WASD_SUMMARY_OF_WORK

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

5/2017

SECTION 01010

SUMMARY OF WORK

PART 1 GENERAL

1.01 SCOPE OF WORK

A. This Section describes the project in general, and provides an overview of the
extent of the work to be performed under this Contract. Detailed requirements and
extent of work is stated in the applicable Specification sections and shown on the
Plans. The Contractor shall, except as otherwise specifically stated herein or in
any applicable parts of the Contract Documents, provide and pay for all labor,
materials, equipment, tools, construction equipment, and other facilities and
services necessary for proper execution, testing, and completion of the work under
this Contract.

1.02 CONSENT DECREE PROJECT

A. The Contractor is made aware that this is a Consent Decree Project, and
Stipulated Damages may apply for failure to meet required completion dates.

1.03 SPECIFICATIONS

A. The Specifications included in these Contract Documents establish the minimum


performance and quality requirements for materials and equipment with the
minimum standards for quality of the workmanship and appearance. Generally,
there has been no attempt to separate the Specification sections into groups for
the work of separate subcontractors, or for work to be performed by the various
trades. Should there be any question as to the interpretation of any particular
Specification section or part of Specification section, such question should be
directed to the Department prior to the submittal of a proposal for the work under
this Contract.

B. The work shown on the Plans is intended to be comprehensive and descriptive, not
an exact and complete representation of the actual finished work. Installed work
shall include fittings, joints, supports, nuts, bolts, and all other accessories required
to provide complete and satisfactory systems as specified, even though some
items may not be specifically shown on the Plans.

C. It is the intent of MD-WASD to obtain a complete functional, satisfactory and


legally operable installation under this project, and any items of labor, equipment
or materials which may be reasonably assumed as necessary to accomplish this
end shall be supplied whether or not they are specifically shown on the Plans or
stated herein. The Contractor shall provide all materials for the project unless they
are specifically called out in these specifications as being supplied by the
Department. The Contractor shall also supply all other labor, material or equipment

01010-1 Revision Date: 05/2017


5/2017
required to preclude damage to or loss of functionality of any existing facility or
system.

D. No request for additional compensation or Contract time (except for a non-


compensable item extension at the sole discretion of the Engineer, whose
decision shall be final) resulting from encountering utilities or structures not
shown, or differing in location or elevation from that shown, will be considered.
The Contractor shall explore sufficiently ahead of the Work to allow time for any
necessary adjustments without delay to the progress of the installation. Cost due
to delays occasioned by encountering utilities or structures which could have or
should have been discovered by timely exploration ahead of the work shall rest
solely with the Contractor.

1.04 REASONABLY IMPLIED PARTS OF THE WORK SHALL BE DONE THOUGH ABSENT
FROM SPECIFICATIONS

A. Any part of the work which is not mentioned in the Specifications but is shown on
the Plans, or any part not shown on the Plans but described in the Specifications,
or any part not shown on the Plans nor described in the Specifications, but which
is necessary or normally required as a part of such work, or is necessary or
required to make each installation satisfactorily and legally operable, shall be
performed by the Contractor as incidental work without extra cost to MD-WASD,
as if fully described in the Specifications and shown on the Plans, and the expense
thereof shall be included in the applicable unit prices or lump sum bid for the work.

1.05 DESCRIPTION OF WORK

A. The project consists of furnishing all materials, labor, and equipment necessary to
Upgrade Sewage Pump Station No. XX, including, but not limited to, excavation,
demolition and modification work including: Abandon existing dry well; Remove of
dry well chimney; Remove of existing pumps, valves, piping, fittings, emergency
discharge connection, existing sewer clean out plug, existing concrete slabs;
existing wet well top slab; Remove and Replace in kind to match existing 6’(feet)
wood fence; Remove and Relocate as required: palm trees, bush, existing water
meter and connect line to existing service; existing RTU antenna, existing electric
box, existing concrete slab for electrical service; Relocate as required existing back
flow preventer unit and water faucet, existing plug valve; furnish, installation,
operation, and removal of temporary sewage effluent by-pass pumps, equipment
and accessories; furnish and install wet well concrete top slab / new valve vault
structure concrete and concrete top slab; furnish and install aluminum access
hatches for wet well and valve vault and emergency connection; furnish and install
material for rehabilitation of existing Wet Well with a concrete protecting coating;
furnish and install two (2) XX HP submersible pumps and related equipment;
furnish and install bubbler control system and related equipment; furnish and install
new meter and main disconnect; furnish and install the proposed power/control
system inclusive of the necessary electrical panel, enclosure, telemetry system and
related equipment; install electrical conduits and junction boxes; install R.T.U.
panel and S.C.A.D.A. equipment furnished by the Department; electrical work;

