Fast Creek Project
Fast Creek Project
1) Develop a network drawing for Hill Construction and determine the critical
path. How long is the project expected to take?
Network Diagram:
F
B E
I
A L
G H
C D
J K
Expected Time for Each Activity, t = (a + 4m + b) / 6
Variance of times, v = [(b-a)/6]2
a = Optimistic time, b = assuming very unfavorable conditions, m = most
realistic estimate
B 20 65 80 60 100
C 50 60 100 65 69.44
D 30 50 100 55 136.11
E 25 30 35 30 2.78
G 25 30 35 30 2.78
H 10 20 30 20 11.11
I 20 25 60 30 44.44
J 8 10 12 10 0.44
L 20 25 60 30 44.44
Critical Path A – C – D – G – H – I – L
Project duration – (30+65+55+30+20+30+30) = 260 days
Variance of critical path = 11.11 + 69.44 + 136.11 + 2.78 + 11.11 + 44.44 +
44.44 = 319.44
Standard deviation of critical path = 17.87 days (sqrt(319.44))
3) If it is necessary to crash to 250 or 240 days, how would Hill do so, and at
what costs?