6 Chapter5part2
6 Chapter5part2
PROGRAMMING
TECHNIQUES
Chapter 5(Part 2)
©Sheila Belayutham
LEARNING OUTCOME
At the end of this lesson, students will
be able to:
• Understand the different types of
planning techniques.
• Understand the network analysis.
• Formulate a network diagram.
Planning Techniques Used in
©Sheila Belayutham
Construction
• Bar Chart
• Line of Balance
• Time Grid Diagram
• Network Techniques
– CPM (Critical Path Method)
– Precedence Diagram
– PERT (Programme Evaluation & Review
Technique)
©Sheila Belayutham
BAR CHARTS
Who
1. In 1917, Henry L.Gantt invented a
invented
chart for scheduling.
bar chart?
BAR CHARTS-EXAMPLE
ACTIVITY WORKDAYS
1 2 3 4 5 6 7
Site clearing
Dig trench
Assemble
pipe
Install pipe
backfill
Planning Techniques Used in
©Sheila Belayutham
Construction
• Bar chart weaknesses:
– Does not show relationships between
project activities
– Does not identify activities which control
a project's total duration (i.e., critical
activities comprising critical path)
– Does not relate delay or change of one
activity to the entire project
Planning Techniques Used in
©Sheila Belayutham
Construction
• Network planning methods remedy bar chart
weaknesses:
Method
• Factors that governed the choice of factors
are as follows:
– Familiarity on the technique to be used
• Acceptable by parties involved.
– Type and size of project
• Project with few but repetitive task-Line of Balance
• Med to large project with numerous task-CPM or
Precedence
• Small project-Bar chart
– Purpose of scheduling
©Sheila Belayutham
Network Analysis
• Net work analysis is a method of
project planning done on activities so
that it is connected to each other.
This network is used to optimised the
usage of resources and also for
monitoring and controlling.
• The purpose is to ascertain the
critical path for a certain project.
©Sheila Belayutham
Network Analysis
• Type of network analysis
– CPM
– Precedence Diagram
– PERT
• Techniques
– Activity on arrow (CPM)
• Arrow represents activity
• Activities are represented by arrows whereas the
start or end of each activity is represented by a node.
• One of the main drawbacks of this technique is the
existence of dummy activities, which might
complicate the network and cause some confusion.
©Sheila Belayutham
Network Analysis
– Activity on node (Precedence)
• Node represents activity
Steps in building a network
©Sheila Belayutham
model
• Define activities
• Order activities
• Draw a network diagram
• Assign durations to activities
• Assign resources and cost
• Calculate early and late start/ finish
times.
• Schedule activity start/ finish times.
©Sheila Belayutham
Project Activities
• Very important for a planner to
understand the order of how the job
to be accomplished in the filed.
• Should understand how various
activities of the project related to
each other in term of their logical
sequence.
Logical Relationship of
©Sheila Belayutham
Project Activities
• Example of logical relationships:
– Start of the cut & fill activity can only be
accomplished upon the completion of
the activity ‘strip top soil’.
Project Activities
– ‘Formwork’ and ‘Rebar’ activity must be
accomplished before the start of activity
‘Pour concrete’.
Pour
concrete
Developing an arrow
©Sheila Belayutham
diagram network
• Activity Relationship
– Arrows should always be drawn showing
progress form left to right.
• Basic types of relationship found in a
network:
– One on one relationship between 2
activities.
Activity B Activity G
Hang wallpaper Install mirror
on wall
©Sheila Belayutham
Activity B
Activity G
Hang wallpaper
on wall Install mirror
©Sheila Belayutham
Activity B Activity G
Route electrical Install plasterboard
wiring in walls
©Sheila Belayutham
Activity B Activity G
Dummies
• The relationship that exist among activities
cannot always be shown as simply as those
demonstrated in the previous slides.
• Therefore it is necessary to include in the
diagram a ‘pseudo activity’ called a
dummy.
• Dummy is usually drawn as a dotted line
but assigned no duration.
• Most dummies are required for unique
activity designation and to maintain proper
logic of various construction activities.
©Sheila Belayutham
For Example:
• Activity A-Place concrete slab in garage
• Activity B-Install garage door
• Activity C-Install pre finished shop
cabinets
• Activity D-Install garage door opener
©Sheila Belayutham
For Example:
10 20 25
A C
B D
15 30
From above network, you can conclude that Activity C and D can begin
only after both Activity A and B have been completed.
Suppose Activity C can begin only after Activity A and B completed,
but Activity D can begin as soon as activity B is completed. The
corrected logical sequence can be achieved by using dummy.
©Sheila Belayutham
For Example:
10 20 25
A C
B D
15 16 30
Formulating a Network
©Sheila Belayutham
Diagram
• Form an activity network for a seven-
activity network with the following
precedence :
Activity Predecessors
A ---
B ---
C A,B
D C
E C
F D
G D,E
©Sheila Belayutham
Activity-on-Arrow
©Sheila Belayutham
SOLUTION
• Forming an activity-on-arrow network for this set of
activities might begin be drawing activities A, B and
C as shown in Figure (a).