PS114912 LJS Hyd Spec 230113 Rev C1

Download as pdf or txt
Download as pdf or txt
You are on page 1of 124

HPI ON BEHALF OF PORT MORESBY GENERAL HOSPITAL

PORT MORESBY GENERAL HOSPITAL


CANCER CENTRE
HYDRAULIC SPECIFICATION

JAN 2023
PORT MORESBY GENERAL HOSPITAL
CANCER CENTRE
HYDRAULIC SPECIFICATION

HPI ON BEHALF OF PORT MORESBY GENERAL HOSPITAL

WSP
LEVEL 12, 900 ANN STREET
FORTITUDE VALLEY QLD 4006
GPO BOX 2907
BRISBANE QLD 4001

TEL: +61 7 3854 6200


FAX: +61 7 3854 6500
WSP.COM

REV DATE DETAILS

T1 19/12/19 80% DD Tender Issue

T2 28/01/20 Tender Issue

C1 20/04/20 Construction Issue

C2 10/10/22 Construction Issue

T1 28/10/22 Re-Tender for Brachytherapy Variation

C2 13/01/23 Construction Issue - Updated External Plantrooms

This document may contain confidential and legally privileged information, neither of which are intended to be waived, and must be used only for
its intended purpose. Any unauthorised copying, dissemination or use in any form or by any means other than by the addressee, is strictly
prohibited. If you have received this document in error or by any means other than as authorised addressee, please notify us immediately and we
will arrange for its return to us.

PS114912
SPECIFICATION
NAME DATE SIGNATURE

Prepared by: Reza Hadavandmirzai 13/01/23

Reviewed by: Jittu George 13/01/23

Approved by: Jesse Perkins 13/01/23

PAGE 3
TABLE OF 1 PROJECT INFORMATION ...............................................................1
General ........................................................................................... 1
CONTENT Project Team ................................................................................ 1
S The Project Description........................................................... 2

2 GENERAL REQUIREMENTS ........................................................ 3


General .......................................................................................... 3
2.1.1 Definitions ........................................................................................................................................ 3
2.1.2 Specification Objectives .......................................................................................................... 3
2.1.3 Design Intent.................................................................................................................................. 3
2.1.4 Discrepancies in Documents ............................................................................................. 4
2.1.5 Referenced Documents/Standards ............................................................................... 4

Quality Assurance ..................................................................... 4

Electromagnetic Compatibility ............................................ 6

Building Penetrations .............................................................. 6


2.4.1 Fire Resisting Building Elements ..................................................................................... 6
2.4.2 Non-Fire Resisting Building Elements .......................................................................... 6
2.4.3 Chases ................................................................................................................................................. 6
2.4.4 Limitations ....................................................................................................................................... 7

Required Submissions ............................................................. 7


2.5.1 Samples..............................................................................................................................................8

Materials, Equipment and Components............................ 9


2.6.1 General ............................................................................................................................................... 9
2.6.2 Finishes and Visual Elements.............................................................................................. 9
2.6.3 Manufacturers’ or Suppliers’ Recommendations ................................................ 10
2.6.4 Cleaning and Protection of Finished Work.............................................................. 10
2.6.5 Prohibited Materials ................................................................................................................ 10

Installation .................................................................................. 11
2.7.1 General .............................................................................................................................................. 11
2.7.2 Services/Utilities Connections ............................................................................................ 11
2.7.3 System Integration .................................................................................................................... 11
2.7.4 Setting Out Openings and Making Good .................................................................. 11
2.7.5 Works Programme and Time Chart .............................................................................. 11
2.7.6 Metalwork ....................................................................................................................................... 12
2.7.7 Fixing ................................................................................................................................................. 12

Co-ordination ............................................................................. 12
2.8.1 Co-ordination of Installation with Ceiling Tiles and Finishes ....................... 13

Safety in Design ........................................................................ 13


Existing Site ............................................................................... 14

3 PROJECT REQUIREMENTS AND


DESCRIPTION OF WORKS .........................................................15
General ......................................................................................... 15

Roles and Responsibilities..................................................... 15


3.2.1 Consultant Engineer ............................................................................................................... 15
3.2.2 Obligations of the Contractor ........................................................................................... 15
3.2.3 Contractor’s Design Responsibilities ............................................................................ 16
3.2.4 Alternative Products................................................................................................................ 17

Existing Services ...................................................................... 18

Staging or Sequencing of Works ....................................... 18

Description of Works ............................................................. 18


3.5.1 General ............................................................................................................................................. 19
3.5.2 Inter Services Works ............................................................................................................... 20

Shop Drawing and Construction Drawing


Requirements ........................................................................... 22

Site Provisions and Building Works in


Connection ................................................................................ 23
3.7.1 Building Works In Connection ........................................................................................ 23

Services Interface works .......................................................24

4 DESIGN AND PERFORMANCE CRITERIA .................... 27


General ........................................................................................ 27

Australian/New Zealand Standards & Code


(Hydraulic Services) ................................................................ 27

Seismic Restraints ................................................................... 29


4.3.1 Design Standard ....................................................................................................................... 29

Design Criteria .......................................................................... 29

Design Assumptions/Parameters ....................................... 31


5 PAINTING, PROTECTION AND
IDENTIFICATION ................................................................................33
General Requirements ........................................................... 33

Submissions .............................................................................. 33

Corrosion Protection ..............................................................34


5.3.1 General ............................................................................................................................................ 34
5.3.2 Protection for Steel Surfaces ............................................................................................ 34
5.3.3 Protection for NON-FERROUS Metallic Surfaces ................................................ 35

Painting ...................................................................................... 36
5.4.1 Low VOC ......................................................................................................................................... 36
5.4.2 Preparation of Surfaces ........................................................................................................ 36
5.4.3 Application .................................................................................................................................... 36
5.4.4 Finishing ......................................................................................................................................... 37

Colours ........................................................................................ 37

Identification and Labelling ................................................. 37


5.6.1 General ............................................................................................................................................ 37
5.6.2 Labelling Requirements ...................................................................................................... 38

6 INSPECTION, TESTING, COMMISSIONING,


HANDOVER AND DEFECTS LIABILITY
PERIOD ..................................................................................................... 39
General ........................................................................................ 39
6.1.1 Design .............................................................................................................................................. 39
6.1.2 STANDARDS AND GUIDELINES ...................................................................................... 39
6.1.3 Practical Completion Requirements ........................................................................... 39

Practical Completion Requirements ............................... 40

Management of Inspection, Testing,


Commissioning, Handover and Defects
Liability Period Commitments ............................................ 41
6.3.1 General ............................................................................................................................................. 41
6.3.2 Sequence of Activities ............................................................................................................ 41
6.3.3 Submissions ................................................................................................................................. 43
6.3.4 Inspection and Test Plans ................................................................................................... 43
6.3.5 Commissioning instrumentation ................................................................................. 44
6.3.6 Commissioning personnel ................................................................................................ 44
Testing and Commissioning ............................................... 44
6.4.1 Pre-Energisation Tests ......................................................................................................... 44
6.4.2 Tests.................................................................................................................................................. 44
6.4.3 Pre- Commissioning TESTS ...............................................................................................46
6.4.4 Commissioning .......................................................................................................................... 47

Final Contract and Handover Documentation ............. 48


6.5.1 General Requirements......................................................................................................... 48
6.5.2 As Built Drawings .................................................................................................................... 48
6.5.3 Operating and Maintenance Manuals .......................................................................49
6.5.4 Warranties ..................................................................................................................................... 53
6.5.5 Required Operating Instructions ................................................................................... 53
6.5.6 Training of Principal’s Nominated Personnel ........................................................ 53
6.5.7 Spare Parts Schedule ............................................................................................................. 54

Post Practical Completion and Defects Liability


Period ..........................................................................................54
6.6.1 Warranty and Defects Liability ........................................................................................ 54
6.6.2 General DLP Maintenance Scope .................................................................................. 54
6.6.3 Final Completion ...................................................................................................................... 55
6.6.4 Submissions ................................................................................................................................. 55
6.6.5 DLP Preventative Maintenance and Testing ......................................................... 56

7 SEWER DRAINAGE SYSTEMS................................................ 58


General ........................................................................................ 58

8 SANITARY PLUMBING SYSTEM............................................ 59


General ........................................................................................ 59

Fixture Traps ............................................................................. 59

Insulation of Cold Waste Piping......................................... 59

9 STORMWATER DRAINAGE & DOWNPIPE


SYSTEMS ................................................................................................... 61
General .........................................................................................61

Sub-Soil Drains ..........................................................................61

10 DOMESTIC COLD WATER SYSTEMS................................ 62


General ........................................................................................ 62
Concrete Cold Water Storage Tank .................................. 62

Flushing & Cleaning ................................................................ 63

Backflow Prevention .............................................................. 63

11 DOMESTIC HOT WATER & WARM WATER


SERVICES.................................................................................................64
General ....................................................................................... 64

Hot Water Heaters ................................................................. 64

Flues ............................................................................................ 64

Backflow Prevention .............................................................. 65

Thermal Insulation .................................................................. 65

Regulators .................................................................................. 65

12 NATURAL GAS..................................................................................... 66
General ........................................................................................66

Gas – Systems Shut Off ..........................................................66

Valve Boxes ...............................................................................66

Wall Boxes ................................................................................. 67

Gas Services Risers.................................................................. 67

Gas Vertical Pipe Support Systems ................................... 67

13 EXCAVATION........................................................................................ 68
General ........................................................................................68

Backfilling of Trenches ..........................................................68

Sand for Bedding (Sewer Pipe)...........................................68

Use of Concrete (Sewer Pipes)............................................68

PITS (GAS SERVICES) ..............................................................68

Pits (Stormwater) ....................................................................68

Warning Tapes .........................................................................69


14 TANKS ........................................................................................................ 70
Water Storage Tanks .............................................................70

15 MATERIALS ..............................................................................................71
Considerations for Materials Engineering .......................71

Materials and Workmanship ................................................71

Concrete ......................................................................................71

Covers and Frames ..................................................................71

Trench Grates and Sumps .....................................................71

Fixings ......................................................................................... 72

Flexible Connections .............................................................. 72

Flanges ........................................................................................ 72

Galvanising ................................................................................ 72

Unions.......................................................................................... 72

Valves .......................................................................................... 72

Reflux Valves ............................................................................. 73

Balancing Valves ..................................................................... 73

Pressure Limiting Valves ...................................................... 73

Ball Valves .................................................................................. 73

Thermostatic Mixing Valves ................................................ 73

Sluice Valves ............................................................................ 74

Strainers..................................................................................... 74

Copper and Brass Tubes And Fittings ............................. 74

Stainless Steel Pipes And Fittings .................................... 74

Galvanised Steel Pipes And Fittings ................................ 74

PVC Pipes and Fittings ......................................................... 74

PE Pipes and Fittings ............................................................. 75

PE-X Pipes and Fittings ......................................................... 75

PPR Pipes and Fittings .......................................................... 75


Polybutylene Hot and Cold Water Pipework ................ 75

Jointing ....................................................................................... 76

Expansion ................................................................................... 76

Temperature Gauges ............................................................. 77

Pressure Gauges ...................................................................... 77

THERMAL Insulation Materials ............................................ 77

Pressure Switches ................................................................... 77

Acoustic Treatment to Pipework ....................................... 77

Protective Pipe Wrapping/Coating................................... 77

Roof Penetration Flashings .................................................78

Cold Water Meters ..................................................................78

Valve Boxes ...............................................................................78

Concrete Thrust Blocks .........................................................78

Backflow Prevention Valves ................................................78

16 PUMPS....................................................................................................... 79
Domestic Cold Water Booster & Pressure
Pumps ......................................................................................... 79
16.1.1 Pumps to Comply with the following Requirements ...................................... 79
16.1.2 Control Panel ............................................................................................................................... 79

Hot Water Circulating Pumps ............................................. 79


16.2.1 Pumps to Comply with the following Requirements ...................................... 79
16.2.2 Control Panel .............................................................................................................................. 80

Pump Control Panels ............................................................ 80


16.3.1 Functions ...................................................................................................................................... 80
16.3.2 Control Panels – Construction .......................................................................................... 81
16.3.3 Equipment .................................................................................................................................... 82
16.3.4 Labelling ......................................................................................................................................... 82
16.3.5 Testing ............................................................................................................................................. 82

Tank Water Level Controls ................................................... 82

Flexible Pump Couplings ...................................................... 83

Pump Mountings ..................................................................... 83


17 PIPING, VALVES AND FITTINGS ...........................................84
General ....................................................................................... 84

Dimensions on Site ................................................................ 84

Fixture and Fixture Points ................................................... 84

Pipes in Slab ............................................................................. 84

Setting Out ............................................................................... 84

General Piping Installation Requirements ..................... 85

Support and Fixing of Pipework ........................................86

Building Expansion Joints ....................................................86

Joints in Copper Piping .........................................................87

Joints in Copper Piping – Press Fit ....................................87


17.10.1 Water ................................................................................................................................................ 87
17.10.2 Gas ...................................................................................................................................................... 87

Chasing and Drilling ...............................................................87

Concealing ................................................................................ 88

Grades ........................................................................................ 88

Cover Plates ............................................................................. 88

Capping Off .............................................................................. 88

Chrome Plating ....................................................................... 88

Steel ............................................................................................ 88
17.17.1 Pipes ..................................................................................................................................................88
17.17.2 Joints ................................................................................................................................................. 89
17.17.3 Connections ................................................................................................................................. 89
17.17.4 Bends ................................................................................................................................................ 89
17.17.5 Branches ........................................................................................................................................ 89
17.17.6 Reducers.........................................................................................................................................90

Copper ........................................................................................ 90
17.18.1 Pipes ..................................................................................................................................................90
17.18.2 Joints .................................................................................................................................................90
17.18.3 Connections .................................................................................................................................. 91
17.18.4 Bends ................................................................................................................................................. 91
17.18.5 Reducers.......................................................................................................................................... 91

JAN 2023
Stainless Steel ............................................................................91
17.19.1 Pipes ................................................................................................................................................... 91
17.19.2 Joints .................................................................................................................................................. 91
17.19.3 Bends ................................................................................................................................................ 92
17.19.4 Reducers......................................................................................................................................... 92

ABS and UPVC .......................................................................... 92


17.20.1 Pipes .................................................................................................................................................. 92
17.20.2 Joints ................................................................................................................................................. 92
17.20.3 Bends & Branches .................................................................................................................... 93

Valves & Fittings ...................................................................... 93


17.21.1 General Requirements.......................................................................................................... 93
17.21.2 Water Services Valves & Fittings .................................................................................... 93
17.21.3 Natural Gas Towns Gas and LPG Valves .................................................................... 97

Flow measuring Devices ....................................................... 97

Gauges & Instrument Fittings ............................................. 97

Installation .................................................................................98
17.24.1 Arrangement ............................................................................................................................... 98
17.24.2 Pipework Supports and Anchors ................................................................................... 98
17.24.3 Vibration Isolators ..................................................................................................................100
17.24.4 Pipe expansion and Contraction..................................................................................100
17.24.5 Pipe Penetrations ...................................................................................................................100

Testing of Pipework .............................................................. 101

18 NOISE AND VIBRATION............................................................ 102


General Requirements ......................................................... 102

Vibration Control ................................................................... 102


18.2.1 Acceptance Criteria............................................................................................................... 102
18.2.2 Spring Mounts .......................................................................................................................... 102
18.2.3 Neoprene Pads......................................................................................................................... 102
18.2.4 Anti-Vibration Hangers....................................................................................................... 103

Noise Measurements............................................................ 103

Vibration Measurements .................................................... 103

19 SCHEDULES........................................................................................104
General ...................................................................................... 104

JAN 2023
Schedule of Equipment ....................................................... 104

Schedule of Valves ................................................................ 107

Schedule of Stormwater Pits and Outlets .................... 108

Schedule of floor drains ...................................................... 108

Schedule of insulation ......................................................... 109

Schedule of Pipe Materials ................................................. 109

Schedule of Tapware and Fixtures .................................... 111

Schedule of Boiling Water Units ........................................ 111


1 PROJECT INFORMATION
GENERAL
The project is the construction and integration of the new Cancer Care Centre (CCC) at the existing Port Moresby
General Hospital.
The project delivery being traditional lump sum tender has been adopted for this project. This Technical specification
is to be read in conjunction with other tender documents issued by the Project Manager including:

— Conditions of Tender

— Conditions of Contract

— Contract Preliminaries

This Specification is a technical specification and for the purpose of this Technical Specification, Works shall mean all
works or work as described in this Specification and associated drawings

PROJECT TEAM
The Project Team includes the following team members:

PRINCIPAL/CLIENT Dr Paki Molumi


(CEO Port Moresby General Hospital)

PROJECT MANAGER Owen Korawali

(PM Port Moresby General Hospital)

CONTRACTOR The company who undertakes the Works

ARCHITECT Health Projects International (HPI)

CONSULTANT ENGINEER (MECHANICAL, WSP


ELECTRICAL, FIRE PROTECTION, AND
HYDRAULICS)

STRUCTURAL ENGINEER Stocks and Partners

FIRE SAFETY ENGINEER TBA

BUILDING SURVEYOR Client to confirm

SUSTAINABILITY CONSULTANT TBA

ACOUSTIC ENGINEER TBA

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 1
1118/1.05
THE PROJECT DESCRIPTION
GENERAL DESCRIPTION
The new Port Moresby Cancer Centre (PMCC) plays an important role in providing the country with access to more
cancer treatment which will include some of the most advanced radiotherapy system with a new Linac and Halycon
machine.
The purpose of the PMCC is to provide further access to cancer care treatment for the country. The service available at
the PMCC will include:

— Outpatient clinics,

— Medical day treatment,

— Clinical support,

— Nuclear medicine,

— Patient holding/recovery,

— Treatment bunkers, and

— Staff areas

The project site involves the part demolition of an existing building adjacent to the Walter Strong Wing. The new
works, in relation to the new PMCC, includes the construction of a new 2 story building with dedicated entry and
connection link to existing Walter Strong Wing. The project is limited to the fitout of the ground floor space only,
while level 1 will remain shell and core for future fitout later.
Dedicated services plant space is located above the treatment bunkers and in external plant areas directly adjacent to
the new PMCC building. A new central plant compound will also be constructed as part of this project to house
centralised Chilled Water Generation plant, Fire Sprinkler & Hydrant tank and pumps. All major services connections
will either be new or be provided from existing infrastructure.

LOCATION
Port Moresby General Hospital, Port Moresby, Papua New GuineaUTILITIES
The following utilities are relevant for this project;
1 NCDC PP - Ms Amanda [email protected] Phone 324 0691
2 Electricity- PNG Power Limited (PPL): Piki Ravusiro Ph: +675 324 3492
3 Water – Eda Ranu: Edea Loa, Development Engineer [email protected] +675 750 10287
4 Telecommunications - Telikom PNG Limited: Joyce Warpin +675 300 4197
5 Fire Authority - PNG Fire: Mr Kili Koiro, [email protected] +675 312 2735

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 2
1118/1.05
2 GENERAL REQUIREMENTS
GENERAL
2.1.1 DEFINITIONS
Unless the context otherwise requires, the following definitions apply:
Supply: ‘Supply’, ‘furnish’ and similar expressions mean ‘supply only’.
Provide: ‘Provide’ and similar expressions mean ‘supply, deliver and install’ and include all testing, commissioning,
tuning, interfaces etc.
Proprietary: ‘Proprietary’ means identifiable by naming manufacturer, supplier, installer, trade name, brand name,
and catalogue or reference number.
Samples: Includes samples and prototypes.
Zinc-coated steel: Includes zinc-coated steel, zinc/iron alloy-coated steel and aluminium/zinc-coated steel.

2.1.2 SPECIFICATION OBJECTIVES


The intent of this Specification is to:
1 Provide a basis for competitive tendering for suitably qualified tenderers.
2 Allow competent Contractors to price the works.
3 Provide a clear statement of technical and performance requirements against which compliance can be assessed.
4 Provide documentation required by Authorities to demonstrate design compliance with statutory requirements
for the purpose of building permit application.
5 Provide documentation detailing the scope and quality of the project for the purpose of Client’s confirmation of
compliance to the Client’s project brief.
6 Define the requirements of the Contractor with respect to Quality Assurance.
7 Define the scope of services including project management, installation engineering, testing commissioning,
maintenance and documentation to be provided.
8 Specify the technical requirements of the Installation.
9 The Specification relies upon the Contractor having the necessary specialist services resources to complete the
detailed design, testing and commissioning of the installation in accordance with the design intent and the
requirements of the specification and drawings.

2.1.3 DESIGN INTENT


1 Intent: The Contract documents are intended to call for complete, operational systems. Provide all items (major
and minor), equipment, accessories and incidental work required for the completion of the installation and to
ensure full integration.
2 Diagrammatic layouts: Layouts of service lines, plant and equipment shown on the drawings are diagrammatic
only, except where figured dimensions are provided or calculable. Before commencing work, inspect the site,
obtain all necessary measurements and information.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 3
1118/1.05
2.1.4 DISCREPANCIES IN DOCUMENTS
Give immediate notice in case of any ambiguity, discrepancy or inconsistency in the Contract document. Should
conflict arise between the requirements of specification, drawings, mandatory requirements, standards including
Standards Australia Codes, then the higher standard or most stringent requirements shall prevail and shall be deemed
to have been included in the Contract. The Contract’s order of documents precedence is not intended and shall not be
applicable in this case.
Any ambiguities or discrepancies with the Design Requirements, Technical Requirements and / or Contract Drawings
are to be highlighted at tender stage for clarification.
The Contractor is to review the tender documents, including other services, the architectural drawings, both general
and detailed and satisfy themselves that the spatial allowances made for hydraulic services are adequate for the
purposes of installing, testing and commissioning the works.
Any consequences of the Contractor’s failure to advise the project manager, including any costs associated with
relocation or modification to any area, shall be at the Contractor's risk

2.1.5 REFERENCED DOCUMENTS/STANDARDS


Use referenced documents/standards which are editions, with amendments, current 3 months before the closing date
for tenders, except where other editions or amendments are required by Statutory Authorities.

QUALITY ASSURANCE
1 Provide a Quality Assurance plan in order to propose, establish, maintain, monitor and document a quality
assurance system covering all aspects of the design, purchase, fabrication, installation and completion of the
works. The plan shall be in accordance with ISO 9001./.2 (as appropriate).
2 Designate a Project Quality Inspector to discharge the quality plan, which must include the following minimum:
3 Inspect the installation works regularly and provide installation defects reports on regular basis in order to
systematically reduce the incidences of installation defects. Submit copy of such defects lists to the Consultant
Engineer upon request. This task can be delegated to qualified site foreman if applicable.
4 Check and sign off all shop drawings (including all third-party shop drawings) for conformance to requirements
prior to submission. All such documents shall list all non-conformances with the Specification and Drawings.
5 Check and sign off equipment compliance schedule against the particular Specification requirements and
equipment schedules prior to submission. All such documents shall list all non-conformances with the
Specification and Drawings.
6 Check and sign off all samples for conformance to requirements prior to submission. All such documents shall list
all non-conformances with the Specification and Drawings.
7 Check all tests required for proper manufacturing of the equipment.
8 Check and sign off all manufactured items for compliance prior to dispatch to site.
9 Check and sign off installation of all items under this Specification and Drawings. Provide signed off installation
ITPs for every elements of installation (minimum floor by floor and/or for every individual area up to 1000sqm
whichever is smaller).
10 Check all materials, welding, joining, terminations, fixing and finishes.
11 Check and sign off all associated ITPs for all on-site tests required to commission the works.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 4
1118/1.05
12 Check and sign off operating and maintenance manuals to ensure they contain adequate information to permit
systems to be operated by the Client at the end of defects liability period. (Including adequate training and tuition
of the nominated Client’s representative).
13 Check and sign off all associated integrated ITPs for all integrated on-site tests required to commission the works
and to be carried out by various systems.
14 All trades works including sub trades works shall form part of overall QA and required to have their ITPs, Shop
drawings, technical submissions signed off also by the Project Quality Inspector. This sign off represent all
required checking that these works are consistent and compliant with the rest of the works.
15 Submit the following documentation:
a Quality System third party certification, if any, to the Standards specified by the Joint Accreditation System of
Australia and New Zealand.
b Quality manual detailing, corporate Q.A. policy statement, system element description, register of procedures
and project specific ITPs.
16 Notice:
a Inspect witness points: If notice for inspection is to be given in respect of parts of the works, advise if and
when those parts are to be concealed. Inspect and provide signed off installation ITPs indicating appropriate
methods of installation been carried out.
b Inspection hold points: If notice of inspection is to be given in respect of parts of the works, do not conceal
those parts without approval.
c Minimum notice for inspections to be made: 4 hours for inspections full time on-site, otherwise 2 working
days for on-site inspections, and 5 working days for local pre-delivery inspections.
d Concealed services: Give notice so that inspection may be made of services to be concealed. Irrespective of
Consultant Engineer inspection, inspect the works, sign off relevant ITPs and highlight any noncompliance
and/or defects.
17 Witness tests: Give sufficient notice so that designated tests may be witnessed.
a Minimum notice for tests to be witnessed is 5 working days for site tests; and 10 working days for local pre-
delivery tests.
b Test hold points: Do not carry out designated tests without approval.
18 Testing Authorities:
a General: Except for Site Tests, have type tests carried out by authorities accredited by NATA to test in the
relevant field, or an approved organisation outside Australia recognised by NATA through a mutual
recognition agreement. Co-operate as required with testing authorities.
b Site tests: Use instruments calibrated by authorities accredited by NATA.
19 Reports:
a General: Submit copies of test reports, including certificates for type tests, showing the observations and
results of tests and compliance or non-compliance with requirements.
b Submit Installation Defects Reports carried out on regular basis to the Consultant Engineer upon request.
20 Concealment:
a If tests are to be carried out on parts of the work, do not conceal those parts and do not commence further
work on those parts until the tests have been satisfactorily completed and compliance verified.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 5
1118/1.05
ELECTROMAGNETIC COMPATIBILITY
1 Comply with Australian Communications Authority requirements for electrical and electronics products to limit
electromagnetic interference (EMI).
2 Emissions:
a Passive products with C-tick or Regulatory Compliance Mark (RCM) to AS/NZS 4417.3, marking of electrical
products to indicate compliance with regulations – Specific requirements for electromagnetic compatibility
regulatory applications.
3 Immunity:
a Electrical and electronic apparatus: To AS/NZS 4252.1, Electromagnetic compatibility – Generic immunity
standard – Residential, commercial and light industry (EN 50082-1), or
b EN 5008-2, Electromagnetic compatibility – Generic immunity standard – Industrial environment.
4 Harmonics and Voltage Surges:
a Levels of emissions to be acceptable to the electricity distribution code. Keep the THDI current to 5%
maximum for all individual components/equipment and at least to that level at the first supplying control
panel for all components/equipment connected to the switchboard. Provide active harmonic filters within
the component, or respective control panel. Do not rely on the external harmonic filters to be installed on the
Main Switchboard(s).

BUILDING PENETRATIONS
2.4.1 FIRE RESISTING BUILDING ELEMENTS
1 Seal penetrations to comply with NCC using a system to AS 4072.1, Components for the protection of openings in
fire-resistant separating elements – Services penetrations and control joints.
2 Comply with Section 3 of AS/NZS 1668:1, Fire and Smoke control in Multi Compartment Buildings.
3 AS4072.1 and AS1851 shall be complied with in as-built documentation to identify all fire and smoke containment
compartment walls and barriers. To satisfy specific identification requirements to AS4072.1, permanently fixed
labelling, tagging and signage of all passive fire and smoke containment systems must be provided for on-site
identification. Fire stopping barriers and penetrations shall comply in particular with reference to a service label
affixed adjacent to each fire stop barrier and service penetration (or close proximity group) as detailed in
AS4072.1 and AS1851. This as-built provision amongst other as-built documentation and manuals is essential as
part of handing over process of the project.

2.4.2 NON-FIRE RESISTING BUILDING ELEMENTS


1 Seal penetrations around conduits and sleeves. Seal around cables within sleeves. If the building element is
weatherproof, acoustic rated or subject to pressure, maintain the rating. Acoustically seal penetrations through
plantroom walls and floors.

2.4.3 CHASES
1 Cut, drill and chase as necessary, where possible avoiding finished work. Where chasing of finished work is
essential, make good all damage to the original standards of the finishes.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 6
1118/1.05
2.4.4 LIMITATIONS
1 General: Do not penetrate, or chase the following without approval:
2 Structural building elements including external walls, core walls, fire walls, floor slabs, beams or columns.
3 Acoustic barriers.
4 Other building services.
5 Membrane elements including damp-proof courses, waterproofing membranes and roof coverings.
6 Membranes: If approval is given to penetrate membranes, provide a waterproof seal between the membrane and
the penetrating compound.