01010-2 Revision Date: 05/2017


5/2017
mechanical work; furnish all materials, equipment and supplies necessary for pump
station startup and testing; furnish and install sewage force main pipe and fittings;
connection to existing sewage force main; replacement of any sod, sidewalk,
pavement damaged during construction; site restoration; and other appurtenant
and miscellaneous items for a complete, satisfactory and functional installation.

B. Pumping Station No. XX is located at _______________ in Section __,


Township__, Range __, Miami-Dade County, Florida.

C. It is the intent of the department to obtain a complete and working installation


under this Project and any items of labor, equipment or materials which may
reasonably be assumed as necessary to accomplish this end shall be supplied
whether or not they are specifically shown on the Plans or stated herein.

1.06 TESTING

A. Testing procedures shall be submitted to the Engineer as Shop Drawings and will
be subject to review and approval. The Department reserves the right to require
test procedure and equipment changes and revisions to the extent considered
appropriate by the Engineer whose decision shall be final. The Contractor is
advised that all testing shall be carried out in accordance with the best practices of
the trade, best management practices (bmp) and as recommended in writing by
the engineering/technical/test staff of the manufacturer of the equipment and he
should plan and price his test work accordingly. In no case will test
recommendations of a manufacturer's sales or management groups be considered
sufficient. All necessary temporary power sources, load banks, test materials, test
instrumentation, qualified test personnel including manufacturer's representatives,
fuels and lubricants shall be provided by the Contractor and shall be as approved
by the Engineer and, if not approved, the Contractor shall change the item(s) to
the satisfaction of the Engineer. Where required by the Engineer, testing shall be
carried out utilizing Contractor-supplied power sources and load banks prior to any
connection with FPL. The Contractor shall include in his prices bid all costs for
testing and no extra compensation will be allowed.

B. Factory testing of equipment is in all cases required and test data from these tests
shall be provided to the Engineer prior to shipment. The Department will decide
when to send its personnel or representatives to the factory for witness testing of
equipment. Travel expenses for Department personnel or representatives are paid
for by the Department. Repeat tests due to unsuccessful tests will be borne by the
Contractor. To establish a base line, the Bidder will assume that any piece of
equipment with an invoice cost to the Contractor of one hundred thousand dollars
($100,000) or more will require witnessed testing. The MDWASD will in the
Specifications try in all cases to note which items will require testing.

C. On site testing shall conform to the protocol previously approved by the Engineer,
and shall include testing and calibration prior to energizing of individual cubicles
followed by testing and calibration as a whole system or group of systems. The
Contractor shall supply all material, equipment, power, time, and fully qualified

01010-3 Revision Date: 05/2017


5/2017
specialist personnel to perform all system integration work as necessary to provide
systems that talk to one another and correctly react to one another, including
systems that must communicate with, and react to existing systems, and systems
being or to be installed by others. It is an absolute requirement that upon
completion, all systems installed in the Work be able to correctly communicate and
react to one another and to systems in existence, being or to be installed, external
to the Work. Final testing and calibration will be performed with the equipment
energized and will only take place when the Engineer is satisfied with the results of
earlier tests. Full written reports of tests and results shall be furnished by the
Contractor to the MD-WASD. All costs for this testing, calibration, system
integration and reporting, including the costs for factory and specialist personnel
required during testing, calibration and system integration, shall be included in the
prices bid and no extra compensation will be allowed. Any delays or costs
occasioned by test procedures or results not being satisfactory to the Engineer
shall rest solely with the Contractor and no extra time or compensation will be
allowed. All on site testing shall be witnessed by MD-WASD, and the Contractor
shall make timely arrangements and fully coordinate tests with the Engineer.

D. After installation is completed, the Contractor shall provide records of non-


destructive electrical insulation tests performed by a certified institution approved
by the Engineer, witnessed by MD-WASD personnel and attesting that the
dielectric condition of the equipment and wiring is acceptable.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

END OF SECTION

01010-4 Revision Date: 05/2017

You might also like