Chapter 10 Calculations
Chapter 10 Calculations
❑ Weather conditions
❑ Quality of the workforce
❑ Quality of the supervision
❑ Incorrect sequencing of work
❑ Change orders
❑ Overcrowded job site
❑ Defective materials
❑ Inadequate tools and equipment
❑ Late deliveries
Tracking Quality, Cost, and Time
After three months on the job (July 1), the contractor concluded that (Activities A, B and D
are completed) and 20% of Activity F was completed, 80% of Activity C was completed, and
40% of Activity E was completed. The project has cost the contractor a total of $535. For this
project, using earned value concepts, determine the schedule variance and the cost variance.
State if the project is over or under budget and if it is ahead or behind schedule.
Answer:
ACWP = $535
BCWS = A + B + C + D + (0.5)E
= $50 + $120 + $80 + $200 + $60
= $510