REQUIRED SUBMISSIONS
1 Provide in good time to allow review without impediment to the programme, including possible amendment and
resubmission: -
a Copies of correspondence and notes of meetings with Authorities.
b Documents showing approval of the Authorities whose requirements may apply to the work.
c Certified schedule of compliance for all plant and equipment, prior to placing orders.
d Factory test results where applicable.
e All product data, performance test and commissioning results required by this Specification.
f Shop drawings for fabrication and installation of all equipment and items supplied.
g Manufacturer’s product data for equipment, materials, components and systems including:
i Technical specifications and drawings.
ii Size, arrangement, operating and maintenance clearances.
iii Operating weight.
iv Type test reports.
v Performance and rating curves or tables marked with each selection showing for both duty point and for
part load conditions the capacity; the energy consumption and power factor; and the sound power level.
vi Motor power requirements (both full load and starting).
vii Control details.
viii Recommendations for installation and maintenance.
ix Evidence of compliance with specified product certification schemes.
h Inspection, test and commissioning plans for every section of the works. Detail:
i The procedure of how to complete the task.
ii The skill or competency of the person undertaking the works.
iii The review or testing procedure to assure satisfactory completion of the task.
iv The person within the Works Package’s organisation authorised to sign-off the task as accepted.
i Client handover/training proposals.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 7
1118/1.05
j Record and installation drawings: Record all changes to equipment and services layouts, wiring and any other
items during the construction period, which may have been incorporated into these works.
k Operating and Maintenance manuals.
l Maintenance/service records during the defects liability period.
2 Give notice before commencing work affected by the submissions, unless the submissions have been reviewed
with no exception taken.
3 Do not commence production of equipment, materials, components of equipment, components or systems until
submission has been reviewed with no exception taken.
4 Maintain and submit monthly a schedule of shop drawings and submissions to identify all proposed drawings and
submissions designated in the following categories:
a Accepted.
b Submitted, awaiting acceptance (with submission date and revision number).
c Not yet submitted.
5 Submit electronically (PDF or alternative agreed format).
6 Identify the project, Works Package, supplier/manufacturer, applicable product name, product number, included
product options, and relevant specification references.
7 Where selected equipment or systems do not fully comply with this Specification and associated documents,
submit details of proposed deviations for acceptance. Where such deviations require any changes to the
structure, building works or services, these shall be provided by the Contractor without variation to the Contract.
Apart from deviations listed, it will be taken that the materials and equipment proposed meets with all other
specified requirements. Review of equipment and materials is undertaken on this basis, and that non-complying
equipment/materials may be rejected at any time – even if already installed.
8 Submit amended documents as appropriate, highlighting changes since the previous submission.

2.5.1 SAMPLES

TIMING
1 Co-ordinate submissions of samples as listed in the Schedules. Do not cause delays by making late submissions or
submitting inadequate samples.

QUANTITY
1 Submit a sample of each designated item and 2 copies of supporting documentation. Include ancillary items such
as fasteners and mounting brackets. Amend and resubmit samples which are not accepted.

IDENTIFICATION
1 Identify the project, Contractor, their agents or supplier, manufacturer, applicable product, model number and
options, as appropriate and include pertinent Specification references.
2 Include service connection requirements and product certification.
3 Identify non-compliances with project requirements, and characteristics that may be detrimental to successful
performance of the completed work.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 8
1118/1.05
SAMPLE ACCEPTANCE AND RETENTION
1 Do not commence work affected by samples until the samples have been accepted. Submit further samples as
necessary.
2 Keep approved samples in good condition on site, until Practical Completion.
3 Incorporate in the works samples, which have been approved for incorporation. Do not incorporate other
samples.
4 Installed items will match accepted samples throughout the works.

MATERIALS, EQUIPMENT AND COMPONENTS


2.6.1 GENERAL
1 Provide new materials, equipment and components shall be new, of good quality and fit for purpose, selected for a
reasonable service life. Do not provide without approval products that are obsolete, discontinued or about to be
discontinued.
2 Identification of a proprietary item does not necessarily imply exclusive preference for the item so identified, but
indicates a deemed to comply item.
3 Manufacturers: Provide equipment and associated accessories which are the products of established
manufacturers regularly engaged in the manufacture of such equipment, who issue comprehensive rating data
and certified test data on their products.
4 Consistency: For the whole quantity of each material or product use the same manufacturer or source and provide
consistent type, size, quality and appearance.
5 Safety: Provide all necessary safety devices for the protection of personnel against injury and the protection of
plant and equipment against damage including relief valves, belt guards, safety railing, and effective earthing of
electrical components, electrical interlocks, warning lights, and signs, alarms and local lighting. Provide
permanent lifting eyes for equipment exceeding 40kg.
6 General: Select, if no selection is given, and transport, deliver, store, handle, protect, finish, adjust, prepare for
use, and use manufactured items in accordance with the current written recommendations and instructions of the
manufacturer or supplier.
7 Instructions: Submit the recommendations and instructions, and advise of conflicts with other requirements.
8 Project modifications: Advise of activities that supplement, or are contrary to, manufacturers or suppliers’ written
recommendations and instructions.
9 Product certification: If products must comply with product certification schemes, use them in accordance with
the certification requirements.
10 Provide permanently fixed plates indicating manufacturer, model, serial number, capacity and electrical data for
all equipment. Lettering height: 5mm maximum, 1.5mm minimum.
11 Provide materials or products are supplied by the manufacturer in closed or sealed containers

2.6.2 FINISHES AND VISUAL ELEMENTS


1 Surfaces shall be flat and free of noticeable distortion, warping and twisting.
2 Edges and corners accessible to users dressed to avoid cutting if touched.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 9
1118/1.05
3 Pressings shall be accurate in dimension and profile to ensure consistent mating and clearance gaps and pressing
shape.
4 Mating surfaces between adjacent pressings - flush and accurate to produce smooth distortion free joint.
5 Provide protection against damage until Practical Completion.
6 Surface shall be clean, undamaged and free of stains

2.6.3 MANUFACTURERS’ OR SUPPLIERS’ RECOMMENDATIONS


1 General: Select, if no selection is given, and transport, deliver, store, handle, protect, finish, adjust, prepare for
use, and use manufactured items in accordance with the current written recommendations and instructions of the
manufacturer or supplier.
2 Instructions: Submit the recommendations and instructions, and advise of conflicts with other requirements.
3 Project modifications: Advise of activities that supplement, or are contrary to, manufacturers or suppliers’ written
recommendations and instructions.
4 Product certification: If products must comply with product certification schemes, use them in accordance with
the certification requirements.

2.6.4 CLEANING AND PROTECTION OF FINISHED WORK


During handling and installation of work at the site, clean and protect work in progress and adjoining work. Apply
suitable protective covering on newly installed work where required to ensure freedom from damage or deterioration
at a time of Completion; otherwise, clean and perform maintenance on newly installed work as frequently as necessary
throughout remainder of construction period. Adjust and lubricate operable components to ensure operation without
damaging effects.

2.6.5 PROHIBITED MATERIALS


1 Do not use any of the following materials:
a Lead where the metal or its corrosion products may be directly ingested, inhaled or absorbed, or any lead-
based paints or primers.
b Chromate paint pigment or chromate water treatment.
c Urea formaldehyde foam or materials which may release formaldehyde in quantities which may be hazardous
or irritant.
d Synthetic mineral fibres except in accordance with Worksafe Australia National Standard and National Code
of Practice.
e Materials in which chlorofluorocarbons, hydrochlorofluorocarbons or hexa-fluoroacetones have been used as
a blowing agent.
f Chlorofluorocarbons.
g Polychlorinated biphenyls.
h Other substances generally known to be deleterious to health or safety or which would adversely affect the
works.
i Any that would be contrary to achievement of a required project Green Star or other sustainability rating.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 10
1118/1.05
INSTALLATION
2.7.1 GENERAL
1 General: Carry out the work in a proper and workmanlike manner.
2 Arrangement: Install equipment and services parallel or perpendicular to building elements. Organise reticulated
services neatly. Provide for movement in both structure and service. Under suspended ground floors, keep
services at least 150mm clear above ground surface, additional to insulation.
3 Movement and expansion: Provide expansion facilities in ductwork, piping, cables, cable trays and supports to
accommodate thermal expansion and movement at structural expansion joints.
4 Protection: Protect equipment from weather and the ingress of dirt, moisture, vandalism and tampering.
5 Access: Provide access to all components requiring entry, inspection or maintenance.
6 If interruptions to supply of any service are required co-ordinate the shutdowns to the satisfaction of the
Superintendent, advise the occupants, minimise inconvenience, and advise when supply is reinstated. Arrange
shutdowns out of hours.

2.7.2 SERVICES/UTILITIES CONNECTIONS


1 If the utility provider elects to perform or supply part of the works, make the necessary arrangements. Install
equipment supplied, but not installed, by the utility provider.
2 Connect to utility provider services or service points. Excavate to locate and expose connection points. On
completion reinstate the surfaces and facilities which have been disturbed. Pay connection charges.

2.7.3 SYSTEM INTEGRATION


1 Interconnect system elements so that the installations perform their designated functions.

2.7.4 SETTING OUT OPENINGS AND MAKING GOOD


1 The Specification Drawings are diagrammatic only and unless otherwise stated shall not be used for determining
the precise positions of equipment outlets and like features. The exact location of these shall be determined on
site and/or from shop drawings.
2 All chases, ducts, recesses and penetrations in structural elements not shown on the building and structural
drawings shall be subject to approval.
3 Provide the precise location of all openings, fixings and similar items of work required for these works.
4 Determine requirements at such times as not to cause delay to the work.
5 Check all items to ensure correct positioning.
6 Wrongly located or omitted openings, fixings and similar items of work resulting from incorrect or lack of inter
trade coordination shall be remedied and paid for under these works.

2.7.5 WORKS PROGRAMME AND TIME CHART


1 Sufficient information of construction phase activities shall be provided to enable preparation of a detailed
construction programme incorporating activities of every trades.
2 The programme of work shall be arranged in consultation with all Trades and the installation shall be completed
according to the agreed programme.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 11
1118/1.05
3 The Works programme shall clearly show the start and completion dates with the typical activities listed below.
The list is indicative.
a Submission of shop drawings and major technical submissions.
b Shop fabrication
c Ordering of plant and materials.
d Delivery of plant and materials.
e Erection, testing and painting/identification of pipework/cable trays/ conduits/ducts in false ceilings.
f Erection of duct and pipe risers and installation of electrical wiring in vertical building risers before building
riser walls are completed and closed.
g Permanent power connection.
h Commencement of fitting offs and final terminations.
i Authorities acceptance tests.
j Commencement of testing.
k Commencement and Completion of plant commissioning.

2.7.6 METALWORK
1 General: Use metalwork capable of transmitting the loads imposed, and sufficient to ensure the rigidity of the
assembly without causing deflection or distortion of finished surfaces. Construct to prevent rattle and nuisance.
2 Metal separation: Prevent contact between electrolytically dissimilar metals, by using concealed insertion layers.
3 Edges and surfaces: Keep clean, neat and free from burrs and indentations. Remove sharp edges.

2.7.7 FIXING
1 Fix all plant to structure in approved manner, either directly or via secondary structure as required. Submit
details of types of fixings, locations and loads for approval.
2 Fix only light weight items to non-structural building elements.
3 Do not pierce waterproof roofs, floors or walls with fixings.
4 Fasteners to comply with appropriate Australian / New Zealand Standards.
5 Use proprietary corrosion resistant fasteners capable of transmitting the loads imposed, and sufficient to ensure
the rigidity of the assembly. Use metal expansion bolts for concrete and masonry. Do not use explosive charge
fixings without approval.
6 Corrosion protection: Use corrosion resistant, chemically and electrolytically compatible fasteners. Provide
insulating spacers where necessary.

CO-ORDINATION
Comprehensive co-ordination of all services and associated building work form part of the Works.
These responsibilities shall include:
1 Co-ordination of the works as required.
2 Management of the advance procurement of equipment to meet programme.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 12
1118/1.05
3 Co-ordination of in-ground and in-ceiling services routes, including trenching, trays and pipework.
4 Management of the preparation and approval of fully co-ordinated drawings including penetration drawings.
5 Management of services testing and commissioning
6 Ensuring provision of all test results and required certifications to obtain Certificate of Occupancy from the
relevant Building Surveyor.
During the construction period the works require that a competent supervisor is provided on site responsible for the
comprehensive co-ordination of all engineering services, including civil, structural, electrical, mechanical, hydraulics,
fire and lift services.
Responsibility for the proper direction, supervision, control and co-ordination of the work forms part of the works and
shall assist all other trades in every way possible in meeting this responsibility.
All services shall be thoroughly co-ordinated prior to installation. Should work proceed without co-ordination being
undertaken and authorisation by those with such responsibility and should other trades subsequently not be able to
effectively proceed with their respective installation, the work initially undertaken shall be removed and reinstalled at
the expense of the Contractor.
Any claims for additional costs or delays due to the lack of effective co-ordination by the various trades will be
rejected.
Arrange and co-ordinate all interconnection testing with other services systems, e.g. fire mode tests, power failure
testing, etc.

2.8.1 CO-ORDINATION OF INSTALLATION WITH CEILING TILES AND


FINISHES
Co-ordination shall be carried out to ensure that all building and services elements such as air ducts, outlets and light
fittings, sprinklers, speakers and other ceiling elements are installed in a co-ordinated manner, such that all services
can be connected and maintained as indicated on the Architectural Reflected Ceiling Plans.

SAFETY IN DESIGN
Safety in Design risk management shall form an integral part of these works and shall conform to the requirements of
the Workplace Health and Safety (WHS) Act 2011 & WHS Regulations 2011.
The Safety in Design process shall conform to the State-relevant Compliance and Guidance documentation.
General principles of risk management to be followed shall be as AS/NZS ISO 31000 (2009) Risk Management –
Principles and Guidelines.
The National Standard for Construction Work (NOHSC:1016) shall be used to align design risk management practice
with construction risk management practice.
The Safety in Design Risk Assessment shall include but not be limited to:
1 Understand the range of work activities associated with the intended use of the building / structure as a work
place.
2 Identify hazards, assess risks (quantify and rank), identify control measures, implement control measures, review
and prepare risk register prior to construction of work. Monitor and review throughout construction and
operation. The process includes review and acknowledgement of residual risks identified and communicated by
the designer as defined by the WHS Act and Regulations.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 13
1118/1.05
3 Elimination or where this is not reasonable practicable, minimisation of any risk to health and safety of any
person. The process includes, recommendation of design alternatives that will eliminate / reduce risks,
recommendation of control measures for residual risks; organising participate and facilitating Safety in Design
workshops as required.
4 Report in writing, on health and safety aspects and risks of the design identified. Implementation of control
measures which shall be monitored and reviewed throughout construction and operation.
5 Provide at the conclusion of the project all residual risk information, in the form of a Safety in Design File and the
related instruction and training as required to ensure an understanding of the safety aspects of the installation.
Where local regulatory practice differs from the above the more onerous shall be used as the basis for compliance.

EXISTING SITE
With the submission of their tender the Contractor shall be deemed to have familiarised themselves with any as-built
documentation, visited the site to ascertain any latent conditions and be fully conversant with the conditions and
restrictions pertaining to, including but not limited to any local Authority requirements, in order to be able to provide
the all items relating to the works.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 14
1118/1.05
3 PROJECT REQUIREMENTS AND
DESCRIPTION OF WORKS
GENERAL
Unless varied by Specification Addenda, the requirements set out below in this section are mandatory and no
deviation is permitted.
List and allow in your tender form all the items called in and listed in this section. No deviation from requirements of
this section is permitted unless approved by Superintendent in writings during the tender process.

ROLES AND RESPONSIBILITIES


3.2.1 CONSULTANT ENGINEER
During the construction phase the Consultant Engineer’s role is:
1 Analysis of schedule of technical data and alternatives offered.
2 Review of shop drawings for the purpose of establishing compliance with design intent.
3 Review of samples for the purpose of establishing compliance with the Specification.
4 Periodic review of the progress of the works on the site, noting any observations with respect to quality of the
installation or materials used.
5 Issue of any clarification (Consultants Advice) required to interpret the Specification and Drawings.
6 Prepare and issue Consultants Advice if required to amend the Specification and or Drawings
7 Accompanied by the Contractor’s representative, randomly inspect and verify test records achieved by witnessing
Contractor’s test demonstrations.
8 Review and with attendance by the Contractor’s representative, random commissioning data achieved by
witnessing Contractor’s test demonstrations.
9 Inspect the works at Practical Completion
10 Review Client training proposals.
11 Review ‘As Installed’, and operating and maintenance documents.
12 Review maintenance records during the defects liability period.
13 Inspect the works at the end of defects liability period.

3.2.2 OBLIGATIONS OF THE CONTRACTOR


1 In writing this Technical Specification the Client expects and relies upon the Contractor to provide its own
personnel and its trades possessing specialist trade expertise necessary to complete the works in accordance with
this Technical Specification and Drawings which form part of the overall Contract documentation.
2 In addition, the Contractor has the following obligations:
a To raise in good time, issues requiring design input or clarification from the Consultant Engineer, particularly

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 15
1118/1.05
in respect to:
i interpretation of the Specification or drawings;
ii problems in complying with the Specification together with suggested alternative/substitutions;
iii matters in the Contractor’s opinion, are omissions not discovered during the tender process, together
with suggested alternatives/substitutions
b To allow the design verification costs of the Consultant Engineer when suggesting alternatives and departures
from this Technical Specification and accompanying Drawings.
c To certify compliance with Authority requirements.
d To pay all fees applicable to the works.
e To obtain all Authority permits and certificates to allow the progress of the work.
f To provide manufacturer’s and construction drawings of sufficient detail to allow proper fabrication, co-
ordination and installation and a scale not less than 1:50; incorporating all post-tender changes to
architectural and structural drawings.
g To provide samples and prototypes where specified.
h To provide manufacturer’s factory test records (type tests and witnessed tests) and site installation inspection
and sign-off certifying that the completed installation comply with the manufacturer’s installation guidelines
and requirements
i To provide the completed Services installation that is fully and correctly commissioned and fine-tuned and,
that is functional and operable efficiently in compliance with all requirements of this Technical Specification.
j To provide copies of all monthly/ quarterly maintenance and servicing reports required to the Consultant
Engineer.
k To certify compliance with Contract documents, including all variation instructions, at Practical Completion

3.2.3 CONTRACTOR’S DESIGN RESPONSIBILITIES


1 Specifically, for specialist services trades, the Contractor shall be responsible for the detailed design activities
listed below, as these activities are considered to be normally undertaken through the custom and practice of the
industry.
2 The Contractor shall be responsible for ensuring that the detailed design undertaken is fully co-ordinated and
compatible with the remainder of the project design.
3 Check space requirements of equipment and services which are indicated diagrammatically in the Contract
documents. Select equipment with dimensions to suit the available space.
4 Lay out equipment and services to be accessible for operation, maintenance and replacement and so as not to
interfere with access to other installations. Make offsets as necessary.
5 Set out access ways 2.1m high and 1.0m wide (minimum) to all major plant clear of all obstructions, unless
otherwise approved.
6 Co-ordinate the layout of plant and services with the building layout and structure, and with other plant and
services.
7 Neatly group services, with separate layers for crossing services.
8 Interface details with other trades.
9 Size and location of penetrations in walls and floors.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 16
1118/1.05
10 Physical co-ordination of installation with other trades.
11 Provision of electrical loads to electrical trade and compare with design loads cable sizes and circuit protection
devices, seeking design direction where discrepancies occur.
12 Co-ordination of the construction of the installation.
13 Details of electrical wiring and control diagrams of all equipment supplied showing all interconnections between
equipment to enable the necessary wiring to be undertaken.
14 Thermal expansion accommodation and anchorage, including provision of bellows or bends, taking into account
final installation details and consistent with specified requirements.
15 Mounting, support and fixing details, and fasteners, including any secondary structure which may be required.
16 Cable installation details and derating factors.
17 Settings for protection equipment, time delays, time switches etc.
18 Capacity, location, design and sizing of cable support, trunking and conduit systems.
19 Acoustic design or modification of actual selected equipment that may require change, to meet with the noise
levels specified. Such change to approval of the Consultant Engineer. Specified levels to be achieved with all plant
operating.
20 Selection of all anti-vibration mountings to suit the particular application of the mounts
21 Valve, damper and access locations.
22 System water capacities and chemical additives.
23 Final locations of control sensors, detectors, thermostats, switches, outlets.
24 Calculate system resistances to fluid flow based upon the actual plant layout and selected equipment. Allow for
dirty filters and diversified flows. Allow for standby plant and future demand as shown.
25 Amend piping, fans, pumps, motors and electrical power supplies to suit the requirements of the actual
installation. Submit amended selections for review. Comply with the stricter of the NCC Section J maximum power
ratings and those in the Schedules.
26 Calculate cable rating and voltage drops based upon actual cable lengths and selected make of cables. Allow for
standby plant and future demand as shown. Take into consideration installation conditions, and external
influences short-circuit fault levels and ratings of protection equipment.

3.2.4 ALTERNATIVE PRODUCTS


Should the part of the work be proposed to be done quicker, better or more effectively by substitution of materials or
methods other than those specified, the details of such substitutions or alternatives shall be included in the Tender,
including a comprehensive Report including any performance and life cycle analysis in support of the proposals.
Where the words ‘equal or approved’ are used in this Technical Specification, permission may be requested to use a
substitute for what is specified, provided it and the relevant manufacturer of the item certify in writing that the
substitute is of equal, or better quality and effectiveness to that specified.
Submit for approval full details to allow verification that the alternative products comply with the Contract
Documents. Provide a certificate for each alternate product confirming that the proposed alternative product
complies with the contract documents. Include all compliance and non-compliance items related to Project Brief,
Specifications and Contract Drawings. State if use of proposed alternatives will necessitate alteration to other parts of
the works and include consequential costs.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 17
1118/1.05
1 Allow for additional work resulting from the utilisation of an approved alternative product, including additional
or revised statutory approvals, changes to adjacent work, re-submission of shop drawings and any costs incurred
by the Consultant Engineer in assessing such alternative products. Allow for Consultant Engineer Review cost
based on agreed Market hourly rates. These sums are to be paid irrespective of the alternatives being selected or
not.
Proposals for substitution must include details of:
1 Changes to adjacent work, if any.
2 Cost differences.
3 Life cycle cost differences
4 Quality differences and advantage to the Client.
5 Lead time and program changes.
6 Certificate of compliance.

EXISTING SERVICES
Obtain full information regarding all existing services, including, but not limited to, water, sewer, stormwater,
electrical and telephone - wherever new piping is to be installed.
At time of design “as constructed” drawings were not available. Contractor to investigate existing services on site to
ensure the design as shown is achievable.
Pay any and all costs involved in making good any service damage while excavating, installing or backfilling for any
service noted herein. Investigate for exact location, depth and size of all existing services prior to any installation
being carried out.
Existing services shall be maintained and operational until new works are installed. Allow tracing services as
necessary to determine if services shown or found are ‘live’ and performing connection to new services with the
minimum of downtime. All disconnections and shut downs shall be approved prior to work being commenced.
Where existing branch lines are located and are not shown on the drawings or ‘As Constructed’ drawing (available at
request from the Superintendent) allow to trace and make connection to new services or cap off as appropriate.
Existing services shown on drawings have been documented based upon existing records. The accuracy of location and
size etc shall be verified by the contractor prior to commencement of works.

STAGING OR SEQUENCING OF WORKS


Allow to stage works as directed by the superintendant and/or project manager. Allow for submission of plumbing
approvals to match any separable portion handovers so as not to impede the certificate of classification process.
Existing services shall be maintained and kept operational until new works are installed. Allow for all temporary
services to maintain continuity of services throughout the project as necessary

DESCRIPTION OF WORKS
Whether or not particular works are described in the Technical Specification all items and materials needed for the
complete works are required and shall be installed unless clearly excluded.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 18
1118/1.05
The project includes the detailed design, supply, delivery, installation, commissioning, tuning, testing, placing into
service, maintenance, warranty and defects liability of materials, labour and plant of the services systems in
accordance with this Technical Specification. All components and systems shall be complete in every respect and
tested and commissioned unless otherwise noted specifically.

3.5.1 GENERAL
1 Allow to decommission, make safe and remove any existing redundant services to be deleted within the area of
works.
2 Site visit and familiarization with the site conditions and scope of work required under this contract and making
required allowances to complete the works.
3 All necessary negotiations including formal submissions as required with all Authorities/utilities having
jurisdiction including obtaining of design approval and final certification of the installed systems by an
independent certifier approved by the Authority. Payment of all fees associated with the authorities/utilities
connections and permits for the installation.
4 Provision of detailed safety in design analysis and ensure the installation is in compliance with the Site’s safety in
design proposal including all regulatory requirements.
5 Allow for all requirements in relation to alternatives proposed for the project. Allow for Consultant Engineer
review cost based on agreed market hourly rates. These sums are to be paid irrespective of the alternatives being
selected or not.
6 Collaboration and working with Mechanical Trade who is responsible for the management and coordination of
overall services shop drawing process including providing timely input into the process to allow fully coordinated
shop drawing production for all services Active engagement and provision of nominated staff for input into the
multidisciplinary coordination workshops in relation to shop drawing production as well as onsite installation
methodology and integrated commissioning of multi-disciplinary interfaces
7 Coordinate with the Electrical trade and advise final equipment selections and their power requirements prior to
their ordering and installation of submains to respective switchboard to ensure correct submain cable selections-
Submains cabling from the MSB is provided to the primary mechanical/Hydraulic/Lift switchboards. Provide all
lugs, cable glands and gland plates for the Electrical trades so they can terminate the cabling and do the final
connection to your respective switchboard. Any submains/sub circuit to secondary switchboards/control panels
shall be included in the respective services (Mechanical, Hydraulics, Fire, Civil, Vertical Transportation) works
8 Provision of QA plan including inspection, testing, commissioning ITPs for all systems installed.
9 Preparation of “For Construction” and “Shop Drawings” coordinated with other services prior to commencement
of works including services layouts at the same scale as the design drawings.
10 Provision of all samples and technical submissions. Samples include:
a Basins
b Water Closets
c Tapware
d Longitudinal Trench grates.
e Rainwater outlets
f Inspection point covers
g Floor grates
h Acoustic and Thermal insulation along with appropriate ESD certification.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 19
1118/1.05
i In wall tundishes
11 Identification and coordination of penetrations, provision of fire/smoke sleeves and sealing of all wall, floor,
ceiling penetrations to the required fire/smoke/acoustic rating.
12 Provision of vibration isolation for all rotating equipment.
13 Provision of seismic restraints, including design.
14 Provision of all painting and finishes including identification and labelling schedules,
15 Provision of As-Built drawings and O&M Manuals in compliance with a uniform overall Site Services
Documentation System.
16 Preparation and supply of complete and detailed Operating and Maintenance Manuals which include all
commissioning data in both hard and soft copy format. Ensure Operation and Maintenance Manuals clearly
indicate on an individual equipment basis a schedule of maintenance routines, inspections, preventative
maintenance procedures, test surveys and records conducted on the fire and smoke protections systems installed
as outlined in AS1851. Generic type procedures / inspections are not acceptable.
17 Provision of all training for staff in the operation and preventative maintenance of the systems. Training of the
nominated building facility management staff to the level of understanding of day by day operation of the services
systems.
18 Twelve (12) months statutory testing, servicing, maintenance, defect liability and warranty of all services
systems/equipment installed under this contract from the date of Practical Completion.
19 Fine tuning commissioning of all systems during the defects liability period as per Green Star/NABERS
requirements. The tuning shall involve inspection, check and all adjustments of all systems and controls every
three (3) months after the date of Practical Completion. Detailed final recommissioning of all systems shall be
carried out at the end of the defect liability period.

