Manual 3PH Inverter
Manual 3PH Inverter
Disclaimers
Important Notice
Copyright © SolarEdge Inc. All rights reserved.
No part of this document may be reproduced, stored in a retrieval system or
transmitted, in any form or by any means, electronic, mechanical, photographic,
magnetic or otherwise, without the prior written permission of SolarEdge Inc.
The material furnished in this document is believed to be accurate and reliable.
However, SolarEdge assumes no responsibility for the use of this material. SolarEdge
reserves the right to make changes to the material at any time and without notice. You
may refer to the SolarEdge web site ( www.solaredge.com) for the most updated version.
All company and brand products and service names are trademarks or registered
trademarks of their respective holders.
Patent marking notice: see http://www.solaredge.com/patent
The general terms and conditions of delivery of SolarEdge shall apply.
The content of these documents is continually reviewed and amended, where
necessary. However, discrepancies cannot be excluded. No guarantee is made for the
completeness of these documents.
The images contained in this document are for illustrative purposes only and may vary
depending on product models.
Emission Compliance
This equipment has been tested and found to comply with the limits applied by the
local regulations. These limits are designed to provide reasonable protection against
harmful interference in a residential installation. This equipment generates, uses and
can radiate radio frequency energy and, if not installed and used in accordance with
the instructions, may cause harmful interference to radio communications. However,
there is no guarantee that interference will not occur in a particular installation. If this
equipment does cause harmful interference to radio or television reception, which can
be determined by turning the equipment off and on, you are encouraged to try to
correct the interference by one or more of the following measures:
Reorient or relocate the receiving antenna.
Increase the separation between the equipment and the receiver.
Connect the equipment into an outlet on a circuit different from that to which
the receiver is connected.
Consult the dealer or an experienced radio/TV technician for help.
Changes or modifications not expressly approved by the party responsible for
compliance may void the user’s authority to operate the equipment.
Revision History
Version 1.2 (Feb 2019)
Added appendix 'Determining the Circuit Breaker Size' and paragraph
referencing to it, in the 'Grid Connection Guidelines' section.
Updated guidelines for use of extension cables in power optimizer installation
Torque for plastic cover screws 10.3 N*m/ 7.5 lb-ft.
In Specifications:
Addition of footnote for MC4 inputs: Connection of additional strings in
parallel to a single input is allowed as long as the cumulative current
does not exceed 45A.
Removed the 'Recommended circuit breaker/ fuse size to use at the grid
connection point' table.
Contents
Disclaimers 1
Important Notice 1
Emission Compliance 2
Support and Contact Information 3
Revision History 4
HANDLING AND SAFETY INSTRUCTIONS 7
Safety Symbols Information 7
IMPORTANT SAFETY INSTRUCTIONS 8
Chapter 1: Introducing the SolarEdge Power Harvesting System 10
Power Optimiser 10
Inverter 11
Monitoring Platform 11
Installation Procedure 11
Installation Equipment List 11
Inverter Transport and Storage 12
Chapter 2: Installing the Power Optimizers 13
Safety 13
Installation Guidelines 14
Step 1: Mounting the Power Optimizers 17
Step 2: Connecting a PV Module to a Power Optimiser 17
Step 3: Connecting Power Optimizers in Strings 18
Step 4: Verifying Proper Power Optimiser Connection 19
Chapter 3: Installing the Inverter 20
Inverter Package Contents 20
Identifying the Inverter 20
Inverter Interfaces 20
Mounting the Inverter 25
Chapter 4: Connecting the AC and the Strings to the Inverter 30
Grid Connection Guidelines 30
Connecting the AC Grid to the Inverter 31
Connecting the Strings to the Inverter 33
Selecting a Residual Current Device (RCD) 33
Chapter 5: Activating, Commissioning and Configuring the System Using the
Inverter SetApp 35
Step 1: Activating the Installation 35
Step 2: Commissioning and Configuring the Installation 36
Step 3: Verifying Proper Activation and Commissioning 40
Viewing System Status 40
Disposal requirements under the Waste Electrical and Electronic Equipment (WEEE)
regulations:
NOTE
Discard this product according to local regulations or send it back to SolarEdge.
WARNING!
Before operating the inverter, ensure that the inverter AC power cable and wall
outlet are grounded properly. This product must be connected to a grounded,
metal, permanent wiring system, or an equipment-grounding conductor must
be run with the circuit conductors and connected to the equipment grounding
terminal or lead on the product.
WARNING!
Opening the inverter and repairing or testing under power must be performed
only by qualified service personnel familiar with this inverter.
WARNING!
Do not touch the PV panels or any rail system connected when the inverter
switch is ON, unless grounded.
WARNING!
SafeDC complies with IEC60947-3 when installing the system with a worst case
SafeDC voltage (under fault conditions) < 120V.
The worst case voltage is defined as: Voc,max+ (String Length-1)*1V, where:
Voc,max = Maximum Voc (at lowest temperature) of the PV module in
the string (for a string with multiple module models, use the max value)
String Length = number of power optimizers in the string
CAUTION!
