks
Check with EIM team if the inforecord exists in WPP
Any Key User of Service CL APO APC DP-SNP can request this.
No further approvals are required
Add the vendor to the list of existing vendors and save the variant. (Do not overwrite the
list of vendors in the variant!)
Then activate the integration model (transaction CFM3, variant APC_SNP_MD_VD)
3. Check if vendor exists in APO
Transaction /SAPAPO/LOC3
Enter four zeros preceding the R3 vendornr and check if it exists in APO:
In the “Addit.” Tab of the vendor master, enter the location type as “OEM”.
4. Create subcontracting location
Transaction /SAPAPO/LOC3
Enter RDC location + ‘_’ + vendor location, fill in location type 1050 and click create.
In the next screen, enter the location description. Fill in assigned plant as the RDC
location, and assigned vendor as the vendor location (don’t forget the leading zeros!).
Go to the next tab, fill in mandatory field Country. Leave the other fields blank and save.
Create MOT from RDC to subcontractor to supply finished products. No products should
be added.
Create MOT from subcontractor RDC to supply combi’s. No products should be added.
When this integration model is activated the combi’s will be added to the transportation
lane from subcontractor to RDC automatically.
7.
Add RDC to subcontracting PDS integration model
After this integration model has been activated it will automatically add the components
of the combi’s to the transportationlane from RDC to subcontractor in APO.
8. Check in APO if all masterdata is ciffed correctly