3.5.2 INTER SERVICES WORKS


1 Provision of open end tundishes for all mechanical equipment waste. Tundishes shall be chrome plated where
exposed and to comply with “Materials” section.
2 Provision of floor drainage in mechanical/fire/chiller plant rooms
3 Provision all downstream (of the primary hydraulic distribution board/control panel) power and control wiring
associated with each hydraulic services
4 Provision of a complete sanitary drainage and plumbing system including connection to the existing sewer mains
connection, pipes, junctions, bends, pits, floor wastes, excavation, supports, backfilling, testing and sundry
equipment required for the installation. Coordination shall be carried out prior to any setting out, excavation and
pipe installation taking place
5 Provision of a complete stormwater drainage system including connection to stormwater connection provisions
and all necessary pipes, junctions, bends, pits, floor wastes, excavation, supports, backfilling, testing and sundry
equipment required for the installation. Note: In ground stormwater is not shown on Hydraulic drawings (not
part of scope), this forms part of the Civil scope.
6 Supply and fix the taps and faucets specified in the “Materials” section or as selected by the Architect
7 Provision of a complete domestic cold water system including all fixtures, fittings and faucets requiring domestic
cold water. Include for all pipework, bends, offsets, brackets, pumps, taps and faucets and sundry equipment
required for the installation.
8 Provision of a complete domestic hot water services system including all piping, fittings, supports, insulation, hot
water heaters, valves, circulating pumps and other sundry items of equipment required for the installation. The
PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 20
1118/1.05
hot water system shall consist of a flow and return system from the hot water plant. The hot water is to be
circulated at 65°C. Thermostatic mixing valves will be located in all other areas to maintain the water at 50°C or
43°C
9 Supply and install a hot water circulating pump to the requirements as specified in the “Pumping” and
“Materials” sections
10 Supply and install thermostatic mixing valves to all personal hygiene fixtures, as indicated on the drawings, to
manufacturers requirements and in accordance with the local authorities requirements. Valves shall be set to
43°C.
11 Provision of a new dilution pit with concrete infill gas tight gatic lids as indicated on drawings. The Dilution Pit
shall comply with the requirements in the “Materials” section.
12 Supply and fix concrete 36,000 litre water storage tank and fittings including the supply and installation of all
puddle flanges, sludge drains, overflows and filling valves all to comply to the local regulations. All tank sections
are to be flushed out with clean water before being brought into service. Provide the “puddle-pieces” fabricated
from MP52 approved pipe with flanged ends. Additionally, provide a dimensioned drawing indicating the exact
location of all items to suit main works program. Supply and install a non-PVC, food grade lining and test the tank
installation for a potable supply
13 Provision of a complete gas reticulation system including gas bottles, meters, regulators, filters, pipework and
sundry items to comply to the local gas authorities’ regulations. Provide a system of piping to supply medium /
low pressure (7.0 / 3.0 kPa) natural gas from the authority meter location, and reticulate through the building to
the hot water heaters, and associated wiring etc. required to form a fully functional authority approved system.
14 Services infrastructure-Sewer: The site has frontage to the following Council sewer mains:
a 150mm sewer main.
b All sanitary fixtures will drain via gravity to connect to the existing sanitary drainage on the property.
c Civil Engineer to make application to Local Authority for all new sewer connections if required, and
permission to connect to existing infrastructure.
15 Services infrastructure-Water: The site has frontage to the following Council water mains:
a Existing 150mm water main.
b A new 150mm domestic capped water and fire service will extend to the new Cancer Centre, from the existing
water main.
c Civil Engineer to make application to Local Authority for new 150mm water meter and water service
extension and permission to connect to existing infrastructure.
16 Services infrastructure-Stormwater:
a New storm water reticulation and property connection services will be provided under the Civil
infrastructure works.
17 Arrange for the local Gas Authority to supply and install an appropriate natural gas meter assembly complete with
an automatic shutdown valve, high pressure connection point for hot water plant.
18 The following site connections are to be made:
a Connection to new capped 150mm domestic/fire water service within the site.
b Connection to existing 150mm sewer connection within the property.
c Connection to Civil stormwater services within the site.
d Connection to the new gas storage vessels
PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 21
1118/1.05
SHOP DRAWING AND CONSTRUCTION DRAWING
REQUIREMENTS
Prepare and submit dimensioned drawings showing details of the fabrication, layout and installation of all plant and
equipment, including relationship to building structure and other services.
Prepare and submit drawings of penetrations and “built-in” components in the same form and manner as described
for the processing of shop drawings. All penetration measures shall relate to grid lines, co-ordinates or relative levels.
Submit co-ordinated penetration drawings in sufficient time for review. Any failure to submit requirements within
sufficient time for revision of structural drawings, resulting in re-working of the structure or re-ordering of structural
components shall be responsibility of Contractor and shall not constitute any claim for variation or delay. All
penetration measures shall relate to grid lines, co-ordinates or relative levels.
Provide drawings generally in accordance with the design drawings supplied with this specification.
Sheet sizes: Standard metric series, all sheets the same size. Plant room layout plans 1:50 scale, with sections and
details at 1:20 scale. All services Floor plans at 1:100 scale, with detailed sections.
Drawings:
1 Access to and removal of all plant including locations and sizes of access doors to be installed in finished building
surfaces.
2 Schematic and layout drawings of piping, tray and conduits, electrical and controls.
3 Switchboard and control panel layouts and schematics with terminal numbering.
4 Locations of all control sensors, valves and actuators.
5 Detail of all interfaces with other services and utilities.
6 Services co-ordination drawings for spatial co-ordination with building structure and other services with details
for restricted locations.
7 Control logic diagrams with settings.
8 Foundations, plinths, chases, ducts, pits and penetrations through structure.
9 Layout and details of services cast in concrete. (for co-ordination and review by structural engineer /architect)
10 Structural support details and methods of fixing to structure.
11 Construction loadings (for structural engineer review).
12 Lifting point loads. (for structural engineer review)
13 Maintain current sets of drawings on site and progressively record variations which lead to creation of as-built
drawings.
Please note when shop drawings review comments states “satisfactory subject to comments”, resubmit the revised
drawings with comments incorporated within a period of no longer than 2 weeks. However, this should not stop the
installation works.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 22
1118/1.05
SITE PROVISIONS AND BUILDING WORKS IN
CONNECTION
1 This clause is provided to highlight the project requirements in relation to the Site provisions as well as Building
Works in Connection BWIC and to ensure that they have been allowed for part of the Contractor Tender
submission. Contractor is responsible for demarcation of tasks and responsibilities between various trades in
relation to these items to suit his/her delivery methodology.
2 Site Provision include but not limited to;
a Hoisting and Lowering:
b Scaffolding:
c Temporary Services – Water, Electricity:
d Site facilities including Sheds.
e Power and Fuel for Testing and Commissioning

3.7.1 BUILDING WORKS IN CONNECTION


Allow for the following;
1 Demolition:
a Services decommissioning, disconnection from supply, capping and sealing.
b Services demolition and removal.
2 Ground Works: Services trenches; excavation and backfilling.
3 Concrete:
a Chasing, coring, cutting and making good.
b Placing, casting in and protection of pipe sleeves and conduits.
c Bases and plinths for equipment (excluding galvanised steel edge surround to be provided as part of the
Mechanical Services Works Package).
d Piers and beams under cooling towers, fluid coolers and adiabatic coolers.
e Water-proof curbs round floor penetration in plant rooms.
f Sealed air rise shafts for supply and exhaust systems where shown on the mechanical drawings, including fire
rating where required.
4 Masonry:
a Chasing, coring, cutting and making good.
b Plant enclosures, masonry air ducts and service risers.
5 Structural Steel:
a Lifting beams.
b Platforms and walkways for maintenance to equipment.
6 Roofing:
a Openings and under flashings including over flashings

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 23
1118/1.05
b Services works.
c Roof access walkways.
7 External Walls:
a Metal louvre grilles complete with bird mesh for air intakes and exhausts.
8 Internal walls
a Setout of cut-outs including cut-out and trimming of openings
9 Doors:
a Cut-outs in doors and trimming of openings
b Undercutting of doors for ventilation purposes.
c Access doors and hatches for maintenance of Services equipment.
10 Ceilings:
a Removal and replacement of ceiling tiles.
b Co-ordination of penetrations.
c Ceiling access panels to equipment, valves, dampers and duct access panels above solid ceilings.
d Sealed air Plenums for smoke exhaust systems.
11 Dry wall/ Plenum Construction
a Sealed air plenums for supply and exhaust systems where show on the drawings, including fire rating and
thermal insulation where required.
b Co-ordination of penetrations.
c Vapour barriers within walls where required.
12 25mm thick waterproof ply supports for sanitary fixtures on dry wall construction.
13 Access doors and hatches for access to hydraulic equipment.
14 Bollards and mechanical protection to pipework, stacks and equipment.
15 Roof, Gutters, Gutter Sumps, Gutter outlet and external downpipes.
16 Supply and installation of waterproof membranes in all wet areas.
17 Set out of building grids to allow set out of core holes.
18 Supply and install all roof/parapet/balcony overflows.
19 All in-situ concrete sumps and grated drains (grates and frames to be supplied and installed part of the Hydraulics
Works Package) that form part of the structural slab.
20 Concrete pump plinths. Note: Metal forms to be provided part of the Hydraulics Works Package.
21 Pipe penetration guards for pipes in carpark

SERVICES INTERFACE WORKS


Contractor is responsible to carry out the works outlined under all contract documents including this Specification to
achieve a fully operational installation including all required interfaces between various systems. Whilst the
responsibilities for interface works and division of works is solely with Contractor the following information is

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 24
1118/1.05
provided for guidance only. Contractor has full control to alter and modify the trade allocation/demarcation of
interface works to suit the Contractor’s overall programme and delivery methodology in order to achieve a fully
integrated, interfaced and operational whole services installations, systems and sub-systems.
Table below indicate key areas where different work packages will interface with each other. Column 1 indicate the
disciplines/work packages identified and column 2 and 3 outline the key interface works between these two work
packages.

DISCIPLINE 1 DISCIPLINE 2

Hyd1/ — Provision of HLI or LLI for generating status of — BMS cabling from Water meters and other BMS
Mech2 equipment on BMS for (See table xx-x below) monitoring switchboards/control panels/tanks
locations back to BMS controllers and specific BMS
— Pump Control panels LLI
graphic screens to demonstrate facilities water
— Meters HLI, metering and consumptions in logical subdivisions
— Sensors LLI — Connection of mechanical drains from equipment to
— Pits tundishes.

— Tanks level sensors — Extension from valved branches and final


connections of water supplies to mechanical
— Valves status
equipment e.g. cooling towers, boilers
— Coordinate location and provision of open end
tundishes for all mechanical equipment

— Provision of water supply to mechanical plant.


Terminate with valved branch.

Hyd1/ — Coordinate for final hydraulic equipment selections — Coordinate and advise after final equipment
the MD for each hydraulic switchpanel or DB to selections the MD for each hydraulic switchpanel or
Elec 2
ensure correct submain cable selections for the DB to ensure correct submain cable selections for the
respective hydraulic switchpanel and DB prior to respective switchpanel and DB
installation of submains.
— Provision of all lugs, cable glands and gland plates for
— Pressure pumps submain terminations and provision of final
connections of submains to all switchpanel and DBs
— Hot water units

— Stormwater/Sewer pump stations

— Hot water return circulating pumps

— Water Filtration systems

— Electronic tapware

Fire1 — Provision of fire test drain interface locations and — Provide test flow rates for all test drains.
requirements.
/Hyd2 — Connection of fire drains from equipment to
— Wiring and connection to the FIP of monitoring tundishes
devices on nominated isolating valves associated
— Extension from capped water supply to pumps, tanks
with fire protection system water supplies.
and booster.
— Provision of isolating valves complete with
electronic monitoring devices (Class A) on incoming
fire hydrant and sprinkler water supplies.

— Provision of gas shut off solenoid

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 25
1118/1.05
DISCIPLINE 1 DISCIPLINE 2

Hyd1 — Provide drainage to stormwater as required for all — Provide details of all requirements including finished
planter boxes surface and planter box levels.
/LandArc2
— Provide non potable water service as required sized — Install irrigation pipework as required including
in accordance with irrigation flow and pressure provisions for all cast in elements and conduits.
requirements provided by landscape architect or
irrigation specialist

The BMS interface works shall include points and electrical wiring from the following:

ITEM LOCATION SIGNAL TYPE INPUT / OUTPUT NUMBER

Cold water booster pump Hydraulic Plant Area Failure (digital) Output 2

Domestic water storage Hydraulic Plant Area Low and high level alarm Output 1
tank (digital)

Chlorine Dosing system Hydraulic Plant Area Failure (digital) Output 1

Water meter – potable cold Hydraulic Plant Area Pulse (digital) Output 1
water

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 26
1118/1.05
4 DESIGN AND PERFORMANCE
CRITERIA
GENERAL
1 The following standards are applicable throughout the project.
2 National Construction Code 2019 (Referred throughout this specification as NCC) including all relevant Australian
Standards called in the NCC
3 National Construction Code (NCC) Part 3 – Plumbing Code of Australia (PCA)
4 Relevant Occupation/Workplace Health and Safety legislation
5 The Environmental Protection Authority
6 Workcover
7 Any other Authority having jurisdiction over all or part of the installation to ensure that the equipment and
installation, when manufactured and installed, will comply with the rules and regulations.
8 The Hydraulic Services shall be to the approval of:
a Local Plumbing Authority
b Local Fire Services Authority.
The following standards are applicable throughout the project as a minimum. Where items of equipment are required
the relevant Australian Standard to the equipment will apply. If clarification required, the Contractor shall seek
clarification at the time of tender.
Where Australian Standards and Codes do not exist, the appropriate British Standard or Code shall apply.
Details of documents applicable to this:

AUSTRALIAN/NEW ZEALAND STANDARDS & CODE


(HYDRAULIC SERVICES)
STANDARD / CODE TITLE

AS ISO 7.1 Dimensions, tolerances and designation

AS ISO 1000 The international system of units (SI) and its application

AS 1170.4 Structural design Actions - Earthquake actions in Australia

AS/NZS 1200 Pressure equipment

AS 1210 Pressure vessels

AS/NZS 1254 PVC-U pipes and fittings for stormwater and surface water applications

AS 1318 Use of colour for the marking of physical hazards and the identification of certain equipment in
industry (known as the SAA Industrial Safety Colour Code)

AS 1319 Safety signs for the occupational environment

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 27
1118/1.05
STANDARD / CODE TITLE

AS 1345 Identification of the contents of pipes, conduits and ducts

AS 1349 Bourdon tube pressure and vacuum gauges

AS 1366.1 Rigid cellular plastics sheets for thermal insulation - Rigid cellular polyurethane (RC/PUR)

AS 1366.3 Rigid cellular plastics sheets for thermal insulation - Rigid cellular polystyrene - Moulded (RC/PS - M)

AS 1428.1 Design for access and mobility – General requirements for access – New building work

AS 1428.2 Design for access and mobility – Enhanced and additional requirements – Buildings and facilities

AS 1428.3 Design for access and mobility – Requirements for children and adolescents with physical disabilities

AS 1432 Copper tubes for plumbing, gas fitting and drainage applications

AS/NZS 1477 PVC pipes and fittings for pressure applications

AS 1548 Fine grained, weldable steel plates for pressure equipment

AS 1628 Water supply - Metallic gate, globe and non-return valves

AS/NZS 1716 Respiratory protective devices

AS 1722.2 Pipe threads of Whitworth form – Fastening pipe threads

AS/NZS 2280 Ductile iron pressure pipes and fittings

AS/NZS 2310 Glossary of paint and painting terms

AS/NZS 3500.0 Plumbing and drainage – Glossary of terms

AS/NZS 3500.1 Plumbing and drainage – Water services

AS/NZS 3500.1.1 Plumbing and drainage – Water supply – Performance requirements

AS/NZS 3500.2 Plumbing and drainage – Sanitary plumbing and drainage

AS/NZS 3500.2.1 Plumbing and drainage – Sanitary plumbing and drainage - Performance requirements

AS/NZS 3500.3 Plumbing and drainage – Stormwater drainage

AS/NZS 3500.3.1 Plumbing and drainage – Stormwater drainage – Performance requirements

AS/NZS 3500.4 Plumbing and drainage – Heated water services

AS/NZS 3500.4.1 Plumbing and drainage – Heated water services – Performance requirements

AS/NZS 3518 Acrylonitrile butadiene styrene (ABS) compounds, pipes and fittings for pressure applications

AS 3690 Installation of ABS pipe systems

AS 3715 Metal finishing - Thermoset powder coating for architectural applications of aluminium and aluminium
alloys

AS 4041 Pressure piping

AS 4072.1 Components for the protection of openings in fire-resistant separating elements - Service penetrations
and control joints

AS/NZS 4251.1 Electromagnetic compatibility (EMC) - Generic emission standard - Residential, commercial and light
industry

AS/NZS 4766 Polyethylene storage tanks for water and chemicals

AS 5200.000 Technical specification for plumbing and drainage products – Procedures for certification of plumbing
and drainage products

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 28
1118/1.05
STANDARD / CODE TITLE

ATS 5200.004 Technical specification for plumbing and drainage products – Urinal flushing cisterns

ATS 5200.006 Technical specification for plumbing and drainage products – Reflux valves - Sewerage

ATS 5200.007 Technical specification for plumbing and drainage products – Metal-bodied water hammer arresters

ATS 5200.012 Technical specification for plumbing and drainage products – In-line valves for use in plumbing water
supply systems – Miscellaneous types metallic and non-metallic

ATS 5200.014 Technical specification for plumbing and drainage products – Joining materials

AS/NZS 6400 Water efficient products – Rating and labelling

CIBSE Commissioning Codes

SEISMIC RESTRAINTS
4.3.1 DESIGN STANDARD
1 NCC - Building Code of Australia.
2 AS 1170.4 - Structural design actions - Earthquake actions in Australia
Design and install the scope of works to withstand the earthquake forces in accordance with the requirements of the
BCA and AS1170.4. Refer to Strucutral Engineer for Design Parameters/Criteria.

DESIGN CRITERIA
ITEM AUSTRALIAN STANDARD DESIGN CRITERIA

Water supply – mains Water Supply Code of Australia (WSA 03) Australian Drinking Water Guidelines
water

Water Supply AS/NZS 3500.1 Water Services To local Water Authority Standards

In accordance with AS 6400 – Water Efficient Rating and


Labelling

Plumbing Code of Australia


2.1 m/s
Supply Conditions Max Water velocity within Building
500 kPa
Max operational pressure

Min operational pressure 250 kPa

Pipe sizing design criteria - Australian Standard 2200 The Institute of Plumbing Australia
Hot & Cold (Selection and Sizing of Copper Tube for Water Piping Systems. B Smith)

Faucets, cocks and outlets AS1428.1 WaterMark ™

Design for Access and mobility

Water conservation AS 6400 Water Efficiency Labelling and Standards (WELS) Scheme
measures

Heating Hot Water AS/NZS 3500.4 Heated Water Service To Local Authority Standards

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 29
1118/1.05
ITEM AUSTRALIAN STANDARD DESIGN CRITERIA

Supply Conditions Stored HW temperature 65°C

Max personal hygiene delivery temp 50°C

Max personal hygiene delivery temp for aged, 42°C


sick, children or people with disabilities

Max allowable flow velocity (circulatory) 1.1 m/s

Max allowable flow velocity (other) 2.1 m/s

Max temp loss through circulatory system 5°C

Max wait time for hot water an any outlet 10 sec

Heated water temperature AS/NZS 3500.4 Heated Water Service To local Authority Standards
control
AS 4032.1 New South Wales Health Guidelines for Legionella Control

Hot water plant AS/NZS 3500.4 Heated Water Service Hot Water Plant to be sized to meet peak hourly demand and
daily demand
Redundancy shall be provided within each plant of 1 additional
component (1 x burner and 1 x storage tank)

Sanitary AS/NZS 3500.2 To local Authority Standards

Sanitary Plumbing and Drainage All sanitary fixtures connected by pipes and fittings shall collect
and convey an approved, Authority Sewer.

Sanitary fixtures shall have water or mechanical seal to prevent


noxious odours our sewer smells

Discharge Conditions All wastewater from the community, including faecal matter,
urine, household and commercial wastewater shall be collected
and convey to an approved Authority Sewer or treatment
system

Drainage Systems The drainage system shall be designed to allow the removal of
foul gases to atmosphere via an open vent pipe
A barrier or water seal shall be maintained at each fixture to
prevent foul gases entering the building environment.

Industrial & Tradewaste AS/NZS 3500.2 Industrial and Trade waste drainage to the Local Authority
requirements. Sewer Waste Characteristics including
Sanitary Plumbing and Drainage
— Hydrocarbon based product
AS 1546

On site Domestic and Waste Management — Fats Oils and Grease (FOG)

— BOD,

— TSS

— pH

shall be treated or removed to approved Local Authority limits

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 30
1118/1.05
ITEM AUSTRALIAN STANDARD DESIGN CRITERIA

Treatment Queensland Urban Utilities – Trade waste Type Dissolved air flotation (DAF)
sizing grease and oil arrestors system

Treatment capacity Meet final hourly tradewaste


volumes established in
accordance with QUU
tradewaste guidelines

Buffer Tank effective 100% of peak hourly treatment


volume capacity

Tank level monitoring Via ultrasonic sensors


calibrated for effluent level (%)

Tank level warnings Mid level, high level

Emergency storage Min 1 hour at peak inflow

Monitoring of end Automated


quality

Gas AS 5601.1 Gas Installations Mains Supply and delivery to meet the Gas Authority and
network operator requirements.
AG-006 Gas Installations
Gas meters and pressure reduction stations to meet the Gas
authority and network provider

Stormwater AS/NZS 3500.3 To local Authority Standards

Stormwater Plumbing and Drainage The stormwater installation to cater for the Annual Rainfall
Intensity (ARI) for the site

Discharge Conditions To AS/NZS 3500.3

DESIGN ASSUMPTIONS/PARAMETERS
Provide the following
Sanitary
1 Gravity / pumped drainage
2 Existing Authority Civil Sewer, connecting to existing gravity drainage
3 On site waste water management and disposal
Stormwater Drainage
1 Gravity drainage by Civil, all inground stormwater drainage by Civil
2 Downpipes to connect to Civil
3 Authority Civil connection point and internal Civil rainwater/stormwater connection points
Potable Water
1 Connect to existing Authority mains supply - Water grade - permission to connect to existing and application to
local authority

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 31
1118/1.05
2 Fire protection usage for water
3 Civil water meter design and application to local authority
4 Domestic water criteria water storage volumes & treatment
5 Building pressure requirements
6 Isolation of cold water (area valves)
Hot Water
1 Hot water generation heating source
2 Peak demand length of time / storage
3 Centralised plant generation

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 32
1118/1.05
5 PAINTING, PROTECTION AND
IDENTIFICATION
GENERAL REQUIREMENTS
1 Select painting and finishes in accordance with the area environmental conditions.
2 Review the risk assessment and statutory and authority requirements completed as part of the system testing,
commissioning and handover requirements and provide labelling and signage as determined.
3 Where exposed to view paint exposed equipment, cable trays, ductwork and pipework
4 Where ductwork, pipework, cable trays exposed to view is not specified to be painted, all factory and installation
markings shall be removed.
5 All black steel surfaces and surfaces subject to corrosion shall be primed with at least two coats of primer and
protected.
6 Protect all items of work during dispatch and whilst on site during progress of installation.
7 Fabricated pipe and steelwork shall be delivered to site prime coated
8 Concealed pipe work to be prime coated
9 If exposed to view, paint new services and equipment including in plant rooms, except chromium, anodised
aluminium, GRP, UPVC, stainless steel, non-metallic flexible materials and normally lubricated machined surfaces.
Repaint proprietary items only if damaged.
10 Do not combine paints from different manufacturers in a paint system.
11 Remove or protect fixtures, equipment, surfaces and labels before starting to paint, and re-instate after
completion of painting.
12 All internal surfaces of air outlets and openings exposed to view shall be painted matt black
13 Repair factory finishes if damaged with identical finishes.
14 Finish visible joints made by welding, brazing or soldering using methods appropriate to the class of work
(including grinding or buffing) before further treatment such as filling, painting, galvanising or electroplating.
15 If galvanised surfaces have been cut or welded after galvanising, prime the affected area using zinc rich organic
binder AS/NZS 2312.
16 Before applying coatings to metalwork, complete cutting, drilling and other fabrication, remove all grease, oil and
other contaminants and prepare surfaces to AS 1627.0
17 Use relevant Australian Standards for the following finishes; Galvanising, Electroplating, Anodising, Thermoset
powder coating, Two-pack liquid coating, Air-drying enamel, Stoving enamel

SUBMISSIONS
1 Provide the following submissions or samples:
a Proposed Labelling Systems.
b Schedule of statutory, maintenance and operating signage.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 33
1118/1.05
c Valve Identification

CORROSION PROTECTION
5.3.1 GENERAL
1 Apply corrosion protection measures to all metallic surfaces.
2 Select an appropriate protective coating system to suit atmospheric corrosivity category as defined in referenced
Standards/Codes.
3 Fastenings are to be protected to have a corrosion resistance equivalent to the parts fastened.
4 All welding is to be completed before any corrosion protection treatment is applied.

ATMOSPHERIC CORROSIVITY TYPICAL EXTERIOR TYPICAL INTERIOR ENVIRONMENT


CATEGORY ENVIRONMENTS

C1: Very Low Few alpine regions Heated or air conditioned buildings, such as
most of commercial buildings.

Unheated or non-air conditioned buildings in


semi-sheltered locations remote from marine
or industrial influence

C2: Low Dry, rural areas as well as other Unheated or non-air conditioned buildings,
where some condensation may occur, such as
regions remote from the coast or sources of
warehouses and sports halls, can be in this
pollution.
category.
Typical areas occur in arid and rural inland
Proximity to the coast is an important factor.
regions, most inland cities and suburbs of
cities on sheltered bays.

C3: Medium Coastal areas with low salinity Food processing plants, laundries, breweries,
printing works, dairies

C4: High Sea-shore (calm) Swimming pools, dye works, paper


manufacturers, foundries, smelters and
chemical processing plants, livestock
buildings

C5-I: Very High (Industrial) Sea-shore /offshore -

C5-M: Very High (Marine) Shoreline (severe surf) Adjacent to acidic processes

T: Inland Tropical Non-coastal tropics -

5.3.2 PROTECTION FOR STEEL SURFACES


1 Apply corrosion protection to meet the performance criteria scheduled in the table below.
2 Standards of surface preparation procedures and of corrosion treatments are to meet the specified criteria and the
referenced Standards/Codes for the relevant application.
3 Surface preparation procedures and coating systems for corrosion protection are to meet all relevant
requirements of the referenced Standards/Codes.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 34
1118/1.05
ATMOSPHERIC SURFACE PREPARATION COATING SYSTEM
CORROSIVITY
CATEGORY

C1: Very Low Class Sa 2½ Blast Cleaning 1st Coat – zinc phosphate alkyd primer, 75 microns thick

‘Very thorough’ (commonly called 2nd Coat – full gloss alkyd finish, 50 microns thick
‘near white’) blast cleaning which
3rd Coat – full gloss alkyd finish, 50 microns thick
removes millscale, rust and foreign
particles to the extent that only traces Or
remain. Factory applied zinc primer and thermoset powder coated
finish

C2: Low Class Sa 2½ Blast Cleaning 1st Coat – zinc phosphate alkyd primer, 75 microns thick
2nd Coat – full gloss alkyd finish, 50 microns thick

3rd Coat – full gloss alkyd finish, 50 microns thick

Or

Factory applied zinc primer and thermoset powder coated


finish

C3: Medium Class Sa 2½ Blast Cleaning 1st Coat – Organic zinc primer, 75 microns thick

2nd Coat – polyurethane, 100 microns thick

Or
Factory applied zinc primer and thermoset powder coated
finish

C4: High Class Sa 2½ Blast Cleaning 1st Coat – Organic zinc primer, 75 microns thick

2nd Coat – polyurethane, 100 microns thick


Or

Factory applied zinc primer and thermoset powder coated


finish

C5-I Very High Industrial Manufacturer’s recommendation To approval

C5-M Very High Marine Class Sa 2½ Blast Cleaning 1st Coat – Organic zinc primer, 75 microns thick

2nd Coat – polyurethane, 100 microns thick


Or

Factory applied zinc primer and thermoset powder coated


finish

T Inland Tropical Class Sa 2½ Blast Cleaning One coat inorganic zinc coating, 75 microns thick

Or
zinc or aluminium thermal spray metallic coating.

5.3.3 PROTECTION FOR NON-FERROUS METALLIC SURFACES


1 Standards of surface preparation procedures and of corrosion treatments are to meet the specified criteria and the
referenced Standards/Codes for the relevant application.
2 Surface preparation procedures and coating systems for corrosion protection are to meet all relevant
requirements of the referenced Standards/Codes.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 35
1118/1.05
PAINTING
5.4.1 LOW VOC
The following additional requirements are to be met if required by the Green Star Schedule in Schedules.
1 All painted surfaces to use low-VOC paints.
2 VOCs are to be in accordance with The Australian Environmental Labelling Association, Inc. Standard No: AELA 23-
2005 ‘Australian Voluntary Environmental Labelling Standard Architectural and Protective Coatings’.
Conformance with VOC levels listed in this standard (refer to table below) shall be demonstrated by providing test
reports from laboratories accredited to carry out the relevant tests and/or calculations and appropriate
documentation of production methods and quality controls.

