Lecture Note for Project Management
Lecture Note for Project Management
institute of technology
Department of Architecture
Project Management for Architects
Course Code: Arch 5362 ECTS: 4 Sem: II
Target Group: G5-Architecture Students
Lecture Note
Prepared By: Melese Becha (MSc.)
Course Description
❖ This course introduces project management, project life cycle, and project appraisal
❖It examines activities related to project planning, scheduling time, and estimating
project cost.
❖It also examines processes for managing project resources; labor, material, and
machinery
➢ Define the function of management, the role of managers, and the level of management in the
construction
➢ understand project management knowledge areas such as integration, scope, time, cost, quality,
human resource, communication, risk and procurement management,
➢ Prepare Work break Structure, schedule, estimate duration and project cost
❑ Construction Planning
❑Construction Scheduling
❑ Construction Estimation
3. Construction planning, scheduling and estimating Techniques
❑ Construction Planning
➢ is a fundamental and challenging activity in the management and
execution of construction projects.
➢ involves the choice of technology, the definition of work tasks, the
estimation of the required resources and durations for individual
tasks, and the identification of any interactions among the different
work tasks.
❖ A good construction plan is the basis for developing the budget
and the schedule for work.
❖ Developing the construction plan is a critical task in the
management of construction, even if the plan is not written or
otherwise formally recorded.
3. Construction planning, scheduling and estimating Techniques
❑ Construction Planning
❖ Essential aspects of construction planning include;
➢ the generation of required activities,
➢ analysis of the implications of these activities, and
➢ choice among the various alternative means of performing activities.
❖ In developing a construction plan, it is common to adopt a primary emphasis on
either cost control or on schedule control;
➢ construction planning is cost or expense oriented;
• a distinction is made between costs incurred directly in the performance of an activity
and indirectly for the accomplishment of
➢ the project. scheduling of work activities over time is critical and is emphasized in
the planning process,
• the planner insures that the proper precedences among activities are
maintained and that efficient scheduling of the available resources prevails
3. Construction planning, scheduling and estimating Techniques
❑ Construction Planning
❖ the functional requirements for
construction planning such as technology
choice, work breakdown, and budgeting;
❖ Construction planning is not an activity
which is restricted to the period after the
award of a contract for construction.
❖ It should be an essential activity during
the facility design.
❖ if problems arise during construction,
replanning is required
3. Construction planning, scheduling and estimating Techniques
❑ Construction Planning
❖ Technology choice:
• choices of appropriate technology and methods for construction
• should consider the relative costs, reliabilities, and availability of equipment
• implications of different methods depend upon numerous considerations for which information
• a useful approach is to simulate the construction process either in the imagination of the planner or
with a formal computer based simulation technique.
❖ Work breakdown:
• define the various work tasks that must be accomplished.
• The terms work "tasks" or "activities" are often used interchangeably in construction
plans to refer to specific, defined items of work.
• an activity is any subdivision of project tasks.
❖ Budgeting:
• Execution of an activity requires time and resources, including manpower and
equipment
3. Construction planning, scheduling and estimating Techniques
❑ Construction Planning
❖ Work breakdown Structure:
• a well-defined work breakdown structure (WBS) that divides the project into
identifiable parts that can be managed
• WBS is the cornerstone of the project work plan
• It defines the work to be performed, identifies the needed expertise, assists in
selection of the project team, and establishes a base for project scheduling and
control.
• WBS is a graphical display of the project that shows the division of work in a multi-
level system.
• WBS is used from the start to the finish of the project for planning and controlling.
• It is an effective means of defining the whole project, by parts, and providing
effective communication channels for exchange of information that is necessary for
management of the project.
3. Construction planning, scheduling and estimating Techniques
❑ Construction Planning
❖WORK PACKAGES:
• A work package provides a detailed description of the work required to
meet project needs and to match the project manager's initial work
plan.
• A work package is divided into three categories: scope, budget, and
schedule.
• A work package is the lowest level in the WBS and establishes the
baseline for project scheduling, tracking, and cost control.
• The work package is extremely important for project management
because it relates the work to be performed to time, cost, and people.
3. Construction planning, scheduling and estimating Techniques
❑ Construction Planning
❖Project planning is the process of identifying all the activities necessary to
successfully complete the project.
