IT Spec 2 - Project Management (Time and Cost)
IT Spec 2 - Project Management (Time and Cost)
Required Estimated
Equipment/Tool Estimated
Activity Human Duration to
s Needed Material Cost
Resources Complete
Requirements 1 Project Manager, Meeting Room, None 2 weeks
Gathering 2 Business Collaboration Tools
Analysts
Design 1 UI/UX Designer, 1 Design software Stock Images 5 weeks
Graphic Designer (e.g., Adobe XD)
5. Estimating activity
durations involves estimating
the number of work periods
that are needed to complete
individual activities. Outputs
include activity duration
estimates and project
documents updates.
UI/UX Design 3 weeks November 26, 2024 December 17, 2024 Requirements
Gathering
Backend 4 weeks November 26, 2024 December 24, 2024 Requirements
Development Gathering
Frontend 4 weeks December 18, 2024 January 15, 2025 UI/UX Design
Development
Integration 2 weeks January 16, 2025 January 30, 2025 Backend and Frontend
Development
Direct Cost
Direct Cost
Indirect Cost