Module 5 notes
Module 5 notes
Types of Cofferdams
1. Single-Wall Cofferdams
o Application: Suitable for shallow water and low hydraulic pressure situations.
2. Double-Wall Cofferdams
o Description: Consist of two parallel walls with a space in between, often filled
with sand or gravel.
o Application: Used in deeper water or where higher pressures are anticipated. The
inner wall can provide extra stability and reduce water seepage.
3. Earthfill Cofferdams
o Application: Effective for large areas and provides good resistance to water.
They are typically used for long-term applications.
4. Braced Cofferdams
5. Inflatable Cofferdams
o Description: Made of flexible materials that can be inflated to create a barrier
against water.
Design Considerations
• Hydraulic Analysis: Assess water levels, currents, and potential wave action to
determine design loads.
• Soil Conditions: Evaluate the soil properties (bearing capacity, stability) to ensure that
the cofferdam can withstand the pressure exerted by water and soil.
• Safety Factors: Incorporate safety factors in the design to account for uncertainties in
water flow, soil conditions, and construction practices.
• Seepage Control: Design to minimize water seepage through the cofferdam walls, using
materials and configurations that enhance water tightness.
Construction Process
Single-Wall Cofferdam
1. Site Preparation:
o Drive or install sheet piles vertically along the perimeter where the cofferdam will
be located.
3. Water Removal:
o Once the sheet piles are in place, pump out water from inside the cofferdam to
create a dry working area.
4. Excavation:
o Begin excavation within the cofferdam for the intended construction project.
Double-Wall Cofferdam
1. Initial Steps:
o Similar to the single-wall cofferdam, prepare the site and install the outer sheet
piles.
o Install a second row of sheet piles parallel to the first, leaving a gap between
them.
o Fill the space between the walls with sand, gravel, or other suitable material to
provide stability and reduce water seepage.
o Pump out water from the inner area and proceed with excavation.
Earthfill Cofferdam
1. Site Preparation:
2. Construction of Embankment:
3. Water Removal:
4. Excavation:
Characteristics
• Materials: Typically made from steel, but can also be constructed from reinforced
concrete or plastic. Steel is the most common due to its strength and durability.
• Installation: Sheet piles are driven into the ground, often overlapping to ensure
watertightness.
Construction Process
1. Site Preparation:
o Clear the area and assess existing site conditions, including soil and water levels.
o Driving Method: Use a vibratory hammer or impact hammer to drive the sheet
piles vertically into the ground along the designated perimeter.
o Overlap: Ensure that the sheet piles overlap to minimize gaps and enhance water
resistance.
3. Water Control:
o Once the sheet piles are in place, use pumps to remove water from inside the
cofferdam, creating a dry working environment.
4. Excavation:
o With the area dewatered, proceed with excavation work for foundations or other
construction activities.
5. Monitoring:
o Continuously monitor the structure for signs of instability or water ingress during
the construction process.
• Effective Water Control: Provides a reliable barrier against water, allowing for dry
construction areas.
• Quick Installation: Sheet piles can be installed relatively quickly compared to other
methods.
Limitations
• Cost: Sheet piles can be expensive, especially when using high-quality materials like
steel.
• Depth Restrictions: In very deep waters or strong currents, sheet pile cofferdams may
not provide sufficient stability without additional support.
Characteristics
• Modular Design: Often constructed in sections or panels that can be assembled on-site
and moved as needed.
• Water Tightness: Designed to minimize water seepage, with careful attention to joints
and seals.
Design Considerations
1. Hydraulic Analysis: Assess water levels, currents, and potential wave action to
determine the design loads on the cofferdam.
2. Soil Conditions: Evaluate soil properties to ensure stability and resistance to lateral earth
pressures.
3. Structural Integrity: Ensure that the design accounts for potential loading scenarios,
including buoyancy, uplift, and lateral forces.
Construction Process
1. Site Preparation:
2. Panel Fabrication:
3. Assembly:
o Assemble the panels to form the cofferdam. Ensure that joints are tightly sealed to
minimize water ingress.