This unit must be operated according to the technical specification datasheet
provided with the unit.
CAUTION!
HEAVY OBJECT. To avoid muscle strain or back injury, use proper lifting
techniques, and if required - a lifting aid.
NOTE
The inverter is IP65 rated . Unused conduit openings and glands should be
sealed with appropriate seals.
NOTE
Use PV modules rated according to IEC 61730 class A.
NOTE
The symbol appears at grounding points on the SolarEdge equipment. This
symbol is also used in this manual.
NOTE
A SolarEdge inverter may be installed in a site with a generator, however must
not operate at the same time as the generator.
Operating an inverter and a generator simultaneously will void the warranty.
SolarEdge requires installing a physical or electronic interlock, which will
prevent the generator and inverter from operating simultaneously. Interlock
procurement, installation, maintenance and support are the responsibility of
the installer. Damage to the inverter due to incorrect interlock installation or
use of an interlock that is incompatible with the SolarEdge system will render
the SolarEdge warranty invalid.
NOTE
The following warning symbols appear on the inverter warning label:
Power Optimiser
The power optimizers are DC-DC converters connected to PV modules in order to
maximize power harvesting by performing independent Maximum Power Point
Tracking (MPPT) at the module level.
The power optimizers regulate the string voltage at a constant level, regardless of string
length and environmental conditions.
The power optimizers include a safety voltage function that automatically reduces the
output of each power optimizer to 1 Vdc in the following cases:
During fault conditions
The power optimizers are disconnected from the inverter
The inverter ON/OFF switch is turned OFF
The safety switch on the DC Safety Unit is turned OFF
The inverter AC breaker is turned OFF
Each power optimizer also transmits module performance data over the DC power line
to the inverter.
Inverter
The inverter efficiently converts DC power from the modules into AC power that can be
fed into the main AC service of the site and from there to the grid. The inverter also
receives the monitoring data from each power optimizer and transmits it to a central
server (the monitoring platform; requires Internet connection).
Some inverters are available with an optional DC Safety Unit. The DC Safety Unit has a
manually operated switch for disconnecting the DC power of a SolarEdge system.
The DC Safety Unit is located below the inverter and is connected to the inverter with
AC and DC wires.
Monitoring Platform
The monitoring platform enables monitoring the technical and financial performance of
one or more SolarEdge sites. It provides past and present information on the system
performance both at the system and module levels.
Installation Procedure
The following is the procedure for installing and setting up a new SolarEdge site. Many
of these also apply to modification of an existing site.
1. Connecting Power Optimizers in Strings, page 18.
2. Recording power optimizer serial numbers (optional), page 47.
3. Mounting the inverter, Page 25.
4. Connecting the AC and the Strings to the Inverter, page 31, or Connecting the AC and the
String to the DC Safety Unit , page 68.
5. Commissioning and activating the installation, page 35.
6. Connecting the inverter to the monitoring platform, page 48.
CAUTION!
Installing a SolarEdge system without ensuring compatibility of the module
connectors with the optimizer connectors may be unsafe and could cause
functionality problems such as ground faults, resulting in inverter shut down. To
ensure mechanical compatibility of the power optimizers’ connectors with the PV
modules’ connectors to which they are connected:
Use identical connectors from the same manufacturer and of the same
type on both the power optimizers and on the modules; or
Verify that the connectors are compatible in the following way:
The module connector manufacturer should explicitly verify
compatibility with the SolarEdge optimizer connector; and
A third-party test report by one of the listed external labs (TUV,
VDE, Bureau Veritas UL, CSA, InterTek) should be
obtained,verifying the compatibility of the
connectors.
For more information, refer to
https://www.solaredge.com/sites/default/files/optimizer-input-
connector-compatibility.pdf
Installation Guidelines
The minimum and maximum string length guidelines are stated in the power
optimizer datasheets. Refer to the Designer for string length verification. The
Designer is available on the SolarEdge website at
https://www.solaredge.com/products/installer-tools/designer#/.
Frame-mounted power optimizers are mounted directly on the
module frame , regardless of racking system (rail-less or with rails).
For installation of frame-mounted power optimizers, refer to
http://www.solaredge.com/sites/default/files/installing_frame_mounted_
power_optimizers.pdf.
The steps in this chapter refer to module add-on power optimizers. For smart
modules, start from Step 3: Connecting Power Optimizers in Strings on page
18Step 3: Connecting Power Optimizers in Strings on page 18 Also refer to the
documentation supplied with the smart modules.
The power optimizer can be placed in any orientation.
If connecting more modules than optimizer inputs in parallel, use a branch
cable. Some commercial power optimizer models have a dual input.
Position the power optimizer close enough to its module so that their cables
can be connected.
Make sure to use power optimizers that have the required output conductor
length:
Do not use extension cables between a module and a power optimizer,
between two modules connected to the same optimizer, or between two
optimizers other than in the cases specified below.
