Problems Chapter 13
Problems Chapter 13
To determine whether the inspection position should be eliminated, we need to compare the
cost of maintaining the inspection position with the cost of replacing defective items later.
Let's calculate the costs:
If the inspection position is eliminated, defective units will go into product assembly and will
be detected later. So, the cost of replacing defective units later = Number of defective units *
Cost to replace each defective unit.
In this case, eliminating the inspection position would result in a slightly higher cost of
$20/hour compared to the current cost of inspection at $18/hour. So no, it shouldn’t be
eliminated.
Total cost to inspect each unit = ($18/hour + $450/hour) / 50 units/hour = $468 / 50 = $9.36
per unit
Total cost of inspection per hour = Cost to inspect each unit * Inspection rate
$9.36/unit * 50 units/hour = $468/hour
Now, let's compare the total cost of inspection with the cost of replacing defective items later:
There is a clear cost benefit associated with the current inspection process. The total cost of
inspection per hour ($468) is significantly lower than the cost of replacing defective items
later ($20). Therefore, the current inspection process results in a cost savings.
Problem 3
Cost to inspect each Item = Inspection cost/hr / Inspection rate/hr = 8/20 = $0.4/unit
Cost not to inspect each item = defective rate*replacement cost = 0.02*$25 = $0.5/unit
Benefit from inspection process = Cost not to insp/unit - cost to insp./unit = 0.5 - 0.4 = 0.1
It’s better to inspect before
Problem 7
Sp = Sp Rt of [(p-bar)(1-p-bar)/n]
=[ (0.053/(0.94,7/15]
= Sq Rt of (0.00335) = 0.0578
Problem 9
a) Develop an Xbar chart and R-chart and plot the values
Similarly compute 15 R Values by subtracting the bigger one by the smallest one.
Sample 1 = 1010-985 = 25
Sample 2 = 1009 - 994 = 15
25 22 26 11 38 15 18 28 17 28 22 15
Sample 15 =1013-992 = 21
A2 = 0.729 D3 = 0 D4 = 2.282
Constructs X bar limits
Construct R limits
UCLr = R bar* D4
= 21.7*2.282
= 49.52
LCLr = R bar*d3
= 21.7*0
=0
b) What comments can you make about the process ?
X-bar Chart:
● Center Line (CL) or Average (X-double bar): 998.97
● Upper Control Limit (UCLx-bar): 1014.5193
● Lower Control Limit (LCLx-bar): 982.881
The process average (X-bar) of 998.97 falls within the control limits. This suggests that, on
average, the process is stable and centered around the expected value.
R Chart
● Center Line (CL) or Average (R-bar): 21.7
● Upper Control Limit (UCLr): 49.52
● Lower Control Limit (LCLr): 0
● Observation: The range (R) of 21.7 falls within the control limits. This indicates that
the variability in the process is stable and within expected limits.
In summary, based on the control chart analysis, the process appears to be in control both in
terms of the average (X-bar) and variability (R). This suggests a stable and consistent
process. However, it's important to continue monitoring future data points to ensure ongoing
process stability.
Problem 15
Given Specifications:
AQL (Acceptable Quality Level) for the LSI manufacturer: 1.5%
LPTD (Lot Percent Defective) acceptable by the assembly department: 4%
Sampling Plan:
Select a Sample Size (n):
● Assume a sample size of 100 items.
Determine Acceptance Number (c) and Reject Number (r):
● Assume an acceptance number (c) of 3 and a reject number (r) of 5 based on
statistical tables.
Establish the Sampling Plan Parameters:
● AQL: 1.5%
● LPTD: 4%
● Sample Size (n): 100
● Acceptance Number (c): 3
● Reject Number (r): 5