4. Placement:
5. Water Control:
o Pump out water from the inside of the cofferdam to create a dry working area.
Ensure that the structure can withstand the external water pressure.
6. Movement:
o Once the work is complete in one area, the cofferdam can be moved to another
location as needed. This may involve disassembling panels or using transport
equipment.
o Continuously monitor the cofferdam for stability and integrity during its use,
especially when repositioning.
Advantages
• Flexibility: The ability to move the cofferdam makes it suitable for projects where
construction activities are not fixed to one location.
• Water Control: Effective at managing water ingress, allowing for dry working
conditions in aquatic environments.
Limitations
• Cost: Higher initial costs due to the materials and fabrication processes compared to
other types of cofferdams.
• Weight: The weight of concrete can make it more challenging to reposition compared to
lighter materials.
• Installation Time: Assembly and placement may require more time and specialized
equipment compared to simpler cofferdam designs.
Applications
• Water Treatment Facilities: Employed in the construction of facilities that require dry
working conditions.
• Repair Works: Ideal for repairing existing structures in water bodies, allowing for safe
and efficient work.
Characteristics
• Purpose: Designed to prevent water from entering the work area, enabling safe
construction activities, especially when working near rivers, lakes, or coastal areas.
• Materials: Can be constructed from various materials, including soil, sandbags, sheet
piles, or reinforced concrete, depending on the site conditions and project requirements.
• Height and Design: The height and design of the cofferdam depend on the anticipated
water levels and soil conditions.
1. Earthfill Cofferdams:
o Often used for larger areas where significant water control is needed.
o Involves driving sheet piles into the ground to create a barrier against water.
o Suitable for areas with higher hydraulic pressures or where soil stability is a
concern.
o Provides high durability and stability, especially in areas with challenging soil
conditions.
Design Considerations
• Hydraulic Analysis: Assess potential water sources, flow rates, and pressure levels that
could impact the cofferdam’s integrity.
• Soil Properties: Evaluate soil characteristics, including bearing capacity and drainage
capabilities, to ensure stability.
• Seepage Control: Design to minimize water infiltration, ensuring that the work area
remains dry throughout construction.
• Structural Integrity: Include safety factors in the design to account for unexpected
water levels or soil movement.
Construction Process
1. Site Preparation:
2. Cofferdam Installation:
o Sheet Pile Cofferdam: Drive sheet piles into the ground along the perimeter,
ensuring that they are tightly sealed.
3. Water Control:
o Use pumps or drainage systems to remove any water that enters the work area
during construction.
o Proceed with excavation and construction activities within the dry work area.
5. Monitoring:
Advantages
• Effective Water Management: Allows for safe and dry working conditions in areas
prone to flooding or high groundwater levels.
• Temporary Nature: As a temporary solution, land cofferdams may not be suitable for
long-term water management.
Applications
• Soil Stabilization: Helps manage water levels during soil stabilization projects.
Components
1. Soldier Piles: Vertical steel beams, usually H-shaped or I-shaped, driven into the ground
at regular intervals to provide structural support.
2. Lagging: Horizontal wood or concrete panels placed between the soldier piles to retain
soil and water.
3. Bracing (if necessary): Diagonal braces may be added to provide additional stability,
especially in deeper excavations.
Advantages
• Strength: Soldier piles provide robust lateral support for deep excavations.
• Flexibility: The design can be adapted to various soil and water conditions.
Design Considerations
• Soil Properties: Evaluate soil stability, bearing capacity, and drainage requirements.
• Load Analysis: Consider the loads acting on the soldier piles and lagging to ensure
structural integrity.
Construction Process
1. Site Preparation:
o Driving: Use a pile driver or vibratory hammer to install the soldier piles
vertically into the ground at predetermined intervals.
3. Lagging Installation:
o Once the soldier piles are in place, insert lagging panels horizontally between the
piles, starting from the top and working downward.
o Secure the lagging to the soldier piles to retain soil and manage water ingress.
5. Dewatering:
o Use pumps to remove water from the excavation area to create a dry working
environment.
6. Excavation:
o Proceed with excavation work within the cofferdam, ensuring the area remains
stable.
