Oracle Primavera P6 R17.x Post-Install Functionality Test Spec
Oracle Primavera P6 R17.x Post-Install Functionality Test Spec
x
Post-Install Functionality Test
TABLE OF CONTENTS I
DETAILS III
1 PURPOSE 4
2 CONSIDERATIONS 4
3 PREREQUISITES 4
ACCEPTANCE 26
i
Post-Install Functionality Test | Table of contents LogiKal Projects | Commercial in confidence
ii
Post-Install Functionality Test | Table of contents LogiKal Projects | Commercial in confidence
Details
Submitted to:
Name
Title
Telephone
Email
Company
Address
Prepared by:
Document History
iii
Post-Install Functionality Test | Table of contents LogiKal Projects | Commercial in confidence
1 Purpose
This document is to be used by LogiKal consultants and Client Staff to validate the functionality of the installation of Primavera
Project Management in a Client’s working environment.
2 Considerations
This version of P6 will be used by the client in the client’s workplace environment. Ensure that during the testing process, no Global
values are changed, only change setting for the test project being set up. Ensure the test project is deleted at the end of the test
and no remnants of the test exist once complete, Such as Global User Defines Fields, Global Activity codes etc.
3 Prerequisites
Check with the client which day of the week is required to be the first day. E.g. Western companies usually have ‘Monday’. Others
may have ‘Sunday’ or even ‘Saturday’
Therefore, ensure that the users performing the test script have sufficient privileges to complete the steps.
4
Post-Install Functionality Test | Pre-amble
Tick when
Task No Instructions
complete
1.4 Open the first Sample Project and confirm you can view the nodes and activities listed (layout is not
important)
5
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
4.2 Create new project
Tick when
Task No Instructions
complete
From the projects screen, create a new project by selecting File>New and follow the wizard:
Select Finish
2.1
2.2 Once setup is complete, ensure the project can be viewed in the “Projects” Window
6
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Task No Instructions Tick when
complete
Select the Projects radio button to display project specific Calendars and click on Add:
7
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Task No Instructions Tick when
complete
3.2 Highlight “Standard 5 Day Workweek” and click select, to use this calendar as a basis.
8
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Task No Instructions Tick when
complete
9
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Task No Instructions Tick when
complete
3.5
Make Fridays a non-workday (For this month). Ensure all workdays have the same number of hours and
there are no exception days (Coloured white)
Ensure
the
time
p
eriods match the work day and work week hours for a 4 day week.
3.7 Close the Calendar windows and return to the Activities screen
1
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
4.4 Create a WBS
Tick when
Task No Instructions
complete
Right Click on the Project ID “Test1” under WBS code, and select Add
Do not change the WBS code ID, ensure the code automatically formats as shown below.
4.2
Apply different WBS view Layouts through View>Layout>Open Layout and Apply the various layouts
4.3
defined. Check to ensure the layout changes with different selections
Tick when
Task No Instructions
complete
5.1
1
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
1
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
Create 3 Activities under each WBS node. Name them New Activity 1, to New Activity 6
5.2
In the General tab, make Activity Type “Task Dependent” and % Complete as “Physical”
5.3
Create a Finish Milestone under each WBS node
Ensure to change the Activity Type to “Finish Milestone” in the General tab
5.4 Check the Activity ID number to ensure all activity IDs have automatically increment sequentially
Check the activity Duration in the Status tab to ensure the duration matches the default duration of 5
days.
5.5 Assign TestCalendar, which was created earlier. to the three activities in Node1
Do this by selecting the relevant activity and change the calendar in the General Tab in the bottom
layout. Ensure you select “TestCalendar” from the list of Project Calendars rather than the Global
Calendars.
1
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
5.6
Schedule the Project using F9 or the schedule button. Set Current Data Date to 08 June 2018
1
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
Alternatively, turn the relationships on through the Layout Menu>Bar Chart Options…
Note that the first three 5-day tasks continue into subsequent weeks due to the ‘test Calendar’ making
Fridays non-work time; and Task2 has a constraint.
