Baseline ghant chart fro 33 story building
Baseline ghant chart fro 33 story building
Baseline ghant chart fro 33 story building
mpp
ID Task Name Duration Start Finish Predecessors % Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
Complete June July August SeptemberOctober November December January February March April May June July August
-2 -1 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960
1 Bangsar Trade Centre Remainin Works- 363 days Tue 18-06-24 Sun 15-06-25 4%
Block F
2 MILESTONE COMPLETION DATES 186 days Tue 10-09-24 Sat 15-03-25 0%
3 MILESTONE 1 Roof Topping Up 0 days Sat 14-12-24 Sat 14-12-24 214 0% MILESTONE 1 Roof Topping Up 14-12
4 MILESTONE 2 Water Tightness 0 days Wed 05-02-25 Wed 05-02-25 362 0% MILESTONE 2 Water Tightness 05-02
5 MILESTONE 3 Mock-Up Unit 0 days Tue 10-09-24 Tue 10-09-24 236 0% MILESTONE 3 Mock-Up Unit 10-09
6 MILESTONE 4 Power Energization 0 days Sat 15-03-25 Sat 15-03-25 384 0% MILESTONE 4 Power Energization 15-03
9 Structural Drawing 6 days Sat 22-06-24 Thu 27-06-24 8FS-2 days 100% Structural Drawing
10 M&E Drawing 6 days Fri 28-06-24 Wed 03-07-24 9 100% M&E Drawing
13 Tower crane permit renewal 40 days Mon 01-07-24 Fri 09-08-24 95% Tower crane permit renewal
16 Site Cleaning 7 days Mon 15-07-24 Sun 21-07-24 15,12 100% Site Cleaning
17 Site mobilization 10 days Mon 15-07-24 Wed 24-07-24 12 100% Site mobilization
18 Surveyor As Built and Verticality 45 days Mon 15-07-24 Wed 28-08-24 12 80% Surveyor As Built and Verticality Check
Check
19 Re-inspect tower crane & 4 days Sat 10-08-24 Tue 13-08-24 13 0% Re-inspect tower crane & Passenger hoist
Passenger hoist
20 Structural Work 143 days Thu 25-07-24 Sat 14-12-24 4%
21 Dismantle of formwork 7 days Thu 25-07-24 Wed 31-07-24 17 80% Dismantle of formwork
22 Demolition works 7 days Mon 12-08-24 Sun 18-08-24 21,19FS-2 days 50% Demolition works
27 Rebar Installation 2 days Sat 24-08-24 Sun 25-08-24 26FF+1 day 0% Rebar Installation
31 Formwork & Concrete 1 day Wed 28-08-24 Wed 28-08-24 30 0% Formwork & Concrete
39 Formwork closing L22 1 day Wed 04-09-24 Wed 04-09-24 38 0% Formwork closing L22
45 Rebar Installation 2 days Mon 02-09-24 Tue 03-09-24 44FF 0% Rebar Installation
Page 1
BTC Work Program Baseline Rev.06.mpp
ID Task Name Duration Start Finish Predecessors % Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
Complete June July August SeptemberOctober November December January February March April May June July August
-2 -1 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960
47 Column 3 days Tue 03-09-24 Thu 05-09-24 0%
48 Rebar 2 days Tue 03-09-24 Wed 04-09-24 45SS+1 day 0% Rebar
49 Formwork & Concrete 1 day Thu 05-09-24 Thu 05-09-24 48 0% Formwork & Concrete
53 Rebar & Formwork Closing 2 days Sat 07-09-24 Sun 08-09-24 52 0% Rebar & Formwork Closing
59 Rebar Installation 2 days Thu 12-09-24 Fri 13-09-24 58FF 0% Rebar Installation
