Project Developement Plan
Project Developement Plan
Team Structure
To complete the website within 7 days, we will require a team of 6 members with the following roles:
1. Project Manager (1): Responsible for overall coordination, timeline management, and risk
mitigation.
2. UI/UX Designer (1): Focused on creating and refining the design based on the provided
Figma files.
4. Backend Developer (1): Handles server-side logic, database integration, and API development.
5. Quality Assurance Specialist (1): Ensures the website is bug-free and meets all
functional requirements.
Project Manager
UI/UX Designer
Page 1
Project Management Plan for 7-Day Website Completion
Frontend Developers
Backend Developer
- Objective: Ensure the team has a clear understanding of the project requirements and resources.
- Tasks:
Page 2
Project Management Plan for 7-Day Website Completion
- Tasks:
- Tasks:
➢ Frontend Developers create the product listing grid and filter/sort functionality.
➢ Backend Developer integrates product data API.
➢ QA verifies product data display and functionality.
- Tasks:
➢ Frontend Developers design the product detail page (images, descriptions, price, reviews).
➢ Backend Developer ensures API support for adding/removing items from the cart.
➢ Cart page developed to show summary, quantities, and calculated totals.
➢ QA tests individual page interactions and navigation.
- Tasks:
➢ Frontend Developers create the checkout page (form validation, payment integration).
➢ Order tracking page shows order status dynamically.
➢ Backend Developer ensures secure payment processing and order management.
➢ QA focuses on functional testing for the checkout process
Page 3
Project Management Plan for 7-Day Website Completion
.
Day 7: Final Testing, Bug Fixes, and Deployment
- Objective: Ensure the entire website is functional, bug-free, and ready for deployment.
- Tasks:
➢ Conduct end-to-end testing of all pages.
➢ Fix bugs and address any inconsistencies.
➢ Deployment of the website to the live server.
➢ Final team review and approval.
Risk Management
Potential Risks
Mitigation Strategies
- Testing Phases: QA begins testing in parallel with development to reduce last-minute bugs.
- Buffer Time: Allocate Day 6-7 for extensive testing and debugging.
Page 4
Project Management Plan for 7-Day Website Completion
Page 5