You can use extension cables between power optimizers only from row
to row, around obstacles within a row, and from the end of the string to
the inverter, as long as the maximum distance is not exceeded.
NOTE
The total conductor length of the string (excluding
power optimizers’ conductors; including home runs and
necessary extensions between optimizers) should not
exceed the following:
NOTE
The images contained herein are for illustrative purposes only and may vary
depending on product models.
3. Attach each power optimizer to the rack using M6 (1/4'') stainless steel bolts, nuts
and washers or other appropriate mounting hardware. Apply torque of 9-10 N*m /
6.5-7 lb*ft.
4. Verify that each power optimizer is securely attached to the module support
structure.
5. Record power optimizer serial numbers and locations, as described in Reporting and
Monitoring Installation Data on page 46.
Connect the Minus (-) output connector of the module to the Minus (-) input
connector of the power optimizer.
Inverter Interfaces
The following figure shows the inverter connectors and components, located at the
bottom of the inverter.
via the LEDs and on the SolarEdge SetApp mobile application screen,
and performing the following functions:
P Position
Function Comments
duration
Displays (via
LEDs) production
information for 5 While the switch is in P, all
Switch moved LEDs are ON.
seconds, or error type
to P for less When the switch is released
indications (if exist)
than 5 all LEDs turn OFF for 0.5 sec
for 5 seconds.
seconds, then and then display the
Activates the Wi-Fi
released. production or error
access point for indication.
connecting to the
SetApp
Switch moved
to P for more Pairing is indicated by all 3
than 5 Starts pairing LEDs blinking
seconds, then simultaneously.
released.
LEDs
(1)
LEDs: three LEDs indicate, by color and state (on/ off/ blinking /
(2) (3)
flickering /alternating ), different system information, such as errors or
performance indications.For more information, refer to
https://www.solaredge.com/leds .
The main LED indications are:
Blue ON - the inverter is communicating with the
monitoring platform
Green ON - the system is producing
(2) Flickering = Turns ON for 100 mS and turns OFF for 5 seconds
Figure 7: LEDs
The following table describes system performance information by LED color and
ON/OFF/P switch position.
ON/ OFF/
LED color
P
Indication Comment
switch
position Red Green Blue
S_OK: ON
S_OK: ON communication
Power
with the
optimizers not OFF Blinking No S_OK:
paired monitoring
OFF
platform is
established.
Pairing Blinking Blinking Blinking
Wake-up/ Grid ON (1) OFF Blinking Blinking
Monitoring
S_OK: ON
System
OFF ON No S_OK:
Producing
OFF
S_OK: ON
Night mode
OFF Flickering No S_OK:
(no production)
OFF
ON/ OFF/
LED color
P
Indication Comment
switch
position Red Green Blue
S_OK: ON
Inverter is OFF
OFF Blinking No S_OK:
(Safe DC)
OFF
OFF (0)
S_OK: ON
Inverter is OFF
Blinking Blinking No S_OK:
(DC not safe)
OFF
Inverter
configuration ON / P ON ON ON
or reboot
Inverter The upgrade
firmware ON / P Alternating Alternating Alternating process can take
upgrade up to 5 minutes
Refer to Errors
ON/ OFF/
ON/ OFF / and
Error Any ON Blinking/
Blinking Troubleshooting
Flickering
on page 62
The following table describes producution percentage of AC information by LED color
and ON/OFF/P switch position.
ON/
LED color
OFF/ P
Indication Comment
switch
position Red Green Blue
Percentage of AC
Production: OFF OFF OFF
0%
Percentage of AC This indicates
Production: OFF ON OFF power
0 - 33 % production as
ON (1)
Percentage of AC percentage of
Production: OFF OFF ON rated peak AC
33 - 66 % output power
Percentage of AC
Production: OFF ON ON
66 - 100 %
NOTE
When the DC Safety Unit is OFF (for example during maintenance) it may be
locked to prevent a safety hazard:
1. Move the switch to the Lock position.
2. Insert the lock through the knob opening
and lock.
NOTE
Make sure the mounting surface or structure can support the weight of the
inverter and bracket, and make sure that it spans the width of the bracket.
CAUTION!
HEAVY OBJECT. To avoid muscle strain or back injury, use proper lifting
techniques, and if required - a lifting aid.
CAUTION!
SolarEdge inverters and power optimizers can be installed at a minimum
distance of 50 m/ 164 ft from the shoreline of an ocean or other saline
environment, as long as there are no direct salt water splashes on the inverter or
power optimizer.
1. Determine the inverter mounting location, on a wall, stud framing or pole. It is
recommended to mount the inverter in a location protected from direct sunlight.
2. To allow proper heat dissipation, maintain the following minimum clearance areas
between the inverter and other objects:
If installing a single inverter:
At least 20 cm (8") from the top and bottom of the inverter; if installing
an inverter with a DC Safety Unit, make sure to leave sufficient clearance
for cable entry.