63 Formwork & Concrete 1 day Sun 15-09-24 Sun 15-09-24 62 0% Formwork & Concrete
67 Rebar & Formwork Closing 2 days Tue 17-09-24 Wed 18-09-24 66 0% Rebar & Formwork Closing
73 Rebar installation 2 days Sat 21-09-24 Sun 22-09-24 72FF 0% Rebar installation
77 Formwork & Concrete 1 day Tue 24-09-24 Tue 24-09-24 76 0% Formwork & Concrete
81 Rebar & Formwork Closing 2 days Thu 26-09-24 Fri 27-09-24 80 0% Rebar & Formwork Closing
87 Rebar Installation 2 days Mon 30-09-24 Tue 01-10-24 86FF 0% Rebar Installation
91 Formwork & Concrete 1 day Thu 03-10-24 Thu 03-10-24 90 0% Formwork & Concrete
Page 2
BTC Work Program Baseline Rev.06.mpp
ID Task Name Duration Start Finish Predecessors % Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
Complete June July August SeptemberOctober November December January February March April May June July August
-2 -1 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960
95 Rebar & Formwork Closing 2 days Sat 05-10-24 Sun 06-10-24 94 0% Rebar & Formwork Closing
100 Formwork installation 3 days Mon 07-10-24 Wed 09-10-24 99 0% Formwork installation
101 Rebar Installation 2 days Tue 08-10-24 Wed 09-10-24 100FF 0% Rebar Installation
102 Concrete slab 1 day Thu 10-10-24 Thu 10-10-24 101 0% Concrete slab
105 Formwork & Concrete 1 day Fri 11-10-24 Fri 11-10-24 104 0% Formwork & Concrete
109 Rebar & Formwork Closing 2 days Sun 13-10-24 Mon 14-10-24 108 0% Rebar & Formwork Closing
114 Formwork installation 3 days Wed 16-10-24 Fri 18-10-24 113 0% Formwork installation
115 Rebar Installation 2 days Thu 17-10-24 Fri 18-10-24 114FF 0% Rebar Installation
116 Concrete slab 1 day Sat 19-10-24 Sat 19-10-24 115 0% Concrete slab
119 Formwork & Concrete 1 day Sun 20-10-24 Sun 20-10-24 118 0% Formwork & Concrete
123 Rebar & Formwork Closing 2 days Tue 22-10-24 Wed 23-10-24 122 0% Rebar & Formwork Closing
128 Formwork installation 3 days Thu 24-10-24 Sat 26-10-24 127 0% Formwork installation
129 Rebar Installation 2 days Fri 25-10-24 Sat 26-10-24 128FF 0% Rebar Installation
130 Concrete slab 1 day Sun 27-10-24 Sun 27-10-24 129 0% Concrete slab
133 Formwork & Concrete 1 day Mon 28-10-24 Mon 28-10-24 132 0% Formwork & Concrete
137 Rebar & Formwork Closing 2 days Wed 30-10-24 Thu 31-10-24 136 0% Rebar & Formwork Closing
142 Formwork installation 3 days Fri 01-11-24 Sun 03-11-24 141 0% Formwork installation
Page 3
BTC Work Program Baseline Rev.06.mpp
ID Task Name Duration Start Finish Predecessors % Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
Complete June July August SeptemberOctober November December January February March April May June July August
-2 -1 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960
143 Rebar Installation 2 days Sat 02-11-24 Sun 03-11-24 142FF 0% Rebar Installation
144 Concrete slab 1 day Mon 04-11-24 Mon 04-11-24 143 0% Concrete slab
147 Formwork & Concrete 1 day Tue 05-11-24 Tue 05-11-24 146 0% Formwork & Concrete