❖project planning is a prerequisite to project scheduling because there is no
way to determine the sequence or start and finish dates of activities until
they are identified.
❖ Planning is the first step to project scheduling.
❖Planning is a process and not a discrete activity.
❖As changes occur, additional planning is required to incorporate the changes
into the schedule.
3. Construction planning, scheduling and estimating Techniques
❑Construction Scheduling;
➢ Project scheduling is the process of determining the sequential
order of the planned activities, assigning realistic durations to
each activity, and determining the start and finish dates for
each activity.
➢ In order to develop a schedule;
1. Define the activities
2. Sequence the activities in the right order
3. Estimate resources needed
4. Estimate the time needed to complete the task
3. Construction planning, scheduling and estimating Techniques
❑Construction Scheduling;
➢ Activity Sequencing Process;
✓ Focus on the order of the work;
✓ Predecessors: activity that comes first
✓ Successors: activity that follows the previous task
✓ Establish Start to Finish (S-F) diagram.
❖ There are two general methods that are commonly used for
scheduling techniques: the bar chart and the Critical Path
Method.
3. Construction planning, scheduling and estimating Techniques
❑Construction Scheduling;
❖ technique used for project scheduling;
➢ THE BAR CHART OR GANT CHART
• is a graphical time-scale of the schedule
• developed by Henry L. Gantt during World War I,
• an effective technique for overall project scheduling, but has limited
application for detailed construction work;
o it is difficult to update, does not show interdependences of activities, and
does not integrate costs or resources with the schedule.
o the many interrelationships
o of activities, which are required for construction work, are not defined.
o the bar chart does not integrate costs with the schedule, nor does it provide
resources, such as labor hours,
3. Construction planning, scheduling and estimating Techniques
❑ The Bar Chart Or
Gant Chart;
❑ Sample view
3. Construction planning, scheduling and estimating Techniques
❑Construction Scheduling;
❖ technique used for project scheduling;
➢ Critical Path Method (CPM)
• a deterministic approach to scheduling.
• commonly used in the engineering and construction industry.
• developed in 1956 by the DuPont Company
➢ Program Evaluation and Review Technique (PERT),
• probabilistic approach to scheduling
• developed in 1957 by the U.S. Navy
• more commonly used by the manufacturing industry
• it can be used for risk assessment of highly uncertain projects.
3. Construction planning, scheduling and estimating Techniques
❑Construction Scheduling;
❖ technique used for project scheduling;
➢ Critical Path Method (CPM)and Program Evaluation and Review
Technique (PERT),
• Both methods are often referred to as a network analysis
system.
• The CPM provides interrelationships of activities and
scheduling of costs and resources.
• it provides more detailed information that is required for
effective project management.
• It also is an effective technique for overall project scheduling
and detailed scheduling of construction
3. Construction planning, scheduling and estimating Techniques
❑Construction Scheduling;
❖ Network Analysis Systems (NAS);
➢ A network analysis system (NAS) provides a comprehensive method for project planning,
scheduling, and controlling.
➢ NAS is a general title for the technique of defining and coordinating work by a graphical
diagram that shows work activities and the interdependences of activities.
• Activity: the performance of a task required to complete the project, such as, design of
foundations, review of design, procure steel contracts, or form concrete columns.
o An activity requires time, cost, or both time and cost.
• Network: A diagram to represent the relationship of activities to complete the project.
o The network may be drawn as either an "arrow diagram" or a "precedence diagram.“
• Duration: the estimated time required to perform an activity.
o The time should include all resources that are assigned to the activity.
3. Construction planning, scheduling and estimating Techniques
❑ Construction Scheduling;
❖ Basics of Critical Path Method;
• There are two basic methods of
drawing CPM diagrams: the arrow
diagram (sometimes called activity
on arrow) and the precedence
diagram (sometimes called activity
on node).
• The precedence method can also
provide the start-to-start, finish-to-
finish, start-to-finish, and finish-to-
start relationship of activities,
which can significantly reduce the
number of activities that are
required in a network diagram.
3. Construction planning, scheduling and estimating Techniques
❑ Construction Scheduling;
❖ Basics of Critical Path Method;
• The arrow diagram: Activity on Arrow (AoA)
• A dummy activity is assumed to have no time duration and can be graphically
represented by a dashed line in a network