Cost Abstract for Springfield Layout.xlsx
Cost Abstract for Springfield Layout.xlsx
Cost Abstract for Springfield Layout.xlsx
S NO DESCIPTION MATERIALS
A UNIT BOQ RATE COST
1 TOTAL STATION SURVEY AND PLOT STONE DAYS 1
DEMARCATION,
2 CONSTRUCTION OF LABOUR SHED
3 GROUND LOWERING AND LEVELLING BY JCB HRS 24
4 PLOT STONE FIXING N0 160.00 120.00 19200.00
C ELECTRICAL WORKS
EARTHWORK EXCAVATION WITH BACKFILLING FOR
12 CABLE LAYING, ATTENDING TO RELATED ALL ACRE 4.75 294637.70 1399529.08
WORKS,and 17 NOS ERECTION OF POLES
COMPLETION AS PER ENGINEER IN CHARGE
DRAINS AND CC CULVERT
13 EARTHWORK EXCAVATION WITH BACKFILLING BY JCB HRS 120.00
14 0.45 M ,CC DRAIN RMT 1247.00 1093.95 1364150.31
15 CC CONTINUOUS CROSS ROAD CULVERT RMT 63.00
D WBM ROADS
16 GSB MURUMMA FILLING AND LEVELLING, TRIP 150 2500.00 375000.00
17 LEVELLING AND LOWERING WITH COMPACTION BY HRS 48.00
JCB
18 ROAD ROLLER M 1.00
F OTHERS
22 SIGN BOARD 8'X 6' 1
23 PLANTS NOS 170.00 35.00 5950.00
24 WATER TANKAR M 3.00
25 WATCH MAN WAGES M 3.00
26 PLOT STONE AND SIGN BOARD WRITING WORK LS 1.00
27 PLOT STONE FIXING RE FITTING NOS 160.00
F
28 ADD OVERHEAD EXPENSES 2% OF THE PROJECT COST
MATE BOQ
TOTAL COST OF THE PROJECT 7607967.62
COST OF THE PROJECT PER Sft 66.89
LABOUR/MACHINE
RATE COST TOTAL COST COST PER Sft
15000.00 15000.00 15000.00
143385.00
850.00 20400.00 20400.00
90.00 14400.00 33600.00
212385.00 1.87
375000.00
850.00 40800.00
40800.00
35000.00
450800.00 3.96
127244.98 595026.98
66000.00 102300.00
64180.58 99479.90
796806.88 7.01
0.00 12500.00
250.00 42500.00 48450.00
25000.00 75000.00 75000.00
8000.00 24000.00 24000.00
10000.00
90.00 14400.00 14400.00
184350.00 1.62
TOTAL 7245683.44
362284.17 3.19
7607967.62
66.89
GARDEN PERIMETER 558.092 RFT 170.15
UNIT DETAILS NOS LENGTH UNIT WT
1 MS TUBE RMT 40*40*2 50 6 300 6.5 1950
2 MS TUBE RMT 75*75*2 20 6 120 6.5 780
3 MS TUBE RMT 40*20*1.6 23 6 138 6.4 883.2
4 MS PATTI RMT 32*20*5 20 12 240 6.28 1507.2
5 2.5" D/MESH GI RMT 1200X75*3 170.15 680.6 4.75 3232.85
FABRICATION
UNIT NOS L B D
GRILL SFT 1 558.092 6 3348.552 38
BEAM RFT 1 558.092 558.092 115
PILE RFT 60 10 600 110
CIVIC AMINITIES
CC POLE 60 150
LABOUR CHARGES 60 90
56 109200.00
56 43680.00
56 49459.20
56 84403.20
56 181039.60
467782.00
127245
64180.58
66000
257425.6
9000
5400
14400
SPRINGFIELD LAYOUT GOPANKOPPA
SCOPE OF WORK: CONSTRUCTION OF 8 NOS OF BBM UGD CHAMBER
MASONARY
Sl. No Description N0'S Wastage Unit
BRICKS L B D
Size of brick STD Size 0.19 0.09 0.09 m
Size of brick with mortar 0.18 0.08 0.08 m
Proportion 1 4
QTY TOTAL QTY
Volume of brick masonary 8 1.47 12 cum
Number of bricks 8 955.09 7641 No.
