pmpc expt 10
pmpc expt 10
pmpc expt 10
10
Module 5: Project Monitoring & Cost Control
Experiment Title: Project Crashing and Trade-Off Analysis
Task :
Select a network diagram of a construction project, including tasks, durations, and costs.
Perform crashing analysis to shorten the project timeline, considering cost implications.
Update the project schedule and cost estimates after applying crashing techniques.
Deliverable:
1. Project Overview
For this experiment, let’s consider a hypothetical construction project to build a multi-story
residential building. The project involves several critical tasks, including design, foundation
construction, superstructure work, and finishing. Each of these tasks has associated durations
and costs.
Example Tasks:
Architectural Design
Structural Design
Site Preparation
Foundation Work
Superstructure Construction
MEP (Mechanical, Electrical, Plumbing) Installation
Finishing and Handover
We will apply project crashing techniques to reduce the overall project duration while
examining the associated increase in project costs.
Before performing the project crashing, we need an initial network diagram of the
construction project. This network will show the tasks, their durations, dependencies, and
costs.
Note: These are example values; adjust the durations and costs based on the specific project
being studied.
Project crashing is the process of reducing the project’s duration by shortening task durations,
typically by adding more resources. While crashing reduces time, it usually increases costs,
so the challenge is to find the optimal balance between time reduction and additional costs.
Let’s examine the project duration and determine where crashing would have the most
significant impact. The following steps outline the crashing process:
Step 1: Identify the critical path in the project network. This is the longest path
through the network, and any delay on the critical path will delay the entire project.
Step 2: Determine which tasks on the critical path can be crashed. Each task will have
a “crash cost,” which is the cost of reducing the task duration by one day.
Step 3: Calculate the potential crash time for each task and evaluate the cost of
crashing each task.
Step 4: Apply the crashing analysis. Crashing can involve extending working hours,
increasing the number of workers, or using more equipment. Adjust the project
schedule by shortening the durations of tasks on the critical path.
Let’s assume that we are focusing on the Foundation Work (Task 4) and the
Superstructure Construction (Task 5), which are critical tasks in the network.
After applying the crashing techniques, the project duration is reduced from 140 days to 135
days.
The project schedule will be adjusted to reflect the new, shortened task durations.
Additionally, the costs will be updated to include the crash costs for the affected tasks.
Learning Outcome:
Conclusion
In this experiment, we demonstrated how to apply project crashing techniques to reduce the
overall duration of a construction project while analyzing the associated costs. By focusing
on critical tasks and optimizing resources, project managers can make informed decisions
about project schedules and costs. The time-cost trade-off analysis is crucial for managing
construction projects effectively and ensuring that deadlines are met without exceeding the
project budget.