151 Rebar & Formwork Closing 2 days Thu 07-11-24 Fri 08-11-24 150 0% Rebar & Formwork Closing
156 Formwork installation 3 days Sat 09-11-24 Mon 11-11-24 155 0% Formwork installation
157 Rebar Installation 2 days Sun 10-11-24 Mon 11-11-24 156FF 0% Rebar Installation
158 Concrete slab 1 day Tue 12-11-24 Tue 12-11-24 157 0% Concrete slab
161 Formwork & Concrete 1 day Wed 13-11-24 Wed 13-11-24 160 0% Formwork & Concrete
165 Rebar & Formwork Closing 2 days Fri 15-11-24 Sat 16-11-24 164 0% Rebar & Formwork Closing
170 Formwork installation 3 days Sun 17-11-24 Tue 19-11-24 169 0% Formwork installation
171 Rebar Installation 2 days Mon 18-11-24 Tue 19-11-24 170FF 0% Rebar Installation
172 Concrete slab 1 day Wed 20-11-24 Wed 20-11-24 171 0% Concrete slab
175 Formwork & Concrete 1 day Thu 21-11-24 Thu 21-11-24 174 0% Formwork & Concrete
179 Rebar & Formwork Closing 2 days Sat 23-11-24 Sun 24-11-24 178 0% Rebar & Formwork Closing
184 Formwork installation 3 days Mon 25-11-24 Wed 27-11-24 183 0% Formwork installation
185 Rebar Installation 2 days Tue 26-11-24 Wed 27-11-24 184FF 0% Rebar Installation
186 Concrete slab 1 day Thu 28-11-24 Thu 28-11-24 185 0% Concrete slab
189 Formwork & Concrete 1 day Fri 29-11-24 Fri 29-11-24 188 0% Formwork & Concrete
193 Rebar & Formwork Closing 2 days Sun 01-12-24 Mon 02-12-24 192 0% Rebar & Formwork Closing
198 Formwork installation 3 days Tue 03-12-24 Thu 05-12-24 197 0% Formwork installation
199 Rebar Installation 2 days Wed 04-12-24 Thu 05-12-24 198FF 0% Rebar Installation
200 Concrete slab 1 day Fri 06-12-24 Fri 06-12-24 199 0% Concrete slab
203 Formwork & Concrete 1 day Sat 07-12-24 Sat 07-12-24 202 0% Formwork & Concrete
204 Lift Shaft Roof Level 5 days Sat 07-12-24 Wed 11-12-24 0%
205 Scaffolding installation 1 day Sat 07-12-24 Sat 07-12-24 200 0% Scaffolding installation
207 Rebar & Formwork Closing 2 days Mon 09-12-24 Tue 10-12-24 206 0% Rebar & Formwork Closing
212 Formwork installation 3 days Wed 11-12-24 Fri 13-12-24 211 0% Formwork installation
213 Rebar Installation 2 days Thu 12-12-24 Fri 13-12-24 212FF 0% Rebar Installation
214 Concrete slab 1 day Sat 14-12-24 Sat 14-12-24 213 0% Concrete slab
215 MILESTONE 1 COMPLETED 0 days Sat 14-12-24 Sat 14-12-24 214 0% MILESTONE 1 COMPLETED 14-12
220 Façade work 4 days Sun 18-08-24 Wed 21-08-24 219 0% Façade work
221 Ponding Test 2 days Thu 22-08-24 Fri 23-08-24 220 0% Ponding Test
225 Column/Drop/Ceiling Panel 7 days Sat 24-08-24 Fri 30-08-24 224 0% Column/Drop/Ceiling Panel Skim
Skim
226 Plastering 7 days Sat 24-08-24 Fri 30-08-24 224 0% Plastering
227 Painting work 7 days Tue 27-08-24 Mon 02-09-24 226SS+3 days 0% Painting work
230 Plaster Ceiling 7 days Tue 27-08-24 Mon 02-09-24 226SS+3 days 0% Plaster Ceiling
231 Floor & Wall Tiles 7 days Sat 31-08-24 Fri 06-09-24 230SS+4 days,221 0% Floor & Wall Tiles
232 Floor Finishes 7 days Sat 31-08-24 Fri 06-09-24 230SS+4 days,221 0% Floor Finishes
