SAP PP Configuration Steps Linkedin
SAP PP Configuration Steps Linkedin
Purpose:
Steps:
Path: SAP Customizing Implementation Guide > Production > Basic Data
> Bill of Material > General Data > Define Material Types Allowed for BOM
Header
1 | SEDHUPATHY
o Define Allowed Material Types for BOM Items: Define the
material types in conjunction with BOM usages that are
allowed for the BOM items. You can make a generic entry in
the fields “BOM usg”, “Mat type headr”, and “Mtype BOM
item”.
Path: SAP Customizing Implementation Guide > Production > Basic Data
> Bill of Material > Item Data > Define Allowed Material Types for BOM
Items
2 | SEDHUPATHY
o Person Responsible for Work Center: Person responsible in
work center is a person who will maintain (Create, Change
work center) in SAP based upon the changes happening on the
Shop floor.
3 | SEDHUPATHY
o Parameters: Define parameters, which you then assign to
the standard value keys. You can assign any meaning to these
standard values. Please keep in mind that the meaning of the
fields is specified by the key words.
Path: SAP Customizing Implementation Guide > Production > Basic Data
> Master Data > Work Center > General Data > Standard Value > Define
Parameters
4 | SEDHUPATHY
Path: SAP Customizing Implementation Guide > Production > Basic
Data > Master Data >
Work Center > General Data > Standard Value > Define Standard
Value Key
o Define control key: The Control Key you can define Business
functions to be carried out with operation.
5 | SEDHUPATHY
Path: SAP Customizing Implementation Guide > Production > Basic
Data > Master Data > Work Center > Capacity Planning> Work
Center Formulas> Define formula parameters for work centers
•
o MRP Type: MRP type determines whether and how the
material is planned. This is maintained for each material at
plant level.
6 | SEDHUPATHY
o
MRP Controller: In this step, we define a number that is assigned to
the MRP controller. The MRP controller is a person or a group of persons
responsible for monitoring material availability. We can use the number
entered here, for example, to select the planning results per MRP
controller. Every material that is relevant to the planning run must be
assigned an MRP controller number in the material master record.
o MRP Groups: MRP groups are used when the plant division
for planning is not enough for the division of the different
materials MRP requirements. You assign different groups
according to the requirements to run MRP (different Settings).
These settings will be taken in account when you run MRP for
single item or total planning.
7 | SEDHUPATHY
o Lot Size Procedure: The system uses lot-sizing procedure within
materials planning to calculate the quantity to be procured or produced.
8 | SEDHUPATHY
o Scheduling Margin Key: The system uses this key to determine
the floats required for scheduling an order. The key is
maintained for the material at plant level.
9 | SEDHUPATHY
Path: SAP Customizing Implementation Guide > Production>Shop
Floor Control> Master
Data> Order> Define Order-Type-Dependent Parameters
Planning Tab:
Production versions:
Selection ID:
You can also select the task list type that you mandatorily want to be
selected in the order.
Routing Selection:
10 | SEDHUPATHY
This setting governs the selection method of Routings in the Order
and not the selection of routing types in the order.
Implementation Tab:
11 | SEDHUPATHY
Costing Tab:
12 | SEDHUPATHY
Display Profile Tab:
The final tab is the Display Profile tab that wants you to enter the
reporting profiles for collective orders and missing part list. You can
as well keep the standard profiles here.
13 | SEDHUPATHY
o
Production Scheduling Profile: In a production scheduling profile, we can
specify that in a production order particular business transaction are
carried out in parallel
Path: SAP Customizing Implementation Guide > Production>Shop
Floor Control> Master Data> Define Production Scheduling Profile
14 | SEDHUPATHY
o Production Supervisor: Define the production supervisors for your
plants. By assigning production supervisors to materials within the
application, you can define responsibilities for a material within
production activity control.
15 | SEDHUPATHY
o Order Type Confirmation Parameters: In this step, we define the
confirmation parameters for each plant and order type. Using
checks, you can define
• what happens when the sequence of operations is not
adhered during confirmation
• what happens when you want to confirm a larger
quantity than was confirmed for the preceding operation
• We can choose between a termination message, an
error message, a warning message, and an information
message.
• whether we want the total confirmed quantity of an
operation checked for under delivery or over delivery
tolerance in the order header
• What effect a QM result recording has on the
confirmation.
o whether dates (for example, posting date, end of lead time,
etc) should also be displayed with a date that is further in the
future than the time of creation
16 | SEDHUPATHY
Operations> Confirmation > Define Confirmation Parameters
17 | SEDHUPATHY