7. Monitoring:
Applications
• Foundation Construction: Used for building foundations in areas near rivers or lakes.
• Retrofitting and Repairs: Effective for repairing existing structures that require
dewatering.
1. Integrated Design: The ICOS method integrates various construction techniques and
materials to optimize the cofferdam’s performance and stability.
Advantages
• Efficiency: The modular nature and prefabricated components speed up construction and
reduce labor costs.
• Safety: Enhances safety during construction through streamlined processes and improved
structural integrity.
• Cost-Effectiveness: Reduces material waste and construction time, resulting in lower
overall project costs.
Design Considerations
1. Hydraulic Analysis: Thorough assessment of water pressure, flow rates, and potential
wave action.
Construction Process
1. Site Preparation:
2. Prefabrication of Components:
o Components may include wall panels, anchors, and other structural elements.
3. Installation:
o Transport the prefabricated components to the site and assemble them according
to the design.
o Use cranes or other lifting equipment for safe handling of heavy elements.
4. Water Management:
o Install dewatering systems as necessary to remove water from the work area and
maintain a dry environment for construction activities.
o Proceed with excavation and other construction tasks within the dry cofferdam
area, ensuring structural integrity is maintained throughout.
6. Monitoring and Maintenance:
o Continuously monitor the cofferdam for signs of instability or water ingress and
make adjustments as necessary.
Applications
• Marine Structures: Used in the construction of docks, piers, and other waterfront
structures.
• Utility Installations: Effective for installing pipelines or other utilities in wet conditions.
5.7 Cofferdams with Touching and Interlocking Piles and Diaphragm Wall
Cofferdams constructed with touching and interlocking piles combined with a diaphragm
wall are sophisticated temporary structures designed to create a dry working area in aquatic
environments or areas with high groundwater. This method enhances stability and
watertightness, making it suitable for a variety of construction projects.
Key Features
o Touching Piles: These piles are installed closely together, creating a barrier that
helps resist water pressure.
o Interlocking Piles: The piles are designed with interlocking features (often
tongue-and-groove) to improve watertightness and structural integrity.
2. Diaphragm Wall:
o A continuous wall made from reinforced concrete that provides additional lateral
support and helps in minimizing water ingress.
Advantages
• High Stability: Provides strong lateral support, which is critical in unstable soil or deep
water conditions.
• Versatility: Suitable for various applications, including foundation work, underwater
construction, and utility installations.
Design Considerations
1. Hydraulic Analysis: Evaluate water pressures, flow rates, and potential wave action that
may impact the structure.
3. Structural Load Analysis: Calculate the loads acting on the cofferdam, considering
factors like hydrostatic pressure and lateral soil pressures.
Construction Process
1. Site Preparation:
2. Installation of Piles:
o Driving: Install the touching and interlocking piles using a vibratory hammer or
impact hammer.
o Alignment: Ensure piles are installed in a straight line with appropriate spacing to
maintain structural integrity.
4. Water Management:
o Implement a dewatering system to keep the work area dry, using pumps as
necessary.
Applications
• Bridge and Pier Construction: Used for constructing bridges, piers, and other structures
requiring deep foundations.
CAISSONS
A caisson is a large, watertight structure used in construction, particularly for building
foundations in or under water. It is designed to provide a dry working environment in submerged
conditions, allowing for the excavation and construction of foundations for bridges, piers, and
other marine structures.
• Waterproof: Designed to keep water out, enabling construction activities to take place
without flooding.
• Varied Shapes: Can be box-shaped, cylindrical, or other forms depending on the specific
application.
• Construction Techniques: Can be built on land and floated to the site, or constructed in
place using specialized techniques.
Purpose
Caissons are primarily used to create stable foundations where traditional building methods
would be impractical due to water or soft soil conditions.
1. Box Caissons
2. Pneumatic Caissons
3. Open Caissons
4. Floating Caissons
5. Combination Caissons
1. Box Caissons
Overview: Box caissons are rectangular or square watertight structures used primarily for
underwater construction, often serving as foundations for bridges, piers, and other marine
structures.