233 Door & Window installation 2 days Sat 07-09-24 Sun 08-09-24 232 0% Door & Window installation
234 Sanitary Fittings & Wares 3 days Sat 07-09-24 Mon 09-09-24 232 0% Sanitary Fittings & Wares
235 Vanity Counter Top 2 days Sat 07-09-24 Sun 08-09-24 232 0% Vanity Counter Top
Page 5
BTC Work Program Baseline Rev.06.mpp
ID Task Name Duration Start Finish Predecessors % Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
Complete June July August SeptemberOctober November December January February March April May June July August
-2 -1 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960
236 Ironmongeries 2 days Mon 09-09-24 Tue 10-09-24 233 0% Ironmongeries
237 MILESTONE 3 COMPLETED 0 days Tue 10-09-24 Tue 10-09-24 236 0% MILESTONE 3 COMPLETED 10-09
241 Façade work 4 days Sun 01-09-24 Wed 04-09-24 240 0% Façade work
242 Ponding Test 2 days Thu 05-09-24 Fri 06-09-24 241 0% Ponding Test
243 Screeding 7 days Thu 22-08-24 Wed 28-08-24 239SS+7 days 0% Screeding
244 Column/Drop/Ceiling Panel 7 days Thu 29-08-24 Wed 04-09-24 243 0% Column/Drop/Ceiling Panel Skim
Skim
245 Plastering 7 days Thu 29-08-24 Wed 04-09-24 243 0% Plastering
246 Painting work 7 days Sun 01-09-24 Sat 07-09-24 245SS+3 days 0% Painting work
247 Plaster Ceiling 7 days Sun 01-09-24 Sat 07-09-24 245SS+3 days 0% Plaster Ceiling
248 Floor & Wall Tiles 7 days Sat 07-09-24 Fri 13-09-24 247SS+4 days,242 0% Floor & Wall Tiles
252 Façade work 4 days Sun 15-09-24 Wed 18-09-24 251 0% Façade work
253 Ponding Test 2 days Thu 19-09-24 Fri 20-09-24 252 0% Ponding Test
254 Screeding 7 days Thu 05-09-24 Wed 11-09-24 250SS+7 days 0% Screeding
255 Column/Drop/Ceiling Panel 7 days Thu 12-09-24 Wed 18-09-24 254 0% Column/Drop/Ceiling Panel Skim
Skim
256 Plastering 7 days Thu 12-09-24 Wed 18-09-24 254 0% Plastering
257 Painting work 7 days Sun 15-09-24 Sat 21-09-24 256SS+3 days 0% Painting work
258 Plaster Ceiling 7 days Sun 15-09-24 Sat 21-09-24 256SS+3 days 0% Plaster Ceiling
259 Floor & Wall Tiles 7 days Sat 21-09-24 Fri 27-09-24 258SS+4 days,253 0% Floor & Wall Tiles
263 Façade work 4 days Sun 29-09-24 Wed 02-10-24 262 0% Façade work
264 Ponding Test 2 days Thu 03-10-24 Fri 04-10-24 263 0% Ponding Test
265 Screeding 7 days Thu 19-09-24 Wed 25-09-24 261SS+7 days 0% Screeding
266 Column/Drop/Ceiling Panel 7 days Thu 26-09-24 Wed 02-10-24 265 0% Column/Drop/Ceiling Panel Skim
Skim
267 Plastering 7 days Thu 26-09-24 Wed 02-10-24 265 0% Plastering
268 Painting work 7 days Sun 29-09-24 Sat 05-10-24 267SS+3 days 0% Painting work
269 Plaster Ceiling 7 days Sun 29-09-24 Sat 05-10-24 267SS+3 days 0% Plaster Ceiling
270 Floor & Wall Tiles 7 days Sat 05-10-24 Fri 11-10-24 269SS+4 days,264 0% Floor & Wall Tiles
274 Façade work 4 days Sun 13-10-24 Wed 16-10-24 273 0% Façade work
275 Ponding Test 2 days Thu 17-10-24 Fri 18-10-24 274 0% Ponding Test
276 Screeding 7 days Thu 03-10-24 Wed 09-10-24 272SS+7 days 0% Screeding