PRODUCT TYPE MAXIMUM VOC CONTENT (G/LITRE)

Latex Primer for galvanised iron and zincalume 60

Exterior latex undercoat 55

Interior latex undercoat 65

Interior gloss 75

Interior semi-gloss 16

Exterior gloss 75

3 VOC limits on architectural coatings covered. Allowable levels include water content in the formulation.
4 For solvent-based coatings the paint shall not contain VOCs in excess of 200g/litre. For recycled paints the VOC
level (averaged across batches) in the paint must not exceed 100g/litre.
5 The VOC content of the paint shall either be calculated from the VOC data for each of the raw materials or,
experimentally by ASTM D3960, as qualified the Australian Environmental Labelling Association, Inc. Standard No:
AELA 23-2005 ‘Australian Voluntary Environmental Labelling Standard Architectural and Protective Coatings’.
6 Where the raw material is a mixture of compounds, some of which contain VOCs, the VOC content of the mixture
may in turn be calculated from the VOC content of the individual components. Where this is not known, it must be
determined by the methodology detailed in AELA 23-2005.

5.4.2 PREPARATION OF SURFACES


1 Preparation: all surfaces shall be prepared by thorough cleaning of all dirt, grease, scale, welding flux and
corrosion in accordance with AS/NZS 2312.
2 For galvanised surfaces that have been subsequently cut or welded, prime the affected area with organic zinc rich
coating for protection of steel to AS/NZS2312, two pack or accepted alternative.
3 Prime/undercoat all surfaces. Galvanised and non-ferrous surfaces must be etch primed.

5.4.3 APPLICATION
1 First coat: apply the first coat immediately after the substrate preparation and before contamination of the
substrate can occur.
2 Apply all paint systems in strict accordance with manufacturer’s recommendations.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 36
1118/1.05
3 Finish: each coat of paint or finish shall be uniform in colour, gloss, thickness and texture and free of runs, sags or
blisters.

5.4.4 FINISHING
1 Concrete Bases: 2 coats synthetic emulsion paint
2 Equipment Panels/Switchboards: 2 final coats full gloss enamel
3 Equipment: Factory spray application
4 Other surfaces: 2 final coats full gloss enamel

COLOURS
Paint colours nominated are to be in accordance with AS 2700 and AS 1345.

IDENTIFICATION AND LABELLING


5.6.1 GENERAL
1 Mark all systems and equipment including wiring, piping, control panels, switchboards, ductwork, equipment
cabinets, conduits, controls, gauges, valves and fittings to that they are readily identifiable.
2 Equipment requiring special maintenance procedures or presenting occupational health and safety hazards:
provide permanent labels complying with statutory requirements.
3 Locate labels so that they are easily seen and either attached to, below or next to item referred.
4 Labelling to match installation documentation schedules.
5 For systems containing hazardous materials provide labelling in accordance with AS 1318.
6 Where a pipe or duct passes through a wall, slab or partition provide labelling each side.
7 Equipment and Service labels shall be in accordance with the Legend of Symbols nomenclature for the respective
service. Provide appropriate Emergency and Operating Instructions to every equipment and system.
8 Provide text and simple diagrams where practicable. Locate at a fixed point and point of operation.
9 Affix hazardous equipment with warning signs.
10 Labels shall be permanent.
11 Type: select from the following:
a Engraved and black filled lettering on stainless steel or brass plate, minimum 1mm thick mechanically fixed.
b Stencil with black or white lettering contrasting with background.
c Engraved two-colour laminated plastic mechanically fixed.
d Adhesive labelling.
e Painted.
12 Adhesive labels and laminated plastic labels shall not be used where exposed to the environment.
13 Painted labels shall be in the same finish paint type as the installation.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 37
1118/1.05
5.6.2 LABELLING REQUIREMENTS

ITEMS REQUIREMENTS

Pipework(Mech, Fire and Labelling and lettering to AS 1345 and AS1318


Hyd)

Conduits Labelling and lettering to AS 1345

Exposed Conduits Labelling and lettering to AS 1345

Valves Labels shall be colour coded laminated labels indicating service, function and normal position, and
attached to hand wheels or spindles using a vandal resistant permanent chain/ring

Switchboards(general) 1 Main switches: 10mm.


2 Outgoing electrical functional units: 8mm.
3 Automatic controls electrical equipment and instruments: 5mm.
4 Rear covers of switchboards: 5mm.
5 Components inside electrical enclosures and control panels: 3.5mm
6 Locate labels so that they are easily seen from normal access adjacent to the item being marked.
Do not install labels on components normally removed or replaced.

All equipment such as 1 Label in accordance with the specification abbreviations, symbols and acronyms scheduled or
chillers, pumps, fans, air otherwise approved.
handling units, generators 2 Locate labels so that they are easily seen from normal access adjacent to the item being marked.
including controls, gauges Do not install labels on components normally removed or replaced.
and fittings to that they are
3 Major equipment nameplates: 40mm.
readily identifiable
4 Minor equipment nameplates: 20mm.
5 Danger, warning and caution notices: 10mm for heading, 5mm for test.
6 Warning notices: 7mm.
7 Minor lettering: 3mm.
8 Lettering Style: Helvetica Medium.
9 Fixing: Use mechanical fixings. Do not penetrate isolation vapour barriers.
10 Equipment requiring special maintenance procedures or presenting occupational health and
safety hazards: provide permanent labels complying with statutory requirements.
11 Equipment requiring consumables including replacement belts, oils, filters and strainers:
provide labels indicating consumable component details and quantities and corrective
maintenance trigger point such as filter pressure drop.

Fire services in ceiling 1 Provide identification to ceiling tile or access panel for servicing to test drain valves, flow
identifications switches, concealed detectors or similar.
2 Use colour markers of ‘black’ for general servicing and ‘red’ for Code required identification e.g.
concealed detectors.
3 Use self-adhesive ‘dot’ type markers on ceiling suspension or plastic headed pins for insertion in
ceiling material.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 38
1118/1.05
6 INSPECTION, TESTING,
COMMISSIONING, HANDOVER
AND DEFECTS LIABILITY PERIOD
GENERAL
1 This section sets out the engineering and quality assurance requirements for the completion of the installation,
inspection regime, testing, commissioning, handover and defects liability period.

6.1.1 DESIGN
Complete the detail engineering of the testing commissioning and handover of the works to the specified
requirements.
Comply with applicable authority design guidelines and codes of practice and requirements.
Commissioning guidelines as detailed by CIBSE Commissioning Codes shall be used as a minimum to undertake the
commissioning of services listed in this section.

6.1.2 STANDARDS AND GUIDELINES


Refer to Design and Performance Criteria section

6.1.3 PRACTICAL COMPLETION REQUIREMENTS


1 Notwithstanding any other provisions of the Contract with regard to the granting of Practical Completion, the
following requirements, listed in order of importance / priority, shall be completed and completion submissions
made prior the date of Practical Completion:
2 Minimum submissions required for application for Occupancy Permit:
3 Submission of signed off testing and commissioning schedules to confirm that Testing and Commissioning has been
finalised and that all plants and systems operate in a safe, stable and automatic manner under all conditions of full
and partial load - full commissioning data.
4 Submission of Authority approvals including Statutory Authority approvals and Certification of Compliance with
the NCC
5 Submission of Certification that works comply with the Contract Documents
6 Operating Instruction and Maintenance manual sections covering all Safety Services as required by regulations
7 Other submissions:
8 Submission of correctly and completely executed ITPs including test results completed in accordance with the
Contractors Quality Plan and the satisfaction of the Consultant Engineer
9 Adequate training and instruction of the Principal’s representatives in safe operation of the plant
10 Official Equipment manufacturer’s acceptance certification for the installation

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 39
1118/1.05
11 Completed Operating and Maintenance manuals and ‘as built’ drawings
12 The Defects Liability period may be extended in the event:
a Specific systems fail to achieve the desired outcomes after two attempts are made to rectify the drawback.
These specific systems include those that are fire and life safety or business / mission critical to the Principal.
b If there have been more than three (3) attempts to rectify the defect, in which instance a further 12 months of
monitoring will be required after the defect is rectified to monitor that the desired outcomes are achieved
without further shortfalls.

PRACTICAL COMPLETION REQUIREMENTS


1 Notwithstanding any other provisions of the Contract with regard to the granting of Practical Completion, the
following requirements, listed in order of importance / priority, shall be completed and completion submissions
made prior the date of Practical Completion.
2 Minimum submissions required for application for Occupancy Permit
3 Submission of signed off testing and commissioning schedules to confirm that Testing and Commissioning has been
finalised and that all plants and systems operate in a safe, stable and automatic manner under all conditions of full
and partial load - full commissioning data.
4 Submission of Authority approvals including Statutory Authority approvals and Certification of Compliance with
the NCC
5 Submission of Certification that works comply with the Contract Documents
6 Operating Instruction and Maintenance manual sections covering all Safety Services as required by regulations
7 Other submissions:
8 Submission of correctly and completely executed ITPs including test results completed in accordance with the
Contractor Quality Plan and the satisfaction of the Consultant Engineer
9 Adequate training and instruction of the Principal’s representatives in safe operation of the plant
10 Official Equipment manufacturer’s acceptance certification for the installation
11 Completed Operating and Maintenance manuals and ‘as built’ drawings
12 The Defects Liability period may be extended in the event:
a Specific systems fail to achieve the desired outcomes after two attempts are made to rectify the drawback.
These specific systems include those that are fire and life safety or business / mission critical to the Principal.
b If there have been more than three (3) attempts to rectify the defect, in which instance a further 12 months of
monitoring will be required after the defect is rectified to monitor that the desired outcomes are achieved
without further shortfalls.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 40
1118/1.05
MANAGEMENT OF INSPECTION, TESTING,
COMMISSIONING, HANDOVER AND DEFECTS
LIABILITY PERIOD COMMITMENTS

6.3.1 GENERAL
1 Manage the whole process so as to
a Ensure complete execution of Project Specific Quality Plan and specifically Installation and Commissioning ITPs
are completed progressively from commencement of the project.
b Test and verify the operation of individual items of plant and equipment, sub-systems, systems and the overall
installation including the interfaces with other building services systems forming part of the project.
c Create and record accurately and verify all “As Built “drawings progressively prior to services being concealed
by construction of ceilings, wall cavities and shafts.
d Ensure completed Operating and Maintenance manuals inclusive of comprehensive system descriptions,
operating modes and associated control functionality, tailored and project specific manufacturers literature.
e Responsive defects rectification process during the construction phase as well as post Practical Completion
during Defects Liability Period.
f Ensure Responsive approach towards maintenance and operational fine tuning during the Defects Liability
Period

6.3.2 SEQUENCE OF ACTIVITIES


Generally, follow the sequence of activities listed below. Modify to suit specific requirements of the project however
no reduction of scope is allowed.
1 Submission of Project specific Project Quality Plan including generic and project Specific ITPs within the first
quarter of the project programme after site possession.
2 Ongoing inspection of installation works by relevant Quality Manager and/or his nominated staff for meeting
project quality requirements including preparing Inspection reports (listing all observed installation defects) not
longer than fortnightly and also checking that all Installation ITPs are signed off.
3 Initiate Safety in Design process and documentation where applicable
4 Evidence of adequate commissioning programme allowance in construction programme.
5 Production and submission of commissioning Inspection and Test Plan (ITP) 12 weeks after site possession
6 Amendment to ITP as necessary and re-submission at least 1-2 weeks after the original submission.
7 Submission of controls manufacturer’s functional descriptions elaborating on the methodology proposed to
implement the requirements of the control strategies the manufacturer’s controls functional descriptions shall be
prepared and submitted at least 12 weeks prior to start of installation and commissioning of controls systems.
8 Nomination of those to be involved in commissioning including individuals with responsibility for management,
engineering and field testing and commissioning.
9 Liaison with and briefing of Authorities to ensure that the connection to their assets and commissioning procedures
and resultant data provided for their approval is consistent with their requirements and records.
PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 41
1118/1.05
10 Preparation of periodic (minimum monthly) progress reports on testing and commissioning.
11 Early and active engagement of Independent Commissioning Agent ICA where applicable.
12 Early (within the first quarter of the project construction programme) submissions of Operating and Maintenance
Manual (for Safety Services and, for preliminary draft of the overall manual). Confirmation of acceptance of
proposed Electronic Operating and Maintenance Manual software/platform.
13 Submission of detailed commissioning procedures for review by the Consultant Engineer. Submission shall be made
early, at least 12 weeks prior to the commencement of commissioning when the project construction period greater
than 12 months, or 6 weeks when the project construction period is less than 12 months’ duration.

EXPECTED PROJECT DURATION SUBMISSION REQUIREMENT RE-SUBMISSION


(UP TO PC) REQUIREMENT.

8 weeks Prior to Week 1 or Prior to commitment Within 3 days.


of work whichever the sooner.

12 weeks Prior to Week 1 or Prior to commitment Within 5 days


of work whichever the sooner.

16 weeks Prior to Week 2 or Prior to commitment Within 5 days


of work whichever the sooner.

20 weeks Etc. Within 5 days

24 weeks Within 10 days.

9 months Within 10 days.

12 months + Within 10 days.

14 Rectification of all defects likely to interfere with testing and commissioning.


15 Commencement of “As Built” drawing production
16 Carryout preliminary commissioning including pre-commissioning procedures until achievement of correct
operation and performance. Providing statement that the pre-commissioning activities for each system are
completed.
17 Testing and commissioning of major plant and equipment, complete systems, interfaces between systems and
finally all systems which interact together under normal or emergency conditions.
18 Integrated testing and commissioning of multi systems (including multi-disciplinary systems) and their associated
interfaces
19 Inclusion of all completed Commissioning ITPs in the Operating and Maintenance Manual.
20 Rectification of any further defects and deficiencies found during testing and commissioning.
21 Provide notification of completion of remedial work in sufficient time to permit re-inspection as necessary before
the intended date for re-testing.
22 Repetition of sequence of activities as necessary until works comply with acceptance criteria as set out in the ITPs.
23 Final handover of Final Operating and Maintenance Manuals
24 Certification that works comply with the Contract Documents and with the NCC and Statutory Authorities and are
ready for granting of Practical Completion.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 42
1118/1.05
6.3.3 SUBMISSIONS
Required submissions include but not limited to the following;
1 Installation and commissioning Inspection and Test Plans ITPs. 4 Copies of ITPs to be supplied, 3 bound into
Installation Manuals and 1 bound separately
2 Evidence of periodic (weekly) Quality Inspection/defects reports
3 Testing and commissioning procedures including integrated commissioning procedures.
4 Evidence of Safety in Design process during the construction phase is completed where applicable
5 Evidence of currency of calibration of equipment to be used in commissioning procedures.
6 Records of all pre-commissioning checks and final commissioning data. All records/data to be certified as being
conducted in accordance with agreed and approved procedures.
7 Manufacturers’ certificates for all proprietary items, to confirm that the installation complies with their installation
and maintenance requirements prior to start-up of equipment. Certificates shall also be provided at commencement
of equipment installation to confirm their requirements with respect to installation are being provided for.
8 Manufacturers’ test certificates of all capacity/performance verification checks carried out at factory prior to
dispatch to site.
9 Accurate and verified (by QA manager) “As Built” drawings
10 Complete Operating and Maintenance Manuals (Electronic system/package and, unless instructed otherwise, hard
copies)
11 Warranties
12 Maintenance Plan and Schedules following acceptance of technical submission and installation minimum 4-8 weeks
prior to Practical Completion with priority with respect to timely completion given to plan and schedules covering
Safety Services.

6.3.4 INSPECTION AND TEST PLANS


1 Inspection and test plans are to be prepared specifically for the project but may be based on or customised from
generic ITPs. All commissioning result forms shall be completed, including the following:

Tested By: …………………………………… Please print Witnessed By: ………………………………………………

Signed: ……………………………………………………… Signed: ………………………………………………………

Date: ………………………………………………………… Date: …………………………………………………………

Test Device used: ………………………………………………………………………………………………………………

Serial Number: …………………………………………………………………………………………………………………

Date of Calibration: ……………………………………………………………………………………………………………

Method of Testing: ………………………………………………………………………………………………………………

2 List acceptance criteria for each element and sub-element of the installation in ITPs. Acceptance criteria to include:
a Specification details in regard to materials, construction methods, physical requirements, performance and
operational requirements.
b Schedule of Technical Data in respect of make, model and performance details of equipment.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 43
1118/1.05
c Shop drawings.
d Control logic and diagrams.
e Authority inspection and testing requirements.
f References to specific clauses of this Specification for acceptance criteria

6.3.5 COMMISSIONING INSTRUMENTATION


1 All instrumentation used in the commissioning of the installation shall be managed in accordance with the
requirements of AS 3912 or NEBB.
2 Reference instruments are to be NATA certified.
3 All commissioning results to include instrument calibration documentation.

6.3.6 COMMISSIONING PERSONNEL


1 Provide only qualified registered / licensed personnel specific to the trades as required by local regulations, and
where regulatory requirements do not apply, personnel certified by appropriate industry bodies.
2 Submit a schedule of key commissioning personnel together with their qualifications prior to undertaking
commissioning activities on site.
3 All personnel used in the commissioning of the installation shall be managed in accordance with the requirements
of NEBB and shall be NEBB certified.

TESTING AND COMMISSIONING

6.4.1 PRE-ENERGISATION TESTS


Prior to energisation of any system with electrical connections, conduct the following tests:
1 Tightness of screwed and bolted connections.
2 Physical integrity.
3 Motor rotation.
4 Insulation resistance tests.
5 Test operation of all trips, interlocks, motor driven devices, contactors and control circuits and devices by
instigating or simulating inputs.

6.4.2 TESTS
Include the following in testing of installation:
1 Pump installation including all pump controls and interfaces.
2 Domestic hot water plant.
3 Backflow prevention devices
4 Ultra Violet disinfection plant

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 44
1118/1.05
5 Bag filters
6 BMS interface
7 Hot water return
8 Water meters and interface to the BMS
9 Thermostatic valves
10 Tapware operating satisfactorily
11 Downpipe/overflow, planter drains, waste and drain systems clear of blockage
12 Plastic inspection opening covers have been replaced with final chrome plated brass covers
13 Sanitary and Stormwater pump station chamber and pump level indicators, check all BMS interfaces and offline
power interface
14 Gas meters and submeters, check gas meter emergency safety shut off and isolation working correctly
15 Sanitary plumbing-Provide a hydrostatic test to maximum choke level to the satisfaction of the authority
16 Provide a hydrostatic test to choke level for a minimum period of 15 minutes and as required by the testing
authority and the Contractor and as specified under “Preliminaries” section.
17 On completion, all work shall be hydrostatically tested under expected maximum choke condition including box
gutter sump and box gutter for a period of two (2) hours
18 Provide a water pressure test of 1500 kPa for a period of two hours. Disconnect any equipment connected to the
service not rated to the test pressure before testing commences.”
19 Natural Gas-Test all pipework 1700 kPa for a period of two hours. On completion, test the installation under full
supply conditions all to the satisfaction of the QFRS
20 Provide a water pressure test of 1500 kPa for a period of two hours. Disconnect any equipment connected to the
service not rated to the test pressure before testing commences
21 Hydrostatic Tests:
a All cold-water piping shall be hydrostatically tested to a head of one and a half times the working head.
Hydraulic (testing) pumps shall be disconnected immediately after pressurisation and all test heads shall be
maintained until the Contractor has satisfied himself as to the soundness of the pipe work and equipment.
b In no case, shall the period of test be less than 30 minutes.
c Before applying specified test head, all air shall be expelled from the piping being tested. If necessary, supply
and install approved air relief valves for this purpose.
d Equipment is not to be connected to the respective services while hydrostatic tests are being carried out.
e Provide a suitable pump and gauge and do all necessary work for carrying out the tests.
f All testing of cold water piping is to be carried out before:
i Finishing trades have commenced their work;
ii Ceilings are installed;
iii Insulation of pipe work.
g At completion of testing, all cold-water lines shall be kept charged full of water at all times.
22 Choke Tests:

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 45
1118/1.05
a All sanitary drains, stormwater drains, sanitary plumbing, rainwater pipes, shall be choke (water) tested by
plugging at the lowest, or other approved positions and filling with water to the overflow level.
b Choke tests shall be maintained until the Contractor and/or Authorities have satisfied themselves as to the
soundness of the pipe work.
c In no case, shall be period of test be less than one hour.
d Fixtures are not to be connected to the respective services while choke tests are being carried out.
e Provide all necessary plugs and do all necessary work for the carrying out of the tests.
f All testing of the above system shall be carried out before:
i Finishing trades have commenced their work,
ii Ceilings are installed,
iii Backfilling has commenced,
iv Absorption into pipe wall is complete.
23 Fixtures:
a Fixtures shall be filled to spill level with water after installation and visually checked for leaks.
24 Test of Completion:
a Upon completion, the Hydraulic Works Package shall be tested under normal working conditions and as
directed by the Contractor; such tests shall continue until the Contractor is satisfied that the terms of this
specification has been compiled with and that the Hydraulic Works Package are capable of meeting all
requirements.
b All defects disclosed during the tests shall be remedied immediately and, if required by the Contractor fresh
tests shall be carried out.
c The duration of the tests will be decided by the Contractor. The maximum duration of any one test will not
exceed eight hours.

6.4.3 PRE- COMMISSIONING TESTS


Prior to commencement of the commissioning of the systems, carry out the following:
1 Progressively during the construction phase regularly purge cold water from all systems to ensure that stagnation
shall not occur.
2 Clean and purge all cisterns, grease arrestors and pressure vessels, remove all scum lines and high water marks
3 Thoroughly clean out and flush out all water systems to ensure only clean water is within the systems.
4 Pressure and leak test all water systems as outlined in Section ‘Pipework, Valves & Fittings‘.
5 Thoroughly clean and flush out all water systems including package pressure system.
6 Protect the filtered and treated water systems by the complete flushing out of the system prior to commissioning
and installation of the filters.
7 Provide manufacturers test certificates for all proprietary manufactured items including pumps, water filters,
backflow preventers, thermostatic valves and Ultraviolet disinfection systems -. Mount test certificates for
pressure vessels in glazed frames adjacent the equipment. Fix to pressure relief valves the manufacturers tags
indicating the set pressure of the valves and stamp all pressure valves with the manufacturer's design and test
pressure ratings.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 46
1118/1.05
8 Overhaul all installed backflow preventers including full commissioning of same by manufacturers representative
9 Check and prove all pressure and flow actuated controls, relief devices, bleeds, vents and drains.
10 Fully open all control valves during balancing of water flows. Permanently mark final settings of all regulating
valves in an appropriate manner.
11 Check installed thermostatic mixing valves, back flow preventers and trap primers and set by the manufacturer’s
representative.
12 Check all Backflow prevention devices and record and submit to the appropriate authorities in accordance with
manufactures and local authorities’ requirements.
13 Check level indicators on rainwater and greywater storage tanks are monitored correctly by the BMS. High and
low level alarms to be generated.
14 Adjust period controls and activate by competent personnel provided by the manufacturer or his authorised
agent. Maintain a complete log of the settings and readings of all controls, gauges and instruments throughout the
Commissioning period.
15 Check all water meters to be commissioned and monitored via the BMS. Maintain a complete log of the settings
and readings throughout the Commissioning period.
16 Adjust level sensors and commission pumps as required. Pumps controlled by controller provided as part of the
packaged pump station. BMS to monitor high and low level alarms.
17 Commission all pumps.
18 Check BMS to monitor pump failures (all pumps) and temperature on hot water return lines.
19 Check hot water system and ensure plant is operational and working within to the required peak hourly flow rate
of 1800L/hr. BMS to monitor water meter located on cold water inlet of hot water plant.
20 BMS to monitor temperature sensor on solar storage tanks to provide data on temperature rise through hot water
plant.
21 Grey water plant and all associated interfaces to be commissioned by specialist grey water treatment plant
manufacturer and operator. Data from grey water plant control panel to be monitored by BMS.
22 Check the operation of all indicating and recording instruments and associated equipment and the indicating
lights and associated flashers and relays under full working conditions.

6.4.4 COMMISSIONING
Operate the installation to prove the performance, capacities and ability to provide the required service.
Undertake commissioning in 4 stages:
1 Individual component functionality testing including verification of defects free installation
2 Major items of plant and equipment and components.
3 Systems and sub-systems.
4 Inter-system operation and interfaces.
Commissioning to include:
1 Performance of individual plant items and components.
2 Operating sequences, interlocks and safeties.
3 Final controls calibration.
PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 47
1118/1.05
4 System operation under all operating modes and under all conditions of load.
5 Inter-system operation and correct interfacing connections under all operating conditions and under simulated
fire conditions.
6 Noise and vibration tests.
7 Thermoscan survey of switchboards.
8 Environmental audit as required by Authorities.
9 Rectification and correction of any defects and deficiencies.
10 Continue commissioning until achievement of correct performance and operation.
11 Electrical testing and verification to AS/NZS 3000.
12 Cleaning of plant room, switchboards and all equipment and devices.

FINAL CONTRACT AND HANDOVER


DOCUMENTATION

6.5.1 GENERAL REQUIREMENTS


1 Documentation is required in electronic and hard copy format. Electronic documentation shall be supplied on the
latest Microsoft and AutoCAD Software versions at the time of Practical Completion.
2 Scope of the documentation and format requirements comprise:

Document Format Sets

Operating and Maintenance Manuals, including Electronic installed on BAS File Server 1
Final commissioning data
USB – Microsoft Office Latest Version 3

Hardcopy 3

As Built Drawings USB – AutoCAD 3

Hardcopy – Full Size with hanging strips 1

A3 Size 2

Control Software USB 1

OH&S Safety Signage Permanent 1

6.5.2 AS BUILT DRAWINGS


1 All as Built/As Installed documents submitted shall have a stamp with similar words to the following and be signed
prior to submission for review.

AS INSTALLED DRAWING

We certify that this drawing is an accurate record of the work installed by our company under the terms of our contract.
Contractor’s Name …………………………………………………………………………………………………………………
Contractor’s Address ………………………………………………………………………………………………………………

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 48
1118/1.05
……………………………………………………………………………………….
Signed ………………………………………………………………………………… Date …………………………………
Printed ……………………………………………………………………………………………………………………………

2 Progressively record changes to form a record of work as installed.


3 Prepare and submit for approval as-built drawings covering all aspects of the work.
4 Show dimensions, types and locations of equipment, cables, piping, ductwork pits and markers in relation to
permanent site features and other underground services.
5 Show the ‘as-installed’ locations of building elements, plant and equipment with particular emphasis on items
requiring maintenance or clearing.
6 Show off-the-grid dimensions where applicable. Include relationship to building structure street features and
other services and changes made during commissioning.
7 Show inverts of drainage and relative locations of gully and boundary traps
8 Provide as Built documentation as per Schedule of Required as Builts.