Characteristics
• Shape: Typically box-shaped, though they can be customized to fit specific project
requirements.
• Materials: Made from reinforced concrete, they are designed to withstand significant
loads and resist environmental conditions.
Construction Process
2. Floating to Site: Once completed, the caisson is floated to the desired location on the
water.
3. Sinking: The caisson is gradually sunk to the required depth, often using ballast (such as
water or other heavy materials) to help it descend.
4. Excavation: Once in place, excavation can occur at the base to ensure proper seating and
stability.
Applications
• Bridge Foundations: Ideal for supporting bridge piers in rivers and other bodies of
water.
• Retaining Walls: Can be used to create stable retaining walls in waterfront
developments.
• Marine Structures: Suitable for various marine construction projects where dry working
conditions are needed.
Advantages
• Stability: Provides a strong and stable base for construction, especially in soft or unstable
soil conditions.
• Controlled Environment: Being constructed on land allows for better quality control
and construction practices.
• Adaptability: Can be designed to meet specific load and size requirements based on the
project.
Disadvantages
• Limited Depth: Not suitable for very deep underwater conditions compared to
pneumatic caissons.
2. Pneumatic Caissons
Overview: Pneumatic caissons are specialized underwater construction structures that allow for
excavation and building at significant depths while maintaining a dry working environment.
They are typically cylindrical or box-like in shape and are used in situations where water
pressure is a concern.
Key Features
• Pressurized Environment: Pneumatic caissons operate under air pressure to keep water
out, allowing workers to excavate safely at depth.
• Construction: Made from reinforced concrete, they are designed to withstand both the
weight of the structure above and the pressure of the surrounding water.
• Access: Workers enter and exit through a lock system that maintains pressure, ensuring
the interior remains dry.
Construction Process
1. Placement: The caisson is floated to the construction site and then sunk to the desired
depth using its own weight or added ballast.
3. Excavation: Workers can then excavate soil and rock from the base of the caisson while
it remains pressurized.
4. Foundation Construction: After reaching the desired depth, the foundation for the
intended structure is built inside the caisson.
Applications
• Bridge Foundations: Commonly used for constructing deep foundations for bridge piers
in rivers and coastal areas.
Advantages
Disadvantages
• Cost: Can be more expensive than other methods due to the complexity of pressurization
and safety measures.
3. Open Caissons
Overview: Open caissons are large, hollow structures that are open at the bottom, allowing for
excavation from within. They are typically used in shallow water or on land where water
pressure is manageable.
Key Features
• Shape: Usually cylindrical or rectangular, designed to be heavy enough to sink into the
ground under their own weight.
• Excavation Method: The open bottom allows workers to excavate soil or rock directly
from inside the caisson, facilitating sinking to the desired depth.
• Materials: Constructed from reinforced concrete or steel, designed to withstand the loads
imposed by the structures they support.
Construction Process
1. Placement: The open caisson is positioned at the construction site, often using cranes or
barges.
2. Sinking: It sinks into the ground or seabed under its own weight, and additional ballast
may be added if necessary.
3. Excavation: As the caisson sinks, workers excavate the material from inside, allowing it
to descend further.
4. Foundation Construction: Once the caisson reaches the desired depth, a foundation can
be built within it, typically involving pouring concrete to form a stable base.
Applications
• Bridge Piers: Commonly used for foundations in rivers or shallow marine environments.
• Buildings: Can be used in urban construction where foundations need to be placed in soft
or unstable soil.
• Marine Structures: Suitable for jetties and other structures that require a solid base.
Advantages
• Simplicity: The construction process is relatively straightforward and does not require
complex pressurization systems.
• Cost-Effective: Generally less expensive than pneumatic caissons, making them a good
option for certain projects.
• Versatility: Effective in a variety of soil conditions, particularly where water depth is not
extreme.
Disadvantages
• Water Intrusion: If used in deep water or high-water pressure environments, they may
not be as effective due to potential water intrusion.
• Limited Depth: More suitable for shallow applications compared to pneumatic caissons,
which can handle greater depths.
