Starting and stopping of DC link
Starting and stopping of DC link
Starting and stopping of DC link
LINK
Energization and Deenergization of a Bridge:
⦿ Consider N series connected bridges at a converter station. If
one of the bridges is to be taken out of service, there is need
to not only block, but bypass the bridge.
⦿ This is because of the fact that just blocking the pulses does
not extinguish the current in the pair of valves that are left
conducting at the time of blocking.
⦿ The continued conduction of this pair injects AC voltage into
the link which can give rise to current and voltage oscillations
due to lightly damped oscillatory circuit in the link formed by
smoothing reactor and the line capacitance.
74
⦿ The transformer feeding the bridge is also subjected to DC
magnetization when DC current continues to flow through the
secondary windings.
⦿ The bypassing of the bridge can be done with the help of a
separate bypass valve or by activating a bypass pair in the
bridge (two valves in the same arm of the bridge).
⦿ The bypass valve was used with mercury arc valves where the
possibility of arc backs makes it impractical to use bypass
pairs. With thyristor valves, the use of bypass pair is the
practice as it saves the cost of an extra valve.
Suppose valves 2 & 3 are conducting when the blocking
command is given.
1 & 4 are selected as bypass pair.
Commutation from 2 to 4 is as usual, but commutation
from 3 to 5 is prevented.
In case of a predetermined bypass pair, the time lapse
between the blocking command and the current
transfer to bypass path can vary from 60° to 180°.
This time lapse can be reduced if the bypass pair
includes the lower valve number carrying current
at the instant of blocking.
In the inverter, there is no time lag involved in
the activation of the bypass pair.
The current from the bypass pair is shunted to a
switch S1.
With the aid of the isolators S, the bridge can
now be isolated.
ENERGIZATION OF A BRIDGE
Energization of a blocked bridge is done in two stages.
First the current is diverted from S1 to the bypass pair.
For this to happen, S1 must generate the required arc
voltage and to minimize this voltage, the ckt
inductance must be small.
In case the bypass pair fails to take over the current, S1
must close automatically if the current in that does not
become zero after a predetermined time interval.
AC breakers with sufficient arc voltage but reduced
breaking capacity are used as S1.
Secondly, the current is diverted from the bypass pair.
Rectifier: Instantaneous diversion of current
(neglecting Overlap)
Inverter: Transition requires some time lag
START-UP WITH LONG PULSE FIRING:
1. De block inverter at about γ = 90°
2. De block rectifier at α = 85° to establish low direct
current
3. Ramp up voltage by inverter control and the
current by rectifier control.
START-UP WITH SHORT PULSE FIRING:
• The current extinction during start-up is a problem
as valve with forward bias is not put into
conduction when the current in that falls
transiently below holding current.
START-UP OF A DC LINK
1. Open bypass switch at one terminal
2. Deblock that terminal and load to minimum
current in the rectifier mode
3. Open bypass switch at the second terminal and
commutate current to the bypass pair
4. Start the second terminal also in the rectifier mode
5. The inverter terminal is put into the inversion mode
6. Ramp up voltage and current.
The voltage is normally raised before raising the
current.
This permits the insulation of the line to be checked
before raising the power.
The ramping of power avoids stresses on the
generator shaft.
The switching surges in the line are also reduced.
The required power ramping rate depends on the
strength of the AC System.
Weaker AC system requires fast restoration of DC
power for maintaining transient stability.
But high ramping rates can result in large voltage
drops due to requirement of reactive power at the
converter.
Such voltage drops may lead to commutation failure
in inverter.
Permissible ramping rate: 2 to 10 pu per second for a
start-up time of 100 to 500 msec.
POWER CONTROL
The current order is obtained as the quantity derived from the
power order by dividing it by the direct voltage. The limits on the
current order are modified by the voltage dependent current
order limiter (VDCOL). The objective of VDCOL is to prevent
individual thyristors from carrying full current for long periods
during commutation failures. By providing both converter
stations with dividing circuits and transmitting the power order
from the leading station in which the power order is set to the
trailing station, the fastest response to the DC line voltage
changes is obtained without undue communication requirement.
POWER CONTROL
78
CONVERTER FAULTS
⦿ The current through arrestor does not have natural zero to aid
in resealing the arrester against sustained DC voltage
⦿ Voltage is buffered by huge lumped inductance (through
smoothing reactors and transformers)
⦿ Special LA are built for DC
OVER CURRENT PROTECTION IN HVDC