10 cm (4") from the right and left of the inverter. For easy access to the
fans , a larger clearance is recommended.
If installing multiple inverters:
When installing inverters one above the other, leave at least 40 cm (16")
between inverters. If installing an inverter with a DC Safety Unit, leave 20
cm (8") between the top of an inverter and the bottom of the DC Safety
Unit).
When installing inverters side by side, follow these clearance
specifications:
Indoor
Location Outdoor Installation
Installation
Locations where the
20 cm / 8"
annual average high
(1) between
temperature is below 5 cm / 2" between inverters (if
inverters
25˚C / 77˚F inverters are also installed one
Locations where the above the other, maintain the
40 cm / 16"
annual average high indoor installation clearance)
between
temperature1 is above
inverters
25˚C / 77˚F
(1)Annual average high temperature – the average of the 12 monthly average highs, for
example:
3. Position the mounting bracket against the wall/pole and mark the drilling hole
locations (refer to Mechanical Specifications on page 67 for inverter and mounting
bracket dimensions):
Ensure that the flat edge of the bracket is at the bottom, as in Figure 11.
Use at least two bracket holes. Additional holes can be used to fix the
bracket. Determine which and how many holes to use according to
mounting surface type and material.
4. Drill the holes and mount the bracket. Verify that the bracket is firmly attached to
the mounting surface.
NOTE
When mounting an inverter on an uneven surface, you may use spacers/
washers behind the top mounting hole of the bracket. Depending on the
angle, use the appropriate size and number of spacers so that the bracket is
perpendicular to the ground. Recommended: a stainless steel 3/4" long screw,
with a 1/4" socket button head , two jam nuts and three washers.
5. Hang the inverter on the bracket (see Figure 11): Lift the inverter from the sides, or
hold it at the top and bottom of the inverter to lift the unit into place. Do not lift
holding the Connection UnitDC Safety Unit as it may be damaged.
6. Align the two indentations in the inverter enclosure with the two triangular
mounting tabs of the bracket, and lower the inverter until it rests on the bracket
evenly.
3. Strip 58 mm / 2.32'' of the external cable insulation and strip 8 mm / 0.32'' of the
internal wire insulation.
5. For SE25K, SE27.6K, and SE33.3K three phase inverters, attach the supplied Ferrite
bead to the AC wires:
1. Insert the AC wires through the supplied bead.
2. Connect the AC wires to the terminal blocks as described in the next steps.
3. Tighten the wires to the bead using the supplied T-wrap.
Connect to
Wire type
terminal
Line 1 L1
Line 2 L2
Line 3 L3
Neutral N
NOTE
If power control is enabled, it is important to respect the order of grid lines
connection to the inverter. A 120deg phase difference should be kept
between L1 to L2 and between L2 to L3 (L1-L2-L3 and not, for example L1-L3-
L2).
If the grid lines are not in this order, an error is displayed on the SetApp
screen and the inverter will not produce power.
7. Connect the wires to the appropriate terminal block connectors in the inverter.
Tighten the terminal block screws with a torque of 1.2-1.5 N*m / 0.88-1.1 lb*ft.
8. Check that the wires are fully inserted and cannot be pulled out easily.
9. Tighten the AC cable gland with a torque of 2.8-3.3 N*m / 2.0-2.4 lb*ft.
10. Verify that there are no unconnected wires to the inverter and that the unused
terminal screws are tightened.
If an external RCD is required by local regulations, check which type of RCD is required
for the relevant electric code. Install the residual-current device (RCD) in accordance
with the applicable local standards and directives. SolarEdge recommends using a type-
A RCD. The recommended RCD value is 100 mA or 300 mA unless a lower value is
required by the specific local electric codes. For extended power three phase inverters
(SE25K, SE27.6K and SE33.3K) an RCD value of 300 mA should be used. When required
by local regulations, the use of an RCD type B is permitted.
NOTE
For multiple inverters, an RCD per inverter is required.
In installations where the local electric code requires an RCD with a lower leakage
setting, the discharge current might result in nuisance tripping of the external RCD. The
following steps are recommended to avoid nuisance tripping of the external RCD:
Select the appropriate RCD for correct operation of the installation: An RCD with
a rating of 30 mA may actually trip at a leakage as low as 15 mA (according to
IEC 61008). High quality RCDs will typically trip at a value closer to their rating.
Configure the trip voltage of the inverter's internal RCD to a lower value than
the trip current of the external RCD. The internal RCD will trip if the current is
higher than the allowed current, but because the internal inverter RCD
automatically resets when the residual currents are low it saves the manual
reset.
For detailed information, refer to the RCD Selection for SolarEdge
Inverters Application Note, available on the SolarEdge website at
http://www.solaredge.com/sites/default/files/application_note_ground_fault_
rcd.pdf.
Internet connection is required for the download and for the one-time registration,
however not required for using the SetApp.
In the main menus, tap the menu red arrows ( ›) to perform the system commissioning
or configuration task. Tap the Back arrow ( ‹) to return to the previous menu.