5.9 Well foundations
Overview: Well foundations, also known as "well-type caissons," are deep foundation systems
used to support structures in locations where soil conditions may be unstable or where significant
load-bearing capacity is required. They are typically cylindrical in shape and are constructed by
digging a large, vertical shaft into the ground.
Key Features
• Construction Method: They are created by excavating a hole in the ground, which is
often lined with concrete or masonry to prevent collapse.
• Depth: Designed to reach stable soil layers below weaker surface soils, making them
suitable for high-load applications.
Construction Process
1. Excavation: A vertical shaft is excavated to the required depth, often using specialized
drilling or digging equipment.
2. Lining: The walls of the excavation may be lined with concrete or reinforced materials to
provide stability.
3. Base Construction: Once the desired depth is reached, the base of the well is typically
filled with concrete to form a solid footing.
4. Column or Pier Installation: A column or pier is then built on top of the well
foundation to support the structure above.
Applications
• Tall Structures: Effective for supporting high-rise buildings and other heavy structures
where deep stability is needed.
• Marine Structures: Suitable for piers, wharves, and other marine constructions that
require a strong foundation.
Advantages
• Load-Bearing Capacity: Well foundations can support substantial loads and are suitable
for various soil conditions.
• Stability: Reaching deeper, stable soil layers provides a solid foundation for
construction.
Disadvantages
• Construction Complexity: The excavation and lining process can be labor-intensive and
may require specialized equipment.
• Cost: Depending on the depth and soil conditions, well foundations can be more
expensive than other types of foundations.
Designing a well foundation involves several key considerations to ensure stability, load-bearing
capacity, and overall structural integrity. Here’s an overview of the essential aspects of well
foundation design:
1. Site Investigation
• Depth Assessment: Determine the depth to stable soil layers, which will influence the
well depth.
• Shape: Typically circular or cylindrical, but may be modified based on specific site
conditions or architectural requirements.
• Diameter: The diameter is influenced by the load requirements and the properties of the
soil. Larger diameters can distribute loads more effectively.
3. Load Considerations
• Vertical Loads: Calculate the total vertical loads from the structure above, including live
loads, dead loads, and any additional loads such as wind or seismic forces.
• Lateral Loads: Assess lateral forces, especially in seismic or wind-prone areas, to ensure
stability against sliding and overturning.
• Embedment Depth: Design the well to extend deep enough to reach stable soil or
bedrock. The embedment depth is critical for load transfer and stability.
• Excavation Depth: Consider the excavation methods and the depth required to facilitate
construction and maintain safety.
5. Material Selection
• Concrete Strength: Use high-strength concrete to resist compressive loads and potential
environmental degradation.
6. Construction Techniques
• Curing: Ensure proper curing of concrete to achieve desired strength and durability.
7. Foundation Cap
• Cap Design: Design a foundation cap or footing to distribute loads evenly across the well
foundation. The cap connects the well to the structure above.
Overview: Pneumatic caissons are large, pressurized structures used for underwater
construction, allowing for excavation in deep water while keeping the interior dry. Here’s how
they are constructed:
Construction Process
1. Design and Fabrication:
2. Floating to Site:
o Once constructed, the caisson is floated to the desired location on water, using
barges or tugboats.
o The caisson is sunk to the required depth by adding ballast (e.g., water or other
heavy materials).
o The interior is pressurized with air to keep water from entering, allowing safe
working conditions.
4. Excavation:
o Excavation occurs at the base to remove soil and rock, enabling the caisson to
sink further until it reaches a stable layer.
5. Foundation Construction:
o Once at the desired depth, the foundation is constructed inside the caisson,
typically by pouring concrete to form a stable base.
6. Finalization:
o After the foundation is set, the caisson is de-pressurized, and the work is
completed.
Designing a pneumatic caisson involves several critical considerations to ensure it can withstand
the pressures of water and support the structures above it. Here’s an overview of the design
process:
1. Site Investigation
• Soil Analysis: Conduct a geotechnical survey to assess soil types, bearing capacity, and
groundwater levels. Understanding soil conditions is crucial for determining the depth
and stability of the caisson.