277 Column/Drop/Ceiling Panel 7 days Thu 10-10-24 Wed 16-10-24 276 0% Column/Drop/Ceiling Panel Skim
Skim
Page 6
BTC Work Program Baseline Rev.06.mpp
ID Task Name Duration Start Finish Predecessors % Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
Complete June July August SeptemberOctober November December January February March April May June July August
-2 -1 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960
278 Plastering 7 days Thu 10-10-24 Wed 16-10-24 276 0% Plastering
279 Painting work 7 days Sun 13-10-24 Sat 19-10-24 278SS+3 days 0% Painting work
280 Plaster Ceiling 7 days Sun 13-10-24 Sat 19-10-24 278SS+3 days 0% Plaster Ceiling
281 Floor & Wall Tiles 7 days Sat 19-10-24 Fri 25-10-24 280SS+4 days,275 0% Floor & Wall Tiles
285 Façade work 4 days Sun 27-10-24 Wed 30-10-24 284 0% Façade work
286 Ponding Test 2 days Thu 31-10-24 Fri 01-11-24 285 0% Ponding Test
287 Screeding 7 days Thu 17-10-24 Wed 23-10-24 283SS+7 days 0% Screeding
288 Column/Drop/Ceiling Panel 7 days Thu 24-10-24 Wed 30-10-24 287 0% Column/Drop/Ceiling Panel Skim
Skim
289 Plastering 7 days Thu 24-10-24 Wed 30-10-24 287 0% Plastering
290 Painting work 7 days Sun 27-10-24 Sat 02-11-24 289SS+3 days 0% Painting work
291 Plaster Ceiling 7 days Sun 27-10-24 Sat 02-11-24 289SS+3 days 0% Plaster Ceiling
292 Floor & Wall Tiles 7 days Sat 02-11-24 Fri 08-11-24 291SS+4 days,286 0% Floor & Wall Tiles
296 Façade work 4 days Sun 10-11-24 Wed 13-11-24 295 0% Façade work
297 Ponding Test 2 days Thu 14-11-24 Fri 15-11-24 296 0% Ponding Test
298 Screeding 7 days Thu 31-10-24 Wed 06-11-24 294SS+7 days 0% Screeding
299 Column/Drop/Ceiling Panel 7 days Thu 07-11-24 Wed 13-11-24 298 0% Column/Drop/Ceiling Panel Skim
Skim
300 Plastering 7 days Thu 07-11-24 Wed 13-11-24 298 0% Plastering
301 Painting work 7 days Sun 10-11-24 Sat 16-11-24 300SS+3 days 0% Painting work
302 Plaster Ceiling 7 days Sun 10-11-24 Sat 16-11-24 300SS+3 days 0% Plaster Ceiling
303 Floor & Wall Tiles 7 days Sat 16-11-24 Fri 22-11-24 297,302SS+4 days 0% Floor & Wall Tiles
307 Façade work 4 days Sun 24-11-24 Wed 27-11-24 306 0% Façade work
308 Ponding Test 2 days Thu 28-11-24 Fri 29-11-24 307 0% Ponding Test
309 Screeding 7 days Thu 14-11-24 Wed 20-11-24 305SS+7 days 0% Screeding
310 Column/Drop/Ceiling Panel 7 days Thu 21-11-24 Wed 27-11-24 309 0% Column/Drop/Ceiling Panel Skim
Skim
311 Plastering 7 days Thu 21-11-24 Wed 27-11-24 309 0% Plastering
312 Painting work 7 days Sun 24-11-24 Sat 30-11-24 311SS+3 days 0% Painting work
313 Plaster Ceiling 7 days Sun 24-11-24 Sat 30-11-24 311SS+3 days 0% Plaster Ceiling
314 Floor & Wall Tiles 7 days Sat 30-11-24 Fri 06-12-24 313SS+4 days,308 0% Floor & Wall Tiles
318 Façade work 4 days Sun 08-12-24 Wed 11-12-24 317 0% Façade work
319 Ponding Test 2 days Thu 12-12-24 Fri 13-12-24 318 0% Ponding Test
320 Screeding 7 days Thu 28-11-24 Wed 04-12-24 316SS+7 days 0% Screeding
Page 7
BTC Work Program Baseline Rev.06.mpp