The next sections provide more information about configuration options (in addition to
Country and Language and Pairing, described in Step 2: Commissioning and
Configuring the Installation on page 36).
WARNING!
The inverter must be configured to the proper setting in order to ensure that
it complies with the country grid code and functions properly with the
country grids.
Pairing
1. From the main menu, select Pairing.
2. Tap Start Pairing.
3. When Pairing Complete is displayed, the system startup process begins:
Since the inverter is ON, the power optimizers start producing power and the
inverter starts converting AC.
WARNING!
When you turn ON the inverter ON/OFF/P switch, the DC cables carry a high
voltage and the power optimizers no longer output a safe 1V output.
When the inverter starts converting power after the initial connection to the AC, the
inverter enters Wakeup mode until its working voltage is reached. This mode is
indicated by the flickering green inverter LED.
When working voltage is reached, the inverter enters Production mode and
produces power. The steadily lit green inverter LED indicates this mode.
4. Tap OK to return to the main menu.
Communication
Communication settings can be configured only after communication connections are
complete. Refer to Setting Up Communication on page 49.
1. Select the Communication menu to define and configure the following:
The communication option used by the inverter to communicate with the
monitoring platform
The communication option used to communicate between multiple
SolarEdge devices or other external non-SolarEdge devices, such as
electricity meters or loggers.
2. Tap the Server red arrow to set the communication method to be used for
NOTE
The Server menu shows only the communication options installed in the
inverter.
For detailed information about all the configuration options, refer to the
Communication Options Application Note, available on the SolarEdge
website at https://www.solaredge.com/sites/default/files/solaredge-
communication_options_application_note_v2_250_and_above.pdf.
Power Control
Power control options are detailed in the Power Control Application
Note, available on the SolarEdge website at
https://www.solaredge.com/sites/default/files/application_note_power_control_
configuration.pdf.
The Grid Control option may be disabled. Enabling it opens additional options in the
menu.
The Energy Manager option is used for setting power export limitation, as
described in the Export Limitation Application Note, available on the
SolarEdge website at https://www.solaredge.com/sites/default/files/feed-in_
limitation_application_note.pdf.
Device Manager
From the Commissioning menu, select Device Manager to configure various system
Smart Energy Management devices.
For more information refer to https://www.solaredge.com/products/device-
control#/.
Maintenance
From the Commissioning menu, select Maintenance to configure various
system settings, as described below.
Date and Time: Set the internal real-time clock. If connected to the monitoring
platform, the date and time are set automatically and only time zone should be
set.
Reset Counters: Resets the accumulated energy counters that are sent to the
monitoring platform
Factory Reset: Performs a general reset to the default device settings.
Arc Fault Circuit Interrupter (AFCI): Enables or disables production interruption
in case of arc-fault, sets the reconnection mode, and enables or disables manual
AFCI self-test.
Refer to https://www.solaredge.com/sites/default/files/arc_fault_
detection_application_note.pdf .
Firmware Upgrade: Perform a software upgrade.
Diagnostics: Displays the Isolation status and power optimizer
status screens. Refer to
https://www.solaredge.com/sites/default/files/application_note_
isolation_fault_troubleshooting.pdf.
Activate Standby Mode: Enables/disables Standby Mode - for
remote commissioning.
Grid Protection: Available in specific countries. Enables viewing and setting grid
protection values.
Board Replacement: Backs up and restores the system parameters, including
energy counters; Used during board replacement according to the instructions
supplied with replacement kits.
Information
From the Commissioning menu, select Information to view and set various system
settings, as described below.
CPU Version: The communication board firmware version
DSP 1/2 Version: The digital board firmware version
NOTE
Please have these numbers ready when you contact SolarEdge Support.
Serial Number - The inverter serial number as appears on the enclosure sticker
Hardware IDs: Displays the following HW serial numbers (if exist, and
connected to the inverter):
This inverter: the inverter's ID
Meter # : Energy meter ID (up to 3 meters can be connected)
ZB: ZigBee Plug-in MAC address
WiFi: Wi-Fi MAC address
Error Log: Displays the last five errors, and enables resetting (clearing) the log.
Warning Log: Displays the last five warnings, and enables resetting (clearing)
the log.
A gray clock icon ( ) may appear at the top left corner of a status cell, indicating a
temporary status, such as a connection process. When the process is complete, the icon
disappears and a constant status message is displayed.
Status
Inverter
SN 07318000C
Power Voltage Frequency
50 kW 230Vac 50 Hz
P_OK: 15 of 20 Server Comm.
Optimizers S_OK
Connected (LAN)
Status Switch
Production OFF
CosPhi Limit Country
1.00 No Limit Netherlands
Voltage Temp Fan
350 Vdc 20 C N/A
Switch Off. Production disabled ›
Commissioning ›
Inverter: The inverter serial number
Power: The AC output power
Voltage (Vac): The AC output voltage
Frequency: The AC output frequency
S_OK: The connection to the monitoring platform. (Server Connected appears
only if the inverter is connected to the monitoring platform).
