PROJECT : MEHTA BUNGLOW , PUNE
ID Task Name Duration Start Finish Predecessors June July August September
W-2 W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W
1 Mr. Mehta Bunglow 75 days Mon 19-06-23Wed 13-09-23
2 Grey Box 75 days Mon 19-06-23 Wed 13-09-23
3 Balance RCC Slab 37 days Mon 19-06-23 Mon 31-07-23
4 Terrace Waterproofing 30 days Wed 05-07-23 Wed 09-08-23 3SS+15 days
5 Toilet Waterproofing Work 30 days Wed 05-07-23 Wed 09-08-23 4SS
6 Balance RCC area waterproofing 24 days Mon 31-07-23 Mon 28-08-23 3
7 Misc Masonary work for waterbody 5 days Mon 19-06-23 Fri 23-06-23 3SS
8 Wall Cheasing & concealed conduititng 10 days Wed 21-06-23 Sat 01-07-23 7SS+2 days
9 Wall Chasing & Concealed Piping 10 days Fri 23-06-23 Tue 04-07-23 8SS+2 days
10 Zarring Plaster 7 days Tue 04-07-23 Wed 12-07-23 9
11 Gypsum Plaster work 32 days Thu 06-07-23 Sat 12-08-23 10SS+2 days
12 Gypsum Plaster Level marking 2 days Thu 06-07-23 Sat 08-07-23 10SS
13 Gypsum Plaster 30 days Sat 08-07-23 Sat 12-08-23 12
14 Trimming Tree Branches in staircase area 5 days Wed 12-07-23 Tue 18-07-23 10
15 Removal of Tree roots 3 days Tue 18-07-23 Fri 21-07-23 14
16 Soling & PCC for Staircase 5 days Fri 21-07-23 Thu 27-07-23 15
17 Fabrication & Installation of Steel Staircase 15 days Tue 18-07-23 Fri 04-08-23 14
18 Fabrication & Instalaltion of service area 10 days Wed 09-08-23 Mon 21-08-23 4
ladder
19 Staircase railing 7 days Fri 04-08-23 Sat 12-08-23 17
20 Fxing door frames 21 days Sat 15-07-23 Wed 09-08-23 10FS+3 days
21 Floor Screedinbg / Mozaic tile 30 days Wed 09-08-23 Wed 13-09-23 20
22 Fabrication of canopy 10 days Mon 19-06-23 Thu 29-06-23 3SS
23 DG Foundation foundation work 7 days Sat 24-06-23 Sat 01-07-23 7
24 HVAC WORK 45 days Sat 24-06-23 Mon 14-08-23
25 Tagging & Bolt fixing 15 days Sat 24-06-23 Tue 11-07-23 7
26 Framing & Ducting 30 days Tue 11-07-23 Mon 14-08-23 25