Assuming wastage 8 5% 47.75 382 No.
Total 1002.85 8035 No.
Mortar qty 8 0.37 3 cum
CEMENT
Cement qty 8 35% 106.82 855 kg
Total 8 3.00 24 bags
SAND````````
8 0.30 2.4 cum
8 0.57 4.6 tonnes
Sand qty
8 10.48 83.8 cft
8 0.11 0.8 brass
LABOUR cost of construction of BBM 0.23thick,1.80m dia UGD Chamber with both
side plastering and chamber cover fixing as per engineer in charge.
LABOUR
CONSTANT
IS
Rate per
CONSIDER Total amount
Sl. No Labour Unit day
CONSTRUC (Rs.)
(8 hr)
TION OF 3
CHAMBERS
PER DAY
NOTE:
PLASTER(12MM THICK)
Sl. No Description Qty TOTAL QTY
1 Proportion of mortar 1 6
2 Area of plastering 8 12.762 102.10
3 Thickness of plastering 8 12.000 96.00
4 Vol of plastering 8 0.153 1.23
5 Adding 60 % for voids and 20 % for uneveness 8 0.276 2.21
8 0.039 0.31
6 Cement
8 1.500 12.00
8 0.236 1.89
8 0.453 3.62
7 Sand
8 8.334 66.67
8 0.084 0.67
Unit
sq.m
mm
cum
cum
cum
bags
cum
tonnes
cft
brass
SPRINGFIELDLAYOUT GOPANKOPPA
SCOPE OF WORK: CONSTRUCTION OF CC DRAIN 1247M LENGTH,0.45M
VENT,
Length = 1247.00
Width = 1.55
Depth = 0.10
Volume of concrete = 193.29
Proportion = 1 2 4
304175.366
892976.7
1364150.31
1093.94571
SPRINGFIELDLAYOUT GOPANKOPPA
SCOPE OF WORK: CONSTRUCTION OF CC DRAIN 1247M LENGTH,0.45M
VENT,
PCC
Length = 9.00 Length =
Width = 6.00 Width =
Depth = 0.10 Depth =
Volume of concrete = 5.40 Volume of concrete =
Proportion = 1 4 8 Proportion =
COAT OF MATERIAL
S NO DESCRIPTION UNIT QTY MR AMOUNT
CEMENT BAGS 526.00 315.00 165690.00
SAND M TONNES 55.89 1050 58682.07
AGGRIGATE TONNES 125.75 850 106885.21
STEEL TONNES 10.60 56000 593331.48
924588.76 1590.69
10MM
725.25 kg
STEEL M/BAR,8MM
D/B,150MM C/C,
0.73 tonnes
TOP SLAB
Length = 8.70
Width = 5.70
Depth = 0.15
Volume of concrete = 7.44
Proportion = 1 1.5 3
SCOPE OF WORK: Construction of three temporary sheds for the watchman, cement
and labour with CC block masonry and GI sheet roofing 10X10.
Details of Purchase Stock Cost of
SN Material name Unit Balance
material/Brand quantity quantity Value
01 CC Block 200X200X150 No s 1939 1939 58170
4" dia Wooden
02 Solid 12' length No s 15 15 1440
Purlis
03 Cement CCI 43 Grade Bags 25 25 7875
04 Sand M sand Cft 100 100 2500
Precast Door
05 frame with Fibres No s 3 3 5400
shutter.
Comarcial
06 Gi sheet No s 20 20 24000
0.14mm
Total 99385
Construction labou cost 15000
AC Sheet roofing 7000
solar connection 22000
total 143385
Remark
Department Deputy
Requester Financial Audit Department review
review manager
SCOPE OF WORK: Construction of 8 No,s of UGD Chamber and CC Drain 1247m length,0.45m width
Total
Remark
Department Deputy
Requester Financial Audit Department review
review manager
m length,0.45m width,
Cost of Value
56,241.87
175,590.14
427,000.00
313,121.70
892,976.70
1,864,930.42
artment review
Director