Status: The inverter operation status: Off, Not Paired, Night Mode, Error,
Pairing, or Production
Switch: Indicates the position of the inverter ON/OFF/P switch: On, Off, or P
position.
CosPhi: Indicates the ratio between active and reactive power.A negative value
indicates a lagging CosPhi.
For more information, refer to the Power Control Application
Note, available on the SolarEdge website at
https://www.solaredge.com/sites/default/files/application_note_power_
control_configuration.pdf.
Limit: The inverter maximum output power
Country: The selected country and grid setting
Voltage (Vdc): The DC input voltage
Temp (°C or °F): The inverter heat sink temperature
Site Status
The Site status screen shows the accumulated status of all inverters connected to a
master inverter in a chain (bus) and the master inverter status.
Status
Site
Production Limit Inverters
90 kW 1.00 MW 10/10
Inverter
SN 07318000C
Power Voltage Frequency
100 kW 277 Vac 60.9 Hz
P_OK: 31 0f 31 S_OK
Optimizers Connected Server Connected
Status Switch
Production OFF
CosPhi Limit Country
1.00 Export ITA
Switch Off. Production disabled ›
Commissioning ›
Site status:
Production: The AC output power
Limit: Limitation setting (Export or Production)
Inverters: Number of connected inverters in the cluster, including the
master.
Communication Status
This screen displays the status of connection option(s): LAN, RS485, Wi-Fi, cellular or
ZigBee Plug-in.
Communication
RS485-1 RS485-2
LAN
SE Slave Modbus
Connected
NC 2 of 2
ZigBee
Cellular Wi-Fi
MP Slave
N/A NC
M not Found
Inverter Energy
Meter Status
Meters
Type and function: Displays the meter functionality (Production, Export, Import,
Export+Import)
Status: Displays OK if the meter is communicating with the inverter
<Error message>: If there is a meter error, it is displayed in this line.
Power: Depending on the meter type connected to the inverter, this line
displays the exported or imported power
Energy: The total energy read by the meter. The value displayed in this line
depends on the meter type connected to the inverter and its location:
If a bidirectional meter is connected at the consumption point, this
value is the consumed energy.
If the meter is installed at the production connection point, this value is
the energy produced by the site.
If the meter is installed at the grid connection point, this value is the
energy exported to the grid.
NOTE
This data is accumulated according to an internal real-time
clock.
Designer
Designer recommends inverter and power optimizer selection per site
size and enables report generation.You can create a project in Designer
and export the site design with the string layout to the monitoring
platform.
For more information, refer to
https://www.solaredge.com/products/installer-tools/designer#/.
Mapper Application
Use the Mapper smart phone application to scan the power optimizer and inverter 2D
bar-codes and create a virtual map of a PV site for enhanced monitoring and easier
maintenance.
Th Mapper application is integrated with the monitoring platform and enables:
Simple on-site registration of new systems.
Creating, editing and verifying system physical layout.
Scanning and assigning the power optimizer serial number to the correct
module in the system physical layout.
For detailed information, refer to the Mapper demo movies:
Creating new sites using the Mapper mobile application
Communication Options
The following types of communication can be used to transfer the monitored
information from the inverter to the monitoring platform.
Only communication products offered by SolarEdge are supported.
Always connect the communication options when the relevant devices are powered
down - Commercial Gateway, inverter, etc.
Ethernet
Ethernet is used for a LAN connection. For connection instructions refer to Creating an
Ethernet (LAN) Connection on page 52 .
RS485
RS485 is used for the connection of multiple SolarEdge devices on the same bus in a
master-slave configuration. RS485 can also be used as an interface to external devices,
such as meters and third party data loggers.
RS485-1: Enables the connection of multiple devices (inverters/Commercial
Gateway) over the same bus, such that connecting only one device to the
Internet is sufficient to provide communication services for all the devices
on the bus.
RS485-2: Enables connection of multiple SolarEdge devices and of non-
SolarEdge devices over the same bus.
Wi-Fi
This communication option enables using a Wi-Fi connection for connecting to the
monitoring platform.
The Wi-Fi station is built into the inverter. An antenna is required and available from
SolarEdge for connection to the monitoring platform.
ZigBee
This option enables wireless connection to one or several Smart Energy products, which
automatically divert PV energy to home appliances.
The Smart Energy products are provided with an installation guide, which
should be reviewed prior to connection. Refer to
https://www.solaredge.com/products/device-control#/.
The ZigBee station is built into the inverter. An antenna is required and
available from SolarEdge.
Communication Connectors
Two communication glands are used for connection of the various communication
options. Each gland has three openings. The table below describes the functionality of
each opening. Unused openings should remain sealed.
NOTE
If using a cable longer than 10 m / 33 ft in areas where there is
a risk of induced voltage surges by lightning, it is recommend
to use external surge protection devices.
For details refer to: http://www.solaredge.com/files/pdfs/lightning_
surge_protection.pdf.
