INSPECTION & TEST PLAN

CLIENT: Synergy DATE: 6/08/2024


CONTACT: Paul Bettridge REQ.: JME-303771-2
PROJECT: Synergy Collie battery Energy Storage System 1 J/N: 2467
Panel & Liner Tank INSPECTION CRITERIA LEGEND
MODEL: APCSPT-GCFH 1171/460D-E1234I2LS600X-401369 H - HOLD POINT W - CLIENT WITNESS
DETAIL: TANK INSTALLATION ITP-00000-0 R - REVIEW ONLY

REMARKS/
VERIFICATION
ACT No. ACTIVITY CONTROL PROCEDURE ACCEPTANCE CRITERIA CONTROL DOCUMENT SYNERGY
RECORD APPROVAL
AP AP Sign Chubb SCEE

1 INSTALLATION TANKS

Approved Tank GA Drawing #


1.1 Check Slab / Ring Beam are correct size Physically measure the Slab/Ring Beam Visual Checks/Confirmation 303771-2 This Document R R

Mark out Nozzle and Ladder positions Approved Tank GA Drawing #


1.2 Mark out Tank onto Ring Beam / Slab Visual Checks/Confirmation 303771-2 This Document R W
onto the Ring beam
Assembly of 1st Tank Wall Ring, Roof Approved Tank GA Drawing #
Circular Steel Tank Construction Manual
1.3 Trusses, Hatches, Guardrailing and Inlet AS PER Section 3 & 4 303771-2 This Document R W
V 1.2
boxes
Circular Steel Tank Construction Manual Approved Tank GA Drawing #
1.4 Roof sheeting Fitted and Trimmed AS PER Section 5 303771-2 This Document H R
V 1.2

Install Liner and fit upper Nozzle Circular Steel Tank Construction Manual Approved Tank GA Drawing #
1.5 As Per Section10 303771-2 This Document H R
penetrations V 1.2
Approved GA
Circular Steel Tank Construction Manual
1.6 Assemble remainder of Tank wall rings As Per Section 6 & 8 Drawing/Circular Steel Tank This Document R R
V 1.2
Construction Manual
Circular Steel Tank Construction Manual Circular Steel Tank
1.7 Hold Down Bolts fitted As per Section 17 This Document R R
V 1.2 Construction Manual V 1.2

Install Ladders / Cages and Security Circular Steel Tank Construction Manual Circular Steel Tank
1.8 As per Secrtion 14 This Document R R
Doors V 1.2 Construction Manual V 1.2

Check all fixings on ladder cages and Circular Steel Tank Construction Manual Circular Steel Tank
1.9 Visual Checks/Confirmation This Document R R
guardrailing correctly tightened V 1.2 Construction Manual V 1.2

Install Lower Nozzle Fittings, SWAH and Circular Steel Tank Construction Manual Circular Steel Tank
1.10 As per Section 15 and 16 This Document R R
Cover (Side Wall Access Hatch) V 1.2 Construction Manual V 1.2

Circular Steel Tank Construction Manual Circular Steel Tank


1.11 Fit Level Indicator Visual Checks/Confirmation This Document R W
V 1.2 Construction Manual V 1.2

Circular Steel Tank


1.12 1st Fill of water to 100 - 150mm deep Operations and Maintenance Manual As per 0.5m full This Document R W
Construction Manual V 1.2

Tank
Installation Supervisor to check off entire ITP
1.13 Practical Completion Visual Checks/Confirmation Commissioning R W&H
tank against all documentation Site File
Report
Revision History
Revision Date Description Allied Pump Author Allied Pumps Approval Client Approval