6.5.3 OPERATING AND MAINTENANCE MANUALS


1 Provide comprehensive Operating and Maintenance documentation to cover all installations in order to provide a
detailed understanding of the plant and its operation, an aid for training of operators, a reference for fault diagnosis
and a framework for preventative and breakdown maintenance.
2 Submit manuals in two stages. Stage 1 include all of the sections (generally sections 1-5) of manuals excluding final
testing and commissioning records and As Built drawings. This manual shall be submitted well in advance of the
Practical Completion and should be signed off by the Consultant Engineer at least 4-6 weeks before programme
Practical Completion Date.
3 First draft manuals Stage 1: Submit a first draft manual 8-10 weeks before the date for practical completion for
review.
4 Second drafts Stage 1: Following receipt of comment on the first draft and not later than 2 weeks after submit a
completed second draft for review. Incorporate comments.
5 Third Draft Stage 1&2: Include all remaining sections and submit 2-3 weeks before Practical Completion. Incorporate
all changes and resubmit until all comments are addressed to the satisfaction of the Consultant Engineer.
6 Final copies Stage 1&2: Submit 3 sets of final volumes within 2 weeks after practical completion. Incorporate
feedback from review and from training of Principal’s staff, including preparation and insertion of additional data.
Include a section containing commissioning test reports.
7 Revisions: Prior to final completion, submit 3 sections sets of loose leaf amendments for insertion in the manuals,
incorporating feedback from the maintenance period.
8 Warning and Cautions: Include to emphasise conditions hazardous to personnel or equipment, giving instructions
to avoid the hazard. Format to be:
9 WARNING: An examining or testing procedure or practice which must be observed or risk loss of life or injury to
personnel.
10 CAUTION: An examining or testing procedure or practice which must be followed or risk damage to equipment.
11 The manual shall be neatly prepared and bound in one, or a series of, vinyl hard-back folder with lettering on the
front and the spine including the following information:

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 49
1118/1.05
OPERATION AND MAINTENANCE MANUAL VOLUME NUMBER

PROJECT NAME DATE OF ISSUE

XX SERVICES CONTRACTOR

CONSULTANT ENGINEERS – WSP SUB CONTRACTOR

12 Pagination: Number pages consecutively. Double sided on A4 size (minimum 50%) recycled white (minimum CIE
whiteness of 140) paper, with reinforced binder perforations.
13 Ring size: 50mm maximum, with compressor bars.
14 Dividers: Durable divider for each separate element, with typed description of system and major equipment
components. Clearly print short titles under laminated plastic tabs.
15 Drawings: Fold illustrative drawings to A4 size and accommodate them in plastic pockets in the binder. Title block
to be visible without removal of drawing
16 All aspects of the style and quality of the manual, including folders and contents shall be submitted for approval
prior to completion.
17 After the draft copy, has been approved, supply 3 copies of the manuals for issue to the Principal and the Consultant
Engineer.
18 Allow for loading the manual onto the Building BAS systems (where available) and arrange to provide the manual
including commissioning results.

ELECTRONIC/DIGITAL FORMAT
1 Documents shall be stored in DVD Disc or Potable USB Flash Drive Storage Drive. Provide labelling to the storage
media.
2 Electronic Storage device shall not be “copy protected”.
3 Manual shall be contained within a single searchable PDF accessible via Adobe or similar PDF reader. PDF shall be
indexed, divided in to folders and titled. Each folder shall contain relevant electronic/digital format documentation
in line with the contents specified below. Refer below of a screen print of Adobe Reader for a typical arrangement.

“Screen Shot” for Reference

4 Avoid submitting manually scanned Manufacturers’ data, where possible include only searchable PDF
documentation.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 50
1118/1.05
5 Include only relevant diagrams, equipment data in clear concise English. Avoid jargon and esoteric pseudonyms.
6 Provide each document included in the PDF with the following naming convention:
7 Section “X” – “Document Description”.pdf
8 Provide clear scanned copies of Statutory Certificates of Compliance
a Accessible Dwg format CAD drawings of the as-built documentation shall be contained within the PDF.

INSTALLATION MANUAL FORMAT


1 Section 1 – Index
a Index all sub-divisions of each section including lists of drawings, equipment, etc. for quick reference.
b Include index in every volume of the manuals.
2 Section 2 - General Description and Capacities of Installations:
a Divide into sub-sections for general items and for each individual system as appropriate and include full details
b Include a directory: Names, addresses and telephone, email and facsimile numbers of Principal, Consultant
Engineer, Sub-Consultants, Contractor, Sub-Contractors and names of responsible parties.
c Include a scope of works: Statement of scope of services and interfacing with other Contracts.
d Include an installation description: General description of installation.
e Systems description: Technical description of the systems installed, written to ensure that the Principal’s staff
fully understand the scope and facilities provided. Identify function, normal operating characteristics and
limiting conditions. Include schematic diagrams.
f System performance: Technical description of the modes of operation of the systems installed.
3 Section 3 – Equipment:
a Sub-divide as for Section 2 and list all major items of equipment installed complete with manufacturer's name,
agent's name, contact details, model and/or type No., serial No., size, design ratings and including all relevant
data necessary for re-ordering or replacing the equipment or components of same. As far as practicable, all
equipment should be broken down to individually identifiable items.
b Provide manufacturers’ technical literature for equipment installed, assembled specifically for the project,
excluding irrelevant matter. Mark each product data sheet to clearly identify specific products and component
parts used in the installation and data applicable to the installation. Do not include advertising literature. Cross
out any section of literature which is not applicable to the project.
4 Section 4 – Installation, Maintenance and Operating Instructions:
a Sub-divide as for Section 2 and include manufacturer's installation, maintenance and operating instructions for
each item of equipment.
b Emergency maintenance procedures, including telephone numbers for emergency services and after hour’s
contact for suppliers and Contractors and procedures for fault finding.
c Manufacturer’s technical literature as appropriate. Register with manufacturer as necessary. Retain copies
delivered with equipment.
d Detailed recommendations for preventative maintenance frequency and procedures which should be adopted
by the Principal to ensure the most efficient operation of the systems installed. Include inspection, testing and
maintenance programme in tabular form showing frequency and level of routine checks for each item.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 51
1118/1.05
e Safe trouble shooting, disassembly, repair and reassembly, cleaning, alignment and adjustment, balancing and
checking procedures. Provide logical step-by-step sequence of instructions for each procedure. Include
calibration and recommissioning of controls.
f Schedule of spares recommended to be held on site, being those items subject to wear or deterioration and
which may involve the Principal in extended deliveries when replacements are required. Include complete
nomenclature and model numbers, and local sources of supply. Include sectionalised diagrams of machines
identifying component parts.
g Schedule of normal consumable items, local sources of supply and expected replacement intervals up to a
running time of 40,000 hours. Include lubricant and lubrication schedules for equipment where applicable.
h Add to the manufacturer’s technical literature, for assembly, operating, maintenance and disassembly, safety
information for all plant, systems or structures installed within the project or for existing plant, systems or
structures where assembly, operating, maintenance and disassembly are altered or amended by the installation
of plant, systems or structures within the project.
i The added safety information shall be included at relevant sections of the manufacturer’s literature and not as
a separate part and shall be made clear and obvious to the user of the manual.
5 Section 5 – Plant Operating Instructions:
a Sub-divide as for Section 2 and provide a complete description and correct sequence of all actions necessary to
start-up, operate and shut-down all plant including procedures for seasonal changeovers where applicable.
These instructions shall include full information on such items as normal and abnormal gauge readings,
instrument settings and control points, differentials, time delays, oil levels, water temperatures, and all similar
relevant variable and adjustable items, to permit checking and adjustments where practicable and
identification of hazardous conditions or malfunction of plant. In addition, the instructions shall include
information on the immediate action to be taken in the event of hazardous conditions arising.
b Add to the manufacturer’s technical literature, for assembly, operating, maintenance and disassembly, safety
information for all plant, systems or structures installed within the project or for existing plant, systems or
structures where assembly, operating, maintenance and disassembly are altered or amended by the installation
of plant, systems or structures within the project.
c The added safety information shall be included at relevant sections of the manufacturer’s literature and not as
a separate part and shall be made clear and obvious to the user of the manual.
6 Section 6 – Performance Test Results:
a This section shall be sub-divided as for Section 2 and shall include all performance test results as outlined in
previous Clauses.
7 Section 7 – Certificates and Warranties
a Statutory Certificates of Compliance for:
b Electrical work.
c Plumbing drainage or gas-fitting work.
d Refrigeration or air conditioning and ventilation work.
e Copies of manufacturers’ warranties.
f Certificates from authorities and utilities.
g Production certification.
h Copies of test certificates for the installation and equipment used in the installation.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 52
1118/1.05
8 Section 8 – Drawings
a Drawings and technical data: As necessary for the efficient operation and maintenance of the installation.

6.5.4 WARRANTIES
Warranty periods are deemed to end at expiry of defects liability period unless specified otherwise.
Name the Principal as warrantee. Register with manufacturers as necessary. Retain copies delivered with components
and equipment.
Commence warranty periods at practical completion or at acceptance of installation, if acceptance is not concurrent
with Practical Completion.
If installation is not being manufactured and product warranty is conditional on the manufacturer’s approval of the
Contractor, submit the manufacturer’s written approval of the installing firm.

6.5.5 REQUIRED OPERATING INSTRUCTIONS


1 Provide operating instructions and schematic diagrams mounted alongside equipment to meet statutory
requirements, e.g. Fire Brigade. Diagrams to be colour-coded, colour-fast, laminated and mounted.

6.5.6 TRAINING OF PRINCIPAL’S NOMINATED PERSONNEL


1 The service of a fully knowledgeable Commissioning Engineer shall be required for a period of 2 full working weeks
to instruct the Owner's nominated representatives in all details of the plant operation.
2 Conduct training at agreed time, at system or equipment location.
3 Immediately after Practical Completion, explain and demonstrate to the building users or nominated
representative, the purpose, function and maintenance of the installations.
4 Use qualified personnel who are knowledgeable about the installations.
5 Prior to Practical Completion, explain and demonstrate to the Principal’s nominated personnel the purpose,
function, operating and maintenance of the installations.
6 Use items and procedures listed in the Operation and Maintenance manuals as the basis for detailed instruction of
Principal’s nominated personnel.
7 Conduct training at agreed time, at each system of equipment location.
8 Upon completion, submit certificates of training, signed by trainer and trainees.
9 Provide qualified manufacturer’s training representatives who are knowledgeable about the installations
10 The services of the Contractor’s Commissioning Engineer and BAS controls commissioning engineer shall be
required for a period of 8 weeks after Practical Completion to assist the operator in the operation of the Facility.
11 During the warranty period, provide technical assistance and advice to the Principal’s nominated personnel
regarding the operation and maintenance of the plant.
12 For equipment requiring seasonal operation, demonstrate during the appropriate season and within 6 months of
Practical Completion.
13 Include copy of training material within the O&M Manual

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 53
1118/1.05
6.5.7 SPARE PARTS SCHEDULE
At least 8 weeks before the date for Practical Completion, submit a schedule of spare parts necessary for maintenance
of the installation. State against each item the recommended quantity, and the manufacturer’s current price, including
for
1 Packaging and delivery to site;
2 Checking receipt, marking and numbering in accordance with the spare parts schedule;
3 Referencing equipment schedules in the operation and maintenance manual; and
4 Painting, greasing and packing to prevent deterioration during storage.

POST PRACTICAL COMPLETION AND DEFECTS


LIABILITY PERIOD

6.6.1 WARRANTY AND DEFECTS LIABILITY


Warrant the whole of the Contract Works, for the Defects Liability Period (DLP), against defective workmanship and
materials and against non-compliance of equipment and/or complete system with specified performance and
operation.
The Defects Liability Period shall continue for a period of 12 months after the date of issue of Practical Completion and
during this period, the Contractor shall be responsible for making good on a timely manner, defects arising from the
defective design materials, premature component failures, or workmanship or from any act of the Contractor that may
develop in the work.
Perform maintenance during the warranty period to maintain warranty conditions. Maintenance shall comply with
the current regulatory requirements.
In the event of inclusion of equipment normally covered by a lesser time warranty, or whose warranty would
otherwise normally expire during the warranty period, allow for and include the costs of extending such warranty to
that covering up to the end of the Defect Liability Period.
Where warranted work or equipment has failed, the warranty shall recommence on the date of acceptance of the
rectified work for an additional period of time, extended by the period during which the Principal was without the use
of the work or equipment. For rectified work involving new replaced equipment, the warranty for the new component
shall be from date of replacement for the 12 months or longer as required by this specification

6.6.2 GENERAL DLP MAINTENANCE SCOPE


Maintenance services shall include:
1 Preparation of a maintenance management plan which includes a detailed maintenance programme, equipment
schedules, statutory and preventative maintenance schedules, OH&S risk assessment, inspection and testing
schedules, breakdown rectification management and reporting systems. Submit maintenance plan and schedules
prior to Practical Completion
2 Preventative and corrective maintenance and testing services to assure specified system reliability and availability.
3 Statutory maintenance and testing required by the Building Regulations and other authorities.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 54
1118/1.05
4 Breakdown and system fault responses. Attend site, ascertain cause of alarm and rectify where possible. Make
system alterations at own cost to prevent future system faults. Pay any Authority charges resulting from callout on
system faults.
5 Statutory regular system fire and life safety system control and performance verification test to be carried out after
hours.
6 Comply with Building and Occupational Health and Safety Regulations. Comply with manufacturer’s recommended
maintenance programme and schedules.
7 Monthly maintenance and servicing in accordance with maintenance schedules recommended by equipment
manufacturers.
8 Rectification of defects at Contractors cost.
9 Replacement of consumables at Contractors cost during the maintenance period.
10 Submission of monthly reports to Principal and Consultant Engineer on maintenance activities performed.
11 Provision and filling out log book which must be kept on site, detailing all visits.
12 Service personnel to be available for call out on a 24 hour per day, 7 day per week basis. Response time for emergency
and corrective maintenance must not exceed 2 hours.
13 Comply with AS/NZS 3666.2. AS/NZS 3666.3 and AS/NZS 1677.2.
14 Maintenance, testing and inspections in accordance with regulatory requirements and relevant Australian
Standards industry guidelines. (such as AIRAH DA19 HVAC&R Maintenance Manual).
15 Operation and verification in conjunction with other services trades, of all fire and life safety systems. Such testing
to be undertaken at 6 monthly intervals.

6.6.3 FINAL COMPLETION


Final Completion will not be granted until maintenance records are complete and signed off and until all defects have
been rectified and inspected.
The Maintenance and Defects Liability Period may be extended unless maintenance and servicing visits have been
made and reported as specified.

6.6.4 SUBMISSIONS
1 Provide;
a Maintenance management plan.
b Monthly Maintenance reports.
c Completed maintenance records
Mandatory maintenance records to include monthly maintenance and service reports, including water treatment
reports, reports on all defects and their rectification, certification of the correct operation of essential services, a
maintenance log book and any other records which must be kept in order to comply with legislative or OH&S
requirements.
Monthly Maintenance and Service Reports to include:
1 Check list of all items serviced and inspected.
2 Description of maintenance performed.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 55
1118/1.05
3 Notes on supplementary maintenance required.
4 Comprehensive water treatment report.
Maintenance Log Book to include:
1 Schedule of all equipment.
2 Schedule of all control sensors and control set point values.
3 Register of maintenance visits and cross reference to service reports.
4 Register of work performed under headings of preventive maintenance, corrective and emergency maintenance
and defects rectification.
The Maintenance Log Book is to be kept in a locked cabinet provided for the purpose in an agreed location on site.
At the conclusion of each maintenance visit the log book is to be duly completed and signed off by an authorised
representative of the Principal /Building Owner and service records are to be forwarded to the Principal /Building
Owner or his representative within 3 days of each visit.

6.6.5 DLP PREVENTATIVE MAINTENANCE AND TESTING

GENERAL
As a minimum, carry out all maintenance and servicing recommended by the manufacturer of each piece of equipment
at the recommended intervals

HYDRAULIC SERVICES REQUIREMENTS

As a minimum, regular maintenance and servicing tasks to include.

Monthly
1 Check all water & gas meters are operational and monthly readings are within seasonal limits
2 Clear as necessary drip trays, strainers and other sediment collecting items.
3 In large toilet or shower areas check for sewer smells, ensure all traps are being primed and sanitary vents are in
good working order.
4 Check reduced pressure zone valves are operational and complete a test discharge of water
5 Check all hot water heaters are in good working order, complete a test discharge of the pressure relief valves,
ensure safety tray are in good working order
6 Check hot water temperatures from basins are within limits and adjust where required
7 Check all stormwater downpipes are intact and water tight
Quarterly
1 Check all pump control panels are clear of dust and debris. Ensure audible alarms and strobes are clear and visible.
Check all building area isolation valves are in good working order. Including isolation valves to major toilet blocks
or riser connections
2 Check and adjust boilers, burners and water levels in water heaters.
3 Check plumbing pipework within walk in services ducts, including wall hung cisterns, urinal flush valves and
priming devices
Six monthly

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 56
1118/1.05
1 Check all roof sections, sumps and gutters are clear of organic debris and fines. Jet blast clean and repair all
damaged over flashing and ;
2 Check all grease interceptors and settling tanks have lids and frames secured and no stormwater ingress.
3 Check all gully traps and grates are secure and jet clean as required
4 Check all manhole lids and stormwater water headwalls are clear of debris
5 Check all external hose taps are not leaking and have backflow device fitted where required.
Last maintenance visit at 12 Months
1 Complete all 6 month checks
2 Complete Hot water warranty testing as noted in manufactures warranty requirement.
3 Replace all filter media disposable filters and UV lamp.
4 Flush all WC’s and check for cistern leaks, test all sanitary fixtures with hot and cold water flush
5 The date for the final maintenance visit to be advised 7 days prior to the proposed visit so that a representative
may be present to inspect the equipment when end covers are removed.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 57
1118/1.05
7 SEWER DRAINAGE SYSTEMS
GENERAL

1 Make the connection to the local authority’s connection branch in an approved manner and to local inspector’s
requirements.
2 Ascertain the depth, position and suitability of the sewer connection points prior to the commencement of any
work and incorporate any adjustments required to execute the work. No claims for redundant work will be
considered due to failure to comply with this requirement. Make connection to the property drainage connection
branch.
3 Pipelines shall be laid true to line and bore from point to point.
4 Unless otherwise indicated on the drawings pipelines shall be graded in accordance with the Authorities
requirements and as specified under “Excavation & Pipework Requirements” section.
5 Supply and install an overflow gully to provide a safe release from the connection point. Gully shall be
constructed of 100mm diameter “P” trap and 100mm riser. Top of riser shall incorporate 200mm cast iron grate
with concrete surround. Terminate gully top to comply with current authorities’ regulations.
6 Provide a hydrostatic test to choke level for a minimum period of 15 minutes and as required by the testing
authority.
7 Provide and install clear-out inspection fittings to provide rodding access to all lines. Riser from pipeline shall
extend vertically to finished floor level and terminate with a brass screw out and frame.
8 Supply and install all reflux valves in the locations indicated or as required by the local authority and as specified
in the “Materials” section
9 Carry out all necessary concrete encasing as specified in “Excavation & Pipework Requirements” section and as
shown on drawings
10 Supply and install all basket traps in the locations indicated on the drawings or as required by the local authority
and as specified in the “Materials” section.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 58
1118/1.05
8 SANITARY PLUMBING SYSTEM
GENERAL
Sanitary plumbing works above ground shall include all those works generally considered by authorities and trade
practice to be soil, waste, vent above ground as distinct from drainer's work.
1 Terminate all vents through roof with a cowl. Finish vents 3 metres above ground level, 300mm above roof level
and 6 metres clear of openings and fresh air intakes as required by the local authority and as indicated on the
drawings. Flashing of vents, which penetrate the roof, shall be carried out within the hydraulics scope of works.
2 Install inspection openings in accessible locations so that each section of pipework can be cleaned. Inspection
opening sizes shall be in accordance with authorities’ requirements. Install testing gates on all stacks at every 5th
floor level and at the base of each stack.
3 Supply and install approved expansion joints to all soil, waste, relief and main vent lines. Expansion joints shall be
installed on each line at intervals not exceeding 3000mm on both vertical and horizontal pipelines and on either
side of building expansion joints
4 When a branch line enters a vertical pipe the branch fitting must be wholly outside the vertical pipe such that the
internal bore of the pipe is maintained at all times. For vertical branches of up to and including 80mm a radius of
at least 25mm must be maintained on the throat of the bend and a radius of 50mm for larger junctions. All
horizontal branches shall connect to the main branch line through a 45° or sweep type junction
5 Use sweep bends of 300mm radius (or alternatively 2off 45° bend), and provide maximum fall between bends
6 Traps shall be of the same material as the branch drainage except traps in visible locations shall be chrome plated.
Refer “Materials” section for specified pipework.
7 Unless otherwise noted all pan collars to soil type fixtures shall be of approved PVC materials and pattern. Collar
shall incorporate an approved neoprene rubber ring joint
8 Pipe wrapping shall be Soundlagg 4525C or approved equal. Ensure all drainage pipework located over sensitive
area are acoustically insulated
9 Use trap with 100mm riser and 50mm or 65mm outlet of self-cleansing pattern. Grate to be as specified in the
“Materials” section.

FIXTURE TRAPS
75mm water seal traps shall be provided for the following fixtures:
1 Sinks 50 mm two part universal pattern.
2 Basin 40 mm CP copper two part S or P-trap with 40 mm CP extension riser.

INSULATION OF COLD WASTE PIPING


All waste pipes receiving discharge from cool rooms, FDC units and refrigerated cabinets which pass through areas
where condensate forming externally on the pipework may cause damage such as in multi-level buildings and car
parks shall be insulated.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 59
1118/1.05
The insulation material shall be “Thermotec 4 Zero” low temperature pipe insulation or approved equal with
aluminium foil outer sheathing and shall be fully vapour sealed at all joints with aluminium adhesive tape strictly in
accordance with the manufacturer’s recommendations.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 60
1118/1.05
9 STORMWATER DRAINAGE &
DOWNPIPE SYSTEMS
GENERAL
1 Make the connection to the local Authorities stormwater in an approved manner and to local Authorities
requirements. Ascertain the depth, position and suitability of the stormwater connection points prior to the
commencement of any work and incorporate any adjustments required to execute the work
2 Pipelines shall be laid true to line and bore from point to point.
3 Provide inspection pits at changes of direction. Pits to be reinforced concrete of appropriate dimensions to Code
with depths to match invert levels of pipeline
4 Install drainage turn up in spoon drains by terminating pipe collar at the invert of the spoon drain. Grates are
only required if specifically noted on the drawings. Encase drainage turn up riser in 150mm thickness concrete
surround.
5 Provide roof and balcony drainage outlets in the positions indicated on the drawings and as scheduled. Each outlet
shall be cast into the concrete slabs complete with rubber ringed inverted adapter and connection to the vertical
downpipes. Support each sump during construction with wire ties, set level both ways, to suit roof falls
6 The overflow system shall either directly discharge through the external walls or interconnect via a piping system
then discharge independently of the main stormwater runs.
7 Downpipes cast in columns shall be HDPE. Internal downpipes shall be provided with test gates at the base to
enable full testing. Flexible rubber ring joints are to be provided where the downpipe connects to the box gutter
outlet
8 Test gates shall be provided at the base of all internal downpipes and of the same size as the downpipes prior to
connecting to stormwater drainage lines. Inspection openings generally shall be provided at every junction, bend
and change of direction
9 Supply and fix approved, flat or domed type roof drainage outlets cast in the concrete roof structure in positions
indicated on the drawings. Set grates, flush and matching with adjoining surfaces. Grates shall have puddle flange
and membrane clamp
10 Where a branch line enters a vertical pipe, the branch fitting must be wholly outside the vertical and horizontal
pipe, such that the internal bore of the pipe is maintained at all times. All horizontal and vertical branches shall be
made at 45° to the main line

SUB-SOIL DRAINS
For sub soil drainage refer to Civil/Structural documentation.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 61
1118/1.05
10 DOMESTIC COLD WATER SYSTEMS
GENERAL
1 Locate valves behind access panels or within accessible ducts. Valves located in ground shall be provided with CI
path box and lid set into concrete surround with pipe riser around valve stem
2 Provide unions at wall or floor surface and at fixtures and appliances to allow removal and replacement without
the need to adjust connections.
3 To all changes of direction on rubber ring jointed pipelines below ground install concrete thrust blocks to restrain
the internal operating pressures of the pipeline under all conditions. Concrete mass shall be poured around and
behind fittings and bear against virgin soil material. A minimum of 0.75 cubic metres of concrete shall be used at
each position.
4 Unless indicated otherwise taps and faucets shall be all brass construction. All connections and cover plates shall
be bright chromium plated finish. Taps shall be fitted with anti-splash nozzles, except for hose taps and/or where
otherwise specified.
5 Supply and install an approved BFPD in the domestic cold water supply and irrigation system as required by the
Water Authority and as specified in the “Materials” section. Include maintenance instructions in as-built manuals
to be supplied at end of project establishing an authorised maintenance programme including registration and
certification of all installed devices. Provide isolation valves upstream and downstream of valve and line strainer
at inlet to BFPD. Flush piping before installing device and test device after installation and prior to operation in
service
6 Provide and install hose taps with anti-vandal heads. Each tap shall consist of a 20mm diameter copper riser with a
back plated elbow and a 20mm diameter brass finish hose tap. The tap shall be 450mm above the floor unless
otherwise directed. Install back flow prevention suitable for hazard rate of the area which is being servred by hose
taps.
7 Provide a water pressure test of 1500 kPa for a period of two hours. Disconnect any equipment connected to the
service not rated to the test pressure, before testing commences
8 Allow to provide a water supply connection from the cold-water service in size as nominated on the Fire Services
drawings and terminate with a blank Table E flange at the hydrant booster assembly. Refer fire services drawings
for pipework continuation.
9 Provide a water pressure test of 1500 kPa for a period of two hours. Disconnect any equipment connected to the
service not rated to the test pressure, before testing commences

CONCRETE COLD WATER STORAGE TANK


Provide and co-ordinate all connections as follows, and as further detailed on the drawings.
1 Tank panel support beams (co-ordinate only).
2 All inlet and outlet connections.
3 Sludge drain and overflow.
4 External and internal stainless steel access ladders.
5 Electronic water level controls and alarms.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 62
1118/1.05
6 “Light Proof” roof.
7 Roof access hatch and inlet box.
8 All internal components below water level shall be stainless steel.
9 Visual water level indicators.
10 Wave eliminator tube – for level controls (transparent).
11 Vortex plate.
12 Puddle flanges for all connections to tank.
13 All surfaces in contact with potable water to comply with AS 4020:2018.

FLUSHING & CLEANING


1 Immediately after the satisfactory completion of the sectional/first fix and the whole system/final fix hydraulic
pressure tests the Hydraulics Sub-contractor shall flush out, remove all foreign matter and clean all the systems.
2 Water systems shall be flushed out with clean water. Whenever possible the flushing medium shall be fed into
the system at high points and flushed out at low points on the system via suitably sized valve
3 The flushing and cleaning medium shall be fed into the system at the highest pressure that the system will safely
withstand and be carried out for a sufficient period of time to ensure that all foreign matter is removed.
4 The flushing shall be witnessed by the Superintendent for the duration of the flushing of each service and shall be
recorded by the Hydraulics Sub-contractor and certified by the Managing Contractor

BACKFLOW PREVENTION
Provide approved BFPDs in the domestic water supply as required by the Authority
Provide isolation valves upstream and downstream of valve and line strainer at inlet to BFPD.
Flush piping before installing device and test device after installation and prior to operation in service

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 63
1118/1.05
11 DOMESTIC HOT WATER & WARM
WATER SERVICES
GENERAL
1 Provide unions at wall or floor surface and at appliances to allow removal and replacement without the need to
adjust connections
2 Supply and install control valves to each group of fixtures. Locate behind access panels or within accessible ducts.
3 Make adequate provision for expansion and contraction by the provision of clips/brackets with wooden
expansion blocks so that under all working conditions no strain is imposed on pipework or fittings, Pipes located
in walls and floors shall be provided with sufficient insulation so that expansion and contraction does not impose
a strain on the pipework or finished surfaces. No joints will be allowed within or under concrete slabs where slab
is on ground.
4 Branch pipes off straight lengths of unrestrained supply pipes shall incorporate a minimum of 3 long radius pipe
bends and a straight length of pipe not less than 1000mm long between the branch connection and the first
branch pipe restraint to facilitate movement of the supply pipe without imposing strain on the pipe connections
and fittings.

HOT WATER HEATERS


Provide heaters with the following:
1 An automatic surface mounted temperature control thermostat with adjustable ranges on automatic over-
temperature cut out to shut down the fuel or power supply should the thermostat malfunction.
2 A temperature and pressure relief valve to conform to the requirements of AS 1357 and terminate over a tundish
or FW as noted on drawings.
3 Electric hot water heaters shall be in accordance with AS 1056 and be tested and approved by the electrical supply
authority.
4 Gas hot water heaters shall be in accordance with AS 5601 and be read in conjunction with AS 1056 Parts 2 and 3.
5 A safe tray shall be supplied and installed under the hot water heater. A 32mm outlet shall be fitted and sealed to
the tray and discharge as noted on the drawings.
6 Hot water heaters shall be mounted on the safe trays and supported on 40mm x 25mm hardwood batons, no closer
than 20mm from the sides of the tray.

FLUES
Flues from the hot water heaters to be similar and equal to Abbey Dura Vent round twin wall type B, gas flue to
terminate above roof line with approved cowl and roof flashing. The flue pipes and fittings shall be securely held and
supported by non-combustible brackets for fastenings suitable for the design and weight of the flue system material
and to maintain the required clearance from building construction.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 64
1118/1.05
BACKFLOW PREVENTION
Provide approved BFPDs in the domestic hot water supply as required by the later Authority and as specified in the
“Materials” section.
Provide isolation valves upstream and downstream of valve and line strainer at inlet to BFPD.
Flush piping before installing device and test device after installation and prior to operation in service.