• Hydrological Studies: Analyze water depth and flow characteristics to inform design
choices.
2. Load Analysis
• Vertical Loads: Calculate the total vertical loads from the structure that the caisson will
support, including dead loads (weight of the structure) and live loads (temporary loads
like traffic).
• Lateral Loads: Consider lateral forces from water pressure, wind, and seismic activities
that may affect the caisson.
• Diameter and Height: Determine the diameter and height of the caisson based on load
requirements and site conditions. Larger diameters can distribute loads better but may
require more material and cost.
4. Material Selection
5. Pressurization System
• Air Pressure Design: Determine the required internal air pressure to keep water out
during excavation. The pressure must counteract the hydrostatic pressure from the
surrounding water.
• Safety Factors: Incorporate safety factors into the design to account for variations in
water levels and unexpected loads.
• Excavation Method: Plan for safe excavation practices within the caisson under
pressurized conditions. This includes the use of airlocks for worker entry and exit.
• Curing and Setting: Design a method for curing the concrete in the caisson once
construction is complete, ensuring it achieves the necessary strength.
• Stability Checks: Perform stability analyses to ensure the caisson will not float or shift
during construction or in response to environmental conditions.
• Decompression Measures: Plan for safe decompression procedures for workers when
exiting the caisson after construction.
• Drainage Design: Consider drainage solutions to manage any groundwater that may
infiltrate during construction or use.
Precast Caissons
Overview: Precast caissons are constructed off-site in a controlled environment and then
transported to the construction site. They are typically box-shaped or cylindrical and are used for
various foundation applications.
Construction Process
o Develop detailed designs for the precast caisson, considering load requirements
and site conditions.
2. Precasting:
3. Curing:
o Allow the precast elements to cure adequately to achieve the required strength
before transportation.
4. Transportation:
o Transport the precast caisson to the construction site using specialized trucks or
barges, depending on the size and location.
5. Installation:
o Position the precast caisson at the intended location using cranes or other lifting
equipment.
o If the caisson is being used in a water environment, ballast may be added to assist
in sinking it to the desired depth.
o Once the caisson is installed, backfill around it if necessary, and construct any
additional foundations or superstructures as required.
The design of precast caissons involves several critical steps to ensure structural integrity, load-
bearing capacity, and adaptability to site conditions. Here’s an overview of the design process:
1. Site Investigation
• Geotechnical Analysis: Conduct soil tests to determine soil properties, bearing capacity,
and groundwater conditions. This information helps in deciding the caisson dimensions
and depth.
• Hydrological Assessment: Evaluate water levels and flow patterns, especially if the
caisson will be submerged.
2. Load Analysis
• Vertical Loads: Calculate the total vertical loads from the structure, including dead loads
(weight of the structure) and live loads (temporary loads, such as traffic or occupancy).
• Lateral Loads: Assess lateral loads due to soil pressure, water pressure, wind, and
potential seismic forces.
• Diameter and Height: Determine the appropriate diameter and height based on load
requirements and soil conditions. Larger diameters may help distribute loads more
evenly.
• Shape: Precast caissons are typically cylindrical or rectangular, but the shape may be
modified based on specific project needs.
4. Material Selection
• Concrete Mix Design: Specify high-strength concrete that meets durability requirements,
especially for exposure to harsh environmental conditions (e.g., water, freeze-thaw
cycles).
5. Precasting Process
• Mold Design: Create molds for the caisson components, ensuring they are capable of
achieving the desired shape and dimensions accurately.
• Casting and Curing: Pour concrete into the molds and allow for proper curing to reach
the required strength before transportation. Utilize curing methods that prevent cracking
and ensure quality.
6. Connection Details
• Joint Design: Plan for the connections between caisson segments, ensuring they are
robust enough to handle the anticipated loads and forces.
• Transportation Logistics: Plan for transporting the precast caisson to the construction
site, considering the size and weight of the components.
• Stability Analysis: Assess the stability of the caisson during installation and operation,
considering factors like buoyancy and soil conditions.
• Safety Measures: Incorporate safety factors in the design to account for uncertainties in
loads and soil behavior.