ID Task Name Duration Start Finish Predecessors % Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
Complete June July August SeptemberOctober November December January February March April May June July August
-2 -1 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960
321 Column/Drop/Ceiling Panel 7 days Thu 05-12-24 Wed 11-12-24 320 0% Column/Drop/Ceiling Panel Skim
Skim
322 Plastering 7 days Thu 05-12-24 Wed 11-12-24 320 0% Plastering
323 Painting work 7 days Sun 08-12-24 Sat 14-12-24 322SS+3 days 0% Painting work
324 Plaster Ceiling 7 days Sun 08-12-24 Sat 14-12-24 322SS+3 days 0% Plaster Ceiling
325 Floor & Wall Tiles 7 days Sat 14-12-24 Fri 20-12-24 324SS+4 days,319 0% Floor & Wall Tiles
329 Façade work 4 days Sun 22-12-24 Wed 25-12-24 328 0% Façade work
330 Ponding Test 2 days Thu 26-12-24 Fri 27-12-24 329 0% Ponding Test
331 Screeding 7 days Thu 12-12-24 Wed 18-12-24 327SS+7 days 0% Screeding
332 Column/Drop/Ceiling Panel 7 days Thu 19-12-24 Wed 25-12-24 331 0% Column/Drop/Ceiling Panel Skim
Skim
333 Plastering 7 days Thu 19-12-24 Wed 25-12-24 331 0% Plastering
334 Painting work 7 days Sun 22-12-24 Sat 28-12-24 333SS+3 days 0% Painting work
335 Plaster Ceiling 7 days Sun 22-12-24 Sat 28-12-24 333SS+3 days 0% Plaster Ceiling
336 Floor & Wall Tiles 7 days Sat 28-12-24 Fri 03-01-25 335SS+4 days,330 0% Floor & Wall Tiles
340 Façade work 4 days Sun 05-01-25 Wed 08-01-25 339 0% Façade work
341 Ponding Test 2 days Thu 09-01-25 Fri 10-01-25 340 0% Ponding Test
342 Screeding 7 days Thu 26-12-24 Wed 01-01-25 338SS+7 days 0% Screeding
343 Column/Drop/Ceiling Panel 7 days Thu 02-01-25 Wed 08-01-25 342 0% Column/Drop/Ceiling Panel Skim
Skim
344 Plastering 7 days Thu 02-01-25 Wed 08-01-25 342 0% Plastering
345 Painting work 7 days Sun 05-01-25 Sat 11-01-25 344SS+3 days 0% Painting work
346 Plaster Ceiling 7 days Sun 05-01-25 Sat 11-01-25 344SS+3 days 0% Plaster Ceiling
347 Floor & Wall Tiles 7 days Sat 11-01-25 Fri 17-01-25 346SS+4 days,341 0% Floor & Wall Tiles
351 Façade work 4 days Sun 19-01-25 Wed 22-01-25 350 0% Façade work
352 Ponding Test 2 days Thu 23-01-25 Fri 24-01-25 351 0% Ponding Test
353 Screeding 7 days Thu 09-01-25 Wed 15-01-25 349SS+7 days 0% Screeding
354 Column/Drop/Ceiling Panel 7 days Thu 16-01-25 Wed 22-01-25 353 0% Column/Drop/Ceiling Panel Skim
Skim
355 Plastering 7 days Thu 16-01-25 Wed 22-01-25 353 0% Plastering
356 Painting work 7 days Sun 19-01-25 Sat 25-01-25 355SS+3 days 0% Painting work
357 Plaster Ceiling 7 days Sun 19-01-25 Sat 25-01-25 355SS+3 days 0% Plaster Ceiling
358 Floor & Wall Tiles 7 days Sat 25-01-25 Fri 31-01-25 357SS+4 days,352 0% Floor & Wall Tiles
362 Façade work 4 days Sun 02-02-25 Wed 05-02-25 361 0% Façade work
Page 8
BTC Work Program Baseline Rev.06.mpp
ID Task Name Duration Start Finish Predecessors % Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
