Project Cost Analysis - Estimate Costs
Project Cost Analysis - Estimate Costs
Estimate Costs
Dr. Hisham Ali Sayed
1
Estimate Costs
The process of developing an approximation of the monetary resources
needed to complete project work.
Special
Inflation allowance Contingency costs Cost of financing
Categories :
3
Law of Diminishing Returns
• The more you put into something, the less you get out of it.
• For example, adding twice as many resources to an activity may not
get the activity done in half the time.
4
The accuracy of a project estimate
• The accuracy of a project estimate will increase as the project progresses
through the project life cycle.
• In some organizations, there are guidelines for when such refinements can
be made and the degree of confidence or accuracy that is expected.
5
07.2 Estimate Costs
7
07.2 Estimate Costs
Contingency reserves
(allowances)
9
Analogous Estimating (Top Down)
Analogous estimating : A technique for estimating the duration or cost
of an activity or a project using historical data from a similar activity or
project.
10
Parametric Estimating
Parametric estimating: An estimating technique in which an algorithm
is used to calculate cost or duration based on historical data and
project parameters.
Use Parameters From Previous
Reliable if: Projects
Values: Measures of Scale:
• Historical information used - Scope - Size
was accurate. -Cost - Weight
• The parameters used in -Duration - Complexity
the model are readily
quantifiable.
Estimate Same Parameter for
• The model is scalable (i.e.
works for both a small and Current Project
larger project). 11
Bottom-Up Estimating
Bottom-Up Estimating: A method of estimating project duration or cost
by aggregating the estimates of the lower-level components of the
work breakdown structure (WBS).
12
Three-Point Estimating
Three-Point Estimating: A technique used to estimate cost or duration
by applying an average of optimistic, pessimistic, and most likely
estimates when there is uncertainty with the individual activity
estimates.
13
Three-Point Estimating
Depending on the assumed distribution of values within the range of
the three estimates the expected cost, cE, can be calculated using a
formula:
Triangular Distribution:
cE = (cO + cM + cP) / 3
• Contingency reserve
• Management reserve
15
Reserve Analysis
• At this stage Cost estimates may include contingency reserves or
buffers (a percentage of the estimated cost, a fixed number of work
periods, or may be developed by using quantitative analysis
methods).
• As More information is available , the contingency reserve may be
used, reduced, or eliminated.
• Contingency should be clearly identified in cost documentation.
• Estimates may also include Management reserve of cost for the
project.
16
Vendor Bid Analysis
• Cost estimating methods may include analysis of what the project
should cost, based on the responsive bids from qualified vendors.
17
Group Decision-Making Techniques
Team-based approaches, such as brainstorming, the Delphi or nominal
group techniques, are useful for engaging team members to improve
estimate accuracy and commitment to the emerging estimates.
18
Categories of Construction Costs
Variable
Cost
Fixed Cost
Indirect
Cost Direct Cost
19
Variable Costs vs Fixed Costs
Variable Costs:
• Costs that change with the amount of production or the amount of
work.
• Examples: the cost of material, supplies and wages.
Fixed Costs:
• These are costs that do not change as production changes.
• Examples: set-up, rental, etc.
20
Direct Costs vs Indirect Costs
Direct Costs:
• Costs that are directly attributable to the work on the project.
• Examples: team travel, team wages, recognition, and costs of material
used on the project.
Indirect Costs:
• Overhead items or costs incurred for the benefit of more than one
project.
• Examples: Include taxes, fringe benefits …
21
Direct, Indirect, and Special Categories Costs
Cost estimates can be presented in summary form or in detail. Costs
are estimated for all resources that are applied to the activity cost
estimate
22
Discussion about Activity Cost estimates
Classification
1. RC for Columns for the 2nd Floor.
2. Rental cost for company head office.
3. Permits Cost for the project.
23
Discussion about Activity Cost estimates
Classification
Fixed Cost Variable Cost
Direct Cost 3-Permits Cost 1-RC for
for the project Columns for the
2nd Floor
In Direct Cost 2-Rental cost for -
company head
office
24
Depreciation
• Depreciation is the decrease in value of an asset over a period of time for
accounting and tax purposes.
• Depreciation Methods: Initial
Cost
• Straight Line Depreciation:
• Property depreciates the same
Salvage
• amount every year Value time
• Accelerated Depreciation:
• Property depreciates more rapidly in Initial years than Straight Line Depreciation.
Some examples are:
• Double Declining Balance Initial
Cost
• Sum of the Year Digits
Salvage
Value
time
25
07.2 Estimate Costs
Basis of estimates
27