(1)
Wire Color 10Base-T Signal
RJ45 Pin #
T568B T568A 100Base-TX Signal
1 White/Orange White/Green Transmit+
2 Orange Green Transmit-
3 White/Green White/Orange Receive+
4 Blue Blue Reserved
5 White/Blue White/Blue Reserved
6 Green Orange Received-
7 White/Brown White/Brown Reserved
8 Brown Brown Reserved
(1) The inverter connection does not support RX/TX polarity change. Supporting crossover Ethernet cables depends on
10. Verify the connection, as described in Verifying the Connection on page 60.
NOTE
If using a cable longer than 10 m/33 ft in areas where there is a
risk of induced voltage surges by lightning, it is recommend to
use external surge protection devices. For details refer to:
https://www.solaredge.com/sites/default/files/lightning_surge_
protection.pdf.
If grounded metal conduit are used for routing the communication wires, a
lightning protection device is not required.
If not using surge protection, connect the grounding wire to the first inverter
in the RS485 chain; ensure it is not in contact with other wires. For inverters
with a DC Safety Unit, connect the grounding wire to the grounding bus-bar
in the DC Safety Unit.
The following sections describe how to physically connect the RS485 bus and how to
configure the bus.
NOTE
Do not cross-connect B, A and G wires.
NOTE
Only the first and last SolarEdge devices in the chain should be terminated.
The other inverters in the chain should have the termination switch OFF
(down position).
11. If not using surge protection, connect the grounding wire to the first inverter in the
RS485 chain; make sure the grounding wire is not in contact with other wires. For
inverters with a DC Safety Unit, connect the grounding wire to the grounding bus-
bar in the DC Safety Unit.
Status
Inverter
SN 07318000C
Power Voltage Frequency
Optimizers S_OK
Connected Server Connected
Status Switch
Production ON
CosPhi Limit Country
1.00 No Limit Netherlands
Voltage Temp Fan
Commissioning
2. Check that S_OK - Server Connected status appears in the main inverter section.
3. Scroll down to the Communication section and check that the communication
options are as required. For more information refer to Communication Status on
page 43.
Communication
RS485-1 RS485-2
LAN
SE Slave Modbus
Connected
NC 2 of 2
ZigBee
Cellular Wi-Fi
MP Slave
N/A NC
M not Found
Identifying Errors
Errors may be indicated in various system interfaces: On the inverter bottom panel, a
red LED indicates an error. In the monitoring platform and the SetApp, errors are
displayed with codes.
For more information on the codes displayed for error and warning
messages, refer to http://www.solaredge.com/sites/default/files/se-inverter-
installation-guide-error-codes.pdf. This document describes errors that
appear in SetApp, monitoring platform, and LCD (for inverters with LCD).
To identify the error types, use the methods described below.
Troubleshooting Communication
Additional Troubleshooting
1. Check that the modem or hub/router is functioning properly.
2. Check that the connection to the internal connector on the communication board is
properly done.
3. Check that the selected communication option is properly configured.
4. Use a method independent of the SolarEdge device to check whether the network
and modem are operating properly. For example, connect a laptop to the Ethernet
router and connect to the Internet.
5. Check whether a firewall or another type of network filter is blocking
communication.
Figure 29: Inverter with bracket - front, side and rear views
3. Loosen the screws on the front cover of the DC Safety Unit, as shown below:
7. Connect the grounding wire to the equipment grounding terminal in the DC Safety
Unit.
NOTE
Connect the equipment grounding before connecting the AC wires to the
AC terminal block.
8. Insert the remaining four wires through the AC conduit to the inverter, and connect
them to the appropriate terminal blocks in the inverter according to the labels on
the terminal blocks (N, L1, L2 and L3).
6. Ensure proper cable entry sealing: inspect the entire cable run and use standard
sealants to avoid water penetration.
Appendix D: SafeDC™
When AC supply to the inverter is shut off (by shutting off the AC breaker at the site), or
when the inverter ON/OFF/P switch is turned to OFF, the DC voltage drops to a safe
voltage of 1V per optimizer.
The SolarEdge inverters are certified for compliance with the following standards as
disconnection devices for PV generators, meaning that they can replace a DC
disconnect:
IEC 60947-3:1999 + Corrigendum: 1999 + A1:2001 + Corrigendum 1:2001 +
A2:2005;
DIN EN 60947-3
VDE 0660-107:2006-03
IEC 60364-7-712:2002-05
DIN VDE 0100-712:2006-06.
In compliance with these standards, the disconnection mechanism operates as follows:
1. Turn the inverter ON/OFF/P switch, located at the bottom of the inverter, to OFF, or
disconnect the AC by shutting off the AC breaker at the site. The DC voltage
displayed on the SetApp screen begins to decrease.
2. When the DC voltage reaches a safe voltage, the PV connectors at the input to the
inverter can be disconnected. A galvanic separation then exists between the PV
array and the inverter.
WARNING!