THERMAL INSULATION
Provide all necessary insulation to hot water piping to prevent heat loss.
Insulation shall not be installed until all relevant tests and inspections have been carried out.
Insulation shall be as specified in the “Materials” section.
The pipe insulation shall comprise closed cell polyethylene foam and shall be installed around the pipework surface as
tightly as possible without gaps, with the edges and ends tightly butted together.
All joints shall be taped using a 75mm adhesive backed PVC tape or, if faced with aluminium foil, joints shall be taped
using a 75mm pressure sensitive aluminium tape. Where necessary the preformed sections shall be cut (using a sharp
knife or scissors) and mitred, to ensure a tight fit around bends and at tees. Joints in insulation and at brackets, bends,
along longitudinal joints and elsewhere at 500mm centres shall all be taped as described above.
At union flanges, valves and strainers, or any areas share access is required for maintenance; insulation shall
incorporate the press seal fastener system.
Where supports and spacer blocks are used to support the pipework, the pipe insulation shall be butted tightly up to
the spacer blocks and sealed using a silicon sealant.
Apply insulation in accordance with manufacturer’s instructions in a neat and workmanlike manner so as to present a
smooth even finish.
Provide timber blocks at brackets to ensure even support without affecting insulation.
Insulation to piping chased into walls to be 10mm Ableflex or approved equal. Ensure that such insulation permits
adequate expansion and contraction.

REGULATORS
Provide regulators to inlet of hot water plant.
Regulators shall be capable of passing the required megajoules, and be approved by the Energy Retailer.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 65
1118/1.05
12 NATURAL GAS
GENERAL
1 Install regulators in the positions indicated on the drawings and under and over pressure shut-off regulator with
the capacity to pass the required amount of gas reducing the pressure from 210 kPa to 5kPa or 2.75 kPa. Regulators
are to be the OPSO type and be capable of delivering the required megajoule rating and be vented to the
requirements of the Gas Authority.
2 Allow to purge the pipework in accordance with standards and local authorities.
3 Gas pipework shall maintain a gradient of 1:230 unless otherwise indicated or directed by the gas authority. The
graded pipes are to grade to low points terminating in a tail pipe with a 20mm capped valve in an approved easily
located and nominated position
4 Provide all gas piping, appliance or equipment gas control valves, gas appliance regulators, stainless steel flexible
pipe connections, gas unions and ancillary fittings for all gas burning appliances and other equipment or
machines wherever located in the building to ensure the full operation of these items of equipment.
5 Before connecting gas to gas heaters, appliances and equipment ensure that the appliance is approved in
accordance with the requirements of the local Gas Examiner and is correctly installed and that all supports, flues,
connections, flame failure devices comply with the regulations.

GAS – SYSTEMS SHUT OFF


Supply and fix automatic shutdown control with bypass, as approved by the local Authority and the project Fire
Engineer, to shut down the gas supply if the automatic fire sprinkler/suppression is activated.
Automatic shutdown equipment shall incorporate valves, motorised valves, pressure switch, flanges and other items of
equipment as necessary. Connect control wiring from the emergency power supply for power operation of motorised
valves. The whole equipment shall shut down the gas supply during a fire event and must be reset manually before
gas supply can be restored.
Activation of each control valve (shut down gas supply) shall be from the fire indicator panel (FIP) and shall shut
down the gas supply when the following conditions are met;
1 Each FIP zone signal shall only be sent to relevant slam shut control valve during sprinkler/suppression activation
(not alarm)
2 All supply pipework passing through a fire compartment that is compromised, shall be shut down by the relevant
FIP zone signal , whilst maintaining all other gas supplies that reticulate through an uncompromised zone
Provide a set of voltage free alarm contacts to the Gas Service Automatic Shutdown valve for connection to the BMS
System. The Shut-Off system is to be similar to those manufactured by SCE Systems 3.

VALVE BOXES
Supply and install valve boxes for access to underground valves. The boxes shall be standard cast iron boxes with
hinged covers. Set tops flush with pavement surfaces, or 15 mm above unpaved surfaces. Provide an in situ concrete
surround 150 mm thick, to the top, bottom and sides of the box, with exposed surface steel trowelled. Set a shaft of
pipe beneath each box to give access to the valve. Stamp the box cover with the word "GAS".

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 66
1118/1.05
WALL BOXES
Provide wall boxes to accommodate above ground valves, regulators and the like. The boxes shall be constructed of
1.2mm stainless steel plate continuous welded box construction with leading edge folded twice at 90° to form 25 x
25mm frontal surround. Fix to masonry backing with four 10mm galvanised masonry bolts. Set the bottom of the box
to fall outward. Form four 10mm diameter holes in the frontal surround section at box floor level. Provide, to the box
floor inlet and outlet pipes, sleeves formed of 1.2mm thick steel tube with 1.2mm galvanised flanges to pipe diameter
plus 50mm. Bed each flange on epoxy mortar and rivet to the floor of the box with four 3mm diameter rivets.
Provide metal frame doors with 2.5mm clear float glass glazing. Affix to the glass with adhesive a white laminated
plastic label 200 x 100mm, engraved with red letters "IN CASE OF EMERGENCY BREAK GLASS AND SHUT VALVES".
Provide lock, keys and two 100mm brass hinges.

GAS SERVICES RISERS


All gas pipework risers shall be installed in pipe riser shafts containing gas services only. The services ducts/shafts
shall be ventilated at top and bottom in accordance with AS5601.1 appendix K, and shall form a single seperate fire
compartment. Allowances shall be made for adequate airflow and ventilation throught the enite riser shaft.
Horizontal penetrations shall be fire protected to ensure separate compartmentation is maintained in accordance with
the BCA.

GAS VERTICAL PIPE SUPPORT SYSTEMS


Gas pipework shall be installed in accordance with AS5601.1 appendix K sections K7, K8, and K9.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 67
1118/1.05
13 EXCAVATION
GENERAL
Refer Civil/Strcutural Engineer for all works associated with excavation.

BACKFILLING OF TRENCHES
Refer Civil/Strcutural Engineer for all works associated with backfilling of trenches.

SAND FOR BEDDING (SEWER PIPE)


Shall be approved and conform to the following: -
1 Loss of weight after thoroughly washing with water shall not exceed 10%.
2 Not less than 25% by weight shall be retained on Tyler 28 mesh sieve.

USE OF CONCRETE (SEWER PIPES)


Provide 20 MPa concrete not less than 100 mm thick with exposed surfaces cement rendered as follows:
1 Around pipes and fittings wherever required by appropriate authority.
2 Around pipes and fittings pass under footing beams to the invert of the footing beam.
3 Under and around bases of inclined junction and bends.
4 Under roadways and footpaths / stabilised sand 10 MPa only.
5 Where regulation cover cannot be provided over drains, surround pipes with 150 mm of 20 MPa concrete.
6 Provide 150mm thick pads under all vertical bends and on the outside of all changes in direction.

PITS (GAS SERVICES)


For below ground, house control valves in concrete access its with removable pit covers.
Pits to be constructed to give 300mm clear space all around the fittings in the pit.
Use Grade N20 concrete to AS 1379,100mm thick, reinforced with F82 fabric with concrete covers to AS3996. Mark pit
covers with the work ‘GAS’.
Grade floor to a point on one side and provide a gravity drain to remove water from the pit. Do not connect the drain
to other substructures or drains. Carry the pit walls up to 50mm above finished ground level. Cast in the pit cover
frame flush with the top. Trowel the top smooth.

PITS (STORMWATER)
Provide a smooth, seamless finish, using steel trowelled render or concrete cast in steel forms and as specified in the
“Materials” section.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 68
1118/1.05
Cove or splay internal corners with metal access covers and grates to AS3996.
The top of cover or grate, including frame in paved areas shall be flush with the paving surface.
In landscaped areas 25 mm above finished surface and gratings taking surface water runoff located to receive runoff
without ponding.

WARNING TAPES
All buried gas, water and fire services shall be identified with a 150mm wide polyvinyl chloride utility service warning
tape placed 75 millimetres above the top of the service.
The PVC strip shall be a continuous length coil and colour coded to international standards, in addition to naming the
service. e.g. BLUE - water supply.
The warning tape shall be equal in all respects to VINICOVER as distributed by VINIDEX TUBEMAKERS PTY. LTD.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 69
1118/1.05
14 TANKS
WATER STORAGE TANKS
Water storage tanks with pump suction shall have the following minimum requirements;
1 Total effective storage capacity shall not include upper freeboard (including inlet air gap), and lower freeboard
(prevent air suction and pump cavitation).
2 Tank shall have central divider splitting the tank into two effective halves.
3 Inlet shall be equally split into two delivering approximately the same flow to each half.
4 Outlet/pump suction shall be equally drawn from each tank half
5 Each half shall have ability to be isolated (inlets and outlets) to enable maintenance of tank half without effecting
continual operation
6 Pump suction shall have vortex plate in tank to reduce the lower freeboard volume.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 70
1118/1.05
15 MATERIALS
CONSIDERATIONS FOR MATERIALS ENGINEERING
Consideration for proposed materials, used to convey, support and fix services are an essential part of the engineering
design process for this project. Materials used for conveying of services could possibly be subjected to accelerated
surface corrosion from the sea water spray, high humidity and exposure of Ultra-Violet radiation, if inappropriate
materials and or surface treatments are selected.
All materials selected & installed for this project will be suitable for their location and environment. All materials used
for conveying of services will have a minimum replacement (life) period of 20 years. All materials used for supporting
& fixing of service materials will have a minimum replacement (life) period of 15 years.

MATERIALS AND WORKMANSHIP


All materials are to be new and the best of their respective kind. All labour shall be skilled in its particular craft and all
shall be in accordance with best practices for works of this kind. The items shall include all labour, equipment,
materials and transportation necessary to construct and complete the work.
All pipes and fittings must carry an Australian Standards approval, and watermark approval numbers.
All materials and workmanship not of the stated quality may be rejected.

CONCRETE
Concrete shall be of 25 Mpa strength, or as directed by the structural engineer. All site mixed concrete shall be of 4:2:1
mix. Mortar shall be 2:1 cement mix. Waterproof render shall be 3:1 mortar waterproofed, with approved brand of
waterproofing compound used directly in accordance with the manufacturer's direction.

COVERS AND FRAMES


Covers and frames shall be manufactured in accordance with AS3996 and be 'Havestock' or approved equal cast iron
covers and frames with all edges machine fitted and have removable plastic lifting hole plugs. Each cover shall have a
brass or stainless steel plate bearing the name of the service.
The covers and frames shall be set to the level of the finished surface and filled in with the same material as used for
the surrounding path or roadways, lawned areas shall be infilled with concrete. Brass edge trimmed covers and frames
shall be used in areas where tile, paver or carpet finish is required. All covers and frames shall have the manufacturers
recommended lubricant applied prior to installation.
All internal covers shall be lock down type.
Cover duties selected may not be appropriate for construction type traffic. Allow protecting installed covers during
the construction phase. All covers damaged shall be replaced without incurring additional costs to the contract.

TRENCH GRATES AND SUMPS


All trench grates, roof sumps and outlets, sump grates and frames used, shall be manufactured in accordance with
AS3996 and be of the required strength to carry the vehicular or pedestrian traffic. The trench grates used shall be

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 71
1118/1.05
longitudinal bar gratings suitable for vehicle and cyclist traffic, set flush with surrounding finished levels. Trench
grates in pedestrian areas shall be of the “heelguard” type.
Grates and frames may not be of appropriate duties to withstand construction traffic. Allow to protect installed grates
and frames during the construction phase. All grates damaged shall be replaced without incurring additional costs to
the contract.

FIXINGS
Fixings shall be 'Dynabolts', 'Dynasets' or equal approved rawl expansion type and shall be installed in direct
accordance with the manufacturer's instructions. Plastic or nylon type fixing or anchors will not be accepted.
Sure drive metal expansion anchors will be accepted on small-bore pipes up to 20mm diameter.

FLEXIBLE CONNECTIONS
Flexible connections or anti-vibration couplings shall be fitted to all pumping equipment and be 'S' flex flexible
couplings installed in accordance with the manufacturer's instructions. Flexible connections shall be the same size as
the pipe work, not the equipment.
Flexible connections shall be installed with the aid of adjustable threaded spacers and shall be adjusted correctly to
dimensions recommended by the manufacturer prior to fixing of the pipe work, the maximum angular deflection
allowed on the flexible connection shall not exceed five (5) degrees and shall be installed only where indicated on the
drawings.
Flexible connections on submersible pumps shall be jointed to pump/s and pipe work with male and female 'Kamlok'
quick release 'cam type' couplings.

FLANGES
Flanges shall conform to AS 2129, AS 2528 and AS 4087. Use brass flanges for copper tubing, galvanised mild steel
flanges screwed type for galvanised mild steel, cast iron flanges for cast iron pipes and PVC flanges for PVC piping.

GALVANISING
All galvanising of steel work shall be hot dip process in accordance with AS 1650 to give 0.1mm minimum thickness
coating.

UNIONS
Unions shall be four (4) piece compression type unions (2 part cones) or three (3) piece brass, bull nose taper type
unions. Brass and copper type union connections shall not be used under any circumstances, in concealed or
inaccessible locations.
Unions shall be located on the outlet side of all control valves.

VALVES
All valves used shall be in accordance with AS1628 and be Reliance Manufacturing Company” (RMC) or approved equal.
All valves shall be of one type and of one manufacturer. All valves shall be placed in easily accessible positions for
PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 72
1118/1.05
operation and repair. Valves in ducts shall be positioned at 600mm from the finished floor level, unless noted
otherwise on the drawings.
Control valves to main branch lines and outlet positions shall be of the gate or ball valve pattern. Elsewhere the
control valves shall be of the loose jumper pattern where required by code. All valves shall be tested to a pressure of
1700 kPa and marked by an approved Testing Authority.
Valves up to and including 50mm shall be screwed. Valves above that size shall be flanged with Table E flanges. All
valves shall be suitable for temperatures up to 90°C.
Spindles shall be non-rising type and must not project into the bore of the valve when the valve is in the fully open
position. The bore must be clear and unobstructed when in this position.

REFLUX VALVES
All valves shall be manufactured in accordance with AS1628, be fully approved and tested to a pressure of 2000 kPa and
marked by an approved Testing Authority. Valve shall be generally constructed of bronze, have replaceable valve discs
and be suitable for temperatures up to 90°.

BALANCING VALVES
Balancing valves shall be “Tour and Andersson Therm” valves with screwed connections.

PRESSURE LIMITING VALVES


Pressure limiting valves shall be “Caleffi” or equal approved. Strainers shall be fitted to the inlet side of the valves.
Pressure limiting valves shall be installed in parallel and under no flow conditions, still maintain the desired outlet
pressure. The valves and strainers shall be suitable for operation under the pressures and flows it shall be subjected
to. The valves shall be adjustable and the outlet and inlet ranges to be approved by the Consultant Engineer.

BALL VALVES
Ball valves shall be manufactured in accordance with AS1628, be fully dezincification resistant, watermarked to MP52,
full bore, and screwed BSP connection.
Ball valves may be used in preference to loose jumper type valves where approved by the authority.

THERMOSTATIC MIXING VALVES


The valve must have a wax element which gives complete fail-safe and have built in stop valves for serviceability. The
valve shall be a pressure balanced thermostatic mixer equal in all respects to “Enware”
All valves shall have their temperature set to code requirements and tested following completion of works and all test
results shall be recorded and included within the Instruction and Maintenance Manual. Testing shall include failsafe
testing with isolation of cold-water service. Provide signage where valves are concealed.
Temperature limiting (tempering) valves shall not be used.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 73
1118/1.05
SLUICE VALVES
All sluice valves shall be manufactured in accordance with AS2638 and be fully approved.

STRAINERS
‘Y’ strains shall be fitted upstream of all back flow prevention devices, TMV’s, solenoid and similar valves. ‘Y’ strainers
shall be approved by the local authority and be as manufactured by RMC or equal.

COPPER AND BRASS TUBES AND FITTINGS


Copper tubes shall be solid drawn in accordance with the following standards: -
1 Water Service Pipe AS 1432 Type A and B.
2 Waste pipes shall be as AS1432 Type D and Type B for fabrication of junctions, fittings to AS1589.
Brass tubes shall be solid drawn with minimum wall thickness of 1.6mm. Fittings for copper and brass pipes shall be a
minimum 60/40 gunmetal or brass and stamped by the approved Authority.

STAINLESS STEEL PIPES AND FITTINGS


Stainless steel pipework used for high pressure water services shall be schedule 10S, 316 grade and be “Prochem” or
approved equal. Fittings to be “Victaulic” or approved equal. Jointing method to be stainless steel compatible roll
groove.

GALVANISED STEEL PIPES AND FITTINGS


Galvanised pipe and fittings to be “heavy grade” for pipework subject to working pressures less than 1700kpa and
schedule 40 for pressures exceeding 1700kpa, with roll groove or flanged fittings

PVC PIPES AND FITTINGS


Sanitary and stormwater drainage shall be unplasticised polyvinyl chloride (PVC-U) drain waste and vent (DWV) with
solvent welded jointing. Class of pipe to be equivalent of SH for above ground and in ground up to 3000mm depth, for
depths greater than 3000mm class SHE or equivalent. The system shall be equal in all respects to “Iplex Pipelines”.
Water services in ground 100mm and larger shall be PVC-M with a class pressure rating to suit the application with
rubber ring jointing. The system shall be equal in all respects to “Iplex Pipelines BLUE Rhino”. Fittings shall be ductile
iron suitable for contact with potable water systems complying with AS/NZS4020. Fittings are to be equal in every
aspect to “Crevet”.
Sanitary and stormwater rising mains to be PVC-U Pressure Pipe class PN12 with solvent welded jointing.
The system shall be equal in all respects to “Iplex Pipeline Systems”.
Where a ring seal adaptor is fitted to the socket of the fittings, care must be taken to leave the required gap between
the end of the pipe and the shoulder of the socket of the fittings.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 74
1118/1.05
PE PIPES AND FITTINGS
All pipes and fittings must carry an Australian Standards approval, and watermark approval numbers.
All high density polyethylene (HDPE) pipe work and fitting joints shall be butt-welded or fused, utilising approved butt
fusion welding equipment under factory controlled conditions. Butt welds shall be used only on stormwater systems,
vertical plumbing stacks and vents. All sanitary and trade waste drainage (horizontal) shall have joints made with
electro fusion couplings. All site welds may be either butt or fusion, utilising approved butt fusion welding equipment
or electro fusion sleeves installed strictly in accordance with the manufacturer's direction. No other jointing methods
are to be used. All pipes and fittings are to be equal in every aspect to “Geberit HDPE”
Pipework used for pressure applications shall be PE100, SDR13.6, PN12.5 at a minimum. Pressure rating shall be
increased where required to suit the application. All pipes and fittings are to be equal in every aspect to “Iplex
Pipelines Poliplex”.
All persons carrying out the jointing procedure shall complete the installation course and be accredited by the
manufacturer prior to commencing works.
Confirmation of accreditation numbers of all personnel intending to install the HDPE system shall be provided prior to
commencement of works.

PE-X PIPES AND FITTINGS


Cross linked polyethylene pipes and fittings must carry an Australian Standards approval, and watermark approval
numbers.
Jointing shall be by specifically designed crimp press fit fittings. Pushfit type “pipe grip” fittings will not be permitted.
All fittings shall be of same manufacturer of pipework. Crimp tooling shall be approved by the manufacturer of the
pipe and fittings. Crimping methods shall be in accordance with manufacturers techniques.
Where possible pipework colour shall be selected dependant on the type of service.

PPR PIPES AND FITTINGS


Polypropylene pipes and fittings to be used for chemical sensitive drainage and be rubber ring jointed in accordance
with AS 1646. All pipes and fittings are to be equal in every aspect to “Valsir”.
Large stormwater pipework to be twin walled corrugated polypropylene with rubber ring jointing. All pipes and
fittings are to be equal in every aspect to “Vinidex Stormpro”.

POLYBUTYLENE HOT AND COLD WATER PIPEWORK


Polybutylene pipes and fittings for hot and cold water shall be a manifold system (as detailed on the hydraulic services
drawings) with an individual pipe run from the outlet of the manifold and/or control valve to each fixture and/or
shop tenancy.
Jointing shall be press-fit with continuous pipe runs from manifold to fixture, no joints or branches shall be permitted
between these two points.
The system shall be equal in all respects to the HEP2O polybutylene manifold system manufactured by HEPWORTH
BUILDING PRODUCTS.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 75
1118/1.05
JOINTING
All joints shall be cleaned free of any foreign material, dirt, and grease etc., before any attempt is made to do the joints.
Joints shall be cut true and square, remove all burrs and swarfs, etc. and grind or file a chamfer lightly around the pipe.
Polyvinyl chloride (PVC or PVC-U) pipes jointed by solvent welding of the type recommended by the manufacturer.
Clean joints with approved solvent cleaning fluid.
Silver Brazing Alloy shall contain not less than 15% silver; verification of the silver content shall be given in writing to
the Consultant Engineer. Care shall be taken not to overheat the joint. Apply the correct flux as recommended by the
manufacturer slightly carbonising flame shall be used. Failure to use 15% silver brazing alloy will result in rectification
of all joints.
Steel Pipe Welding (Fusion Welding). The joint shall be properly prepared before commencement and will be made in
accordance with AS CB15.
Bronze Welding the joint shall be chamfered and the filler rod and flux shall be of the type recommended by the
manufacturer.
Sewer Drainage - Rubber Ring Joints shall be in accordance with AS 1646 and installed in accordance with AS 1260.4, AS
2032. All rubber rings shall be of the type recommended by the manufacturer and approved by the local Authority.
Rubber ring jointed in accordance with the AS 1646 and the local Authority, and to be of the type and size
recommended by the manufacturer. Where the pipe connecting is of a different material - a varying size ring as
supplied by the manufacturer shall be used.
Flange type gaskets shall be material canvas or fibre reinforced rubber of 3 mm minimum thickness.
Lubricant for lubricating the rubber ring and insertion type gaskets and the outside surfaces of the spigot ends or
pipes shall be of an approved non-toxic vegetable based type and shall be applied in accordance with the
manufacturer's instructions.
Nuts and Bolts generally shall conform to AS 2451 and be heavily galvanised by the hot dip process. Where galvanised
iron to cast iron, and cast iron to cast flanges butt, brass bolts shall be used.
Silicone shall be Selleys or approved equal, have low VOC content and used as recommended by the manufacturer,
white shall be used around vitreous china sanitary ware and clear for seal under fixing taps stainless steel etc.

EXPANSION
Expansion for pressure type services where expansion shall be allowed for because of either excessively long runs
exposed to temperature variations (i.e. in excess or 20m), shall be allowed for by means of expansion loops or
approved mechanical expansion device.
They shall be of the type, material and manufacture approved by the Authority governing the works, and installed in
such a manner that the axial movement of adjacent sections of the pipe and to the extent that the pipe work is above
to extend to its possible maximum expansion in both directions without any restrictions.
Expansion joints shall be installed at intervals of no more than 20m and between fixed points exceeding three metres
(3m) on all horizontal lines and branches that experience temperature variations and pipes crossing structural
expansion joints.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 76
1118/1.05
TEMPERATURE GAUGES
Provide 100mm diameter waterproof temperature gauges on the outlet side of central hot water plant.

PRESSURE GAUGES
Gauges shall be AMBIT Model ME – AS B522 - 75L or equal. The face on the gauge shall be minimum of 100mm diameter
and gauges shall be waterproof and oriented so that the gauge can be read at a height of 1600mm above floor level.
Each gauge shall be complete with approved gunmetal stopcock and copper piping connected to the relevant pipe
work. Provide pressure gauges upstream and down stream of all pumping or pressure reduction devices and plant.

THERMAL INSULATION MATERIALS


Pipes shall be lagged to the manufacturer's standards or as specified in hot water insulation section. Where joints,
fittings, bends, branches and valves etc., the lagging shall be cut and trimmed to fit around the section and then taped
over.
Insulation shall be close celled polyethylene from “Thermotec” or approved equal. Insulations shall have no Ozone
Depleting Potential (ODP) in either its composition or its manufacture.

PRESSURE SWITCHES
Shall be 'Honeywell' pressuretrol or approved equal and adjusted in strict accordance with the manufacturer's
instructions.

ACOUSTIC TREATMENT TO PIPEWORK


Acoustic treatment, where necessary, shall be supplied and fixed as required to comply with BCA standards, and the
acoustic report. Accoustic insulation shown on drawings is indicative only and does not alleviate the contractors
responsibility to insulate all pipework as required.
Pipe wrapping shall be “Soundlag 4525C” or approved equal.

PROTECTIVE PIPE WRAPPING/COATING


All in ground metal pipes 80mm diameter and greater shall be protected by a polyethylene continuous sleeve (green
sock) sealed with a waterproof duct tape. The sleeving shall be fitted to affect a smooth, closely contoured envelope
with minimum barrel and socket gaps. There should be sufficient slack in contouring to allow the sleeving to follow
the profile of the spigot-socket interface to prevent damage during backfill.
Sleeving shall be equal to MAC-WRAP protective sleeving as distributed by CHARMAC INDUSTRIES PTY. LTD.
All in ground metal pipes smaller than 80mm diameter shall be wrapped with a layer of petrolatum impregnated fully
synthetic woven carrier tape.
All clean pipes and fittings shall be primed with a compatible priming paste prior to wrapping of the tape.
All pipes and fittings shall be covered with a minimum overlap of 30 millimetres.
Tape shall be equal in all respects to DENSO.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 77
1118/1.05
ROOF PENETRATION FLASHINGS
All service pipes penetrating the roof shall be made watertight by use of a flexible pipe flashing prior to fitting a cowl.
The pipe flashing shall be designed and installed to conform closely to the roof profile.
Seal the flashing by use of a neutral cure silicone sealant (HILTI CS204 or equal approved) prior to fixing the flashing
with 10-gauge zinc plated self-drilling steel screws, or equal approved.
Pipe flashings shall be equal in all respects to the standard round 'DEKTITE' roof flashings manufactured from
ethylene propylene dilne monomer polymer (E.P.M.D.) and distributed by DEKS INDUSTRIES PTY. LTD.

COLD WATER METERS


For Master cold water meters refer to Civil documentation.
Domestic cold-water services shall be fitted with a low friction turbine meter with integral line strainer, modular
meter insert and non-return valve.
All meters shall be fitted with upstream and downstream unions and an upstream control valve, and comply in total
with AS 3565.
All meters shall be fitted with upstream and downstream flanges and an upstream control valve.
All meters shall have provision for pulse output to future connection to BMS system. Pulse output shall be 1 pulse per
10 litres.

VALVE BOXES
Shall be "Havestock" or approved equal cast iron with an identification mark stamped on top.

CONCRETE THRUST BLOCKS


Concrete thrust blocks shall be constructed at all stop ends, fittings, changes of direction and on every fourth straight
and continuous length of pipe and where indicated on the drawings.
Thrust blocks shall be constructed for a minimum length of 500mm along the pipe and 300mm over the barrel of the
pipe, the trench shall be under cut for a depth of 150mm into both sides and the bottom of the trench, reinforcing steel
F82 shall be installed to tie the concrete around the pipe and into the rebates at the sides of the trenches.
The thrust blocks shall be supported or backed during the pour with approved formwork and the quantity of concrete
shall be not less than 0.5 cubic metres, concrete to be as previously specified, all joints in the pipe work shall be left
exposed.

BACKFLOW PREVENTION VALVES


Supply and install backflow prevention valves in accordance with AS/NZS 3500. All valves shall comply with AS 2845.1.
Allow all costs to register each valve with the local regulatory Authority and provide certification. Valves shall be
“Tyco” or approved equal.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 78
1118/1.05
16 PUMPS
DOMESTIC COLD WATER BOOSTER & PRESSURE
PUMPS
16.1.1 PUMPS TO COMPLY WITH THE FOLLOWING REQUIREMENTS
Pump set is to incorporate the following:
1 Multiple vertical variable speed displacement pumps.
2 Separate distribution board fitted with main power supply isolating switch with separate circuit breakers for each
unit.
3 Inlet side of each pump pre-plumbed with an isolating valve and non-return valve, connected to a common inlet
manifold with a neoprene vibration eliminator.
4 Discharge side of each pump fitted with an isolation valve and a common manifold is to be provided with a
separate main isolating valve, neoprene vibration eliminator and a full flow bypass. On the discharge manifold
65mm pressure gauge is provided together with a single pressure tank in accordance with the manufacturers
specification. This system will maintain a set pressure with a maximum variation of 2.0%.
5 Site commissioning by trained Service Personnel after installation by others.
Refer “Schedules” section for details.

