Project Schedule

Project Schedule for Villa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
247 views1 page

Project Schedule

Project Schedule for Villa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT : MEHTA BUNGLOW , PUNE

ID Task Name Duration Start Finish Predecessors June July August September
W-2 W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W
1 Mr. Mehta Bunglow 75 days Mon 19-06-23Wed 13-09-23
2 Grey Box 75 days Mon 19-06-23 Wed 13-09-23
3 Balance RCC Slab 37 days Mon 19-06-23 Mon 31-07-23
4 Terrace Waterproofing 30 days Wed 05-07-23 Wed 09-08-23 3SS+15 days
5 Toilet Waterproofing Work 30 days Wed 05-07-23 Wed 09-08-23 4SS
6 Balance RCC area waterproofing 24 days Mon 31-07-23 Mon 28-08-23 3
7 Misc Masonary work for waterbody 5 days Mon 19-06-23 Fri 23-06-23 3SS
8 Wall Cheasing & concealed conduititng 10 days Wed 21-06-23 Sat 01-07-23 7SS+2 days
9 Wall Chasing & Concealed Piping 10 days Fri 23-06-23 Tue 04-07-23 8SS+2 days
10 Zarring Plaster 7 days Tue 04-07-23 Wed 12-07-23 9
11 Gypsum Plaster work 32 days Thu 06-07-23 Sat 12-08-23 10SS+2 days
12 Gypsum Plaster Level marking 2 days Thu 06-07-23 Sat 08-07-23 10SS
13 Gypsum Plaster 30 days Sat 08-07-23 Sat 12-08-23 12
14 Trimming Tree Branches in staircase area 5 days Wed 12-07-23 Tue 18-07-23 10
15 Removal of Tree roots 3 days Tue 18-07-23 Fri 21-07-23 14
16 Soling & PCC for Staircase 5 days Fri 21-07-23 Thu 27-07-23 15
17 Fabrication & Installation of Steel Staircase 15 days Tue 18-07-23 Fri 04-08-23 14

18 Fabrication & Instalaltion of service area 10 days Wed 09-08-23 Mon 21-08-23 4
ladder
19 Staircase railing 7 days Fri 04-08-23 Sat 12-08-23 17
20 Fxing door frames 21 days Sat 15-07-23 Wed 09-08-23 10FS+3 days
21 Floor Screedinbg / Mozaic tile 30 days Wed 09-08-23 Wed 13-09-23 20
22 Fabrication of canopy 10 days Mon 19-06-23 Thu 29-06-23 3SS
23 DG Foundation foundation work 7 days Sat 24-06-23 Sat 01-07-23 7
24 HVAC WORK 45 days Sat 24-06-23 Mon 14-08-23
25 Tagging & Bolt fixing 15 days Sat 24-06-23 Tue 11-07-23 7
26 Framing & Ducting 30 days Tue 11-07-23 Mon 14-08-23 25

Page 1