We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 22
UNIT FIVE: PROJECT PLANNING AND
PROJECT MANAGEMENT 4.1. Project planning • Project Planning is foreseeing with blue print towards some predicated goals or ends.
• Project plan is a skeleton which consists of bundle of
activities with its future prospects; it is a guided activity.
• It is a plan for which resources are allocated and
efforts are being made to commence the project with great amount of preplanning. CONT… • Need For Project Planning • To Completely define all work requested so that it will be readily identifiable to each project participant. Besides,
– To eliminate or reduce uncertainty
– To improve efficiency of the operation – To obtain a better understanding of the objectives – To provide a basis for monitoring and controlling work CONT… Functions of Project Planning
• It should provide a basis for organizing the work on the
project and allocating responsibilities to individuals.
• It is a means of communication and co-ordination
between all those involved in the project.
• It induces the people to look ahead.
• It instills a sense of urgency and time consciousness
• It establishes the basis for monitoring and control.
CONT… • In planning a project, the project manager must structure the work into small elements that are: – Manageable, – Independent, – Integrated and – Measurable in terms of progress.
• Project planning must be systematic and flexible
enough to handle unique activities, disciplined through reviews and control and capable of accepting multifunctional inputs. CONT… Tools of project planning and management techniques • These planning tools sometimes called Scheduling techniques for project implementation. • The most common scheduling techniques will be discussed as follows: i. Work break down ii. Ghantt chart iii. Network analysis. CONT… 1. Work breakdown structure (WBS) • The purpose of work breakdown structure (WBS) is to help plan effectively for a project by breaking key tasks or activities down in to more manageable and smaller units of work.
• WBS produces a detailed list of tasks to be
performed for a project, helping to deliver better costing, scheduling and resource planning for a project. CONT… • It is a convenient means of graphically presenting the work of the project in readily understandable format.
• The project key stages form the highest level
of the WBS, which is then used to show the detail at the lower levels of the project.
• The WBS does not show dependencies and is
not time based (no time scale on the drawing). • See the sample WBS in pp.63 CONT… 2. Gantt Charts • A time chart devised by Henry Gantt in 1917, an American engineer.
• A Gantt chart is a horizontal bar chart used for project scheduling.
• Each activity or task is depicted as a block over time; actual performance is
recorded in real time and compared to planned deadlines necessary for achieving completion.
• The use of Gantt Charts as a tool
• Can be used to plan time scale for a project
• Can be used to estimate resources required • Graphical illustration of a schedule of tasks to complete • Helps to plan, coordinate, and track specific tasks for a project • Good for small projects when the number of tasks or activities are small and not complex e.g. good for simple projects. CONT… Sample Gantt chart CONT… 3. Critical path analysis (CPA) or network analysis • Gantt charts are a poor time management tools when projects are lengthy and complex, can not display or indicate interdependencies in large projects .
• Network (or critical path) analysis can display more logically
the sequence and timing of each activity, they communicate interdependency and a more effective time management tool for large and complex projects.
The use of critical path analysis as a tool:
• Good visual communication and planning tool for effective time management CONT… • Displays clearly interdependent relationships that exist between the different activities or tasks to be completed • Arranges tasks or activities into an optimum sequence of events allowing a project to be completed in the most efficient time possible
• ̧Elapsed time (or estimated time) to complete the
project can be calculated.
• Highlights those activities which are critical activities’
e.g. those tasks which must be completed within their planned time otherwise the elapsed time (or estimated time) of the project will not be achieved. CONT… • Enables more effective resource planning, resources can be diverted away from non-critical to critical activities
• Highlight ‘float times for all activities e.g. the
amount of time an activity or task can slip past its planned completion time without delaying the elapsed time (or estimated time) of the project.
• All critical activities have a float time of zero,
because each must be completed within their planned completion time otherwise the elapsed time of the project wont be achieved. CONT… Process of critical path analysis • Break down project in to a logical sequence of activities to be completed • Estimate the time duration of each activity. • Arrange activities in the most efficient sequence of events and estimate the elapsed time of the project CONT… • The technique can be broken down into 3 stages: • 1. Planning: • Identify tasks and estimate duration of times; • Arrange in feasible sequence; • Draw diagram. • • 2. Scheduling: • Establish timetable of start and finish times. • • 3. Analysis: • Establish float; • Evaluate and revise as necessary. CONT… Example of an Activity Network
➢ Circles, representing events within the development lifecycle, such as
the start or completion of a task. ➢ lines, which represent the tasks themselves. Each task is additionally labeled by its time duration. ➢ The primary benefit is the identification of the critical path. ➢ The critical path = total time for activities on this path is greater than any other path through the network (delay in any task on the critical path leads to a delay in the project). CONT… CONT… To Produce the Diagram
• There is a single start and end event;
• Time flows from left to right • Events are given a unique number (activities then have a unique label i.e. head & tail event numbers); • The network can then be drawn taking into account the dependencies identified; • Working from the start event forward, calculate the earliest times, setting the earliest time (EET) of the first event to zero. • Add the job duration time to the earliest event time (EET) to arrive at the earliest time for the successor event. • Where the successor has more than one activity dependent on, the latest time is entered; CONT… • Workings from the finish event backwards, calculate the latest times (LET). • Set the latest time to the earliest time for the finish event. • Subtract job duration from the latest time to obtain predecessor latest event times. • Where the predecessor event has more than one arrow emanating from, it enter the earliest time; • Event slack(ES) is calculated by subtracting the earliest event time (EET) from the latest event time (LET); ES= LET-EET • Critical path(s) are obtained by joining the events with zero event slack (ES=0). CONT… • Example • Activity Durations (weeks) preceded by (dependent on) • A 5 -- • B 4 -- • C 3 B Interpretation A and B could start immediately, therefore can start on the same circle (Event). C must be preceded by B e.g. C cannot start until B has been completed. CONT… • Activity Durations (weeks) Preceded by (Dependent on) • A 5 -- • B 4 -- • C 3 A, B • Interpretation • Activity A and B could start immediately, on the same circle (Event). • C must be preceded by A and B e.g. C cannot start until A and B has been completed. CONT… Example 3 • Task preceded by) Duration • A - 3 • B - 6 • C - 3 • D A 5 • E C 2 • F B, D, E 6 • G A 9 CONT… • Interpretation • Activity A, B and C could start immediately; therefore, they can start on the same circle (Event). • D and G must be preceded by A; they can not start until A has been completed. • E must be preceded by C; E can not start until C has been completed and • F must be preceded by B, D and E. F can not start until B, D & E has been completed.