16.1.2 CONTROL PANEL


Provide control panel, tank level controllers (for tank suction pressure pump sets) and wiring to give automatic
operation of pumps.
For control panel requirements refer to “Pump Control Panels” section.

HOT WATER CIRCULATING PUMPS


16.2.1 PUMPS TO COMPLY WITH THE FOLLOWING REQUIREMENTS
1 Provide and install pressure gauges and gauge control valves on the inlet and outlet of each pump.
2 Fit a “Gate” valve on the inlet of each pump and a balancing valve on the outlet of each pump.
3 Provide stainless steel flanged vibration eliminators on the suction and delivery connection to each pump.
Provide stainless steel vibration eliminators on the pipework connection to and from the pump set group.
4 Provide air eliminators on each side of the pump.
5 Provide and install anti-vibration mounts as required.
6 Provide electrical power, control and alarm wiring with conduits from the pumps electrical control panels to
pump motors. Pumps to have thermal overload protection auto/off/manual selector for each pump,
auto/change-over selection switch, motor, circuit breakers, AC on light, pump run lights, pump fail lights, alarm
button and mute button.
7 Electrical wire each pump for 24 hours running with an automatic change over to the second pump after each 24-
hour duty.
PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 79
1118/1.05
Refer “schedules” section for details.

16.2.2 CONTROL PANEL


Provide control panel, and wiring to give automatic operation of pumps.
For control panel requirements refer to “Pump Control Panels” section.

PUMP CONTROL PANELS


Supply and install all equipment necessary to operate the pumps specified under hydraulic services.
Allow for all control cabinets, mounting brackets, contactors, isolating and control switches, auxiliary switches,
alarms, wiring between pump and panel, panel and level controls, and other associated equipment necessary for the
safe and effective operation of the pumps as required for the installation and in accordance with statutory
requirements to AS 3000.
Provide a complete specification and drawings of pumps and control equipment prior to installation.

16.3.1 FUNCTIONS

ALL CONTROL PANELS


Each control panel shall contain the following minimum.
1 Circuit breakers for each pump.
2 Control circuit breaker.
3 Auto/Off/manual switch to each pump.
4 Automatic alternation of pumps.
5 Audible alarm complete with reset type mute button.
6 Individual digital hour meters for each pump operation.
7 All switches to be fitted in inner door to prevent unauthorised usage.
8 Individual digital hour run meters for each pump operation.

PUMP STATION CONTROL PANELS


1 Indicating lights for the following:
a power on 1 off
b pumps run 1 off for each pump
c pump fail 1 off for each pump
d high level alarm 1 off.
2 Volt free terminals on separate terminal strip for each pump run, each pump fail, high level alarm, wiring to
remote indication panel by other nominated Works Packages.

BOOSTER/TRANSFER PUMPS CONTROL PANELS


1 Indicating lights for the following:
a power on 1 off

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 80
1118/1.05
b pumps run 1 off for each pump
c pump fail 1 off for each pump
d low discharge alarm (will stop pumps) 1 off.
2 Volt free terminals on separate terminal strip for each pump run, each pump fail and low discharge pressure.
3 Low discharge pressure switch to stop pumps when pressure drops below 100 kPa.

PRESSURE PUMPS CONTROL PANELS


1 Indicating lights for the following:
a power on 1 off
b pumps run 1 off for each pump
c pump fail 1 off for each pump
d low storage tank level (will stop pumps) 1 off
e low suction (will stop pump) 1 off.
f low discharge alarm (will stop pumps) 1 off.
2 Volt free terminals on separate terminal strip for each pump run, each pump fail, low storage tank level, low
suction, low discharge, wiring to remote indication panel by other nominated Works Packages.

16.3.2 CONTROL PANELS – CONSTRUCTION


1 Control panel shall be provided to house electrical switchgear associated with pumps, and any other equipment
requiring electrical controls for proper operation and safety. The control panels shall be wall mounted adjacent to
equipment or in location shown with top at approximately 1800mm high above floor. In some cases, approval,
will be given for control panels to be mounted on equipment.
2 Control panels shall be totally enclosed cabinet type.
3 Control panels shall be designed for ease of access to all equipment and wiring and shall be provided with at least
10% spare space for the addition of future equipment.
4 Control panels shall comply with AS 1339 as follows:
a IP50 for internal locations.
b IP54 for external locations or where a weatherproof cabinet or enclosure is specified.
5 Doors shall have concealed hinges and an approved key operated lock.
6 Two locks for doors in excess of 1000mm.
7 Vertical locking bars to provide top and bottom fastening shall be provided on all doors exceeding 1500mm in
height.
8 A dustproof seal consisting of a substantial mould neoprene rubber strip shall be provided for doors or removable
panels and covers. Escutcheon panels need not be provided with seals.
9 Switches, indicators, etc. to which wiring is connected shall not be fitted on removable plates.
10 Where conduits or cables enter cabinets, (cables must enter from the bottom), drill the cabinet and locknut the
conduits or the cable glands to the cabinet. Note: No top or side entry without approval.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 81
1118/1.05
16.3.3 EQUIPMENT
11 DIN standard rail mounted terminal strips shall be provided for the termination of all external control circuit
wiring and BAS identification.
12 Equipment shall be neatly arranged and readily accessible for maintenance.
13 Each control panel shall be provided with an isolating switch, neutral and earth link.
14 Control switches shall be rotary type complying with AS 1431.
15 Indicator lights shall match control switches with colours as follows:
a RED Pump fail, alarm – e.g. High and low level.
b AMBER Pump running.
c GREEN Power supply on.
16 Circuit breakers shall be approved by Australian supply authorities and comply with Australian Standards.
17 Time clocks shall be quartz crystal oscillator type with an accuracy of plus/minus 5 minutes per annum and
complete with nickel cadmium battery to proved a 50-hour reserve/digital 100 hour.
18 Covered terminal strips with labelled terminals shall be provided for connection of the Building Management
System (BMS) wiring by others. Wiring to terminals shall provide voltage free contacts for all alarms and faults
and for pump running indication. Contacts to be either normally open or normally closed contacts.

16.3.4 LABELLING
19 All control panels and equipment shall be labelled with engraved laminated type labels. Labels shall be black and
white lettering. Size of lettering shall match importance and location. Labels shall be screw fixed.
20 Cabinets shall be labelled to indicate function
21 Equipment shall be labelled to indicate function and to identify any associated equipment e.g.:
a “PUMP CONTROL SELECTOR”
b AUTO/OFF/MANUAL.

16.3.5 TESTING
Test the system on completion. Furnish two copies of the manufacturer’s test certificate.

TANK WATER LEVEL CONTROLS


Provide a system of water level controls to the storage tank, to automatically operate the pumps and activate the
alarms, including wiring/connection to the pumps panel.
The water level controls shall be ultrasonic sensing type.
The sensor shall be mounted within the tank where it remains accessible and has an uninterrupted reading of water
levels over the entire height of the tank.
Functions shall include:
1 Activate High Level Alarm.
2 Stop Duty Pump.
3 Start Duty Pump.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 82
1118/1.05
4 Stop Standby Pump.
5 Start Standby Pump.
6 Activate Low Level Alarm.
Provide all control wiring between pumps in the pump room, and water storage level controls. The system shall be
installed in accordance with the manufacturer’s instructions and Authorities requirements. A 240-volt power supply
shall be provided by others.

FLEXIBLE PUMP COUPLINGS


Flexible connections or anti-vibration couplings similar to ‘S’ flex flexible couplings installed on the suction and
discharge side of each pump in accordance with the manufacturer’s instructions. Each flexible connector shall have a
hose length of not less than four (4) times the pipe diameter installed with a maximum angular deflection not
exceeding five (5) degrees.

PUMP MOUNTINGS
Pump mountings shall be Silentbloc or approved equal spring isolating mountings on an appropriate size to provide a
minimum 95% vibration absorption.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 83
1118/1.05
17 PIPING, VALVES AND FITTINGS
GENERAL
1 Supply piping in clean, full standard, straight lengths, free from any defects, mill scale, rust, burns, dents and
kinks and protected against mechanical damage.
2 Refer to the Piping Schedule for pipe systems, design pressures and temperatures and permitted pipe materials
and joining methods.
3 Refer to the Piping Systems test criteria and procedures schedule for pipe testing requirements.

DIMENSIONS ON SITE
Be responsible for taking all dimensions on site. The dimensions must be checked before work is commenced or
prefabricated. All levels and dimensions of existing services must be confirmed before commencing work. The invert
levels shown on the drawings are recommended only, and must be checked on site before excavation or installation of
pipe work to ensure connection to supply sources and fall to pipe work etc. is correct.

FIXTURE AND FIXTURE POINTS


Install and supply all materials, backing plate and noggins necessary to make all fixtures and fixture outlet points rigid
(i.e. sanitary fixtures and tap fittings etc.). All fixtures shall be connected via a service pipe and union type fitting. Nut
and olive connection is not acceptable. Direct connection of pipe work to the fixture will not be accepted.

PIPES IN SLAB
Under no circumstances shall any pipe work be cast in slabs, unless clearly noted on the drawings. Any hot and cold
water pipes noted as being 'in slab' shall be contained in UPVC/polyethylene conduits and these pipes shall be totally
retrievable.
The HDPE cast in concrete sanitary plumbing system shall be cast in without any sleeving or wrapping in accordance
with AS 2033 and the manufacturer’s requirements.

SETTING OUT
Set out and identify all trenches, pits, pipelines and plant equipment positions.
Gain approval for the proposed location of the works prior to commencement of any excavation.
Larger scale drawings are to be used in preference to small scale where no dimensions are shown.
Architectural dimensioned drawings are to be used in preference to scaled drawings regardless of their relative scale.
1 Trenches:
a Interpret all levels and grades to determine correct falls to pits and street connections. Advise if grades
cannot be met so that he may determine revised locations or grades for the works.
b The set out of piping, pits and covers shall be arranged in conjunction with other trades so as to be readily
accessible for operating, servicing, maintaining and repairing of it.
PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 84
1118/1.05
c Under no circumstance shall the Authorities and/or the Contractor conceal any drainage pipes etc. before
inspection and approval.
d Piping, pits, etc. which are installed in unsuitable locations shall be removed and relocated as directed by the.
All expenses caused by this action shall be made good without extra charge.
2 Core Holes:
a Set out all core holes and openings as required and necessary for the passage of pipes and/or conduits
throughout the existing structure. Arrange for approval from the Structural Engineer to drill such holes or
openings and pay all cost involved where required in existing slabs.
b Core holes within "in situ" slabs shall be formed using "Gatic" preformed units installed in accordance with
the manufacturer's instructions.
c Do not cut any holes, openings, and chases or otherwise interfere with the work of other trades without the
specific approval of the. Any damage done to other trades shall be made good without extra charge.
3 Cutting of Concrete Floor Slabs and concrete reinstatement:
a Set out lines of trenches and gain structural engineers approval before cutting slabs. Cut slabs to a minimum
depth of 100 mm. Break out slabs and remove spoil form site.
b Demolish slabs as required to enable excavation and installation of all hydraulic services.
c Saw cut topping and structural slab in straight lines. The Hydraulic Services Works Package shall backfill and
compact trenches etc, as specified. Reinstatement of slab will be by Concreting Works Package.
d The Hydraulic Services Works Package shall remove and dispose of demolished and excavated materials from
demolition of topping, slab and trench excavations.
4 Accessibility:
a The set out of piping, valves and equipment shall be arranged in conjunction with other trades so as to be
readily accessible for operating, servicing, maintaining and repairing of it.
b In no circumstances shall the Authorities and/or the Contractor conceal any pipes, valves, etc. before
inspection and approval.
c Piping, valves, etc. which are installed in unsuitable locations shall be removed and relocated as directed by
the. All expense caused by this action shall be made good without extra charge.
d If neither the specification nor plans contain any mention of minor parts, which in the opinion of the
Superintendent are reasonably and obviously necessary for the satisfactory completion of the Hydraulic
Works Package, such parts are to be provided without extra charge.

GENERAL PIPING INSTALLATION REQUIREMENTS


1 All screwed joints shall be made with the best quality pipe joint compound, carefully placed on the threads of the
pipe and not through the fittings.
2 After cutting, all piping, burrs and sharp edges shall be reamed out.
3 Care should be taken when erecting piping; any marked, dented or otherwise damaged piping shall be replaced in
a satisfactory manner.
4 Piping shall be installed as direct as possible between connecting points and parallel to walls.
5 Unless otherwise noted, all piping shall be kept as high as possible to beams, slabs, so as to maintain maximum
headroom.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 85
1118/1.05
6 Obtain approved ceiling heights and install work to clear obstructions and co-ordinate with work of other trades.
7 Connections between pipe, fittings, hangers and equipment of dissimilar metals shall be avoided where possible.
8 Provide a minimum 3 mm thick extruded flexible PVC insulation between supports and service pipe of dissimilar
materials and PVC piping. TAPE WILL NOT BE ACCEPTABLE.
9 Piping shall be carefully installed to provide for proper alignment, slope and expansion, guided and supported in
such a manner so that piping will not sag, buckle or cause water hammer.
10 Provide unions or flanges at connections to each piece of equipment, etc. for easy dismantling and at such other
points to facilitate installation.
11 All fittings and connections at pumps, tanks or other major equipment, 65 mm and over shall be assembled with
flanged joints.
12 All unnecessary lengths of male threads located in exposed pipe work within exposed areas/rooms shall be
trimmed to the minimum necessary lengths.
13 They shall allow for all necessary trimming and machining of threads to obtain the requirements of this clause.
14 Provide special (and approved) threaded sections where necessary.
15 Remove all unnecessary hemp or other jointing materials from joints.
16 Except where otherwise specified, mitred joints shall not be permitted.
17 The arrangement of all piping shall be generally as shown on the drawings.

SUPPORT AND FIXING OF PIPEWORK


Pipes shall be adequately supported and secured in an approved manner.
Pipes shall not be fixed to, supported by, or welded to other pipes.
Pipe work must be free to move without causing stresses in the pipe work or pipe joints. Where provision has been
made for movement in mains, the branch lines shall be unrestrained and in the case of copper tube, annealed for a
minimum of 1500 mm from the main. Where this is not achievable, some other approved provision for movement shall
be made.
Vertical pipes passing through floors shall be supported at maximum 2400 mm centres. Support horizontal pipes at
maximum 1800 mm centres.
Support all pipes except sheet metal gutters and downpipes with galvanised concrete inserts, channels, and pipe
clamps, and pipe hangers, etc. in accordance with the manufacturer's instructions and complying with the catalogue
regarding spans and loads.
Secure all supports and necessary sanitary fixtures with approved "Rawlock" metallic anchors or equal.
Power-driven fixings, wooden plugs or screw-ins shall NOT be used.

BUILDING EXPANSION JOINTS


Crossing building expansion joints with pipelines shall be avoided where possible. Where this is not possible, lines
adjacent to a building expansion joint shall be located in a readily accessible position and fitted with an approved
expansion joint.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 86
1118/1.05
JOINTS IN COPPER PIPING
All joints in copper pipe work shall be made by brazing with low temperature silver brazing alloy containing not less
than 5% silver (15% for gas piping). Use oxy-acetylene heating for all low temperature brazing.
Flux shall be as recommended by brazing alloy manufacturer.
Slip joints shall be permitted to join lengths of copper pipes and shall be made by annealing and expanding ends with a
proper tool to form a slip (capillary) joint.
Fabricated tees or junctions in copper pipe will not be permitted.
Valves shall not be brazed direct onto pipes. Valves shall be indirectly joined to pipes by the use of flanged or screwed
adaptors, which shall be silver brazed onto the pipe and then screwed to the valve. Care shall be taken to prevent
distortion to the valve and/or valve seat.

JOINTS IN COPPER PIPING – PRESS FIT

17.10.1 WATER
Connection with press-fit fitting made of copper or gunmetal. Inspection of un-pressed fittings utilises a positive leak
path for the whole range 2.2kPa to 300kPa when a dry pressure test is performed and 100kPa to 650kPa with a wet
pressure test. This warranted safety function is facilitated by a channel in the metallic body of the fitting. After
pressing, the connection is permanent and inseparable with the safety function effectively removed during the
pressing process. The seal is made of EPDM, with performance characteristics allowing use in solar applications. The
fitting body has a cylindrical pipe guide in front of the seal. Fittings carry Watermark Approval

17.10.2 GAS
Connection with press-fit fittings made of copper or gunmetal. Inspection of un-pressed fittings utilises a positive leak
path in the whole range 2.2kPa to 300kPa with a dry pressure test. This warranted safety function is facilitated by a
channel in the metallic body of the fitting. After pressing, the connection is permanent and inseparable with the safety
function effectively removed during the pressing process. The seal is made of HNBR and the fitting body has a
cylindrical pipe guide in front of the seal. Fittings carry conformance certifications to international Gas standards
DVGW VP 614 and ANSI LC4.

CHASING AND DRILLING


Chasing shall be carried out as follows:
1 Brickwork shall have been built a minimum of 7 days prior to chasing.
2 Chasing shall be carried out using a machine specifically designed for the purpose. Do not use hand tools.
3 Chasing shall be on the same side of the wall and vertically above the outlet it serves.
4 Minimise horizontal chasing.
5 No chase shall be deeper than 35 mm or wider than 80 mm or 3 conduit pipes. Pipes shall be installed so they are
approximately 5 mm below the surface of the bricks. Pipe sizes larger than 25 mm shall be provided with block
outs in walls.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 87
1118/1.05
6 Where two or more chases are necessary in close proximity they shall be at least 100 mm apart.
7 No chases on opposite sides of a wall shall be within 150 mm of each other.

CONCEALING
Generally, all piping is to be concealed by chasing or building-in and generally as indicated on the drawings.

GRADES
All grades and inverts indicated on the drawings shall be established with the use of approved surveying instruments.
Check the topography and finished floor elevations before commencing any excavation work.
The setting of all inverts, etc. at correct elevations is a prime and definite requirement of this specification.
Grades to drains shall generally be as shown on the drawings and as required by the relevant Authorities.
All water piping shall be graded to facilitate draining at a low-level drainage point.

COVER PLATES
Where exposed pipes pass through a floor, wall or ceiling, the joint shall be finished with an approved Chrome-Plated
spun metal cover plate. The cover plate is to be flush with the wall.

CAPPING OFF
Throughout the installation of all piping, special care shall be continuously exercised to protect all openings to
prevent the admission of dirt, stones or other foreign substances that would subsequently obstruct the system.

CHROME PLATING
Waste pipes, flush pipes, water and gas branches, between walls and individual fixtures shall be chrome-plated and
fitted with approved cover plates at walls.
Chrome plating shall be carried out in the best manner; steel or wrought iron shall be heavily coppered, heavily
nickelled and finally chromium plated.

STEEL

17.17.1 PIPES
1 Closed Water Systems: API 5L Grade B to specified design pressure and temperature ranges. Minimum wall
thickness: 4.8mm for pipes less than DN150, 6.4mm for pipes ND150 and over.
2 Open Water Systems: API 5L Grade B to specified design pressure and temperature ranges.
3 Minimum wall thickness: Standard Grade B.
4 All pipes to be supplied with black lacquer finish.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 88
1118/1.05
5 Pipes to be used with weld joints and flanges to be supplied with factory bevelled ends to
AS 1163–1991.
6 Pipes to be used with rolled groove couplings shall be supplied with factory roll grooves by Victaulic certified
supplier. Pipes under DN150 may be supplied with bevelled ends to AS 1163–1991; DN150 be supplied with plain
ends.
7 Pipes specified to be galvanised shall comply with AS 1650 with a minimum coating of 300g/m².

17.17.2 JOINTS
1 Weld Joints: Full penetration welded. Comply with AS 4041–1998 welding requirements and welder certification.
For systems with a design pressure greater than 1400 kPa all welds are to be carried out by qualified welders with
the appropriate AS 1796–1993 certificate.
2 Flanged Joints: to AS 2129–2000 and AS 2528–1982. Gasket material shall be preformed proprietary type at least
0.8mm thick selected for application.
3 Screwed joints: to AS 1074–1989 and AS 1722.1–1975. Screw threads to be sealed with degreased PTFE tape or an
approved thread sealing compound, hemp and paste similar to ‘HAWKINS’. Hemp shall not be used for systems
with a design temperature above 60°C.

4 Rolled groove couplings: Victaulic supplied only. Rolled grooves to be factory rolled by Victaulic registered
supplier. Site rolled grooves to be undertaken by factory-trained personnel, stamped, and recorded to factory
approved quality control system. All Victaulic couplings shall use flush type seals. Design and install in accordance
with Victaulic Design and Installation Manual.
5 Brazed joints to copper pipe and fittings are not permitted.

17.17.3 CONNECTIONS
1 Connections to equipment up to and including DN50 to be ground joint, steel socket welded unions to AS 1074–
1989.
2 Connections to equipment over DN50 to be rolled groove Victaulic type arranged to permit removal without
cutting pipework or breaking any structure.
3 Connections to copper piping and dissimilar metal components to incorporate flange isolation kits, bronze
coupling or Victaulic Style 47 coupling.

17.17.4 BENDS
1 Centreline radius not less than 1.5 times the pipe diameter. Pipe bends with centre line radius of 1.0 time pipe
diameter shall not be accepted.
2 Victaulic Style 10 & 11.

17.17.5 BRANCHES
1 Branches to be welded swept tee type with a minimum centreline radius of not less than one and a half times the
diameter of the pipe.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 89
1118/1.05
17.17.6 REDUCERS
1 Use concentric reducers or Victaulic Style 50 type on all vertical lines.

2 Use eccentric reducers or Victaulic Style 51 on all horizontal line connections ≥ DN50 to pump suctions with
installed flat on top and to other items of equipment with the flat of the eccentric arranged on the top or bottom
of the pipe to allow venting and drainage as required.

COPPER

17.18.1 PIPES
1 Pipes: AS 1432–1996: Type A or Type B for specified design pressure and temperature ranges. Copper Alloy:
AS 2738–2000 Designation 122.
2 All pipe to be Hard Drawn.
3 All joints in copper pipe work shall be made by brazing with low temperature silver brazing alloy containing not
less than 5% silver (15% for gas piping). Use oxy-acetylene heating for all low temperature brazing.
4 Flux shall be as recommended by brazing alloy manufacturer.
5 Slip joints shall be permitted to join lengths of copper pipes and shall be made by annealing and expanding ends
with a proper tool to form a slip (capillary) joint.
6 Fabricated tees or junctions in copper pipe will not be permitted.
7 Valves shall not be brazed direct onto pipes. Valves shall be indirectly joined to pipes by the use of flanged or
screwed adaptors, which shall be silver brazed onto the pipe and then screwed to the valve. Care shall be taken to
prevent distortion to the valve and/or valve seat.

17.18.2 JOINTS
1 Brazed: Use either capillary fittings to AS 3688–1994, or expand one pipe over the other leaving minimum
clearance and an effective overlap not less than:

PIPE SIZE DN OVERLAP MM

< 20 12

≥ 20 to < 32 15

≥32 to < 50 25

≥50 to < 80 30

≥80 to <125 35

≥125 40

2 Brazing alloys to AS 1167 and comprise a minimum of 5% silver.


3 Flanged: Copper alloy flanges to AS 2129–2000 selected for design pressure and temperature, minimum Table E,
brazed to pipe or alternatively may be floating type connected to pipe via a silver soldered copper Van Stone
socket with inbuilt tube stops. Backing flanges polyester resin coated steel or composite material, Cop-a-Mate or
equal.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 90
1118/1.05
4 Nuts, bolts and washers used in flanges to AS 2129–2000 Appendix C and AS 2528–1982; stainless steel, galvanised
or zinc plated after manufacture with non-conductive bushes.
5 Roll Grooved: Victualic Style 606.
6 Victaulic Style 606 mechanical coupling or Style 641 flange adaptor.
7 Brazed joints to steel pipe and fittings not permitted.

17.18.3 CONNECTIONS
1 Use flanged, screwed, compression or roll grooved connections to valves, equipment and fittings arranged to
permit removal of any item of equipment without cutting pipework or without breaking any structure.
2 Screwed connections to be silver soldered bronze socket unions.

17.18.4 BENDS
1 Smooth finish without any discernible flattening or corrugation.
2 Minimum centreline radius of not less than one and a half times the diameter.
3 Victaulic Style 610 or 611 type.
4 Standard proprietary bends may be used subject to compliance with above conditions.
5 Branches from main pipelines to be of swept tee type fabricated from abovementioned bends.

17.18.5 REDUCERS
1 Use concentric reducers or Victaulic Style 650 type on all vertical lines.
2 Use eccentric reducers or Victaulic Style 651 on all horizontal lines, connections to pump suctions to have flat on
top and to other items of equipment with the flat of the eccentric arranged on the top or bottom of the pipe to
allow venting and drainage as required.

STAINLESS STEEL

17.19.1 PIPES
1 ASTM A 312M Grade 316 L.
2 Minimum Wall Thickness:
a Piping up to DN 150: 1.6mm
b Piping from DN 150 to DN 300: 2mm.

17.19.2 JOINTS
1 Use stainless steel of the same grade and wall thickness as the pipe.
2 Weld Joints: Full penetration welded. Comply with AS 4041–1998 Welding Requirements and AS/NZS 3992:1998.
Provide details of qualified welding procedure to be carried out by qualified welding personnel with appropriate
AS 1796–1993 certificate.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 91
1118/1.05
3 Flanged Joints: to AS 2129–2000 and AS 2528–1982. Use flange jointing material similar to Bestobel J2100
preformed proprietary type at least 0.8mm thick.
4 Screwed joints: to AS 1722.1–1975. Screw threads to be sealed with degreased PTFE tape or an approved thread
sealing compound, hemp and paste similar to ‘HAWKINS’.
5 Rolled groove couplings: Victaulic supplied only. Rolled grooves to be factory rolled by Victaulic registered
supplier. Site rolled grooves to be undertaken by factory trained personnel. Use only flush type seals. Design and
Install in accordance with Victaulic Design and Installation Manual.
6 Victaulic rolled groove couplings for connections over 50mm to all equipment to permit their removal without
cutting pipework or breaking any structure.
7 In stainless steel pipe systems use only stainless steel nuts, bolts and washers of same grade as piping.
8 Connections up to and including 50mm to be ground joint, steel socket welded unions to
AS 1074–1989.
9 All connections between copper piping and dissimilar metals to incorporate flange isolation kits, bronze coupling
or Victaulic Style 47 coupling.

17.19.3 BENDS
1 Centreline radius not less than one and a half times the diameter of the pipe.
2 Victaulic Style 10 & 11 type.
3 Branches from main pipelines to be welded swept tee type with a minimum centreline radius of not less than one
and a half times the diameter of the pipe.

17.19.4 REDUCERS
1 Use concentric reducers or Victaulic Style 50 type on all vertical lines.
2 Use eccentric reducers or Victaulic Style 51 on all horizontal lines connections to pump suctions to have flat on
top and to other items of equipment with the flat of the eccentric arranged on the top or bottom of the pipe to
allow venting and drainage as required.

ABS AND UPVC

17.20.1 PIPES
1 TBA

17.20.2 JOINTS
1 Socket formed solvent cement welded type to piping manufacturers recommendations and instructions for
applications where pipework is located in plant rooms, with allowances for changes in direction via bends and
offsets and is not subject to excessive thermal expansion.
2 When subject to expansion and contraction and long lengths of piping above 200mm are involved, use Durapipe
post formed expansion units with lipped neoprene 'O' ring or alternatively use rubber bellows type.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 92
1118/1.05
3 Flanged joints for connections to valves, fittings and equipment to consist of ABS/UPVC flanges, galvanised
backing rings drilled to match flanges and neoprene gaskets.

17.20.3 BENDS & BRANCHES


1 Plain radius type.
2 Fabricate large bends from mitred standard type having at least five sections per bend and with sections welded
with hot gas filler rod technique or other approved.
3 Use standard tee type branch connections for smaller pipes.
4 Use telescopic branch connections for larger pipes to ensure a smooth entry of water to the reduced port.
5 Use preformed saddles fully welded to the pipe for branch connections for flow switches, sensors and other
fittings.
6 Cover all fabricated fittings with an applied layer of 60g CMS fibreglass, consolidated with polyester resin type
RP161 at the rate of 1.2 to 1.9kg per m².

