Oracle ERP Project Plan Sample
Oracle ERP Project Plan Sample
Page 1
ID Task Name Duration Start Finish Predecessors
33 Nominate Master Data Preparation Team 9 days Mon 01/10/18 Wed 10/10/18
34 Nominate Legacy Technical Team 9 days Mon 01/10/18 Wed 10/10/18
35 Planning Documents 15 days Mon 01/10/18 Wed 17/10/18
36 Project Plan 7 days Mon 01/10/18 Mon 08/10/18
37 Submit Project Plan 1 day Mon 01/10/18 Mon 01/10/18
38 Discussion on Project Plan 2 days Mon 01/10/18 Tue 02/10/18
39 Submission of updated Project Plan 1 day Thu 04/10/18 Thu 04/10/18
40 Sign off on Project Plan 1 day Sat 06/10/18 Sat 06/10/18
41 Data Conversion Strategy 15 days Mon 01/10/18 Wed 17/10/18
42 Submit Data Conversion Strategy 1 day Wed 10/10/18 Wed 10/10/18
43 Discussion on Data Conversion Strategy 2 days Thu 11/10/18 Fri 12/10/18
44 Submission of Revised Data Conversion Strategy Document 1 day Mon 15/10/18 Mon 15/10/18
45 Sign off on Data Conversion Strategy 1 day Tue 16/10/18 Tue 16/10/18
46 Master and Cut-Off Data Formats 7 days Fri 05/10/18 Fri 12/10/18
47 Master Data 3 days Fri 05/10/18 Mon 08/10/18
48 Item Master 3 days Fri 05/10/18 Mon 08/10/18
49 Job Data 3 days Fri 05/10/18 Mon 08/10/18
50 Positions 3 days Fri 05/10/18 Mon 08/10/18
51 Locators 3 days Fri 05/10/18 Mon 08/10/18
52 Sub inventory 3 days Fri 05/10/18 Mon 08/10/18
53 Account Aliases 3 days Fri 05/10/18 Mon 08/10/18
54 Purchasing Hierarchies and Approval Limits 3 days Fri 05/10/18 Mon 08/10/18
55 Import Overheads 3 days Fri 05/10/18 Mon 08/10/18
56 Employee Master (For Procurement Users Only) 3 days Fri 05/10/18 Mon 08/10/18
57 User Roles and Responsibility Matrix 3 days Fri 05/10/18 Mon 08/10/18
58 Cut-off Data 1 day Fri 05/10/18 Fri 05/10/18
59 1 day Fri 05/10/18 Fri 05/10/18
60 1 day Fri 05/10/18 Fri 05/10/18
61 Open Orders 1 day Fri 05/10/18 Fri 05/10/18
62 Open Inventory Balances and Per unit costs 1 day Fri 05/10/18 Fri 05/10/18
63 Open Purchase Requisitions 1 day Fri 05/10/18 Fri 05/10/18
64 Open Purchase Orders 1 day Fri 05/10/18 Fri 05/10/18
Page 2
ID Task Name Duration Start Finish Predecessors
Page 3
ID Task Name Duration Start Finish Predecessors
Page 4
ID Task Name Duration Start Finish Predecessors
129 Configuration as per signed off High level BPM Doct. 1 day Thu 06/12/18 Thu 06/12/18
130 Pre costing form changes 1 day Thu 06/12/18 Thu 06/12/18
131 Uploading of sample master data
132 One complete end to end cycle run
133 <New Task>
134 <New Task>
135 CRP 1 12 days Thu 10/01/19 Wed 23/01/19
136 Order Management 2 days Thu 10/01/19 Fri 11/01/19
137 Discrete Manufacturing 2 days Sat 12/01/19 Mon 14/01/19
138 Purchasing 2 days Tue 15/01/19 Wed 16/01/19
139 Inventory 2 days Thu 17/01/19 Fri 18/01/19
140 LCM 2 days Sat 19/01/19 Mon 21/01/19
141 Enterprise Asset Management 2 days Tue 22/01/19 Wed 23/01/19
142 CRP 1 issues identification and agreement on resolution 2 days Thu 24/01/19 Fri 25/01/19
143 <New Task>
144 <New Task>
145 Refine and Validation 20 days Fri 25/01/19 Sat 16/02/19
146 Configure gaps identified during Prototype 1
147 <New Task>
148 <New Task>
149 <New Task>
150 <New Task>
151 <New Task>
152 CRP 2 12 days Sun 17/02/19 Fri 01/03/19
153 Order Management 2 days Sun 17/02/19 Mon 18/02/19
154 Discrete Manufacturing 2 days Tue 19/02/19 Wed 20/02/19
155 Purchasing 2 days Thu 21/02/19 Fri 22/02/19
156 Inventory 2 days Sat 23/02/19 Mon 25/02/19
157 LCM 2 days Tue 26/02/19 Wed 27/02/19
158 Enterprise Asset Management 2 days Thu 28/02/19 Fri 01/03/19
159 Finalize User Role and Responsibility Matrix
160 <New Task>
Page 5
ID Task Name Duration Start Finish Predecessors
Page 6
Responsibility
Page 7
Responsibility
Page 8
Responsibility
Page 9
Responsibility
Page 10
Responsibility
Page 11
Responsibility
Ananta Power Users,PwC Project Manager,PwC Functional Leads,Ananta Legacy Technical Team,Ananta End Users,Ananta Project Team
Ananta Power Users,PwC Project Manager,PwC Functional Leads,Ananta Legacy Technical Team,Ananta End Users,Ananta Project Team
Ananta Process Owners,PwC Project Manager,PwC Functional Leads,Ananta End Users,Ananta Project Team
Page 12