CSV SOP FINAL New
CSV SOP FINAL New
Deputy Manager,
Production Md. Saidur Rahman
Pellet Production
Deputy Manager,
Engineering Md. Hasibur Rahman
Engineering
Deputy Manager,
Engineering S. M. Sajjad Hossain
Engineering
Approved By
Quality Chowdhury Maroof Assistant Manager,
Assurance Ahmed Quality Assurance
Authorized By
Technical GM, Technical
Md. Barkat Ali
Operations Operations
The purpose of this procedure is to carry out Computerized System Validation (CSV)
activities. It defines the procedure and the essential requirements to maintain Computerized
System Validation.
2.0 SCOPE
The scope of this procedure applies to validation activities regarding at GxP critical
Computerized System (mentioned below) at
PLC based Automated Equipment
SCADA based Automated Equipment
Laboratory based Equipment / System
of Healthcare Chemicals Limited, API Industrial Park, BSCIC, Gazaria, Munshiganj,
Bangladesh. Computerized Systems that are not critical to product quality (though important for
the efficient and economic operation of the facility) will not be covered under this scope.
3.2 Definition:
URS (User Requirement Specification):
An URS is an approved statement that outlines the basic requirements for any system and
therefore URS contains a set of criteria or conditions that have to be met. The URS will be a
point of reference throughout the validation life cycle.
Design Qualification (DQ):
Documented verification that the proposed design of the facilities, equipment or systems is
documented as being suitable for the intended purpose.
Installation Qualification (IQ):
IQ is defined as "Establishing confidence that process equipment and ancillary systems are
capable of consistently operating within established limits and tolerances". It should ensure that
the equipment and ancillary systems are installed in accordance with approved design,
specifications and regulatory requirements.
Operational Qualification (OQ):
The documented verification that the facilities, systems and equipment, as installed or modified,
perform as intended throughout the anticipated operating ranges.
Performance Qualification (PQ):
The documented verification that the facilities, systems and equipment, as connected together,
can perform effectively and be replicated, based on the approved process method and product
specification.
Validation:
An action proving, in accordance with the principles of Good Manufacturing Practice, that any
procedure, process, equipment, material, activity or system actually leads to the expected
results. A documented program that provides a high degree of assurance that a specific process,
method or system will consistently produce a result meeting.
DS (Design Specification):
The document includes design details of the system. This documents links installation
qualification. DS is normally written by the Vendor and shall be reviewed and approved by
user.
Revalidation/Requalification:
Revalidation means documentation and execution of the complete set of validation activities
and deliverables that were initially performed.
Template:
A format to be used in the preparation of documents for general activities such as equipment
qualification, process validation etc. Templates contain outlines of the minimum requirements
that should be included in a protocol.
Validation Protocol:
A written plan stating how validation will be conducted and defining acceptance criteria. For
example, the protocol for a manufacturing process identifying processing equipment, critical
process parameters/operating ranges, product characteristics, sampling, test data to be collected,
the number of validation runs and acceptable test results.
Periodic Review:
Periodic reviews are performed to ensure that the Computerized system remains within both
company and regulatory compliance, and is fit for its intended use. The review evaluates the
compliance status of the entire system and plans any required corrective action activities.
Configuration Document (CD):
The Configuration Document (CD) should contain the technical documentation of the additional
(to the standard) configuration which is needed to meet the requirements of an implemented
company.
Revalidation:
Revalidation means documentation and execution of the complete set of validation activities
and deliverables that were initially performed.
4.0 RESPONSIBILITY
Activities Person / Department
Protocol & Report preparation Qualification & Validation
Review of the Protocol & Report Engineering, Qualification & Validation, IT
Approval of Protocol & Report Quality Assurance
5.0 ACCOUNTABILITY
Head of QA / Q&V / User Department
6.0 PRECAUTION
6.1 Only trained personnel are allowed to carry out the Computerized System Validation.
6.2 To keep computerized system validated throughout the lifecycle of that computerized
system.
7.0 PROCEDURE
7.1 Concept Phase:
7.1.1 Perform GxP Assessment for the Computerized system considering GxP Impact
Assessment Categorization of System Software and Hardware, Electronic Records and
Electronic Signature (ERES) Assessment.
7.1.2 Categorize the System Software and Hardware (as per Appendix-I) to establish the
validation approach with deliverables.
7.2 Project Phase
7.2.1 Determine the range of activities to validate a Computerized system by GAMP 5
software and hardware categorization, GxP impact, applicable electronic records and
electronic signatures requirements, and its risk-based lifecycle approach.
7.2.2 Perform the supplier assessment (where required) based on risk assessment through one
of the following:
a) Basic checklist
b) A postal questionnaire
c) An onsite audit
7.2.7 Prepare URS (if not available or sufficient data enough for CSV) which may include
Input/output Alarms/Interlocks / Messages, security & access control, access/privilege
level, data storage/ data archive/Data backup, HMI Parameters/Screens,
power/communication failure, operating environment Hardware configuration, Audit
Trail, Data security (no access to database directly for any operation)
7.2.8 Provide (by supplier) the following documents for complex Computerized systems:
a) FS / FRS
b) DS/ DQ
7.2.9 Prepare CD (Configuration document) for configured software where necessary
7.2.10 Perform code review after custom software where necessary
7.2.11 Create & Perform data migration plan where data has to migrate from legacy system to
new system
7.2.12 Prepare IQ protocol & Report for that Computerized system which will include
verification of the following (Not Limited):
a) Verification of System Identification
b) Verification of System Documentation
c) Verification of System Network Configuration / Hardware Components
d) Verification of System Software Configuration
e) Verification of Software backup certification / letter
f) Verification of Power Utility
g) Verification of Environmental Conditions
7.2.13 Prepare OQ protocol & Report for that Computerized system which will include
verification of the following (Not Limited):
a) Verification of System Start-up and Shutdown
7.3.4 Take decision for revalidation requirement and the extent of revalidation for
Computerized system based on evaluation (annual evaluation or change control
evaluation).
7.3.5 Prepare and execute simple verification protocol (proving that the software is configured
as before change) if same version of software is reinstalled.
7.3.6 Determine the competency and reliability of external validation agency.
7.3.7 Ensure vendor qualification where external validation agency is involved for CSV.
7.3.8 Ensure formal agreement between company and external validation agency that includes
clear statements of responsibilities.
7.3.9 Ensure backup and restoration of electronic data.
7.3.10 Ensure Disaster Management and recovery of Computerized system.
7.3.11 Data should be archived as required.
7.3.12 Periodic Review / Re-validation:
Computerized systems should be periodically reviewed to determine whether the system
remains in a validated state or whether there is a need for revalidation. Evaluate
Computerized system annually for Laboratory based Equipment / System (as per
Appendix-III) and PLC / SCADA based Equipment / System (Appendix-IV) for review /
Revalidation purpose. The frequency of review (Periodic Review) / revalidation depends
on system criticality, risk business impact and complexity.
Revalidation will be performed when significant changes are made. However final
decision should be based on risk assessment:
a) Major changes which also impact the structure
b) Major system faults
c) New hardware and/or software added to existing system
d) New functionality added to the existing Computerized system application
7.3.13 Raise Change Control (as per SOP: GEQA-010) for any changes/modifications to be
implemented in Computerized system.
7.4 Retirement Phase: