Edo State Budget
Edo State Budget
1
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
BUDGET SUMMARY
1 RECURRENT REVENUE
(a) I nternal 23,924,449,152 21% 18,500,000,000 24% 13,875,000,000 10,686,515,511.20 77%
(b) Statutory Allocation 56,000,000,000 49% 45,687,277,124 59% 34,265,457,843 22,414,561,211.43 65%
(c) 13% Oil Mineral Deriv ation Fund 15,000,000,000 13% 4,000,000,000 5% 3,000,000,000 7,167,176,938.03 239%
(d) Excess Crude Oil Reserv e 5,000,000,000 4% - - 9,392,049,830.76
(e) Budget Augmentation 2,500,000,000 2% - -
(f) Multilateral Debt Refund 4,000,000,000 3% - - 2,960,241,251.00
(g) Value Added Tax 9,000,000,000 8% 9,175,285,160 12% 6,881,463,870 5,320,495,852.56 77%
Total: Recurrent Revenue (a) 115,424,449,152 100% 77,362,562,284 100% 58,021,921,713 57,941,040,594.98 100%
2 RECURRENT EXPENDITURE
(a) Personnel Cost 28,681,426,604 44% 21,046,374,304 38% 15,784,780,728 15,507,592,312.54 98%
(b) Ov erhead Costs 17,806,878,000 28% 13,561,828,000 25% 10,171,371,000 #REF! #REF!
46,488,304,604 34,608,202,304 25,956,151,728 #REF!
(c) C.R.F.C. 18,060,491,938 28% 20,218,123,788 37% 15,163,592,841 19,983,868,078.99 132%
(i) Sub-Total Recurrent Expenditure (b) 64,548,796,542 43% 54,826,326,093 42% 41,119,744,570 #REF!
3 CAPITAL RECEIPTS
(i) Transfer from Consolidated Rev enue Fund 50,875,652,610 77% 22,536,236,191 54% 16,902,177,143 #REF! #REF!
(ii) Capital Expenditure 86,417,406,045 57% 77,066,112,008 58% 57,799,584,006 30,652,186,086.51 53%
2
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
REVENUE DETAILS
3
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
FY2012 PROJECTED REVENUE PROFILE
4
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SUB-HEAD DETAILS OF REVENUE APPROVED ESTIMATES APPROVED ESTIMATES APPROVED ESTIMATES ACTUAL REVENUES
2012 2011 2010 JAN-SEPT 2011
-1 -2 -3 -3 -4 -6
N N N N
401 TAXES
5
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SUB-HEAD DETAILS OF REVENUE APPROVED ESTIMATES APPROVED ESTIMATES APPROVED ESTIMATES ACTUAL REVENUES
2012 2011 2010 JAN-SEPT 2011
-1 -2 -3 -3 -4 -6
N N N N
402 FINES AND FEES
MINISTRY OF FINANCE (BOARD OF INTERNAL REVENUE)
1 (a) Pools Betting Licensing Fees 5,000,000 4,000,000 3,000,000
(b) Pools Agents Registration/Renewal 1,500,000 1,000,000 700,000
2 Gamming Machine Licensing Fees/Lottery Application and Licensing - -
Fees 0
3 Stickers Fees 15,000,000 15,000,000 15,000,000
MINISTRY OF FINANCE: OFFICE OF THE ACCOUNTANT-GENERAL
4 Tender Fees
AUDIT DEPARTMENT (OFFICE OF THE AUDITOR-GENERAL (STATE)
5 Audit Fees 4,000,000 3,600,000 3,000,000
OFFICE OF THE AUDITOR-GENERAL (LOCAL GOVERNMENT)
6 Audit Fees 120,000,000 120,000,000 60,000,000
MINISTRY OF ENVIRONMENT
7 Log Control Fees (Forestry) 16,000,000 16,000,000 15,600,000
8 Special Development Levies 50,000 50,000 0
9 Forestry Fines 20,000,000 20,000,000 18,500,000
9a Monitoring Committee on Forestry 8,500,000 8,500,000 4,800,000
MINISTRY OF AGRICUCTURE AND NATURAL RESOURCES
10 Produce Inspection/Control Posts fees/
Grading and Acess fees. 25,000,000 25,000,000 20,000,000
11 College of Agriculture School/Tuition Fees 2,000,000 1,500,000 1,500,000
12 Meat Inspection Fees 9,600,000 9,600,000 7,200,000
13 Road Re-instatement Fees 50,000,000 50,000,000
(a) Contractors Registration and Fees 50,000,000 50,000,000
(b) Tenders/Other Fees 45,000,000 45,000,000
(c ) Staff Training Centre
6
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SUB-HEAD DETAILS OF REVENUE APPROVED ESTIMATES APPROVED ESTIMATES APPROVED ESTIMATES ACTUAL REVENUES
2012 2011 2010 JAN-SEPT 2011
-1 -2 -3 -3 -4 -6
N N N N
14 MINISTRY OF TRANSPORT
a. Fire Precaution/Inspection Fees 4,300,000 4,265,750 41,300,000
(i) Petrol Stations
(ii) Hotels/Guest Houses
(ii) Industrial Enterprises
(iv) Cinema Theatres/Video House
(V) Regulation of activities along major roads/high w ays to improve
ambient
Registration/Renew al of Service providers
(vi) Road obstruction fees
15 MINISTRY OF ENERGY AND WATER RESOURCES
i Edo Urban Water Board Fees/Charges
ii Registration 500,000
iii Tenders 6,000,000
iv Renew al of Registration 500,000
v Table Water levy 10,000,000
vi Urban Water Board:
vii Water Charges 38,880,000
viii Car Wash 1,512,000
ix Revenue from Borehole 1,650,000
x Water Tanker Services 2,520,000
xi Hiring of crane/Welding machines -
xii Hiring of Rigs -
xiii Miscellaneous 738,000
xiv New Connection 4,800,000
16 MINISTRY OF FINANCE
(BOARD OF INTERNAL REVENUE)
17 Road Traffic Examination Fees 40,000,000 30,000,000 30,000,000
17a Sales of Bids 1,000,000
18(i) Stamp Duties and Penalties 50,000,000 50,000,000 50,000,000
(ii) Searching Fees 50,000,000
(iii) Vehicle Registration 50,000,000 50,000,000 100,000,000
(iv) Change of Ow nership 50,000,000
(v) Duplicate General Motor Receipt (GMR) 50,000,000
19 MINISTRY OF WOMEN AFFAIRS AND SOCIAL DEVELOPMENT
(i) Registration Fees of NGOs and Day-Care-Centres 400,000 400,000 300,000
(ii) Administrative Fees for Adoption and Women Development Markets. 1,500,000 1,500,000
1,500,000
(iii) FSP School fees Account - - 3,500,000
7
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SUB-HEAD DETAILS OF REVENUE APPROVED ESTIMATES APPROVED ESTIMATES APPROVED ESTIMATES ACTUAL REVENUES
2012 2011 2010 JAN-SEPT 2011
-1 -2 -3 -3 -4 -6
N N N N
14 MINISTRY OF TRANSPORT
a. Fire Precaution/Inspection Fees 4,300,000 4,265,750 41,300,000
(i) Petrol Stations
(ii) Hotels/Guest Houses
(ii) Industrial Enterprises
(iv) Cinema Theatres/Video House
(V) Regulation of activities along major roads/high w ays to improve
ambient
HEAD 402; FINE AND FEES (CONT’D)
JUDICIARY
20 Court Fees
(i) High Courts 115,000,000 110,000,000 90,000,000
(ii) Customary Courts 50,000,000 50,000,000 35,000,000
21 Court Fines
(i) High Courts 10,000,000 10,000,000 10,000,000
(ii) Customary Courts 3,000,000 3,000,000 3,000,000
MINISTRY OF LANDS, SURVEY AND
HOUSING
22 Deeds (lands, Instruments Registration Law ) 180,000,000
22a Registration fees 200,000,000 200,000,000 169,600,000
23 Certificate of Occupancy (Land Use Decree 1979: Application Fees) 54,000,000 8,000,000 8,000,000
24 Application Fees/Special levy on C of O
25 Tow n Planning/Assessment Fees 480,000,000 950,000,000 841,291,976
25a Administration Charges 12,000,000 100,000,000 168,000,000
MINISTRY OF HEALTH
26 Examination/Enrolment Fees 8,000,000 3,500,000 3,500,000
27 Patient Medicine and Vendors Licensing Fees 5,000,000 1,000,000 1,000,000
27a Essential Drugs Project 7,000,000
402/ FINES AND FEES (CONT’D)
MINISTRY OF HEALTH
28 Hospital Fees/Charges 60,000,000 75,000,000 60,000,000
29 Domiciliary Midw ifery Services 100,000 50,000 50,000
30 School Fees 7,000,000 3,500,000 3,500,000
31 Private Health Institution/Traditional Medicine Registration Renew al Fees 15,000,000 10,000,000
5,000,000
31a Vector Control/Fumigation of Premises 500,000 240,000 120,000
31B Food Vendor 6,000,000
32 Yellow Card Fees 2,000,000 500,000 500,000
33 Eye Test Fees
33a Boarding Fees 500,000 240,000 120,000
MINISTRY OF INFORMATION AND ORIENTATION
34 Public Address Equipment Fees/Cinema 288,000 240,000 200,000
35 Edo Broadcasting Service: Fees/Charges 120,432,000 100,360,000 7,500,000
36 Bendel New s Paper Company 21,308,976 17,757,480 14,797,900
36a Government Printing Press others 6,000,000
37 Registration/Renew al Fees for Community Development Associations 864,000 720,000 600,000
38 Fees from Centre for Community Development Education, Benin City 2,880,000 2,400,000 2,000,000
39 Fees from Government Day Care Centres 288,000 240,000 200,000
MINISTRY OF YOUTHS & SPORTS
402/40 Registration/Renew al Fees for Social Clubs and Voluntary Organisation, 27,000,000
including collection of arrears of previous years
41 Registration of Churches etc. 30,000,000 30,000,000 30,000,000
41A. Licensing of churches for celebration of marriages 2,524,545
41b Renew al of Churches Lincense 1,388,500
41c Fees from Rural Development Training Centres (RTDC), Benin City and
41d Rural Extension Services Training Centre (RDSTC), Irrua
41f Samuel Ogbemudia/Etete Indoor Sport Complex 5,000,000 3,000,000 3,000,000
MINISTRY OF ART, CULTURE AND TOURISM
42 Musical/Cultural Bands (Gr oupsA, B, and C) 3,000,000 3,000,000 3,000,000
43 Fees from Oba Akenzua Cultural Centres 7,200,000 7,200,000
44 Edo Arts Council Dance Troupe 5,000,000 5,000,000
8
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SUB-HEAD DETAILS OF REVENUE APPROVED ESTIMATES APPROVED ESTIMATES APPROVED ESTIMATES ACTUAL REVENUES
2012 2011 2010 JAN-SEPT 2011
-1 -2 -3 -3 -4 -6
N N N N
MINISTRY OF COMMERCE AND INDUSTRY
45 Registration of Business Premises 75,000,000 75,000,000 12,000,000
46 Registration and Renew al of Cooperative Societies 30,000,000 30,000,000 4,000,000
46a Audit fees 3,000,000 3,000,000 2,000,000
46b Arbitration fees 2,000,000 2,000,000 60,000
46c Inspection of Registration Register 2,000,000 2,000,000 50,000
46d Earning from Edo Hotel 1,500,000
46e Earning from Wood w orks 1,500,000
46f Consumer Protection Fee 5,000,000
MINISTRY OF EDUCATION
47 Entrance/Certificate Examination
(i) Primary School Leaving Certificate/Entrance in J.S.S. 30,000,000 30,000,000 20,000,000
(ii) Junior Secondary School Certificate Examination (JSS) fees 49,000,000 40,000,000 30,000,000
(iii) Compulsory Examination for Officers in Admin Class and GEC 303,000 200,000 200,000
(iv) Teachers’ Grade II Examination - - 0
(v) Book Review 200,000 200,000 200,000
(vi) Tender Fees 40,000,000 6,000,000 2,000,000
402 FINES AND FEES (CONT’D)
MINISTRY OF EDUCATION
48 Registration and School Fees
(i) Primary
(ii) Secondary 150,000,000 85,000,000 100,000,000
(iii) Teachers’ Training
(iv) Technical 1,500,000
(v) College of Education Ekiadolor
(vi) Ambrose Alli University, Ekpoma 70,000,000
(vii) Institute of Continuing Education, Benin City 4,608,500
(viii) Michael Imoudu Institute of Physical Education, Afuze 15,512,500
(ix) Edo State Institute of Technology and Management, Usen.
(x) College of Education, Igueben 2,037,500
49 Private Educational Institutions: Application, Registration/Renew al Fees 100,000,000 70,000,000
50,000,000
49b Use of public school facility 5,000,000
Ethiope Publishing Corporation
50 Attestation Fees
51 Schools Fees from the Staff Training Centre 500,000 50,000 50,000
Examinations Fees:
(i) Limited Competitive Examination for entry into the Sub-Clerical Grade 60,000 60,000 60,000
(ii) Confirmation/Promotion Test for Clerical, Stores and Archives Staff 110,000 110,000 110,000
(iii) Edo State Secretarial Examination 130,000 130,000 130,000
(iv) Certificate in Public Administration Programme - - 0
9
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SUB-HEAD DETAILS OF REVENUE APPROVED ESTIMATES APPROVED ESTIMATES APPROVED ESTIMATES ACTUAL REVENUES
2012 2011 2010 JAN-SEPT 2011
-1 -2 -3 -3 -4 -6
N N N N
402/ FINES AND FEES (CONT’D)
GOVERNOR’S OFFICE (GOVERNMENT HOUSE AND PROTOCOL)
52 Fees from Guest Houses
MINISTRY OF JUSTICE
53 Contract Agreement Documentation Fees 90,000,000 80,000,000 80,000,000
54 J.P. Certificate Fees 10,000,000 10,000,000 10,000,000
MINISTRY OF ENVIRONMENT AND PUBLIC UTILITIES
10
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SUB-HEAD DETAILS OF REVENUE APPROVED ESTIMATES APPROVED ESTIMATES APPROVED ESTIMATES ACTUAL REVENUES
2012 2011 2010 JAN-SEPT 2011
-1 -2 -3 -3 -4 -6
N N N N
403 LICENCES
MINISTRY OF FINANCE (BOARD OF INTERNAL REVENUE)
1 Licences
(i) Motor Vehicle Licenses 260,500,000 258,162,845 252,162,846
(ii) Driver’s Licence 83,900,000 84,054,282 84,054,282
(iii) Dealer’s Licence 8,000,000 6,724,343 6,724,343
(iv) Carrier Permit 4,000,000 3,362,171 3,362,171
(v) Hackney Permit 25,000,000 25,216,285 25,216,285
(vi) Learner’s Permit 5,000,000 8,405,428 8,405,428
FORESTRY DEPARTMENT (M.E.&.S.M)
2 Games and Saw-millers Licence 53,794,740 53,794,740 53,794,740
MINISTRY OF LANDS AND SURVEYS (LAND AND SURVEYS OFFICE)
11
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SUB-HEAD DETAILS OF REVENUE APPROVED ESTIMATES APPROVED ESTIMATES APPROVED ESTIMATES ACTUAL REVENUES
2012 2011 2010 JAN-SEPT 2011
-1 -2 -3 -3 -4 -6
N N N N
404 EARNING AND SALES
MINISTRY OF AGRICULTURE AND NATURAL RESOURCES
1 Veterinary Clinic Treatment 500,000 84,000 84,000
2 Registration/Renew al of Private Veterinary Clinics 100,000 - 0
3.. Agricultural Products (Sales) and Lease of Plantation 600,000 - 0
3a Urhonigbe Rubber Estate 1,500,000 1,200,000 1,200,000
4 Sales of Fish Products/Water Pumps - 300,000 300,000
5 Registration/Licensing of Fishermen Fish Crafts, Cold Rooms etc 1,090,000 1,000,000 1,000,000
6 Bush Clearing/Tractor Hiring Service 4,000,000 2,701,559 2,701,559
6(i) Lease of Pig house at ADP, Oko 400,000 200,000 200,000
7 Sale of fertilizers (Commission) 500,000 - 0
8 Sale of Rubber Products - - 0
MINISTRY OF ARTS, CULTURE AND TOURISM
9 Ogba Zoological Garden - - 0
MINISTRY OF FINANCE:BOARD OF INTERNAL REVENUE)
10 Sales of Vehicle Registration Books 5,000,000 5,000,000 5,000,000
11 Sale of Driver’s Badges 600,000 600,000 600,000
12 Sales of Vehicle Number Plates 160,000,000 100,000,000 100,000,000
13 Sales of Certificate of Ow nership 1,000,000 1,000,000 1,000,000
(i) Sales of bumper reflector
(ii) Number Plate Replacement 1,000,000 400,000 400,000
(iii) 3% Development levy 2,034,000,000
(OFFICE OF THE ACCOUNTANT-GENERAL)
14 Jobs done for Non-Governmental bodies - - 0
404/ EARNING AND SALES (CONT’D)
MINISTRY OF HEALTH
15 Boarding/Lodging Fees for Students in Health Institutions 120,000 120,000 120,000
MINISTRY OF LANDS, SURVEY AND HOUSING
16 Sales of Maps and Prints 3,600,000 10,000,000 10,000,000
17 Surveys 7,200,000 12,000,000 12,000,000
MINISTRY OF COMMERCE AND INDUSTRY
18 Auchi Textile Training Centre - - 0
19 Earnings from Wood Unit 240,000 240,000 240,000
20a. Edo Cement Company (Privatisation proceeds) - - 0
20b. Bendel Brew ery (Sales of Shares) - - 0
20c. Deduction Refund - - 0
20d Micro-Credit Loan Refund - - 0
20e. Micro-Credit: Earnings from loans (interest) 200,000 200,000 200,000
12
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SUB-HEAD DETAILS OF REVENUE APPROVED ESTIMATES APPROVED ESTIMATES APPROVED ESTIMATES ACTUAL REVENUES
2012 2011 2010 JAN-SEPT 2011
-1 -2 -3 -3 -4 -6
N N N N
MINISTRY OF WORKS
21 Hiring of Government Plant/Equipment
22 Sales from Wood Workshop 1,200,000 1,300,000
22a Road Reinstatement 90,000,000
22b Contractors Registtration/Renew al 80,000,000
22c Tender 60,000,000
23 Sales of Boarded vehicles, Plant and stores 4,840,000 2,500,000
23a Staff Training School 3,000,000
23b Hiring of Mechanic Workshop 960,000
MINISTRY OF TRANSPORT
24 Earning from Edo Transport Service 10,000,000 10,000,000 10,000,000
25 Earnings from Edo Transport Courier Service 10,000,000 10,000,000 10,000,000
26 Earnings from Passengers Welfare Scheme (PWS) 4,000,000 3,800,000 3,800,000
27 Earning from Edo City Transport Service 10,000,000 10,000,000 10,000,000
28 Demurrage Charges on accidented vehicles - - -
29 Earnings from Motor Cycle Regulation - - -
29a Road Transport Operation 15,000,000 10,800,000 10,800,000
30 Earnings from Sale of Bumper Reflectors 2,500,000 2,500,000 2,500,000
31 Earnings from VEST - - -
31a Private Park Ow ner's colour Code 5,000,000 2,000,000 2,000,000
32a Tender Fees 2,000,000 2,000,000 2,000,000
32b Cooperate Parking Permit 20,000,000
MINISTRY OF INFORMATION AND ORIENTATION
33 Printing Jobs (Sales of Printing materials)
34 Sales of Photographs
GOVERNOR’S OFFICE (EDO STATE LIAISON OFFICE, LAGOS /ABUJA)
35 Guest House, Lagos Office
35a Attestation for Certification of State of origin 4,200,000
13
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SUB-HEAD DETAILS OF REVENUE APPROVED ESTIMATES APPROVED ESTIMATES APPROVED ESTIMATES ACTUAL REVENUES
2012 2011 2010 JAN-SEPT 2011
-1 -2 -3 -3 -4 -6
N N N N
405 RENT ON GOVERNMENT PROPERTY
MINISTRY OF LANDS, SURVEYS AND HOUSING
14
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SUB-HEAD DETAILS OF REVENUE APPROVED ESTIMATES APPROVED ESTIMATES APPROVED ESTIMATES ACTUAL REVENUES
2012 2011 2010 JAN-SEPT 2011
-1 -2 -3 -3 -4 -6
N N N N
406/ INTERESTS, REPAYMENT AND DIVIDENTS INTEREST REPAYMENT (CONT’D)
MINISTRY OF FINANCE, (INVESTMENT AND LOANS) DIVIDENDS FROM
COMPANIES
16 Bendel Insurance Company Plc
17 Edo Pharmaceutical Limited
18 Rubber Estates of Nig. Plc. 100,000,000 2,160,000 8,045,336
19 U.A.C. of Nigeria Plc. 5,000,000 4,644,000 36,569,710
20 A.G. Leventis and Company Plc. 35,000 183,000 182,849
21 Pedrocchi Company Ltd. - - 0
22 Royal Exchange Assurance (Nig) Plc. 400,000 438,000 438,837
23 K. Chellanran and Sons (Nig) Plc. 26,000 20,000 73,139
24 Guinness (Nig) Plc. 5,000,000 10,900,000 10,970,913
25 Nigeria Bottling Company Plc 500,000 511,000 511,976
26 Nigeria Brew eries 2,500,000 5,000,000 10,970,913
27 American International Insurance Company Plc. 200,000 365,697 365,697
28 Agbede-Warrake Farm Ltd. - - 0
29 Unity Bank 1,000,000 292,000 292,558
30 Bendel Cement Company Ltd. - - 0
31 Nigeria Construction and Water Resources Dev. Ltd. - - 0
32 R.T. Briscoe (Nig) Ltd. 30,000 292,000 292,558
33 Bendel Brew ery Ltd. - - 0
34 Ikpoba Dam Hotel Ltd. - - 0
35 Nigerian Agencies (Nig) Ltd. - - 0
- - 0
406/ MINISTRY OF FINANCE (INVESTMENT AND LOANS) DIVIDENDS FROM
COMPANIES (CONT’D)
36 Staco 10,000 10,000 182,849
37 Transcorp 10,000 10,000 365,697
38 Nigerian Agencies (Int) Ltd. London Ltd. - - 0
39 Edo Hotel Board and Tourism Company Ltd. - - 21,942
40 Bendel Feeds and Flour Mill Ltd. - - 365,697
41 Okomu Oil Palm Company Ltd. 2,000,000 5,000,000 5,485,456
42 Paterson Zochonis Industry Plc. 20,000 36,000 36,570
43 Beta Glass Plc. 10,000 10,000 18,285
44 Oando Nig. Plc. 25,000 25,000 731,394
45 D.N. Meyer Plc. 10,000 10,000 10,971
46 Dunlop (Nig) Industry Plc. 10,000 10,000 36,570
47 Cadbury (Nig) Plc. 10,000 10,000 36,570
48 Mobil Oil (Nig) Plc. 10,000 10,000 36,570
49 Director’s Fees 10,000 10,000 182,849
50 Wema Bank 10,000 10,000 73,139
51 C & I leasing 60,000 60,000 182,849
52 Cornest 50,000 50,000 73,139
53 Equity Asur 50,000 50,000 182,849
54 Eterna oil 50,000 50,000 73,139
55 First City Monument Bank 50,000 50,000 182,849
56 Fidelity Bank 70,000 50,000 182,849
57 Fidson 70,000 100,000 237,703
58 Japaul Oil 50,000 50,000 109,709
59 Fin Bank Plc 100,000 300,000 365,697 0
60 Okomu Hotel Resort Ltd 50,000 100,000 182,849 0
62 Platinum 50,000 50,000 182,849 0
15
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SUB-HEAD DETAILS OF REVENUE APPROVED ESTIMATES APPROVED ESTIMATES APPROVED ESTIMATES ACTUAL REVENUES
2012 2011 2010 JAN-SEPT 2011
-1 -2 -3 -3 -4 -6
N N N N
408 MISCELLANEOUS:
MINISTRY OF FINANCE (OFFICE OF THE ACCOUNTANT-GENERAL
1 Deposit Lapsed -
2 Voluntary Contribution by individual/Organisations to revamp the - - -
economy
3 Over-payment Refunded - - -
4 Balance from Stabilization Account - - -
5 Sundries - - -
MINISTRY OF FINANCE (BOARD OF INTERNAL REVENUE/ - - 0
OFFICE OF THE ACCOUNTANT GENERAL - - 0
6 Special General Levy - - 0
(a) 3% Contractors Development Levy 53,289,044 53,289,044 53,289,044
(b) General Development Levy (Adult) N100 - - 0
(c ) Interest on Fixed Deposits - - -
MINISTRY OF JUSTICES - - -
7 7% Administrative Charges on Estates - - 0.00
16
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SUB-HEAD DETAILS OF REVENUE APPROVED ESTIMATES APPROVED ESTIMATES APPROVED ESTIMATES ACTUAL REVENUES
2012 2011 2010 JAN-SEPT 2011
-1 -2 -3 -3 -4 -6
N N N N
MINISTRY OF ENVIRONMENT - - 0.00
8 Charges for Miscellaneous Environmental Abuses 1,776,301 1,776,301 1,776,301
9 Reclamation Levy - - -
10 Environmental Levy/Pollution Management Levy 1,776,301 1,776,301 1,776,301
11 Forestry Trust Fund 21,316 21,316 21,316
12 Special Regeneration Levy 1,243,411 1,243,411 1,243,411
13 Tender fees 639,469 639,469 639,469
MINISTRY OF EDUCATION
13 Infrastructural Development Levy 85,000,000 85,000,000 35,526,029
RURAL ELECTRICITY BOARD - - -
14 Registration of Contractors - - -
15 Tender Fees - - -
Ministry of Women Affairs and Social - - -
Development - - -
16 Miscellaneous (Tender Fees) - - -
TOTAL: HEAD 408 143,745,842 143,745,842 94,271,871 0.00
17
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
RECURRENT EXPENDITURE
18
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
RECURRENT EXPENDITURE PROFILE
2012 APPROVED PROVISION 2011 APPROVED PROVISION INCLUDING SUPPLEMENTARY ACTUAL EXPENDITURE AS AT SEPT 2011
HEAD MINISTRY/DEPARTMENT/
N N N N N N N N N
GOVERNOR’S OFFICE
412A Department of Government House & Protocol 80,000,000.00 2,000,000,000.00 2,080,000,000.00 62,856,493.43 1,615,000,000.00 1,677,856,493.43 47,554,094.51 1,387,879,609.79 1,435,433,704.30
(i) PPP Office - 50,000,000.00 50,000,000.00 - 30,000,000.00 30,000,000.00 -
(ii) Special Duties 10,000,000.00 10,000,000.00
412B Office of the Governor - 1,500,000,000.00 1,500,000,000.00 1,200,000,000.00 1,200,000,000.00 1,188,410,171.68 1,188,410,171.68
(i) Rapid Response Agency 1,500,000,000.00 50,000,000.00 1,550,000,000.00 692,923,749.02 50,000,000.00 742,923,749.02 404,436,459.14 27,821,314.00 432,257,773.14
(ii) Office of the Chief of Staff - 18,000,000.00 18,000,000.00 - 18,000,000.00 18,000,000.00 11,141,000.00 11,141,000.00
(iii) Public Affairs Office - 100,000,000.00 100,000,000.00 - 30,000,000.00 30,000,000.00 28,848,370.00 28,848,370.00
(iv) State Security Vote - 4,500,000,000.00 4,500,000,000.00 - 4,000,000,000.00 4,000,000,000.00 3,086,241,500.00 3,086,241,500.00
(v) Governor’s Lodge, Abuja - 20,000,000.00 20,000,000.00 - 20,000,000.00 20,000,000.00 - -
(vi) Due Process Office - 10,000,000.00 10,000,000.00 - 10,000,000.00 10,000,000.00 2,384,750.00 2,384,750.00
(vii) Directorate of ICT 338,400,000.00 100,000,000.00 438,400,000.00 124,025,461.42 100,000,000.00 224,025,461.42 143,400,489.14 63,707,793.50 207,108,282.64
(viii) Fiscal Governance/Project Monitoring Unit - 20,000,000.00 20,000,000.00 - 30,000,000.00 30,000,000.00 8,977,800.00 8,977,800.00
- 1,500,000,000.00
(x) Cummunity Services/Grants 1,500,000,000.00
412C Office Of The Deputy Governor 30,000,000.00 400,000,000.00 430,000,000.00 16,903,014.15 280,000,000.00 296,903,014.15 12,421,782.04 216,510,220.00 228,932,002.04
(i) Project Implementation Unit (World Bank- Assisted) - 2,500,000.00 2,500,000.00 - 2,000,000.00 2,000,000.00 - 1,350,000.00 1,350,000.00
413A Office of The Secretary To The State Government - 120,000,000.00 120,000,000.00 - 90,000,000.00 90,000,000.00 - 65,780,784.57 65,780,784.57
(i) State Programme Coordinating Committee SPCC of UNDP - - - - - - - - -
(ii) State Action Committee on HIV/AID (SACA) - 12,000,000.00 12,000,000.00 - 10,000,000.00 10,000,000.00 - 5,801,300.00
5,801,300.00
(iii) Agency for Community Based Poverty Reduction Project - 5,000,000.00 5,000,000.00 - 5,000,000.00 5,000,000.00 - 3,391,500.00 3,391,500.00
(CPRP)/Comm. Soc. Devt. Prog. (CSDP)
(iv) Non Governmental Organisation (NGO) - 10,000,000.00 10,000,000.00 - - - - -
(v) UNITAR - 6,550,000.00 6,550,000.00 - 4,000,000.00 4,000,000.00 - 2,930,000.00 2,930,000.00
(vi) Physically Challenged - 5,328,000.00 5,328,000.00 - 5,328,000.00 5,328,000.00 - 3,157,000.00 3,157,000.00
(vii) Office of NEPAD - 50,000,000.00 50,000,000.00 - - - - - -
(viii) MDGs/CGS Unit 20,000,000.00 20,000,000.00 - 20,000,000.00 20,000,000.00 14,310,150.00 14,310,150.00
(viv) Edo State Peace & Conflict Resolution Committee - 15,000,000.00 15,000,000.00 - - - -
413B Directorate of Central Administration 1,348,950,343.00 210,000,000.00 1,558,950,343.00 1,052,335,261.87 210,000,000.00 1,262,335,261.87 811,633,615.76 102,303,852.34 913,937,468.10
(ia) Special Overhead - 350,000,000.00 350,000,000.00 - 350,000,000.00 350,000,000.00 268,200,000.00 268,200,000.00
(i) Special Advisers’ Office - 50,000,000.00 50,000,000.00 - 50,000,000.00 50,000,000.00 49,947,005.50 49,947,005.50
(ii) National Volunteer Service (N.N.V.S.) State - - - - - - - -
(iii) Personnel cost for New employment - - - - - - - -
413C Edo State Liaison Office, Lagos 73,169,412.00 30,000,000.00 103,169,412.00 4,158,784.90 30,000,000.00 34,158,784.90 3,269,181.83 20,604,900.00 23,874,081.83
413D Edo State Liaison Office, Abuja - 40,000,000.00 40,000,000.00 - 40,000,000.00 40,000,000.00 32,000,000.00 32,000,000.00
413E Directorate of Cabinet, Political and Special Services 641,877,733.00 35,000,000.00 676,877,733.00 20,422,974.25 30,000,000.00 50,422,974.25 16,654,758.03 23,869,450.00 40,524,208.03
(i) Security Services - - - - - - - -
19
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
RECURRENT EXPENDITURE PROFILE
2012 APPROVED PROVISION 2011 APPROVED PROVISION INCLUDING SUPPLEMENTARY ACTUAL EXPENDITURE AS AT SEPT 2011
HEAD MINISTRY/DEPARTMENT/
N N N N N N N N N
413G Office of the Head of Service - 50,000,000.00 50,000,000.00 - 50,000,000.00 50,000,000.00 41,857,725.00 41,857,725.00
413H Directorate of Establishment, Training and Management Services 30,000,000.00 40,000,000.00 70,000,000.00 22,426,983.49 40,000,000.00 62,426,983.49 18,319,040.75 53,308,635.75
34,989,595.00
413H (a) Human Capacity Enhancement Programme - 150,000,000.00 150,000,000.00 - 150,000,000.00 150,000,000.00 -
-
413J Edo State Pension Board 28,832,707.60 25,000,000.00 53,832,707.60 20,784,604.64 25,000,000.00 45,784,604.64 18,803,939.74 11,808,400.00 30,612,339.74
(I) 3 Months In Lieu Of Notice - - - - - - -
414 Min. of Agric. and Natural Resources 284,059,018.00 40,000,000.00 324,059,018.00 284,059,018.19 40,000,000.00 324,059,018.19 229,105,182.79 18,105,358.21 247,210,541.00
(i) College of Agriculture, Ighuoriakhi 300,000,000.00 35,000,000.00 335,000,000.00 183,291,337.89 30,000,000.00 213,291,337.89 155,783,379.26 15,582,542.20 171,365,921.46
(ii) Extension Campus, Agenebode - 20,000,000.00 20,000,000.00 - 15,000,000.00 15,000,000.00 - -
(iii) Edo State Committee on Communal Farms - 3,000,000.00 3,000,000.00 - 3,000,000.00 3,000,000.00 644,280.00 644,280.00
(iv) Edo State Agric. Dev. Prog. (ADP) 24,000,000.00 4,000,000.00 28,000,000.00 24,533,333.33 4,000,000.00 28,533,333.33 14,000,000.00 14,000,000.00
(v) Tree Crop Unit - 2,000,000.00 2,000,000.00 - 2,000,000.00 2,000,000.00 517,750.00 517,750.00
415A Ministry of Budget, Planning and Economic Development 80,000,000.00 80,000,000.00 160,000,000.00 46,027,742.86 60,000,000.00 106,027,742.86 34,558,407.78 26,194,140.00 60,752,547.78
(i) - 10,000,000.00 - - -
Monitoring & Evaluation 10,000,000.00 0
(ii) Economic Surveys & Reporting - 20,000,000.00 20,000,000.00 - 20,000,000.00 20,000,000.00 -
(iii) External Interventions / Donor Agencies Unit - 20,000,000.00 20,000,000.00 - 15,000,000.00 15,000,000.00 1,547,750.00 1,547,750.00
(iv) State Employment Expenditure Effectiveness for Results (SEEFOR) - 20,000,000.00 20,000,000.00 - 15,000,000.00 15,000,000.00 1,447,000.00 1,447,000.00
(v) Economic & Strategy Team - 30,000,000.00 30,000,000.00 - 30,000,000.00 30,000,000.00 30,000,000.00 30,000,000.00
(vi) Edo State Bureau of Statistics 10,000,000.00 10,000,000.00
(vii) Central Office of Planning 20,000,000.00 20,000,000.00
415B Min. of Commerce and Industry 85,000,000.00 40,000,000.00 125,000,000.00 84,255,099.62 40,000,000.00 124,255,099.62 55,833,532.09 19,289,261.00 75,122,793.09
(i) Technical Committee on Privatisation and Commercialisation - - - - - - -
(TCPC)
(ii) Consumer Protection Committee - 5,000,000.00 5,000,000.00 - - - -
(iii) Small and Medium Scale Enterprises Committee/NEPAD - - - - 5,000,000.00 5,000,000.00 -
416 Ministry of Education 300,000,000.00 55,000,000.00 355,000,000.00 138,452,451.40 50,000,000.00 188,452,451.40 109,378,166.50 42,414,855.00 151,793,021.50
(i) Ambrose Alli University, Ekpoma 4,440,000,000.00 - 4,440,000,000.00 3,000,000,000.00 - 3,000,000,000.00 1,890,000,000.00 1,890,000,000.00
(ii) College of Education, Ekiadalor 1,200,000,000.00 - 1,200,000,000.00 800,000,000.00 - 800,000,000.00 531,972,026.59 531,972,026.59
(iii) Michael Imoudu Institute of Physical Education Afuze 10,000,000.00 6,500,000.00 16,500,000.00 9,000,000.00 6,500,000.00 15,500,000.00 4,139,256.84 4,139,256.84
(iv) Institute of Continuing Education, B/City 141,000,000.00 - 141,000,000.00 141,000,000.00 - 141,000,000.00 72,030,156.00 72,030,156.00
(v) Post Primary Education Board 4,000,000,000.00 30,000,000.00 4,030,000,000.00 3,560,688,383.84 15,000,000.00 3,575,688,383.84 2,638,933,401.53 14,573,500.00 2,653,506,901.53
(vi) Scholarship and Bursary Board - 2,400,000.00 2,400,000.00 - 2,400,000.00 2,400,000.00 -
(vii) Ethiope Publishing Corporation, B/City. 13,729,879.84 3,600,000.00 17,329,879.84 10,777,750.20 3,600,000.00 14,377,750.20 8,954,269.46 2,730,000.00 11,684,269.46
(viii) School for the Handicapped - - - - - - -
(ix) State Library Board 65,392,296.90 8,000,000.00 73,392,296.90 62,847,439.37 10,000,000.00 72,847,439.37 42,647,150.15 2,250,000.00 44,897,150.15
(x) Model Secondary Schools - - - - - - -
(xi) Edo State Institute of Technology and Management, Usen 382,238,965.55 - 382,238,965.55 279,592,370.92 - 279,592,370.92 249,286,281.88 249,286,281.88
(xii) College of Education, Igueben 141,000,000.00 20,000,000.00 161,000,000.00 96,600,000.00 20,000,000.00 116,600,000.00 92,142,264.60 7,497,000.00 99,639,264.60
(xiii) Board for Technical Edu. B/City 225,000,000.00 50,000,000.00 275,000,000.00 189,355,776.57 4,000,000.00 193,355,776.57 144,771,180.46 3,600,000.00 148,371,180.46
(xiv) State Universal Education Board 3,000,000,000.00 30,000,000.00 3,030,000,000.00 2,316,155,196.64 10,000,000.00 2,326,155,196.64 1,740,100,145.68 9,600,000.00 1,749,700,145.68
(xv) Agency for Adult and Non-Formal Education - 3,000,000.00 3,000,000.00 - 3,000,000.00 3,000,000.00 1,620,000.00 1,620,000.00
416B Ministry of Transport 100,000,000.00 40,000,000.00 140,000,000.00 73,863,019.00 35,000,000.00 108,863,019.00 51,937,191.02 15,280,375.00 67,217,566.02
416B (i) Edo State Transport Service Limited - - - - - - -
417A Ministry of Energy and Water Resources 27,000,000.00 20,000,000.00 47,000,000.00 7,744,797.42 20,000,000.00 27,744,797.42 7,693,052.90 9,255,465.00 16,948,517.90
(i) Edo State Urban Water Board 210,000,000.00 30,000,000.00 240,000,000.00 191,249,627.42 25,000,000.00 216,249,627.42 183,242,751.91 12,642,133.93 195,884,885.84
(ii) Rural Electricity Board 24,736,585.00 10,000,000.00 34,736,585.00 15,057,199.32 25,000,000.00 40,057,199.32 14,549,113.03 3,154,750.00 17,703,863.03
(iii) Rural Water And Sanitation 10,000,000.00 5,000,000.00 15,000,000.00 - - - -
20
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
RECURRENT EXPENDITURE PROFILE
2012 APPROVED PROVISION 2011 APPROVED PROVISION INCLUDING SUPPLEMENTARY ACTUAL EXPENDITURE AS AT SEPT 2011
HEAD MINISTRY/DEPARTMENT/
N N N N N N N N N
417B Ministry of Environment and Public Utilities 150,000,000.00 45,000,000.00 195,000,000.00 87,977,105.48 37,000,000.00 124,977,105.48 90,762,241.77 38,525,590.00 129,287,831.77
(i) Edo State Environmental and Waste Management Board 3,518,162.05 10,000,000.00 13,518,162.05 3,208,695.55 6,000,000.00 9,208,695.55 2,294,453.51 4,276,000.00 6,570,453.51
(ii) Beautification of Towns/Cities - 15,000,000.00 15,000,000.00 - 10,000,000.00 10,000,000.00 -
(iii) State Tenders Board - 6,000,000.00 6,000,000.00 5,000,000.00 5,000,000.00 3,000,000.00 3,000,000.00
(iv) Market and Monthly Sanitation 70,000,000.00 70,000,000.00 10,000,000.00 10,000,000.00 5,500,000.00 5,500,000.00
(v) Environmental Education 10,000,000.00 10,000,000.00 10,000,000.00 10,000,000.00 10,000,000.00 10,000,000.00
418A Ministry of Finance 29,606,599.92 700,000,000.00 729,606,599.92 60,339,973.39 627,000,000.00 687,339,973.39 44,295,717.16 507,928,307.94 552,224,025.10
418C Office of the Accountant-General 120,000,000.00 650,000,000.00 770,000,000.00 70,533,356.06 700,000,000.00 770,533,356.06 56,991,859.75 527,029,417.00 584,021,276.75
418C(ii) Project Financial Management Unit (PFMU) - 3,000,000.00 3,000,000.00 193,657,949.35 3,000,000.00 196,657,949.35 1,000,000.00 1,000,000.00
418D Board of Internal Revenue 180,000,000.00 845,000,000.00 1,025,000,000.00 - 650,000,000.00 650,000,000.00 165,908,163.04 509,038,614.42 674,946,777.46
419 Ministry of Health 350,000,000.00 50,000,000.00 400,000,000.00 231,660,785.30 40,000,000.00 271,660,785.30 199,918,224.11 31,526,150.00 231,444,374.11
(i) Hospitals Management Board 3,650,000,000.00 20,000,000.00 3,670,000,000.00 3,230,823,524.77 20,000,000.00 3,250,823,524.77 2,425,154,720.70 967,500.00 2,426,122,220.70
(ii) Traditional Medicine Board 6,000,000.00 5,000,000.00 11,000,000.00 4,090,550.00 4,000,000.00 8,090,550.00 3,490,000.00 2,341,000.00 5,831,000.00
(iii) Ossiomo Leprosarium 10,000,000.00 25,000,000.00 35,000,000.00 11,240,866.67 20,000,000.00 31,240,866.67 5,265,000.00 19,350,000.00 24,615,000.00
(iv) Sickle Cell Centre 50,000,000.00 10,000,000.00 60,000,000.00 283,666.67 5,000,000.00 5,283,666.67 1,800,000.00 1,800,000.00
(v) Medical Assistance - 100,000,000.00 100,000,000.00 - 50,000,000.00 50,000,000.00 -
(vi) Essential Drug project - - - - - -
(vii) State School of Nursing - 5,000,000.00 5,000,000.00 - - -
(viii) State School of Midwifery - 5,000,000.00 5,000,000.00 - - -
(ix) State School of Health Technology - 5,000,000.00 5,000,000.00 - - -
420A Ministry of Special Duties, Oil and Gas 5,000,000.00 20,000,000.00 25,000,000.00 5,000,000.00 20,000,000.00 25,000,000.00 2,297,741.78 5,988,160.00 8,285,901.78
420B Ministry of Information and Orientation 170,000,000.00 73,000,000.00 243,000,000.00 111,050,484.62 60,000,000.00 171,050,484.62 88,204,096.38 47,127,150.00 135,331,246.38
(i) Edo Broadcasting Service (EBS) 28,016,666.35 - 28,016,666.35 146,474,029.29 - 146,474,029.29 118,247,223.64 118,247,223.64
(ii) Bendel Newspapers Limited 150,000,000.00 2,000,000.00 152,000,000.00 94,564,104.06 2,000,000.00 96,564,104.06 58,053,780.14
58,053,780.14
420C Min. of Local Govt.s & Chieftaincy Affairs 18,672,509.37 16,000,000.00 34,672,509.37 18,672,509.37 16,000,000.00 34,672,509.37 13,474,356.45 17,556,111.45
4,081,755.00
420D Ministry of Youth and Sports (Including Bendel Ins & Inneh 28,525,816.00 400,000,000.00 428,525,816.00 19,455,094.43 180,000,000.00 199,455,094.43 12,063,668.38 171,418,690.00 183,482,358.38
Queens)
(i) Edo State Sports Council 400,000,000.00 6,000,000.00 406,000,000.00 331,488,467.79 4,000,000.00 335,488,467.79 282,531,319.12 3,078,000.00 285,609,319.12
(ii) Youth Development/Empowerment - - - - - - -
(iii) Preparation for National Sports Festival - 170,000,000.00 170,000,000.00 170,000,000.00 170,000,000.00 128,744,000.00 128,744,000.00
(iv) Football Academy 100,000,000.00 100,000,000.00 - 10,000,000.00 -
(v) Sponsorship of Sport Competition including overseas Trip - 10,000,000.00 10,000,000.00
421 Ministry of Justice 323,737,958.96 65,000,000.00 388,737,958.96 171,468,216.84 60,000,000.00 231,468,216.84 145,233,417.38 42,672,122.00 187,905,539.38
(i) Law Reform Commission 30,000,000.00 30,000,000.00 60,000,000.00 14,484,809.90 25,000,000.00 39,484,809.90 26,503,471.96 12,641,885.00 39,145,356.96
(ii) Legal Consultancy 200,000,000.00 200,000,000.00
(iii) Judgement Debt 50,000,000.00 50,000,000.00
422 Ministry of Women Affairs and Social Development 70,000,000.00 35,000,000.00 105,000,000.00 48,012,759.00 30,000,000.00 78,012,759.00 35,936,668.72 21,259,450.00 57,196,118.72
(i) Christian Pilgrims Welfare Boards - 30,000,000.00 30,000,000.00 - 30,000,000.00 30,000,000.00 668,700.00 668,700.00
(ii) Muslim Pilgrims Welfare Boards - 30,000,000.00 30,000,000.00 - 30,000,000.00 10,780,000.00 10,780,000.00
(iii) State Emergency and Management Agency - 4,000,000.00 4,000,000.00 - 4,000,000.00 4,000,000.00 2,617,000.00 2,617,000.00
(iv) Skill Acquisition Centre/Treated/Cured Lunatics - 10,000,000.00 10,000,000.00 - 10,000,000.00 10,000,000.00 4,721,400.00 4,721,400.00
(v) Remand Homes - 5,000,000.00 5,000,000.00 - 5,000,000.00 5,000,000.00 1,440,000.00 1,440,000.00
(vi) Rehabilitation of Destitutes - 10,000,000.00 10,000,000.00 - 10,000,000.00 10,000,000.00 7,893,425.00 7,893,425.00
(vii) Orphans and Vulnerable Children (OVC) - 4,000,000.00 4,000,000.00 - 4,000,000.00 4,000,000.00 1,700,000.00 1,700,000.00
(viii) Child Right Law (Com. On implementation) - 5,000,000.00 5,000,000.00 - 5,000,000.00 5,000,000.00 4,721,500.00 4,721,500.00
(ix) Project Cherilove - 4,000,000.00 4,000,000.00 - 4,000,000.00 4,000,000.00 2,980,000.00 2,980,000.00
(x) Committee on Human Trafficking - 2,000,000.00 2,000,000.00 - - - -
(xi) Celebration/Activities of United Nations Resolutions - - - - 3,000,000.00 3,000,000.00 2,590,000.00 2,590,000.00
xii) Women Fund for Economic Empowerment/ Publicity - - - - - -
21
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
RECURRENT EXPENDITURE PROFILE
2012 APPROVED PROVISION 2011 APPROVED PROVISION INCLUDING SUPPLEMENTARY ACTUAL EXPENDITURE AS AT SEPT 2011
HEAD MINISTRY/DEPARTMENT/
N N N N N N N N N
423 Ministry of Works 164,533,889.04 25,000,000.00 189,533,889.04 121,481,996.30 25,000,000.00 146,481,996.30 80,056,146.05 6,562,271.00 86,618,417.05
423B Ministry of Arts, Culture and Tourism 30,000,000.00 15,000,000.00 45,000,000.00 14,967,950.27 15,000,000.00 29,967,950.27 12,213,346.69 8,328,780.00 20,542,126.69
(i) Edo State Arts Council 31,311,938.90 4,000,000.00 35,311,938.90 27,072,500.26 4,000,000.00 31,072,500.26 20,420,829.72 793,750.00 21,214,579.72
(ii) Tourism Board - 3,000,000.00 3,000,000.00 - 3,000,000.00 3,000,000.00 - -
424 Ministry of Lands, Surveys and Housing 200,000,000.00 60,000,000.00 260,000,000.00 96,264,846.15 60,000,000.00 156,264,846.15 87,035,110.00 33,424,690.00 120,459,800.00
(i) Edo Development & Property Authority 43,761,969.64 18,000,000.00 61,761,969.64 24,095,050.68 18,000,000.00 42,095,050.68 28,540,414.98 5,825,950.00 34,366,364.98
425A Office of the Auditor-General (State) 50,000,000.00 35,000,000.00 85,000,000.00 28,463,519.31 25,000,000.00 53,463,519.31 20,742,807.20 18,948,410.00 39,691,217.20
425B Office of the Auditor-General (Local Govt) 30,000,000.00 20,000,000.00 50,000,000.00 16,691,507.35 20,000,000.00 36,691,507.35 13,085,376.10 5,692,000.00 18,777,376.10
426 Civil Service Commission 28,733,935.14 7,000,000.00 35,733,935.14 20,405,956.22 7,000,000.00 27,405,956.22 18,739,522.92 5,506,250.00 24,245,772.92
427A Edo State House of Assembly 1,104,000,000.00 800,000,000.00 1,904,000,000.00 930,715,689.46 750,000,000.00 1,680,715,689.46 699,967,271.45 610,012,859.00 1,309,980,130.45
(i) Office of Mr. Speaker - 50,000,000.00 50,000,000.00 - 75,000,000.00 75,000,000.00 16,000,000.00 16,000,000.00
(ii) Printing/Other Materials - 40,000,000.00 40,000,000.00 - 30,000,000.00 30,000,000.00 - -
427B House of Assembly Service Commission - 15,000,000.00 15,000,000.00 - 15,000,000.00 15,000,000.00 5,655,500.00 5,655,500.00
428 Edo State Judiciary (Dir. High Court of Justice) 1,184,633,197.00 150,000,000.00 1,334,633,197.00 904,641,565.36 150,000,000.00 1,054,641,565.36 634,019,155.95 117,774,166.00 751,793,321.95
(i) Office of the State Chief Judge - 10,000,000.00 10,000,000.00
(ii) Election Petition Tribunal - 10,000,000.00 10,000,000.00 - 10,000,000.00 10,000,000.00 10,000,000.00 10,000,000.00
(iii) Special Allowance for Judicial Officers (High Court) - - - 50,000,000.00 50,000,000.00 7,400,000.00 7,400,000.00
Special Allowance for Court Registrar/Magistrate - - - - - - - -
(iv)
(v) Seed Money Revolving Fund for Probate Matters 10,000,000.00 10,000,000.00
(vi) Retreat for Judges - 10e -
(vii) Witness Summons Programme - 5,000,000.00 5,000,000.00
428A Special Overhead for Judiciary (Judicial Officers &three(3) - 200,000,000.00 200,000,000.00 - 200,000,000.00 200,000,000.00 199,976,000.00 199,976,000.00
Admin Head)
428B Customary Court of Appeal 720,000,000.00 95,000,000.00 815,000,000.00 423,844,706.59 95,000,000.00 518,844,706.59 322,564,010.96 71,249,999.94 393,814,010.90
(i) Special Allowance for Judicial Officers (Customary Court of Appeal) - - - - - 1,650,000.00 1,650,000.00
(ii) Special Allowance for Chief Registrar/Area Customary Court - 60,000,000.00 60,000,000.00 - - - -
Presidents -
(iii) Office of President Court of Appeal 10,000,000.00 10,000,000.00
429A Judicial Service Commission 94,987,020.94 25,000,000.00 119,987,020.94 39,048,511.86 25,000,000.00 64,048,511.86 35,675,608.00 19,756,000.00 55,431,608.00
429B Local Government Service Commission - 3,000,000.00 3,000,000.00 - 3,000,000.00 3,000,000.00 1,800,000.00 1,800,000.00
429C Edo State Independent Electoral Commission 92,000,000.00 100,000,000.00 192,000,000.00 12,805,684.82 100,000,000.00 112,805,684.82 10,356,317.12 27,195,750.00 37,552,067.12
430 Edo State Oil and Gas Producing Areas Development - - - - - - - - -
Commission
GRAND-TOTAL 28,681,426,604 17,806,878,000 46,488,304,604 21,046,374,304.33 13,561,828,000 34,608,202,304 15,507,592,312.54 10,255,128,544.02 25,762,720,857
22
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
CAPITAL RECEIPT
23
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
CAPITAL RECEIPT SUMMARY
-3 -4 -5
N N N
24
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL RECEIPT
25
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL RECEIPT
26
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL RECEIPT
27
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL RECEIPT
28
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL RECEIPT
g. Primary Education
h. Education Tax Fund Year 2010 I nterv ention
220,000,000 220,000,000
i. Special Schools (Physic Challenged) 30,000,000 30,000,000
j. Self Help (community Pilot Programme 82,000,000 82,000,000
5 FEDERAL GRANTS FOR MINISTRY OF HEALTH:
(i) Primary Basic Health Care Programme 0 0
(ii) Training of Nurses & Health I nspectors 0 0
(iii) M obile Clinic (Rural Health Centres) 0 0
(iv ) M alaria Control 0 0
(v ) Epidemic (Yellow Fev er etc) 0 0
(v i) Onchocarcciasis 0 0
(v ii) Leprosy Control Programme 0 0
(v iii) EPI programme 0 0
(ix) NPI State Gov ernment Support 0 0
443/
(ix) Tuberculosis Control Programme
(x) Guinea Worm Eradication
(xi) Population Control
(xii) World Health Day
(xiii) Drug Abuse
(xv ) National Programme on I mmunization
(xv i) Family Planning Programme
(xv ii) Secondary Health Care Programme
(xv iii) Prev ention of Riv er Blindness
(xix) Otibhor Specialist Hospital, I rrua
(xx) Celebration of Breast Feeding Week
29
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL RECEIPT
30
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL RECEIPT
31
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
32
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
CONSOLIDATED REVENUE FUNDS CHARGES PROFILE
33
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
34
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SUMMARY OF CAPITAL EXPENDITURE
35
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ECONOMIC
SUB-SECTOR: AGRICULTURE
HEAD: 450 A
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan - Se pt 2011 Appropriation
abandone d, Ne w) 2011 2012
N N N
1 Oilpalm seedling supply scheme at Ogba, Abudu, Ehor, Irrua, Afuze, on-going 5,000,000.00
Ora, Ogheghe and Ekpoma
2 Renovation of dilapidated farm offices, warehouses, community halls, on-going 15,000,000 50,000,000.00
and farm infrastructure at the farm settlement
3 Agricultural Show: Celebration of World Food Day, Launching of on-going 3,000,000 Nil 3,200,000.00
Farming Season
4 Edo State Communal Farm:
a) Obayantor: Land preparation- clearing, ploughing, harrowing, on-going 9,435,430 10,000,000.00
planting of food crops,water melon etc
b) Sabongida-ora 30ha: Maize & cas s ava on-going 3,500,000 4,000,000.00
c) Usugbenu Rice and Water Melon on-going 10e
5 Edo State College of Agriculture: 20,000,000 100,000,000.00
i) Iguoriakhi Campus: Infrastructure for accreditation purposes New
ii) Agenebode Campus: Provision of basic Infrastructure for 3,000,000 Nil 100,000,000.00
Permanent site New
6 Edo State College of Agriculture: Construction of 8-classroom New 3,000,000 Nil
bungalow at Iguoriakhi.
7 Agricultural publicity and Information: Printing of Agricultural bulletins on-going 3,000,000.00
etc
8 Seed multiplication farms at Irrua, Usen and Sabongida-ora on-going 29,000,000 4,000,000.00
9 Agricultural Engineering: 20,000,000 Nil
i) Purchase of farm machinery and maintenance on-going 3,350,000 216,050,000.00
ii) Reconditioning of old farm tractors on-going - -
iii) Purchase of spare parts (including tyres, tubes and operators - - 5,000,000.00
uniform.
iv) Construction and euiping a maintenance bay on-going -
6,000,000
36
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
SECTOR: ECONOMIC
SUB-SECTOR: AGRICULTURE
HEAD: 450 A
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan - Se pt 2011 Appropriation
abandone d, Ne w) 2011 2012
N N N
11 Agricultural Development Programme: 1,002,011,556 - 30,000,000.00
a)Refurbishment of ADP Infrastructure on-going
b)Establishment of On Farm Adaptive Research on-going 1,200,000 - 1,200,000.00
c)Dissemination of Scientific Agriculture: 2,000,000 - 2,000,000.00
i) Monthly Technology Review meetings on-going 1,000,000 - 1,000,000.00
ii) Small Plot Adoption Techniques on-going 1,000,000 - 1,000,000.00
d)Farmers Fields School on-going
e)Improved Seed Multiplication on-going 25,000,000 -
12 National Cocoa Development Committee - - -
i) Annual Cocoa Day Celebration on-going - - 25,000,000.00
ii)Chemicals for farmers from NCDC at 50% subsidy on-going - - 10,000,000.00
13 Rehabilitation/Replanting of old Rubber plantation at Uhronigbe and on-going 2,000,000 -
Ugo
14 Agricultural Insurance Scheme: Payment of State share of mandatory on-going -
contribution
15 Hosting of the State Council on Agriculture on-going - - -
16 Purchase of Office Equipment and Furniture on-going 3,000,000 - 11,000,000.00
17 Edo State Agric. Trust Fund: Allottee Farming Scheme at Iguoriakhi, on-going 3,990,231 -
Ekpoma, and Sobe
18 Youth Empowerment: Young farmers' Club Comrade farmers) on-going - - 100,000,000.00
provision of inputs
19 Pest Control/Crop Protection Services: Purchase of Equipment and on-going - - 2,000,000.00
pesticides.
20 FGN Conditional Grant Scheme on-going - - 10e
21 Strategic Conditional Grant Scheme Youth in Edo State. on-going - - 10e
22 State Food Storage Programme: on-going 1,830,927 - 30,000,000.00
23 Produce Ispection Labortory on-going 5,000,000 10e
24 Benchmark survey of Agriculture sector of Edo State. on-going 8,711,556 - 5,000,000.00
25 Small-holder oilpalm supply scheme on-going - - 5,000,000.00
26 Small-holder cocoa scheme on-going - - 8,800,000.00
27 Small-Holder Rubber Development Scheme on-going 1,307,183 - 5,000,000.00
28 Small-Holder Cashew Development Scheme on-going 3,000,000 3,000,000.00
29 Small-Holder Sesame Development Scheme New 3,000,000.00
30 Repair of old pens and poultry houses on-going 1,307,183 2,400,000.00
TOTAL 1,179,836,882 39,443,200 752,144,045.00
37
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ECONOMIC
SUB SECTOR: FISHERIES
HEAD: 450 B
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan - se pt 2011 Appropriation
abandone d, Ne w) 2011 2012
N N N
1 Fishery Projects: 22,575,056 15,000,000
c) Artisanal capture Fisheries, construction of landing jetting, Net loft/fuel Dept., on--going
Fabrication of Fishing gear
d) Culture-based Inland fisheries development programme
ii) Hatchery Equipment, brood stock, fish meal, fish harvesting handling materials on-going 25,000,000 - 6,800,000
38
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ECONOMIC
SUB SECTOR: LIVESTOCK
HEAD : 450 C
b) Control of epizootic- PPR, CBPP and New castle diseases on-going 12,545,034 - 8,500,000
3 Building of Animal disease control posts at Ibillo, Okpella, Agenebode, Evbonogbon and Uzeba
ongoing - - -
4 Veterinary Investigative centre and Diagnostic Laboratory
on-going - - -
5 Cattle ranch Development at Igarra, Edo North through Private-Public Partnership (PPP) arrangement
on-going - - -
6
Rehabilation of Sheep and Goat ranch at Ubiaja through Private-Public Partership (PPP) arrangement on-going - - -
7
Development of grazing reserves at Okpella on-going - - -
8
1 No. Modern Abattoir Development at Benin City. on-going - - -
TOTAL 37,545,034 500,000.00 33,500,000
39
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: SOCIAL
…………………………………………………………
SUB-SECTOR: MINISTRY OF ARTS, CULTURE & TOURISM
HEAD: 451
Sub- Details of Expenditure Status of Projects Approved Actual Expe nditure Approve d
Head (i.e. on-going, Appropriation Appropriation
Jan - Se pt 2011
abandoned, New) 2011 2012
N N N
1 Cultural Exhibition Centre On-going 500,000.00 1,000,000.00
2 Oba Akenzua II Cultural Complex Phase II On-going 40,000,000.00 48,500,000.00
3 Cultural Centre Annex (Royal Hall Building) On-going 13,000,000.00 10,000,000.00
4 Cultural Exchange Programme On-going
5 Costume/Musical Instruments Acquisition On-going 4,000,000.00 4,000,000.00
6 HIV/AIDS Advocacy in Arts/Culture Area On-going
7 Abuja Carnival (Nations Cultural Exposition) On-going 10,000,000.00 10,000,000.00
8 Traditional Festival On-going 1,000,000.00 5,000,000.00
9 Institutional Festival of Arts and Culture (Competition) On-going 1,000,000.00 1,000,000.00
10 UNESCO Culture of Peace (Annual Event). On-going
11 State Festival of Arts, Culture and Tourism (EDOFEST) On-going 21,000,000.00 20,000,000.00
12 Development of Tourism Park in Edo State. On-going 10,000,000.00 10,000,000.00
13 Registration, Classification
National Festival and Grading
of Arts, Culture of Unity
(Natinal Tourism Enterprises.
Festival, On-going 2,000,000.00 - 2,000,000.00
14 NAFEST) On-going 5,000,000.00 5,000,000.00
15 World Tourism Day On-going 500,000.00 500,000.00
16 Tourism Exposition New
17 Ikpoba Dam Hotel/Resort New
18 Okomu Wild-Life Sanctuary/Resort New
19 Benin Moat/Walls New
20 Documentary/Publications New 2,000,000.00
21 State Coral Group/(H.E. Directives) Heart Beat Voices. New
22 Establishment of Edo State Cultural Village. New
23 Adams Oshiomhole Resort and Tourism Centre. New 5,000,000.00
24 Ultra Modern Cultural Market New
25 Tourism Board New
26 Resource Centre, Benin City New 1,750,000.00 1,500,000.00
27 Ososo Tourist Centre, Akok Edo LGA 8,500,000.00 8,500,000.00
TOTAL 118,250,000.00 13,122,500.00 134,000,000.00
40
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ECONOMIC
SUB-SECTOR: COMMERCE & INDUSTRY
HEAD: 452
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan - Se pt 2011 Appropriation
abandone d, Ne w) 2011 2012
N N N
1 Micro Credit Scheme on-going 200,000,000.00
2 Industrialisation Day on-going 1,000,000.00 500,000.00
3 Trade Promotion and Fairs on-going 10,000,000.00 10,000,000.00
4 Edo State Export Promotion Committee on-going 10,000,000.00 5,000,000.00
5 National and State Council on Cooperatives on-going 1,000,000.00 300,000.00
6 National Council on Trade and Investment on-going 1,500,000.00
7 Consultancy Services on Improvement of Ailing Government Industries on-going 2,000,000.00 5,000,000.00
8 Purchase of Office equipment and furniture and renovation of 18 LGA Field Offices and 10,000,000.00
on-going 4,000,000.00
Headquarters
9 Cassava Processing Factory, Uromi on-going 30,000,000.00 70,000,000.00
10 Fertilizer and Chemical Company, Auchi on-going 10,000,000.00 25,000,000.00
11 Technology Incubation Centre New 10,000,000.00
12 Development on Handicraft Centre: New
13 (i) Wood Utilization Centre (Establishment of New 10,000,000.00
14 Auchi Textile Training Centre (Renovation and Refurbishment) New 30,000,000.00
15 Raw Materials Display Centre New 2,000,000.00
16 Edo State Business Directory New 2,000,000.00
17 Development of Permanent Trade Fair complex Benin New 5,000,000.00
18 Consumer Protection Committee Ongoing 19,000,000.00 10,000,000.00
19 One 18 seater bus for revenue collection from Bus. New 8,000,000.00
20 Establishment of Cooperative Data Base New 10,000,000.00
21 Cooperative Week Celebration New 4,000,000.00
22 Entrepreneural Training New 6,000,000.00
23 Edo State Industrial Policy Ongoing 1,500,000.00
24 Establishment of Industrial Parks and provision of furniture equipments Ongoing 30,000,000.00 100,000,000.00
25 Coodination of Artisanship/Craftsmen New 70,000,000.00
26 Update Register and Advert Registration of Business Premises New
27 Production of Standard indigenous measure for Grains/and related production. Ongoing 500,000.00 2,000,000.00
28 New 10,000,000.00
Privatisation of Cassava Factory,Uromi and Fertilizer com. Auchi
29 Upgrading of Edo Hotel New 20,000,000.00
30 Development of Gelegele as Export free Zone New
31 Trades Men and Artisan Week Celebration New 5,000,000.00
32 Promotion of Made-in-Nigeria Products New
33 Training of Cooperative Officers New 10,000,000.00
34 Cluster Market Iyowa Project New 6,000,000.00
35 Sponsorship of Cooperative officers and Hon. Commissioner to Kenya for two weeks to under study the
New
successfuloperation of marketing coperatives in Kenya. 8,700,000.00
41
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
42
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR SOCIAL
SUB-SECTOR EDUCATION
HEAD 453
Sub- Details of Expenditure Status of Projects Approved Actual Expenditure Approved
Head (i.e. on-going, Appropriation Jan - Sept 2011 Appropriation
abandoned, New) 2011 2012
N N N
15 Ethiope publishing Corporation (Course books , Vehicles and Equipment) New 12,000,000 - 5,000,000
Government Science & Tech college,B/C Afuze, Igarra, Agbede, Irrua, Urhonigbe, Igouzuwa, Okpella & Emu, infrastructure & Science
17 facilities. On-going 20,000,000 - 10,000,000
19 Agency for Adult & Non-Formal Educ. Instructional Materials UNICEF/UNDP downstream activities) and purchase of vehicle 1,000,000 - 500,000
: 20. Examination & Standards: Provisions, Security, Vehicles, Computers & Equipments On-going 5,000,000 - 2,000,000
21 Education Resources Centre Instructional Materials, Install. Of Educ. Tech. Equip. & Training. New 14,000,000 - 10,000,000
22 i. Purchase & Installation of Computers,Printers & Accessories, Furnishing & Office Equipment. 2,000,000 - 1,500,000
a Purchase of Vehicles for Monitoring Schools and Projects, ETF Assignment, JCC & NCE matters 15,000,000 -
b Establishment of EMIS in the 18 LGAs and provision of alternative source of power. 5,000,000
Renovation of Ministry of Education Headquarters including re-roofing with long span aluminium, replacement of of doors, ceiling,
25 windows,flooring, alsphating & landscaping. 30,000,000 - 5,000,000
27 Preparation & Production of SESP & SESOP documents for 10 years & 3 years Strategic & Operational Plans for the state Education Sector New 13,000,000 - -
28 Inspectorate Department; purchase of 10 Hilux Vans & other utility vehicles New - - -
29 Higher Education Department; Establishment of Scholarpship Board, Provision of scholarship, bursary & financial assistance New 50,000,000 -
43
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ECONOMIC
SUB-SECTOR: ENERGY (RURAL ELECTRIFICATION)
HEAD: 454A
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan - Se pt 2011 Appropriation
abandone d, Ne w) Including Supplementary 2012
N N N
1 AKOKO-EDO LOCAL GOVT. AREA:-
a. Ogugu/Ibillo Electricity Supply ITC/TDN, 11/.415KV Netwrok Completed 4,500,000.00 4,500,000.00
b. Onumu/Ogbe/Akpama Electricity Supply New - 10,000,000.00
c. Ijaja and Olomu-Okpe Electricty project New 5,000,000.00 15,000,000.00
2 EGOR LOCAL GOVT. AREA:-
a Evbolekpen/Orovie/Obaretin 11/.415KV Network On-going 1,046,900.00 13,000,000.00
b Agbonkina Electricity project Completed 5,000,000.00
3 ESAN CENTRAL LOCAL GOVT. AREA
a Atuagbo/Ekilo/Oghoromi Complex On-going 5,000,000.00 5,000,000.00
b Electricity Supply ITC/TDN. 33/0.415KV Network On-going 5,000,000.00
c. Idumobo Ebudin Electricity Supply New 15,000,000.00
4 ESAN NORTH EAST LOCAL GOVT. AREA
a Idumu-Obodo/Oghonrahenre Electricity Supply 11/.415KV On-going 5,000,000.00 5,000,000.00
b Inegbedion/Idumu/Oniha Electricity Supply 33/.415KV On-going 5,000,000.00 5,000,000.00
c. Ubierumu-Oke Electricity Supply 33/.415KV Network Completed 2,250,000.00 3,000,000.00
d. Idumu-Eran/Idumesan Electricity Supply Completed 3,000,000.00
5 ESAN SOUTH EAST LOCAL GOVR. AREA
a Oria-Onogholo-Ilushi Electricity Supply On-going 30,000,000.00 30,000,000.00
b Orowa/Iyenlen Electricity Supply New 12,203,532.00
c. Oloshi-Uroh Electricity Supply New 10e
6 ESAN WEST LOCAL GOVT. AREA
a Egoro-Eguare-Amede Electricity Supply ITC/TDN, 33/.415KV New 5,000,000.00 5,000,000.00
b Upper Izogen Electricity Supply New 20,000,000.00 20,000,000.00
c. Egoro Naka Electricity Supply New 20,000,000.00
7 ETSAKO CENTRAL LOCAL GOVT. AREA 5,000,000.00
a Oghomere/Ogbago Electricity Supply Completed 3,500,000.00 3,500,000.00
b Udochi Electricity Supply Completed 5,000,000.00 3,500,000.00
c. Osomegbe Electricity Supply Completed 5,000,000.00 3,500,000.00
d. Udaba/Ofukpo/Agbazi Electricity Supply New 15,000,000.00
e. Iyerekhu/Odame Electrity Supply New 15,000,000.00
44
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ECONOMIC
SUB-SECTOR: ENERGY (RURAL ELECTRIFICATION)
HEAD: 454A
45
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ECONOMIC
SUB-SECTOR: ENERGY (RURAL ELECTRIFICATION)
HEAD: 454A
46
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ENVIRONMENTAL
47
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ENVIRONMENTAL
48
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ENVIRONMENTAL
49
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
MINISTRY OF ENERGY AND WATER RESOURCES - EDO STATE CAPITAL ESTIMATES, 2012
SECTOR:- ENVIRONMENTAL
SUB-SECTOR:- RURAL WATER AND SANITATION
HEAD:- 454C
50
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
MINISTRY OF ENERGY AND WATER RESOURCES - EDO STATE CAPITAL ESTIMATES, 2012
SECTOR:- ENVIRONMENTAL
SUB-SECTOR:- RURAL WATER AND SANITATION
HEAD:- 454C
a Provision of 3 units GPS Equipment for site use New 300,000 Nil 300,000
b Provision of tw o (2) w ater Level indicators New 200,000 Nil 200,000
Provision of potable w ater to 36 Rural Communities in Edo State by providing
13 On-going
borehole based w ater supply schemes.
Ground w ater exploration to determine the depth of w ater table in 100 Rural
14 On-going
Communities.
Provision of geophysical survey equipment, such as ABEM Tarameter SAS 4000,
15 complete w ith the necessary cables and accessories; as w ell as the provision of New
Water Level indicator.
Design and Construction of Ventilated Improved Pit (VIP) Latrines in 30 public
16 On-going
primary and secondary schools in Edo State.
17 Provision of Urenals in 30 public primary and secondary schools in Edo State. New
Completion of pilot Rain Water Harvesting System Project at Ukpekimiokolo
18 On-going
and Ulinlin - Ozea in Esan North - East LGA.
Provision of hand w ashing facilities in 100 public primary and secondary schools
19 New
in Edo State.
51
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
MINISTRY OF ENERGY AND WATER RESOURCES - EDO STATE CAPITAL ESTIMATES, 2012
SECTOR:- ENVIRONMENTAL
SUB-SECTOR:- RURAL WATER AND SANITATION
HEAD:- 454C
Purchase of Drilling Rigs , provision of office space, other office equipment and
24 all other necessary logistics required for the establishment of a Rural Water and New
Sanitation Agency in Edo State; to serve as take off grant for the Agency.
52
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ENVIRONMENTAL
SUB-SECTOR: DRAINAGE AND SEWAGE / ENVIRONMENTAL PROTECTION
HEAD: 455A
53
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ENVIRONMENTAL
SUB-SECTOR: FORESTRY
HEAD: 455B
Status of Projects Approved Actual Approved
Sub- Details of Expenditure (i.e. On-going, Appropriation Expenditure Appropriation
Head Abandoned, New) 2011 Jan - Sept 2011 2012
1 Forest Management and Inventory:
(a) Field survey and inventory of Area BC 16/1 Ehor, BC 11/1 Ekiadolor and Ora-luleha-ozalla forest reserves (68,143 hectares) through; NEW 3,125,000 3,125,000
(i) Satellite Imagery.
(ii) Ground Trotting
(iii) Documentation
(b) Purchase of survey materials & Mapping equipments NEW 3,750,000 2,750,000
(c) Purchase of one Toyota Hilux for Field Survey and Inventory NEW 10e
2 Forest Protection, expliotation and Log Control Movement:
(i) Purchase of uniforms; Belts,boots and Berets and other accessories NEW 1,000,000 1,000,000
(ii) Forest regeneration-raising of 400,000 forestry seedlings at Ologbo and South Ibie Forest nurseries -do- 3,000,000
(iii).a. Reforestation of degraded forest land and planting of economic trees at Ologbo and South Ibie Forest Reserves -do- 5,000,000 5,000,000
(iii).b. Fed. Min. of Environment Assisted Forest Plantation at Idu Village Locality 2,000,000
(iv) Production of 150 forest hammers. The present ones in use, produced in 1992 have become obsolette and defaced. As a security
document, it is expected to be changed every five years @ =N=5,000.00/hammer 750,000 750,000
(v) Printing of 2,000 Hammering sheet booklets.(Security document) @ =N=550.00/booklet 1,100,000 1,200,000
(vi) Printing of 1,000 Permit sheet booklets @ =N=600.00/booklet 550,000 600,000
(vii) Purchase of Two Toyota Hilux double cabin 4-wheel Drive for patrol and enforcement on forest exploitation -do- 10e
3 Management of Areas invaded by Cocoa Farmers in the Forest Reserves
(i) One Toyota Hilux for patrol and enforcement On-going 5,000,000 5,000,000
(ii) One Toyota Hiace Bus
(iii) Diagnostic Treatment/Rehabilitation of 250ha of Cocoa degraded Forest land @ N50,000.00/ha. 10,500,000
4 State contribution to Federal Government/International Organization project On-going
(a) Sustainable Forest Management prescription by ATO/ITTO (Africa Timber Organisation/International Timber Trade Organization) to On-going
which Nigeria has just been admitted. 1,875,000
(b) Evasive Water weed integrated project
(i) Three (3) speed Boat for patrol on water 10,000,000
(ii) Forty (40) Life Jackets New 2,000,000
(iii) Forty (40) weed Racks new
(iv) Maintainance of the Speed Boat befor handing over to the Community Training for converging of water weed to organic fertilizer "
5 Edo State Monitoring Committee on Forestry
(i) 4 (Four) 4 - wheel Drive (Jeeps) 10,500,000 -
54
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: SOCIAL
SUB-SECTOR: HEALTH
HEAD: 456
55
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: SOCIAL
SUB-SECTOR: HEALTH
HEAD: 456
21 Integrated Maternal, Neonatal and Child Health (IMNCH) program New 7,500,000 10,000,000
22 Administration of free medical health care New
23 Logistics for revenue drive, supervision, and monitoring of private health facilities, food outlets New 5,000,000 10,897,179
and fumigation outfits, etc)
24 Purchase of Vehicle
(i) Ministry of Health for revenue drive inspection, suervision and monitoring private health New 12,000,000 15,000,000
facilities)
(ii) School of Health Technology (Coaster Bus) New 10,000,000 12,000,000
(iii) School of Nursing (Coaster Bus) New 10,000,000 12,000,000
(iv) School of Midwifery (Coaster Bus) New 10,000,000 12,000,000
(v) HMB: 3 Ambulance Vehicles for Hospital New 18,000,000 18,000,000
25 Provision of Digital X-Ray for Central Hospital, Auchi New 100,000,000 50,000,000
26 Provision of Internet Facility for HMB, Central Hospital (Benin, Auchi & Uromi, Ubiaja) and New 1,885,000 2,000,000
Stella Obasanjo Women & Children, benin City
27 Logistics for implmentation of National Health Insurance Scheme (NHIS) New 5,000,000 5,000,000
28 Renovation of State House Clinic, Govt. House New 5,000,000 10,000,000
29 Procurement of Rescue Ambulances (Benin -Auchi Rd; Benin Ore rd; Benin-Agbor) New 30,000,000 31,102,821
30 Procurement and installation of Oxygen Plants for Stella Obasanjo Hospitals, Benin City. 50,000,000
31 Construction and furnishing of School of Midwifery Hostels New 50,000,000 100,000,000
32 Mandatory Continuing Professional Development for Health Workers. New 50,000,000
33 Development and Fencing of the Herbal Garden at Obayantor to prevent encroachment a 5,000,000
encroachment and ensure availabiliy of .drugs yielding species.
TOTAL 2,710,885,000.00 324,859,191.27 3,928,000,000.00
56
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: SOCIAL
SUB-SECTOR: INFORMATION AND ORIENTATION
HEAD: 457A
4 Installation of Technical Equipment (purchase of OB Vans with Equipment and Studio Air-Conditioner Nonelinear Digital Computerised Editing 200,000,000 100,000,000
Suit at Aduwawa, etc)
b. Replacement of mast as Aduwawa/FM Feeder Cable
c. Provision of Airconditioners and computers for Studio Unit and Offices New - -
5 Development of Bendel Newspapers Company Limited (procurement of pre-press machine, vehicles, Kord machines, Newsprint Litho Machine, On-going 40,000,000 300,000,000
Vsat colour Lab Cutting/Sewing Machines etc)
6 Construction of Photographic Laboratory and Purchase of Colour Laboratory Equipment 12,000,000 50,000,000
9 Purchase of 2 nos 65 KVA Sound Proof Diesel Generator Plus Installation New - -
14 Renovation of Office Block including Resuscitation of Ivue and Ihevbe Relay Stations 39,000,000 -
TOTAL 472,024,355 18,950,000.00 623,100,000
57
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: SOCIAL
SUB-SECTOR: COMMUNITY DEVELOPMENT
HEAD : 457B
Sub- Details of Expenditure Status Approved Actual Approved
Head Appropriation Expenditure Appropriation
2011 Jan-June 2011 2012
N N N
7 Procurement of w orking tools for community dev elopment activ ities "
58
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
59
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
60
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
61
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ECONOMIC
SUB-SECTOR: TRANSPORT
HEAD: 459
8 Provision for Uniform / kits for 194 officers and V.I.O staff 3,500,000.00
12 Edo City Transport Servic: Provision for 2nd year Comprehensive Insurance 45,000,000.00
Premium on 100 Daewo Intracity Buses
13 Edo Transport Service (Edo Line): Provision for 8 (eight) Urban Buses 51,100,000.00
14 Edo Courier: Provision for New Haulage Trucks and Twenty Bikes 10,000,000.00
62
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
63
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SUB-SECTOR: Works (Roads)
HEAD: 461
Approved Appropriation
Sub- Actual Expenditure Approved
Details of Expenditure Status of Project Including Supplementary
Head Jan-Sept 2011 Appropriation 2012
2011
5.0 ESAN WEST
5.1 Ekpoma-Opoji-Ugbegun-Igueben Road, H.R.A. Overlay (19km) On-going -
5.2 Construction of Roads in Iruekpen On-going -
5.3 Ekpoma-Igoh-Emuhi-Ugbiyokho-Urohi Roads New 300,000,000.00 400,000,000.00
5.4 Ujeme-Ekpoma-Evorhakhua New 10e
5.5 Ujogba-Izogen Road New 10e
5.6 Egoronaoka-Uhiele-Ekpoma Junction New 50,000,000.00 -
5.7 Ogwa-Ugun-Amahor-Ebelle Road 150,000,000.00
6.0 ETSAKO CENTRAL
6.1 Ekperi-Anegbette- Road and bridge On-going 950,000,000.00 1,753,381,942.02 1,000,000,000.00
6.2 Agbede-Awain Road (48km) New 200,000,000.00
7.0 ETSAKO EAST
7.1 Ayogwiri-Apana-Imiegba-Imiakebu-Okpekpe-Igodor Road (31km) On-going 800,000,000.00 1,404,852,700.89 1,200,000,000.00
7.2 Ivhioghe-Igiode-Uzanu Road On-going 800,000,000.00 480,115,050.77 530,000,000.00
7.3 Okpella Township Road On-going 150,000,000.00 550,000,000.00
8.0 ETSAKO WEST
8.1 Jattu-Afowa-Iyora-Akpara-Ayogwiri Road (15.2km) On-going 600,000,000.00 1,377,744,340.16 100,000,000.00
8.2 Jattu-Ayua Road (7.4km) On-going 400,000,000.00 420,039,710.72 100,000,000.00
8.3 Jattu-Ibie Ogieneni Market Road (8km) On-going 400,000,000.00 371,562,783.32 300,000,000.00
8.4 Construction and Rehabilitation of Etsako West Township Roads (10km) 750,000,000.00 150,000,000.00
8.5 Dualization of Auchi-Jattu-Afashio-Ikabigbo-Ijio Road On-going 900,000,000.00 935,407,816.36 1,000,000,000.00
8.6 Iyamho-Iyora Road On-going 400,000,000.00 324,426,207.07 500,000,000.00
8.7 Ogbido-Ayoghena Road New 10e 100,000,000.00
8.8 Jagbe-Anwian Road 10e 400,000,000.00
8.9 Auchi-Warrake Road Dualization New 300,000,000.00
8.10 Iyekhe-Aviele Road New 500,000,000.00 300,000,000.00
8.11 Apana-Iraokho Road New 200,000,000.00
8.12 Ikholor-Ogbido Road New 100,000,000.00
64
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SUB-SECTOR: Works (Roads)
HEAD: 461
Approved Appropriation
Sub- Actual Expenditure Approved
Details of Expenditure Status of Project Including Supplementary
Head Jan-Sept 2011 Appropriation 2012
2011
8.13 Jattu/Iyeku Junction Road 10,000,000.00
8.14 Afowa/Elelel Road 10,000,000.00
8.15 Auchi Polythecnic Overhead Bridge 100,000,000.00
9.0 IGUEBEN
9.1 Igueben-Ebudin-Ujogba Road (19km) 50,000,000.00
9.2 Igueben-Udo Road & Ekehen Road On-going 400,000,000.00 236,386,498.65 200,000,000.00
9.3 Ring Road (Oyomo-Idumedo-Idumogbo-Uhe-Egbesan) 4km New
9.4 Ebele-Amahor-Ugun Road New 10,000,000.00 100,000,000.00
9.5 Okalo-Egbiki-Igueben Road New -
10.0 ORHIONMWON
10.1 Ogan-Idumwogo (18km) On-going 200,000,000.00 100,000,000.00
10.2 Evboe ghae -Ugo-Urhome he -Urhonigbe Road with
10.3 a. A spur at Ugbokhirima through Ugbugo to Benin-Abraka Rd
b. A spur at Urhomehe to Agbor-Abraka Road including Mission Road Urhonigbe – Total On-going 1,000,000,000.00 1,006,331,567.96 1,300,000,000.00
10.4
(62km)
10.5 Igbanke Township Roads 700,000,000.00
10.6 Evbuobanosa-Oza-Oghada-Igbanke Road (36km) 350,000,000.00 94,596,748.61 75,000,000.00
11.0 OVIA NORTH EAST
st
11.1 Ekiadolor-Okokhuo-Agekpanu-Uhen-Egbeta-Okada Road (26km) 1 Phase On-going
11.2 Uhen-Olumoye Road (18.6km) On-going 400,000,000.00 243,744,644.66 300,000,000.00
11.3 Okada-Iguobo-Ugbokun Road (22km) New 10e 100,000,000.00
11.4 Olumoye Bridge/Agekpanu/Ogbese Bridge 150,000,000.00
12.0 OVIA SOUTH WEST
12.1 Iguobazuwa-Umaza / Siluko Road (22km) 700,000,000.00 392,522,521.28 500,000,000.00
12.2 Okhomu-Igueze-Igueladibi-Iguelahor-Urehzen-Iguelahor-Obayantor Roads New 300,000,000.00
12.3 Benin-Iguobazuwa Road (Ovia River Bridge) 100,000,000.00
12.4 Udo/Nikorogha/Ofunama New 100,000,000.00
12.5 Old Ugbogui I - New Ugbogui Road New 10e
13.0 OWAN EAST
13.1 Ihieve-Sebe Ogbe Road (16.2km) On-going 200,000,000.00 50,000,000.00
13.2 Sebe-Ogbe-Otuo Road (18km) On-going 400,000,000.00 772,900,606.33 250,000,000.00
13.3 Ovbiomu-Igboa Road, Ovbiomu (0.35km) New
13.4 Ebese-Ubuneke-Usun-Ebese Road (6km) New
13.5 Warrake-Egienu Road New 50,000,000.00
14.0 OWAN WEST
14.1 Uhonmura-Eme-Afuze Road (with a bridge) New 400,000,000.00 200,000,000.00
14.2 Sabogida-Ora / Sobe Road (21km) New 100,000,000.00 10e
14.3 Erueh-Ikhin Road (6km) New 100,000,000.00 600,000,000.00
14.4 Okpuje-Okagben Road (9.8km) New 100,000,000.00
65
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
66
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
67
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
68
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
3 Purchase of Equipment
250,000,000.00
TOTAL 0 - 2,250,000,000.00
69
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: Social
SUB-SECTOR: Women Affairs and Social Development
HEAD: 460
3 Creche Nursery and Primary School; Furnishing/Equipping of of Classrooms; Science Laboratoratory and Library Block. do
7 Edo State Skills Acquisition Centre for the Elderly in Benin City do
10 Expansion of skills acqisition centre at Evbomudu in Edo South, Central and North Senatorial Districts On-going 23,000,000.00
11 Construction/Equipping of a Sheltered Workshop for the Physically Handicapped Persons in the 3 Senatorial Districts. New
20,802,185.00 30,000,000.00
12 Purchase of Emergency Relief Materials/distribution/social emergencies New
50,000,000.00 - 44,100,000.00
Procurement of items for HIV/AIDS/Social Economic
5,000,000.00
13 Construction/Equipping of a Children's Recreational Centre New
10e
14 Construction of Bill Boards on the Child Right Law in the 18 Local Government Councils New
10,000,000.00 5,000,000.00
15 Purchase of Office Equipment including furnishing New
10,000,000.00 5,000,000.00
Economic Investigation/Research Activities
5,000,000.00
16 Provision of two Vehicles (ToyotaHiace Bus & Toyota Hilux Pick-up Van) New 9,000,000.00
9,000,000.00
TOTAL 151,802,185.00 - 154,100,000.00
70
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: SOCIAL
SUB-SECTOR: YOUTH AND SPORTS
HEAD: 462
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan-Se pt 2011 Appropriation
abandone d, Ne w) 2011 2012
N N
1 STADIA DEVELOPMENT
i Ogbemudia Stadium, B/City (including provision of astro-turf synthetic grassing) On-going 80,000,000.00 65,000,000.00
ii Rehabilitation of Boreholes
Upgrading and Provision of Facilities
iii Construction of Hostel Block, Ogbemudia Stadium New
Construction of
iv Mini-Stadium, Irrua ) On-going
v “ “ Afuze } 100,000,000.00 50,000,000.00
v “ “ Abudu }
2 Sports Training for Bendel Insurance Football Club
Inneh Queens Female Football Club etc.
3 Sponsorship of sports competitions including overseas trips for all sporting activities On going 9,000,000.00 -
4 NYSC Orientation Camp, Okada:- Construction and Provision of Equipment On going 90,000,000.00 55,000,000.00
5 Edo State Youth Entre pre ne urship Proje ct:- Woodworks, Dress 15,000,000.00 10,000,000.00
Making, Making of Inverters, Fabrication of Household items Like Wielding Machine, Soap
Moulds, Food processing machine On- going
6 Sponsorship of Youth Exchange Programmes Including Overseas Trips On- going 2,000,000.00 -
7 Provision of Drugs and Medical Equipment for Sports Clinic On- going 2,000,000.00 2,000,000.00
8 Purchase of Office Equipment Furniture On - going 2,000,000.00 2,000,000.00
ii. First Aid Equipment
9 PROVISION OF SPORTS EQUIPMENT FOR STADIA
10 CONSTRUCTION/REHABILITATION OF BOREHOLES On-going
11 DEVELOPMENT OF SPORTS CENTRE, ETETE
i. Construction of Hostel Accommodation New
ii. Construction of Astro Turf Hockey Pitch New
12 Sponsorship of the National Sports Festival including Zonal On going
Elimination Competition
13 Construction and Provision of Equipment for:-
i Youth Centre, Uwelu } On going
ii Youth Centre, Iyamo }
iii “ “ Ewohimi } New
14 Purchase of Ve hicle s for Edo State Sports Council New
71
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ENVIRONMENTAL
SUB-SECTOR: OIL PRODUCING AREAS DEVELOPMENT
HEAD: 463
72
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
73
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
(vi) Purchase of two Ambulance/provision of equipment/ medicine for it on-going 10,000,000.00 10,000,000.00
(vii) Purchase of furniture and equipment for Government House Clinic New 0.00 10,000,000.00
(viii) Special Intervention Fund 1,000,000,000.00 520,000,000.00
(ix) ICT Provision 850,000,000.00 -
2 Public Private Partnership
i Project Development Fund 500,000,000.00
ii Office Furniture and Equipment 10,000,000.00
74
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Approve d
He ad (i.e . on-going, Appropriation Expe nditure Appropriation
abandone d, Ne w) 2011 Jan -Sept 2011 2012
N N N
2(I) Purchase of Office Furniture 10,000,000 10,000,000
(ii) Purchase of Office Equipment 5,000,000 5,000,000
(iii) Press Unit/Equipment 2,000,000 2,000,000
(iv) Radio Communication 3,000,000 3,000,000
(v) Security Equipment 15,000,000 20,000,000
75
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: ADMINISTRATION
SUB-SECTOR: OFFICE OF THE SECRETARY TO THE STATE GOVERNMENT
HEAD: 464
76
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
GENERAL ADMINISTRATION
DIRECTORATE OF CABINET, POLITICAL AND SPECIAL SERVICES
HEAD: 464
77
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
5(1) Acquisition of Video Camera – Panasonic NVGS 32, including Editing Card and DVD On-going 614,560 614,560.00
78
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
(iv) Purchase of rain coats and uniforms for motor drivers etc New 0 5,000,000
79
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
80
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
81
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan-Se pt 2011 Appropriation
abandone d, Ne w) 2011 2012
N N
9
i. Purchase of Office Furniture and On-going 2,000,000.00 0 4,000,000.00
Equipment
ii. Treasury Books and Identity Cards " 500,000.00 0 1,000,000.00
0
TOTAL 2,500,000.00 0 5,000,000.00
82
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan-Se pt 2011 Appropriation
abandone d, Ne w) 2011 2012
N N
10(i) Office Furniture and Equipment 3,500,000.00 - 10,000,000.00
on-going
iii General Economic & Statistical Studies & Surveys on-going 5,000,000.00 - 15,000,000.00
v Consultancy Services for the updating of the State Development Agenda Programmes and publication of on-going 15,000,000.00 - 100,000,000.00
Investment Opportunities in Edo State (TRAIN, Vision 20:2020, MTEF/MTSS etc)
Publication of stastistical Materials 2,500,000.00 - 5,000,000.00
vi
viii Office for the World bank Assisted State Governance & Capacity Building Project. (SGCBP) II 2,500,000.00 - 5,000,000.00
(a) Procurement of Office Equipment Including GPS, internet Facilities, Mapping Devices, Digital Cameras, 5,000,000.000
Public Address Systems, etc
(b) Production of IEC Materials, Bill boards, Jingles, Including Airing, to Communicate MDGs 2,000,000.000
83
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Approve d
He ad (i.e . on-going, Appropriation Expenditure Appropriation
abandone d, Ne w) 2011 Jan-Sept 2011 2012
N N N
84
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
85
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
iii Construction and Renovation of 30 Tax/Motor Licencing Offices in the 18 L.G.As. New 30,000,000.00 50,000,000.00
86
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
87
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
vi Law Publications
88
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: JUDICIARY
SUB-SECTOR: CUSTOMARY COURT OF APPEAL, EDO STATE
HEAD: 464…………………………...