Complete June July August SeptemberOctober November December January February March April May June July August
-2 -1 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960
363 MILESTONE 2 COMPLETED 0 days Wed 05-02-25 Wed 05-02-25 362 0% MILESTONE 2 COMPLETED 05-02
364 Ponding Test 2 days Thu 06-02-25 Fri 07-02-25 362 0% Ponding Test
365 Screeding 7 days Thu 23-01-25 Wed 29-01-25 360SS+7 days 0% Screeding
366 Column/Drop/Ceiling Panel 7 days Thu 30-01-25 Wed 05-02-25 365 0% Column/Drop/Ceiling Panel Skim
Skim
367 Plastering 7 days Thu 30-01-25 Wed 05-02-25 365 0% Plastering
368 Painting work 7 days Sun 02-02-25 Sat 08-02-25 367SS+3 days 0% Painting work
369 Plaster Ceiling 7 days Sun 02-02-25 Sat 08-02-25 367SS+3 days 0% Plaster Ceiling
370 Floor & Wall Tiles 7 days Sat 08-02-25 Fri 14-02-25 369SS+4 days,364 0% Floor & Wall Tiles
373 Door & Window installation 60 days Wed 01-01-25 Sat 01-03-25 372FF 0% Door & Window installation
374 Glass frame & glass installation 60 days Wed 01-01-25 Sat 01-03-25 373SS 0% Glass frame & glass installation
375 Sanitary Fittings & Wares 60 days Wed 01-01-25 Sat 01-03-25 373SS 0% Sanitary Fittings & Wares
376 Toilet Cubicle 60 days Wed 01-01-25 Sat 01-03-25 373SS 0% Toilet Cubicle
377 Glazing Work 60 days Wed 01-01-25 Sat 01-03-25 373SS 0% Glazing Work
378 Vanity Counter Top 45 days Thu 16-01-25 Sat 01-03-25 373SS+15 days 0% Vanity Counter Top
380 Staircase Railing 30 days Fri 31-01-25 Sat 01-03-25 374FS-30 days 0% Staircase Railing
381 Signanage Work 30 days Thu 16-01-25 Fri 14-02-25 373SS+15 days 0% Signanage Work
382 Floor Finishes 45 days Thu 16-01-25 Sat 01-03-25 373SS+15 days 0% Floor Finishes
386 Local Authority Approval 32 days Thu 16-01-25 Sun 16-02-25 385 0% Local Authority Approval
388 Testing & Commisioning 20 days Mon 24-02-25 Sat 15-03-25 387 0% Testing & Commisioning
389 MILESTONE 4 COMPLETED 0 days Sat 15-03-25 Sat 15-03-25 384 0% MILESTONE 4 COMPLETED 15-03
405 2nd Fix (Cable Tray & Trunking) 160 days Thu 29-08-24 Tue 04-02-25 0%
406 L15 3 days Thu 29-08-24 Sat 31-08-24 239 0% L15
Page 9
BTC Work Program Baseline Rev.06.mpp
ID Task Name Duration Start Finish Predecessors % Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
Complete June July August SeptemberOctober November December January February March April May June July August
-2 -1 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960
409 L18 3 days Sun 15-09-24 Tue 17-09-24 408 0% L18
429 3rd Fix (Fitting Installation) 161 days Sun 08-09-24 Sat 15-02-25 0%
430 L15 7 days Sun 08-09-24 Sat 14-09-24 246 0% L15
453 Testing & Commisioning 20 days Sun 16-02-25 Fri 07-03-25 452,516,644 0% Testing & Commisioning
454 Cold & Hot Water 195 days Sun 25-08-24 Fri 07-03-25 0%
518 Sanitary & Plumbings 195 days Sun 25-08-24 Fri 07-03-25 0%
582 Fire Protection Services 195 days Sun 25-08-24 Fri 07-03-25 0%
Page 10
BTC Work Program Baseline Rev.06.mpp