1
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
4.6 Generate Activity Network
Tick when
Task No Instructions
complete
Be sure to undo any changes, but check that the relationships between activities and the details can be
6.2
changed through the Activity Network View.
6.3
Tick when
Task No Instructions
complete
Click Add
Select the “Save a copy of the current project as a new baseline” radio button:
1
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
A dialog will show stating the Job has been scheduled. Click “OK” on the message.
7.1
Check the status of the scheduled job – i.e. the creation of the baseline.
If the job is shown as ‘pending’ or ‘running’ wait a moment and then ‘refresh’ the screen.
Once the job has completed it should show as such in the list:
1
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
Select Project>Assign Baseline and make “Test Project B1” the primary and project baseline:
7.3
1
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
7.4 Verify that the Baseline is displayed in the Gantt Chart as shown
You may need to reschedule and edit the Bars window to ensure baseline bars are visible.
Tick when
Task No Instructions
complete
8.2
Set all resources to type Labor with Prices of $100/h $80/h $60/hr respectively.
1
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
8.3
Click Add and make a new expense named “Test Expense” with budget cost of $2000. Leave the rest as
default.
2
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
4.9 Level resources
Tick when
Task No Instructions
complete
9.1 Display the Activity Usage Spreadsheet View>Show on Bottom>Activity Usage Spreadsheet
While still selecting Resource1, Display the Resource Usage Profile noting the red bars:
9.2
2
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
Tick when
Task No Instructions
complete
10.1 In the Activity window, ensure the physical complete column is viewable
In the status tab mark the following activities as ‘started’ and update the Physical % Complete values:
Activity2: 20%
10.2
Activity5: 80%
Note that the ‘Remaining Duration’ will not change if the tasks are set as ‘Physical’ Percent complete
type.
10.4
2
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
Tick when
Task No Instructions
complete
11.1 Select the Project radio button and click Modify (Ensure it is only created under the current project)
Click Add
11.4 Open the Add Code Value form and Add three values
Dig
Build
Paint
2
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
2
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
11.6
Tick when
Task No Instructions
complete
12.2 Select Activities And add a new UDF titled ‘Last Period Start’ of type ‘Start Date’
12.3 Show the Last Period Start column in the Activities window
Tick when
Task No Instructions
complete
13.1 Log into EPPM with appropriate access rights to administer users
2
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
13.3 Assign the new user a global profile from the ‘Global Security Profile’ drop-down in the column.
Note: it is possible to ‘highlight and cell and ‘drag’ it’s value down to other rows (like a spreadsheet).
13.5 Log out of P6. Login again as the user you just created
13.6 Verify that the new user has access and relevant rights
2
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
13.7 Log out and login again as admin. Delete the new user.
Tick when
Task No Instructions
complete
14.3
14.4 Click OK to save the Change and close the Modify window
14.5 In the Global Change window, highlight TestGlobalChange and click “Apply Change”
2
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Tick when
Task No Instructions
complete
Tick when
Task No Instructions
complete
15.2 Follow the prompts to check out the project to the desktop location
15.4 Return to the P6 Projects screen and ensure the project icon has a small tick on it. This indicated the
project is currently checked out.
Tick when
Task No Instructions
complete
Open the exported data in Excel to ensure the data you have selected to be exported appears as
16.3
expected
2
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
4.17 Delete project and test information
Tick when
Task No Instructions
complete
17.6 In the <Enterprise, User Defined Fields…> area – delete the ‘Last Period Start’ UDF
17.7 Delete the exported test project data from the desktop if not done already (XER, XML))
:
2
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
3
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence
Acceptance
Name:
Position:
Signature: Date:
Name:
Position:
Signature: Date:
3
Post-Install Functionality Test | Pre-amble LogiKal Projects | Commercial in confidence