Sub- Details of Expenditure Status of Projects Approved Actual Expenditure Approved
Head (i.e. on-going, Appropriation Jan-Sept 2011 Appropriation
Abandoned, New) 2011 2012
N N
16(1i) Furnishing of Offices, Conference room, Chambers and Court On-going 1,000,000.00 1,000,000.00
v Furnishing of Quarters for Judges and other Judicial Officers " 500,000.00 2,000,000.00
vi Provision of Computers for twenty-five Area Customary Courts in the State " 15,000,000.00
1ii Renovation and equipping of Customary Court of Appeal " 1,000,000.00 1,000,000.00
2 Extension, Renovation and Fencing of Area Customary Court Buildings " 1,000,000.00 2,000,000.00
3 Renovation of Area/District Customary Courts Quarters in Local Government Area " 2,000,000.00 1,250,000.00
6 Construction of Oredo Area Customary Courts III & IV, Benin City " 2,000,000.00 24,000,000.00
7 Construction of a Court Hall for Oredo Area Customary Court V, Benin City " 10,000,000.00 12,000,000.00
89
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR:GENERAL ADMINISTRATION
SUB-SECTOR: HIGH COURT OF JUSTICE
HEAD: 464
(xv iii) Prov ision of uniforms, raincoats & boots for driv ers, artisans, security men & 3,000,000.00 0 1,500,000.00
labourers.
(xix) Procurement of Walkie Talkie for Honourable Chief Judge's entourage. 1,000,000.00 0 1,000,000.00
(xx)
Purchase of v ehicles for 43 M agistrates and 26 President of Customary Courts 250,000,000
TOTAL 300,000,000.00 0.00 545,000,000.00
90
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan-Se pt 2011 Appropriation
abandone d, Ne w) 2011 2012
N N
18(1) Office furniture and equipment 3,500,000.00 - 3,500,000.00
On-going
2 Purchase of uniforms and raincoats. 50,000.00 - 50,000.00
New
3 Minor works. 1,450,000.00 - 2,150,000.00
New
4 Purchase of cars for Members and Secretary to the Commission. New 25,000,000.00
5 Building of Commission’s Secretariat within the High Court Complex. New 100,000,000.00
91
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan-Se pt 2011 Appropriation
abandone d, Ne w) 2011 2012
N N
19 I Computerisation of the Inspection/Monitoring Dept. and the New 24,678,000.00 2,000,000.00
92
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan-Se pt 2011 Appropriation
abandone d, Ne w) 2011 2012
N N
93
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan-Se pt 2011 Appropriation
abandone d, Ne w) 2011 2012
N N
21 i. Office Furniture and Equipment New 1,500,000.00 - 1,500,000.00
ii. First Aid Equipment New 300,000.00 300,000.00
Execution of the Ministry's Projects
iii. Purchase of 1 Toyota Hilux project monitoring vehicles Ditto
iv. Purchase of Saloon Cars (3 Nos.) Ditto
v. Reabilitation of existing Borehole, replacement of Water Pipes and Sanitary Ditto 10e 10e
Equipment
vi. Uniforms (Drivers, Cleaners) Ditto
vii. Electrical Installation and Equipment Ditto
viii. Purchase of Fire-proof Steel Cabinet and Adding Machine Ditto
ix. Purchase of Digital Video Equipment/Accessories Ditto
x. Purchase of Digital Photocamera/Accessories Ditto
xi. Economic Empowerment/Micro Credit Scheme for Women and Youths in Oil Ditto 3,000,000.00
Producing Communities
xii. Emergency Relief Measures for Oil Producing Communities Ditto 2,000,000.00 2,000,000.00
xiii. Collection of Data/Survey of Oil Wells in Edo State Ditto 1,500,000.00 1,500,000.00
xiv. Research and Publication Ditto 700,000.00 - 700,000.00
xv. Mineral Survey/Exploration of Metallic and Nonmetallic Minerals. Ditto 2,500,000.00 2,500,000.00
xvi. Solid Mineral Exhibition/Stakeholders Forum/Summit Ditto 2,500,000.00 2,500,000.00
xvii. Edo State Oil and Gas Summit Ditto - 3,000,000.00
TOTAL 14,000,000.00 - 14,000,000.00
94
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: OTHERS
SUB-SECTOR: OFFICE OF THE AUDITOR-GENERAL (STATE)
HEAD: 464
95
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan-Se pt 2011 Appropriation
abandone d, Ne w) 2011 2012
N N
23(1) Uniform New 850,000.00 0 850,000.00
2 Library New 950,000.00 0 950,000.00
3 Motor Vehicle New 20,000,000.00 0 20,000,000.00
4 Office Furniture New 5,000,000.00 0 5,000,000.00
5 Office Equipment New 5,000,000.00 0 5,000,000.00
6 Installation of AC etc New 2,000,000.00 0 500,000.00
7 Telephone Line/mini PABX New 500,000.00 0 500,000.00
8 Water and Toilet facilities New 1,000,000.00 0 1,000,000.00
9 Extension of Office block New 20,500,000.00 0 20,500,000.00
10 Drainage and flood control New 5,000,000.00 0 5,000,000.00
96
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan-Se pt 2011 Appropriation
abandone d, Ne w) 2010 2012
N N
464/24
1 Computerizing Civil Service Commission 0
3 Library 0
97
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan-Se pt 2011 Appropriation
abandone d, Ne w) 2011 2012
N N
25(i) Equipment/furnitures on-going 50,000,000.00 50,000,000.00
98
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR:GENERAL ADMINISTRATION
SUB-SECTOR: EDO STATE HOUSE OF ASSEMBLY SERVICE COMMISSION
HEAD: 464
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Appropriation Jan-Se pt 2011 Appropriation
abandone d, Ne w) 2011 2012
N N
26(i) Office Equipment and Furniture on-going 7,000,000.00 6,000,000.00
99
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
(ii) ICT Development (provision of internet facilities at the commission's headquarteers New 10,000,000.00
(vii) Procurement of Election Materials for the Conduct of Local Government Elections New 667,535,250.00 695,953,750.00
100
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
Sub- De tails of Expe nditure Status of Proje cts Approve d Actual Approve d
He ad (i.e . on-going, Appropriation Expenditure Appropriation
abandone d, Ne w) 2011 Jan-Sept 2011 2012
N N N
28
101
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
102
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
103
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
S ECTOR: ………GOVERNMENT HOUS E……………………………………………………………………
S UB-S ECTOR: ………DIRECTORATE OF INFORMATION AND COMMUNICATION TECHNOLOGY……
HEAD: …464………………………...
Sub- De tails of Expe nditure Status of Proje cts State of Approve d Actual Expe nditure Approve d
He ad (i.e . on-going, Comple tion of Appropriation Jan - Se pt 2011 Appropriation
abandone d, Ne w) Proje ct 2011 2012
31 (%) N N
2 SOFTWARE LICENCE:
MICROSOFT On going 70 20,000,000 17,212,382.32 22,400,000
ERP: FINANCIALS AND HUMAN CAPITAL On going 40 200,000,000 354,294,478.72 200,000,000
MANAGEMENT
VEHICLE REGISTRATION On going 0 10,000,000 0 12,800,000
DOCUWARE On going 60 10,000,000 0 9,600,000
TAX SOLUTION On going 15 86,000,000 1,950,000 150,000,000
ASSET MANAGEMENT On going 65 5,000,000 0 20,000,000
INFRASTRUCTURE
DATA CENTRE UPGRADE On going
I.SERVERS 4,000,000 1,697,652 12,800,000
ii.UPS 0 3,200,000
II.MAINTENANCE OF GENERATOR 1,500,000 464,075 5,120,000
III.DIESEL 6,000,000 4,756,500 6,400,000
V.SAT (MDA) 30,000,000 0 25,600,000
VOI P 15,000,000 0 9,600,000
VSAT TO LOCAL GOVT &HOSPITALS 55,500,000 0 35,200,000
ARCHITECTURE 6,000,000 0 3,840,000
FIBER CABLE 20,000,000 15,297,660 32,000,000
BANDWITH 50,000,000 49,350,000 50,000,000
LAN(MDA'S) 50,000,000 84,423,199.87 100,000,000
CONNECTIVITY(SWITCHES,ROUTERS AND RADIO) 14,600,000 1,610,000 12,800,000
GENERATOR 130KVA& STORAGE TANK 3,600,000 0 0
BACKUP SECURI TY 30,000,000 5,137,000 10,000,000
HARDWARE
PURCHASE OF DESKTOPS On going 40,000,000 23,000,000 30,000,000
PURCHASE OF LAPTOPS 30,000,000 0 19,200,000
GI S 0 0 6,400,000
SMART CARDS(LAMI NATE) 82,800,000 0 50,000,000
CARD READER 20,000,000 0 20,000,000
OTHER PROJECTS
BI OMETRI C(I NFORMAL SECTOR On going 48,000,000 1,488,700 64,000,000
CALL CENTRE 15,000,000
PROJECT MANAGEMENT OFFI CE 5,000,000 0 10,000,000
WEBSI TE DEVELOPMENT 2,800,000 1,014,950 10,000,000
EQUI PMENT SUPPORT AND ASSESSORI ES 5,000,000 0 6,400,000
OFFI CE FURNI TURE AND EQUI PMENT 5,000,000 2,814,500 25,000,000
PORTAL CABI N(40 FT) 1,000,000
TRAI NI NG (I NTERNAL) 16,000,000
TRAI NI NG (EXTERNAL) 20,000,000
TRAI NI NG CENTRE RENOVATI ON 800,000
TABLES & CHAI RS 1,000,000
POI NT OF SALE EQUI PMENT,POS ASSESSORI ES 10,000,000
COMPUTERS 3,200,000
TOTAL 850,000,000 977,360,000
104
EDO STATE GOVERNMENT
FY2012 BUDGET OF CONTINUITY
DETAILS OF CAPITAL EXPENDITURE
SECTOR: GENERAL ADMINISTRATION
SUB-SECTOR: GOVERNMENT COUNTERPART CASH CONTRIBUTION
HEAD: 465
Status of Proje cts Approve d Actual Approve d
Appropriation
Expenditure Appropriation
Sub- De tails of Expe nditure (i.e . On-going, Including Supplementary
He ad Abandone d, Ne w) 2011 Jan-Sept 2010 2012
N N N
1 Ministry of Agriculture:
i. FADAMAIII: 56,386,000 10e
ii. IFAD/NDC Community Based Natural Resource Management Programme 40,760,000 10e
iii. IITA Cassava Mosaic Disease (CMD) 18,600,000 18,000,000
iv. National Cocoa Development 5,000,000 5,000,000
v. ECOWAS Fund Fishery Project 10,000,000 10e
vi. National Programme For Food Security (NPFF) 42,770,000 20,000,000
vii. Root and Tuber Expansion Programme 8,500,000 10e
viii. Rural Finance Institution 12,000,000 10e
2 Office of the SSG:
i. HIV/AIDS/SACA ( World Bank Assisted) 20,000,000 10,000,000
iii. UNITAR 50,000,000 30,000,000
iv. Agency for Community Based Poverty Reduction (CPRD) 100,000,000 50,000,000
v. United Nations Development Prograqmme (UNDP) 1,000,000 1,000,000
vi. Counterpart for CGS-MDGs On-going 1,000,000,000 400,000,000
3 Ministry of Health
i. Health Syustem Dev. Project (World Bank and ADB-Assited) 20,000,000 20,000,000
ii. Community Health Insurance Scheme for MDG4/5 190,000,000
4 Min. of Budget, Planning & Economic Development
i. UNICEF 71,000,000 50,000,000
ii. Transforming Rural Areas in Nigeria (TRAIN) 15,000,000 5,000,000
iv. Edo State GCCC for World Bank Assisted SEFEOR Project 0 150,000,000
5 Ministry of Education: U.B.E On-going 2,600,000,000 1,745,000,000
i. Matching fund for TY Dajuma Foundation Educational Kits 0 10,000,000
6 Office of the Deputy Governor:
World Bank Assisted Community Based Urban Development Project 50,000,000 256,000,000
7 Ministry of Commerce and Industry
i. Nigeria Agricultural Cooperative and Rural Development Bank Limited On-going 5,000,000 5,000,000
ii. Counterpart Funding for SMEs and Commercial Hubs (including BoI Cooperation) New 250,000,000 50,000,000
Ministry of Energy and Water Resources
Matching Fund for Rural Water/Sanitation Project 30,000,000
8 Ministry of Environment and Transport: World Bank
Timber Organisation/Information Tinmber Trade Organization (ATO/ITTO) On-going 5,000,000 5,000,000
9 ICT Directorate: NDDC 150,000,000 55,000,000
10 Outstanding Arears/Contingencies 990,000,000 100,000,000
105