SafeDC complies with IEC60947-3 when installing the system with a worst case
SafeDC voltage (under fault conditions) < 120V.
The worst case voltage is defined as: Voc,max+ (String Length-1)*1V, where:
Voc,max = Maximum Voc (at lowest temperature) of the PV module in
the string (for a string with multiple module models, use the max value)
String Length = number of power optimizers in the string
Fan Maintenance
At least once a year, open the fan screen and clean the accumulated dust using a brush.
If the SetApp Status screen displays the status Not Working for the fan (refer to Main
Inverter Status on page 41), replace the fan as described in the next section.
1. After powering up the inverter, check the fan status on SetApp: Select
Commissioning è Status.
Replacing an Inverter
1. Turn OFF the DC Safety Unit (if applicable).
2. Turn OFF the inverter ON/OFF/P switch, and wait until the green LED is blinking ,
indicating that the DC voltage is safe (<50V), or wait five minutes before continuing
to the next step.
3. Disconnect the AC to the inverter by turning OFF the circuit breakers on the
distribution panel.
4. Open the inverter cover as described in Removing the Inverter Cover on page 52.
5. Disconnect the DC plugs and AC wires from the inverter.
6. For inverters with a DC Safety Unit, unscrew the two conduit nuts in the inverter
securing the DC Safety Unit to the inverter.
8. Place the new inverter on the mounting bracket; insert the screws securing the
inverter to the mounting bracket.
9. For inverters with a Connection Unit, screwthe two conduit nuts in the inverter
securing the DC Safety Unit to the inverter.
10. Connect all the wires to the inverter: Follow the instructions of Installing the Inverter
on page 20 and Activating, Commissioning and Configuring the System Using the
Inverter SetApp on page 35.
11. Close the DC Safety Unit cover (if applicable) and the inverter cover.
6. Unscrew the two conduit nuts in the inverter securing the DC Safety Unit to the
inverter, as shown below:
Line 1 L1
Line 2 L2
Line 3 L3
PE (grounding)
4. Tighten the screws of each terminal with a torque of 1.2-1.5 N*m / 0.88-1.1 lb.*ft.
5. Verify that there are no unconnected wires at the output of the DC Safety Unit and
that any unused terminal screws are tightened.
6. Connect the DC and AC wires to the DC Safety Unit. Refer to Connecting the AC and
the Strings to the Inverter on page 30.
7. Ensure proper cable entry sealing; inspect the entire cable run and use standard
sealants to avoid water penetration.
Introduction
Inverters should be protected by circuit breakers. This document describes how to
determine which circuit breaker to use in three phase commercial installations.
Figure 44: Typical transformer and commercial three phase inverter installation topology
There are many considerations for selecting the suitable transformer and its associated
current limiting devices such as circuit breakers and fuses. The considerations must
include at least the following:
The transformer should be designed for a typical PV system production profile:
high daytime loads with no loads at night.
The current limiting devices should protect the electrical circuits and the
inverters from the excess current created by an overload, or a short circuit. If a
short circuit or other overcurrent occurs, the current limiting devices should
block the current flow to the circuit, thus preventing damage to the electrical
circuits and the inverters.
The circuit breakers and the fuses should comply with the transformer
manufacturer recommendations and with the relevant sections in standards
such as IEC 60909, IEC 60364, UL 508A and NEC 2017.
Some manufacturers provide detailed information about the transformer short
circuit calculation procedure, and its effect on the selection of circuit breakers
and fuses at the different hierarchical levels of the installation topology (see
Figure 44).
For an example of a calculation, refer to:
Guidelines on the Short Circuit Current Rating for Industrial Control Panels
To ensure that the circuit breaker and fuses trip as expected, follow their
manufacturers' recommendations, especially with respect to the various de-
rating considerations.
NOTE
Transformer procurement, installation, maintenance and support are the
responsibility of the installer. Damage to the inverter due to incorrect
transformer installation, or use of a transformer that is incompatible with the
SolarEdge system will render the SolarEdge warranty invalid.
NOTE
Transformer procurement, installation, maintenance and support are the
responsibility of the installer. Damage to the inverter due to incorrect
transformer installation, or use of a transformer that is incompatible with the
SolarEdge system will render the SolarEdge warranty invalid.
3. To ensure that the selected circuit breaker trips as expected, at minimum consider
the following:
The circuit breaker rated voltage.
Temperature de-rating due to both close proximity of other circuit breakers and
the effect of ambient temperature on the distribution board.
De-rating due to permanent load.
If the de-rated current of the selected circuit breaker is lower than the maximum output
current of the inverter, consider selecting a circuit breaker that is designed for a higher
rated current, or reducing the temperature de-rating effect by increasing the distance
between adjacent circuit breakers.
NOTE
Make sure to select cables that are suitable for the environmental
conditions, the operating voltage and the selected circuit breaker.
Three or four pole circuit breakers are required. It is recommended to
use a four pole circuit breaker when applicable.
It is recommended to use a circuit breaker with tripping characteristic B
or C.