ID Task Name Duration Start Finish Predecessors % Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
Complete June July August SeptemberOctober November December January February March April May June July August
-2 -1 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930313233343536373839404142434445464748495051525354555657585960
646 Lift Installation 130 days Thu 24-10-24 Sun 02-03-25 0%
647 L09 8 days Thu 24-10-24 Thu 31-10-24 0%
648 Hoistway Preparation 2 days Thu 24-10-24 Fri 25-10-24 127 0% Hoistway Preparation
649 Guilde rail installation 2 days Sat 26-10-24 Sun 27-10-24 648 0% Guilde rail installation
650 Landing Door 2 days Mon 28-10-24 Tue 29-10-24 649 0% Landing Door
651 Electrical & Control System 2 days Wed 30-10-24 Thu 31-10-24 650 0% Electrical & Control System
652 L10 8 days Wed 30-10-24 Wed 06-11-24 649SS+4 days 0% L10
653 L11 8 days Sun 03-11-24 Sun 10-11-24 652SS+4 days 0% L11
654 L12 8 days Thu 07-11-24 Thu 14-11-24 653SS+4 days 0% L12
655 L13 8 days Mon 11-11-24 Mon 18-11-24 654SS+4 days 0% L13
656 L14 8 days Thu 14-11-24 Thu 21-11-24 655SS+3 days 0% L14
657 L15 8 days Sun 17-11-24 Sun 24-11-24 656SS+3 days 0% L15
658 L16 8 days Wed 20-11-24 Wed 27-11-24 657SS+3 days 0% L16
659 L17 8 days Sat 23-11-24 Sat 30-11-24 658SS+3 days 0% L17
660 L18 8 days Tue 26-11-24 Tue 03-12-24 659SS+3 days 0% L18
661 L19 8 days Fri 29-11-24 Fri 06-12-24 660SS+3 days 0% L19
662 L20 8 days Tue 03-12-24 Tue 10-12-24 661SS+4 days 0% L20
663 L21 8 days Sat 07-12-24 Sat 14-12-24 662SS+4 days 0% L21
664 L22 8 days Wed 11-12-24 Wed 18-12-24 663SS+4 days 0% L22
665 L23 8 days Sun 15-12-24 Sun 22-12-24 664SS+4 days 0% L23
666 L24 8 days Thu 19-12-24 Thu 26-12-24 665SS+4 days 0% L24
667 L25 8 days Mon 23-12-24 Mon 30-12-24 666SS+4 days 0% L25
668 L26 8 days Fri 27-12-24 Fri 03-01-25 667SS+4 days 0% L26
669 L27 8 days Tue 31-12-24 Tue 07-01-25 668SS+4 days 0% L27
670 L28 8 days Sat 04-01-25 Sat 11-01-25 669SS+4 days 0% L28
671 L29 8 days Wed 08-01-25 Wed 15-01-25 670SS+4 days 0% L29
672 L30 8 days Sun 12-01-25 Sun 19-01-25 671SS+4 days 0% L30
673 L31 8 days Thu 16-01-25 Thu 23-01-25 672SS+4 days 0% L31
674 L32 8 days Mon 20-01-25 Mon 27-01-25 673SS+4 days 0% L32
675 L33 8 days Fri 24-01-25 Fri 31-01-25 674SS+4 days 0% L33
676 Lift Car Installation 15 days Wed 11-12-24 Wed 25-12-24 662 0% Lift Car Installation
677 Counterweight Rail Installation 15 days Sat 21-12-24 Sat 04-01-25 676SS+10 days 0% Counterweight Rail Installation
678 Testing & Commisioning 30 days Sat 01-02-25 Sun 02-03-25 675,677 0% Testing & Commisioning
681 Final Touch Up 60 days Mon 17-03-25 Thu 15-05-25 680 0% Final Touch Up
682 BOMBA Inspection 7 days Fri 16-05-25 Thu 22-05-25 678,681 0% BOMBA Inspection
683 JKKP inspection 7 days Fri 16-05-25 Thu 22-05-25 678,681 0% JKKP inspection
684 CCC Issuance 20 days Tue 20-05-25 Sun 08-06-25 681SS+10 days,683SS+4 days
0% CCC Issuance
685 CPC issuance 7 days Mon 09-06-25 Sun 15-06-25 684 0% CPC issuance