VALVES & FITTINGS

17.21.1 GENERAL REQUIREMENTS


1 Use valves suitably sized for the application and at least line size unless used for control when a smaller size may
be necessary.
2 Select valves and fittings to meet the operating pressures and operating characteristics of the relevant systems
and to meet higher test pressures where applicable.
3 Design pressure of valves and fittings not less than the system design pressure.
4 All isolating valves and throttling valves shall be rated for full shut-off pressure.
5 All valves and fittings shall be installed in accordance with manufacturer’s recommendations and with valve
shafts installed on or above the horizontal plane and with all tapping points a minimum of 45 degrees off the
vertical downwards plane.
6 Provide extended shafts or bodies for insulated valves to allow full thickness of insulation.
7 Valves up to 50mm diameter; screwed connections to AS 1722.1–1975.
8 Valves over 50mm diameter; flanged connections to AS 2129–2000 Type E minimum or Victaulic rolled groove.
9 Handwheels and handles to be removable with the direction of closing to be marked clearly.
10 Select valves to water supply authority approval where applicable; valves to be stamped with approval details.
11 For each type of valve and fitting, valves and fittings to be supplied from one manufacturer throughout the
project.
12 Where copper alloy valves used, select valves of dezincification resistant type.

17.21.2 WATER SERVICES VALVES & FITTINGS

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 93
1118/1.05
1 Globe Valves:
a Copper alloy body.
b Screwed connections.
c Zinc free non-rising inside screw.
d Set positions to be permanently marked after balancing.
e John Crane D920 or approved equal.

THROTTLING VALVES (OVER 50MM)


1 Butterfly Valves:
a Lug type to BS5155.
b High tensile cast iron body, stainless steel shaft, bronze disc and keyed replaceable EDPM seat.
c Suitable for installation between flanges with spool piece or retaining flanges to facilitate removal of
downstream pipework with valve remaining in place for isolation.
d Lever operated with adjustable infinitely variable memory stops.
e For valves over 150mm diameter, geared or motorised operators with adjustable travel stops.
f Provide chainwheels and chain with handwheel with memory stops or permanently marked at low level for
manually operated valves over 150mm in size, when located above 2 metres above finished floor level.

ISOLATING VALVES (UP TO AND INCLUDING 50MM)


1 Gate Valves:
a Straight through flow, solid wedge type.
b Bronze bodied to AS 1628–1999 with zinc free inside screw of non rising spindle type.
c Medium pattern.
d Integral bronze seat.
e Screwed connections.
2 Ball Valves:
a Full bore pattern with handle parallel to direction of flow when fully open.
b Bronze bodied with hard chromed brass or stainless steel ball, stainless steel stem and PTFE seat.
c Screwed connections.
d John 350 or equal approved.

ISOLATING VALVES (OVER 50MM)


3 Gate Valves:
a Straight through flow, solid wedge type.
b Bronze bodied to AS 1628–1999 or cast iron to AS 3579–1993 or cast steel with zinc free, non-rising inside
screw type spindles.
c Medium pattern.
d Replaceable bronze seat.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 94
1118/1.05
e Flanged connections.
f John 59M or equal approved.
4 Ball Valves:
a Full bore pattern with handle parallel to direction of flow when fully open.
b Bronze bodied with stainless steel ball, stem and PTFE seat.
c Watermark (as defined in SAA MPS2 Section 012) and AGA approved.
d Flanged or rolled groove connection.
e John 360 or equal approved.
f Victaulic style 721 type.
5 Butterfly Valves:
a Lug type to BS5155.
b High tensile cast iron body, stainless steel shaft, bronze disc and bonded EDPM seat.
c Rated for dead end and bi-directional service.
d Suitable for installing between flanges with spool piece or retaining flanges to facilitate removal of
downstream pipework with valve remaining in place for isolation.
e Victaulic Style 300 type to suit service.
f Memory stop for throttling, metering or balancing service.
g For valves over 150mm, geared or motorised operators.
h Provide chainwheels and chain with chain at low level for manually operated valves over 150mm in size when
located above 2 metres above finished floor level.
6 Non Return Valves (up to 50mm):
a Bronze body swing check type to AS 1628–1999 with stainless steel trim.
b Screwed connections.
c To be completely free of hammering under all operating conditions.
d John Figure 4B or equal approved.
7 Non Return Valves (over 50mm):
a Cast iron spring loaded dual flap type to AS 3578–1993 with stainless steel spring and pin, stainless steel
plates, integral nitrile rubber seat.
b Flanged connections or rolled groove connections.
c Hyflo, Stockham or approved equal.
d Victaulic Style 716 Type.
8 Control Valves:
a Modified linear or equal percentage type.
b Valve bodies bronze or cast iron with stainless steel trim and renewable discs and seats.
c Visible position indicators for valve actuators connected to valves above 32mm diameter.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 95
1118/1.05
d Arranged as normally closed valves with 100% close off to items controlled except for bypass valves which are
to be normally open.
e Select for demand authority of items served and for minimum fully open resistance (identified by KV or CV
Valves) of not less than 1.5 times the combined pressure drop of the branch pipe and item served.
9 Pressure Relief Valves:
a Direct acting, spring loaded, side outlet type with adjustable setting to AS 1271–1997.
b Designed to discharge at full capacity at a pressure not greater than 10% higher than set point pressure.
c Bronze bodied with renewable stainless steel disc and seat with springs protected from working fluid.
d Provide easing gear.
e Lockable shield to prevent unauthorised alteration to setting.
f Valve drained to waste.
10 Ball Float Valves:
a Copper alloy or bronze bodied to AS 1910–1994 or cast iron.
b Bronze needle and pins.
c Copper or plastic float with brass or stainless steel linkage.
11 Cold Water Stop Taps:
a Select stop taps of brass to the requirements of the Local Water Supply Authority.
12 Strainers:
a Y type or Victaulic Style 731 suction diffusers complete with pre-filter 16 mesh for pressures up to 2065kPA.
b Screwed bronze body on all lines up to and including 50mm and flanged cast iron body above 50mm with
easily removed perforated stainless steel or brass strainer basket.
c Select mesh for 15kPa maximum pressure drop.
d Fit ball valve and drain line to waste for strainers over 50mm as follows:
e 65, 80 and 100mm strainer – 25mm drain; 125mm – 32mm drain; 150 and 200mm – 40mm drain; 250, 300 and
350 – 50mm drain.
13 Automatic Air Vents:
a Float operated with cast iron or copper alloy body and stainless steel or solid plastic floats and mechanisms.
b Air vents are to be fully rates for the system operating conditions; minimum acceptable is 1,000kPa and 120°C.
c All vents are to be fitted with separate isolation valve on the inlet to allow servicing of the vent without
draining the system.
d Combined air vent discharge capacity of any section of the system being filled must exceed the flow rate at
the fast fill system.
e Flamco Flexvent, Flexvent Super or equal.
14 Expansion Joints:
a Flanged type of high grade neoprene.
b Powersorb type REJ or equal.
15 Flexible Pipework Connections:

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 96
1118/1.05
a Flanged type of high grade EPDM and spirally wound wire and reinforcing having a nominal length of 6 times
nominal pipe diameter.
b Hyflo C-Flex or equal approved.

17.21.3 NATURAL GAS TOWNS GAS AND LPG VALVES


1 Isolating Valves:
a Full bore, dezincification resistant.
b Ball valves operable by one quarter turn.
c Permanently fixed handle indicating direction of gas flow.
d Comply with Gas Supply Authority requirements and AGA / ALGA Standards as appropriate.
e John 360 or equal approved.
2 Pressure Reducing Valves:
a Reliance or Jeavons J48 type.

FLOW MEASURING DEVICES


1 Common manufacture and type throughout project.
2 Low pressure loss type.
3 Magnetic or ultrasonic tube type shall be Panametrics or approved equal.
4 Install in accordance with manufacturers' recommendations and with adequate lengths of straight pipe on either
side of the device.
5 Label with brass plate stamped to indicate all relevant piping data, gauge ranges, flow and temperature
coefficient.
6 Select gauge ranges suitable for each device with the design flow at midscale.

GAUGES & INSTRUMENT FITTINGS


1 Universal Test Points:
a Binder Twinlock type.
b Test points to be installed a minimum of 45o above the vertical downwards plane and as required to provide
access.
2 Thermometers:
a 100mm dial type mercury in steel thermometers matching pressure gauges and calibrated in Deg. C.
b Dial range twice operating temperature range.

c Accuracy ±1% of scale range.

d Bulb type 316 stainless steel.


3 Thermometer Pockets:
a Locate thermometer pockets in positions where no adverse flow conditions exist.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 97
1118/1.05
b Use thermometer pockets of removable screwed stainless steel type in steel lines, inserted through screwed
type boss welded to the pipe.
c Use thermometer pockets of fixed copper tube type brazed into copper piping lines.
d Length of pockets and depth of insertion in pipe adequate to ensure accurate headings.
e Fill pockets with heat conducting fluid to a minimum depth of 50mm and fit caps to each pocket.
f Enlarge pipes smaller than 65mm so as to retain free area.
g Install pockets vertically or at an angle to retain heat conducting fluid.
4 Pressure Gauges:
a Oil filled 100mm dial Bourdon pipe type to AS 1349–1986.
b Fit with ball valve.
c Manually adjustable set point needle incorporated on face of gauge.
d Chrome plated escutcheon and suitable for recessed mounting.
e Select compound type gauges for pump suctions graduated in mm of mercury on vacuum side and kPa on the
pressure side.
f Bourdon pipe material stainless steel for hot water and steam, phosphor bronze for other services.
g Bosses for pressure gauges, standard internally screwed type welded or brazed to side of piping.
5 Gauge Panels:
a Folded sheet metal of adequate stiffness, painted or powder coated with gauges logically grouped and
mounted to approval.

INSTALLATION

17.24.1 ARRANGEMENT
1 Layout piping with adequate provision for expansion, contraction, grading, alignment and access for maintenance
with not less than 50mm clearance (including insulation) between pipes and all other surfaces and services.
2 Co-ordinate and detail offsets and bends required for co-ordination between trades and integration with building
structure and architectural finishes.

17.24.2 PIPEWORK SUPPORTS AND ANCHORS


1 General Requirements:
a Design supports for all static and dynamic load and reactions.
b Install seismic bracing to all pipework as required by AS 1170.4–1993.
c Comply with all Statutory and Code requirements.
d Locate valves and fittings as close as possible to points of support and separately support valves in line sizes
200mm and larger.
2 Support Spacing:

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 98
1118/1.05
a Non ferrous pipe to AS 3500.1 Table 5.2.
b Steel pipe to AS 4041–1998 Table 3.28.2.
c ABS to manufacturer’s recommendations.
3 Pipe Clamps, Spacers and Saddles:
a Individually hung pipes – bolted, two-piece type clamps with clevis or welded yokes of 'Millstrut' PC7 or PC10
series or equivalent. One-piece type clamps with clevis similar to 'Millstrut' PC2 series may be used for pipe
sizes DN65 or less. Clamps rated for the full load of pipe plus its fluid contents, insulation and fittings.
b Spacers – High temperature insulated pipes - fully vapour sealed hardwood spacers located between clamps
and pipes. Spacers wedge shaped hardwood blocks arranged to form circular collars of the same thickness as
the insulation and projecting a minimum of 10mm on either side of the clamps.
c Firmly attach clamps and collars to pipework and/or insulating spacers without applying undue pressure to
the pipe walls.
4 Hanger Rods:
a Fabricate hanger rods and associated fittings from hot dip galvanised or zinc plated mild steel bar of not less
than the following diameters:

NOMINAL PIPE SIZE MM ROD DIAMETER MM

Up to 50 (inclusive) 8

65 & 80 10

100 to 150 12

200 to 250 16

300 to 450 20

500 & above 24

5 Fixed Supports:
a Fix hanger rods direct to structure unless moving supports required to cater for expansion, contraction and
vibration.
b Support two or more pipes on common channel section bracket or trapeze type support:

Pipe sizes up to 100mm Millstrut P1000 Series

Pipe sizes over 1000mm Standard rolled sections

6 Moving Supports:
a Where hanger rods used to take up movement ratio of effective length to pipe movement to be not less than
6:1.
b Provide 'V' shaped brackets with oversize holes for rods. Similarly, clevis or welded yokes on pipe clamps to
have oversize holes for rods. Secure rods at each end using spherical washers and locknuts and do not use any
nuts between brackets and clevis or welded yoke.
7 Anchors:
a Design, supply and install anchors where shown on drawings and where required to accommodate pipework
weight, thrust forces and expansion and contraction.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 99
1118/1.05
b Submit detailed design and installation details for the project structural engineer’s approval and confirmation
that the building structure can resist the anchor forces imposed by the system design.
c Anchor connections to the pipework shall be:

Steel pipe: Fully welded to pipe.

Copper pipe: Anchors comprising bronze flanges fully brazed to pipe and bolted to galvanised steel anchor
plates. Use non conductive bushes and washers.

d Anchor shall comprise steel plates and/or rolled steel sections designed to transfer the weight of pipework,
pipe and thrust forces exerted by the system to the structure.

17.24.3 VIBRATION ISOLATORS


1 Rubber bellows are not to be used to absorb piping movement due to expansion in the system.
2 Rubber bellows should NOT be installed extended, compressed or offset to make up for deficiencies in pipe length
or alignment.
3 Pipework must be properly anchored around the unit, to avoid the bellows bearing the weight of the piping
system.
4 Units must be rated for the system operation pressure and temperature.
5 The Contractor should note the allowable bellows movement in their submission of products.
6 Construction to include flanged connections, bellows to be nylon cord and wire reinforced EPDM rubber suitable
for a working temperature of up to 95°C.
7 Hyflo C-Flex or equal approved.

17.24.4 PIPE EXPANSION AND CONTRACTION


1 Provide means to accommodate piping expansion and contraction in pipe runs longer than 30m from anchor
points which may be a series of full radius bends and diversions, expansion loops or bellows.

17.24.5 PIPE PENETRATIONS


1 Supply 1.6mm galvanised steel sleeves for placement and casting in penetrations. Sleeves to extend a minimum of
100mm above floors.
2 Pipe penetrations in fire rated structures to comply with BCA Clause C3.15 Fire Resistance – Openings for service
installations where applicable – refer to architectural and structural drawings for required fire ratings.
3 Pipe penetration fire rating system to comply with approved type tested installation.
4 Where required provide 100mm guard around fire rated penetrations to ensure no combustible material comes
within 100mm of pipe penetration and pipe.
5 Non fire rated wall penetrations to be sealed with mineral fibre insulation to maintain acoustic rating.
6 Where packing material is mineral fibre material enclose in sisalation.
7 Where exposed to view provide galvanised sheet metal collar.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 100
1118/1.05
TESTING OF PIPEWORK
1 Pressure test all sections of pipework prior to lagging or painting using calibrated pressure gauges. Provide signed
test reports for each pressure test.
2 Isolate any equipment that will not withstand test pressures prior to testing.
3 Provide detailed water treatment and pipework passivation proposal for approval prior to filling any part of the
system. Water which is not chemically treated shall not enter any part of any system. Introduce corrosion inhibiting
chemicals in water used for hydrostatic testing in strict accordance with the recommendations of a water treatment
specialist. If chemically treated water is left in piping after testing the water must be circulated and monitored to
assure protection is maintained.
4 Circulate test water to ensure continuity and effectiveness of corrosion inhibition providing temporary circulation
facility if required.
5 Remake any leaking joint and retest.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 101
1118/1.05
18 NOISE AND VIBRATION
GENERAL REQUIREMENTS
1 Acoustically seal pipe and cable penetrations through noise rated walls and acoustic enclosures.
2 Statically and dynamically balance rotating machinery.
3 Support rotating and reciprocating equipment on anti-vibration/vibration absorbing mounts on hangers.
4 All static equipment in plantrooms with suspended floors to be separated from the structure with double
thickness neoprene pads or equal.
5 All connections to rotating equipment or assemblies containing rotating equipment shall be rendered flexible by
anti-vibration hangers supporting pipework and/or by flexible connections as specified.
6 Plinths for all floor mounted equipment.

VIBRATION CONTROL

18.2.1 ACCEPTANCE CRITERIA


1 Complete systems including individual components not to exceed satisfactory levels as set out in AS 1359 and
AS 2625.
2 Select anti-vibration mounts/hangers for life cycle of building and install in accordance with the requirements of
the Earthquake Code AS 1170.4–1993.
3 Select and install anti-vibration mounts and hangers in locations to prevent transmission of vibration to adjoining
areas and to prevent undue vibration, distortion or fatigue of equipment and connecting piping and cabling.
4 Select vibration isolation mounts/hangers to allow for deflections of building structures and finishes and for
minimum static deflection as specified.

18.2.2 SPRING MOUNTS


1 Free standing and positioned for uniform deflection of all springs.
2 Spring mounting plates and frames hot dip galvanised.
3 Ratio of mean coil diameter to compressed length at specified static deflection of 0.8.
4 Minimum additional travel to solid of 50%.
5 Holding down bolts to be provided.
6 Surge frequency to be beyond 30% of predominant machine frequency of vibration.

18.2.3 NEOPRENE PADS


1 Use up to 9mm static deflection.
2 Loading not greater than 400kPa.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 102
1118/1.05
18.2.4 ANTI-VIBRATION HANGERS
1 Spring and double neoprene cup type in series.
2 Total hanger deflection 25mm minimum.
3 Provide secondary adjustment to transfer load to spring.

NOISE MEASUREMENTS
1 Measure and submit noise measurements in areas nominated above using sound level meter complying with
AS 1259 during the noisiest operating condition.
2 Where noise measurements exceed specified criteria, take additional noise readings in each octave band (125Hz to
4000Hz inclusive) in selected locations with reference to AS 1045-1988, AS 1055, AS 1081, AS 1089, AS 1217 and
AS 1469–1983.

VIBRATION MEASUREMENTS
1 Where a noise hazard exists and all practicable noise attenuation has been carried out, hazardous areas shall be
defined by the erection of signs reading:
NOTICE
HEARING PROTECTION MUST BE WORN
IN THIS AREA
or
NOTICE
HEARING PROTECTION MUST BE WORN
WHEN THIS MACHINE IS RUNNING
2 Signs shall be 'Brady' Indoor/Outdoor, Personal Hazard Warnings or approved equivalent.

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 103
1118/1.05
19 SCHEDULES
GENERAL
The following schedules have been prepared for tendering purposes and to convey design intent. They form a
summary of the preceding Clauses in the Specification and must be read in conjunction with these Clauses and the
Project Drawings.
Where reference Clauses are referred to, they shall be taken as the major Clause, but equipment shall also comply with
all other relevant Clauses in the Specification.
Water quantities and temperatures may be changed slightly to suit the particular manufacturer’s equipment, however
full details shall be submitted for review. Changes shall not be in conflict with any By-Laws, Statutory Requirements
(including BCA Section J where applicable), Public Health Requirements or the overall design in general including
achievement of any energy compliance and Green Star criteria.
Pump duties have been calculated from typical equipment and have been given as a guide only.
The following schedules show details of hydraulic equipment only.
This schedule must be submitted with the tender offer in the current tabulised form with ‘tender’ columns and rows
completed.
Schedule of equipment submitted on alternate forms, manufacturers’ data sheets, Contractor work sheets, etc. will not
be accepted.
Completion of the technical schedule for tender review does not constitute approval of proposed equipment nor does
it absolve the requirement to satisfy the requirements of the specification.

SCHEDULE OF EQUIPMENT

DOMESTIC COLD WATER BOOSTER PUMPS

Location Ground floor Hydraulic Plant area - external

No off 2 off [duty/standby]

Flow rate 1.7 l/s

Head 40m [with minimum mains supply pressure 120KPa]

Operation / Rating 3 Phase: 7,5 kW each

Type Variable speed drive

System Duty / standyby pump set with potable cold water bypass [normally closed],
and inlet pressure-sensor

Make / Model Grundfos, CR 45-2 HQQV

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 104
1118/1.05
HOT WATER CIRCULATING PUMP

Location Ground floor Hydraulic Plant area - external

No off 1 (dual)

Flow rate 0.2 l/s (each)

Head 2m

Operation / Rating Single Phase: 240V, 10 AMP

Type Centrifugal, canned rotor type

System 2 Pumps
duty / standby

Make / Model UPS 20-60

COLD WATER STORAGE TANK

Location Above -ground – external – refer plans

Capacity 36,000 litre potable water

Dimensions 4000 length x 3000 deep x 3000 high

System Concrete tank, including compartments, and all valves and accessories

GAS BOTTLES

Location Above -ground – external – refer plans

Capacity 2 x 210kg

System APA or similar supplier, including all valves and accessories

HOT WATER PLANT

Location 1 Ground floor Hydraulic Plant area

System Rinnai 2 x DD1200E250L

Type Gas

Booster/tanks 2 x 250L Stainless steel storage tanks

Flue System Proprietary

Gas Load (MJ/Hr) @2.75Pa-LPG – 400

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 105
1118/1.05
DILUTION CHAMBER

Location Below-ground – external – refer plans

Capacity 2000 litres

Dimensions 2400 length x 900 width

System Polypropyelene

Make / Model Viking Plastics VP15 Cooling and Straining Tank

WATER METERS UP TO 50MM

Type Pulse

Pulse 1 pulse / 10 litres

Model / Make Elster V100

Accessories Isolation valves upstream and downstream


Strainer upstream
Barrel unions upstream and downstream

GREY WATER UNDERSINK PUMP

Location Ground Floor Bunker - two (2) locations, Linac and Halcyon Basins

Electrical Load Single Phase: 240V, 10 AMP

Model / Make Saniflo Sanivite

MAIN WATER FILTRATION PLANT

Location Ground floor Hydraulic Plant area

Electrical Load Single Phase: 240V, 10 AMP

Model / Make Automatic Screen Filtration - Southland Filtration

STAGE 1 -2 x JUDO JPF ATP 50mm,

STAGE 2-AUTOFINE AF3/80,

STAGE 3-SOUTHLAND D-24-WD,

STAGE 4-SOUTHLAND CHLORINE DIOXIDE DISINFECTION SYSTEM

Complete system to be commissioned by Southland Filtration

Electrical Load STAGE 1 -Single Phase: 240V, 10 AMP

STAGE 2 -Single Phase: 240V, 10 AMP

STAGE 3 -Single Phase: 240V, 10 AMP

STAGE 4 -Single Phase: 240V, 4 X 10 AMP

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 106
1118/1.05
DIRTY UTILITY ROOM SANITIZER FILTRATION

Location Ground Floor Dirty Utility Room

Electrical Load Single Phase: 240V, 32AMP

Model / Make Southland Filtration Endotherm Mini 500 System

SCHEDULE OF VALVES
PRESSURE REDUCING VALVE

Location As shown on schematics

Operation Preset to max 500 kPa as shown on schematics

Make / Model Caleffi 535

THERMOSTATIC MIXING VALVE

Location As shown

Model / Make Enware Aquablend 1500 ATMS719R (hinged stainless steel wallbox with area isolation
valve)

ISOLATION VALVE

Location As shown in schematics

Model / Make RMC with upstream and downstream unions.

HOT WATER BALANCING VALVE

Location End of all hot water flow lines

Model / Make Tour Anderson (TA) Therm

SINGLE CHECK VALVE 100MM

Location All

Model / Make Tyco 100 SC03 C COBFFS

DOUBLE CHECK VALVE UP TO 50MM

Location As shown

Model / Make “Tyco” model: DC03/CO

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 107
1118/1.05
Accessories Isolation valves upstream and downstream
Strainer upstream
Barrel unions upstream and downstream
Bypass with isolation valve

REDUCED PRESSURE ZONE DEVICE (RPZD) VALVE UP TO 50MM

Location As shown

Model / Make “Tyco” model: RP03/CO

Accessories Isolation valves upstream and downstream


Strainer upstream
Barrel unions upstream and downstream
Bypass with isolation valve

TRAP PRIMING VALVE

Location As shown

Model / Make Mifab

SCHEDULE OF STORMWATER PITS AND OUTLETS


REFER CIVIL ENGINEERS SCHEDULE

SCHEDULE OF FLOOR DRAINS


To be read in conjunction with Base Architect, Landscape Architects, Interior Architect schedules for additional outlets
and grated drains.
*Refer architectural, interior, kitchen, pool, and landscape consultant schedules

OUTLET CODE OUTLET NAME LOCATION SPECIFICATION

FW Floorwaste Amenities SPS 130mm round vari-level


vertical drain with stainless steel
grate and cast iron body or
approved equal.

Model: R130S/C

PFW Plantroom Floorwaste All SPS 150mm round floor drain with
brass grate and cast iron body

Model: R150G/C

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 108
1118/1.05
SHR Shower Waste All SPS 130mm round vari-level
vertical drain 65/50mm outlet
with stainless steel grate and cast
iron body or approved equal.

Model: R130S/C

IOS Inspection opening to surface Internal Areas - Amenity Stainless steel body and cover

Galvin Engineering model:


67736SS or approved equal.

IOS Inspection opening to surface Workshops Stainless steel body and cover
suitable for forklift loads

Galvin Engineering model:


67736SS or approved equal.

IOS Inspection opening to surface External Nickel / bronze cover and body
suitable for forklift loads

Galvin Engineering model: 67736


or approved equal.

PD Planter Drain Outlet Planter Boxes 56mm Atlantis Drainage Cell at


base of each planter or approved
equal.
SPS 150 square floor drain with
100mm outlet and no grate to
drain planter base or approved
equal.

SCHEDULE OF INSULATION
TYPE LOCATION DESCRIPTION SPECIFICATION

Thermal All hot water pipework (flow return and Close celled polyethylene – 25mm Thermotec 4-zero
deadlegs) thick

Acoustic All sanitary and stormwater drainage To manufacturers requirements Soundlag 4525C
lines above noise sensitive areas

Note: Alternative insulations must satisfy the stricter of the NCC Section J requirements and the above Consultant
Engineer requirements. In addition, alternatives must have zero ODP in both product and manufacture.

SCHEDULE OF PIPE MATERIALS


SERVICE LOCATION MATERIAL NOMINAL PIPE SIZE

Stormwater Above + Below ground PVC – ‘DWV’ grade 100-300

Sanitary Drainage All PVC – ‘DWV’ grade 100-300

Sanitary Drainage from high All HDPE or PPR 50-100


temperature discharge

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 109
1118/1.05
SERVICE LOCATION MATERIAL NOMINAL PIPE SIZE

Sanitary stack Above ground PVC – ‘DWV’ grade 50-300

Vent pipes Above ground PVC – ‘DWV’ grade 40 -150

Sub-soil drainage planter Below ground E square drainage cell with geotextile NA
fabric wrap – Atlantis

Sub-soil drainage Below ground HDPE Slotted corrugated drainage pipe 110 - 160
with RTA filter sock. – “Draincoil” by
“Vinidex”

Trade waste drainage Above ground HDPE with fusion couplings or PPR 100-150

Trade waste stack Above ground HDPE with fusion couplings or PPR 100-150

Trade waste vent Above ground HDPE or PVC- ‘DWV’ 50-100

Sanitary Plumbing Above ground PVC – ‘DWV’ grade 40-150

Condensate drain Above ground PVC – ‘DWV’ grade 25 -150

Horizontal lines to be lagged.

Cold water mains Below ground Copper tubes to AS 1432-1990 Type B 50-250
wrapped with petroleum impregnated
tape

Or

PVC – pressure PN20

Cold water service Above ground Copper tubes to AS 1432-1990 Type A 15-200
and Type B according to pressure
requirements

Hot water service Above ground Copper tubes to AS 1432-1990 Type A 15-100
and Type B according to pressure
requirements

Hot and cold water rough-ins Above ground Cross–linked polyethylene (PEX), 15-25
Rehau

Non potable water, rough-ins Above ground Cross–linked polyethylene (PEX) 15-25
Rehau, labeled “RAIN WATER”

Reverse osmosis water, rough- Above ground Cross–linked polyethylene (PEX) 25


ins Rehau, Platinum

Fire Hydrant Test Drain All Galvanised steel within fire stair, PVC 100 - 150
– ‘DWV’ grade underground

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 110
1118/1.05
SCHEDULE OF TAPWARE AND FIXTURES
REFER ARCHITECTURAL SCHEDULE

SCHEDULE OF BOILING WATER UNITS


FIXTURE CODE DESCRIPTION LOCATION SPECIFICATION

BWU Zip Boiling Water As shown on plans Manufacturer: ZIP


Unit Product Ref: Zip Hydroboil 5 litre
RM1038-BEV and
Description: Boiling water only. Tapware selection TBC by
RM1077 Staff Room
architect

PROJECT NO PS114912
PORT MORESBY GENERAL HOSPITAL WSP
CANCER CENTRE JAN 2023
MAY 2019
HYDRAULIC SPECIFICATION PAGE 111
1118/1.05

You might also like