SPM 3
SPM 3
PART-A(2-Marks)
3 .What are the three approaches to identify the activities that make up a project?
Essentially there are three approaches to identifying the activities or tasks that make up a
project
✔ The activity-based approach,
✔ The product-based approach
✔ The hybrid approach.
4 .Define activities
✔ If an activity must have a clearly defined start and a clearly defined end-point, normally
marked by the production of a tangible deliverable.
✔ An activity requires a resource (as most do) then that resource requirement must be forecast
able and is assumed to be required at a constant level throughout the duration of the activity.
✔ The duration of an activity must be forecast able — assuming normal circum stances, and the
reasonable availability of resources.
✔ Some activities might require that others are completed before they can beginthese are known
as precedence requirements).
Activities A, B and F may start immediately, so the earliest date for their start is zero.
Activity A will take 6 weeks, so the earliest it can finish is week 6.
Activity B will take 4 weeks, so the earliest it can finish is week 4.
Activity F will take 10 weeks, so the earliest it can finish is week 10.
Activity C can start as soon as A has finished so its earliest start date is week 6. It will take
3 weeks so the earliest it can finish is week 9.
Activities D and E can start as soon as B is complete so the earliest they can each start is
week 4. Activity D, which will take 4 weeks, can therefore finish by week 8 and activity E,
which will take 3 weeks, can therefore finish by week 7.
Activity G cannot start until both E and F have been completed. It cannot therefore start until
week 10 — the later of weeks 7 (for activity E) and 10 (for activity F). It takes 3 weeks and
finishes in week 13.
Similarly, Activity H cannot start until week 9 — the later of the two earliest finished dates
for the preceding activities C and a
The project will be complete when both activities H and G have been completed.
Thus the earliest project completion date will be the later of weeks 11 and 13—
that is, week 13.
The results of the forward pass are shown in Figure 6.18.
A Hardware Selection 5 6 8
B Software Design 3 4 5
C Install Hardware A 2 3 3
E File take-on B 1 3 4
G User training E, F 2 3 4
Expected time: Helps to carry out a forward pass through a network similar to CPM
Activity standard deviation: Used as ranking measure of the degree of uncertainty or risk
for each activity
Pert labeling convention
Activity Optimistic (a) Most Pessimistic Expecte Standard
likely (m) (b) d deviation s
te
A 5 6 8 6.17 0.5
B 3 4 5 4.00 0.33
C 2 3 3 2.83 0.17
E 1 3 4 2.83 0.5
F 8 10 15 10.50 1.17
G 2 3 4 3.00 0.33
5.Explain in detail about the PERT technique and justify how PERT techniques provide
details in identifying the uncertainties and effort in a project. Find out the expected
duration and the standard deviation/ Create precedence for the following project. Calculate
the earliest dates on which each activity may be started and completed of project using
forward approach.
Project Evaluation and Review Technique (PERT) is a project management tool used to schedule,
organize, and coordinate tasks within a project. It estimation considers three values: the most
optimistic estimate (O), a most likely estimate (M), and a pessimistic estimate (least likely
estimate (L)).
Activity Description Precedents Optimistic Most likely Pessimistic(b)
(a) (m)
A Hardware Selection 5 6 8
B Software Design 3 4 5
C Install Hardware A 2 3 3
E File take-on B 1 3 4
G User training E, F 2 3 4
• Expected time: Helps to carry out a forward pass through a network similar to
CPM
• Activity standard deviation: Used as ranking measure of the degree of
uncertainty or risk for each activity.
• Pert labeling convention
Activity Optimistic Activity durations(weeks), Pessimistic
(a) Most likely (m) (b)
A 5 6 8
B 3 4 5
C 2 3 3
D 3.5 4 5
E 1 3 4
F 8 10 15
G 2 3 4
H 2 2 2.5
The above table provides additional activity duration estimates for the network shown in figure
3. There
Activity Standard Deviations
A quantitative measure of the degree of uncertainty of an activity duration estimate may be
obtained by calculating the standard deviation of an activity time, using the formula s=b-a/6.
The activity standard deviation is proportional to the difference between the optimistic and
pessimistic estimates, and can be used as a ranking measure of the degree of uncertainty or risk
for each activity.
The PERT technique uses the following three-step method for calculating the
probability of meeting or missing a target date:
Calculate the standard deviation of each project event;
Calculate the z value for each that has a target date;
Convert z values to a probabilities
6.Explain with an example how critical path can be identified in precedence networks?
∙ Formulating a network model
∙ Constructing Precedence network
∙ Representing lagged activities
∙ Hammock activities
∙ Labeling conventions
∙ Adding the time dimension
Forward pass
Backward pass
A project usually consists of multiple activities that occur both simultaneously and sequentially.
To determine the flow of these activities, you’ll need to create a Precedence Diagram. After
creating the Precedence Diagram, you can identify the activities that would, if delayed, cause
your project to come in late. This is the Critical Path definition. A delay in any of the critical path
activities will delay the entire project, regardless of whether the other project activities are
completed on or before time. The act of determining the Critical Path is known as the Critical
Path Method or the Critical Path Analysis.
To determine the Critical Path and conduct Critical Path Analysis, you need to: ∙ Define the
duration of each activity.
∙ Identify all the paths.
∙ Calculate the duration of each path.
∙ Identify the longest path.
∙ Identifying the critical path
There will be at least one path through the network that defines the duration of the
project. This is known as critical path. Any delay to any activity on this critical path will delay
the completion of the project.
Hammock activities
A hammock activity (also hammock task) is a schedule or project planning term for a grouping
of tasks that "hang" between two end dates it is tied to. A hammock activity can group tasks
which are not related in the hierarchical sense of a Work Breakdown Structure, or are not related
in a logical sense of a task dependency where one task must wait for another.
8.Explain in detail about the risk identification.
Risk identification
Approaches to identifying risks include:
• Use of checklists – usually based on the experience of past projects
• Brainstorming – getting knowledgeable stakeholders together to pool concerns
• Causal mapping – identifying possible chains of cause and effect
Boehm’s top 10 development risks
PART- C
1.Explain how you will identify the major risks that might affect your project and identify
the strategies for minimizing each of those risks
Risk Evaluation After the potential risks have been identified, the project team then evaluates the
risk based on the probability that the risk event will occur and the potential loss associated with
the event. Not all risks are equal. Some risk events are more likely to happen than others, and the
cost of a risk event can vary greatly. Evaluating the risk for probability of occurrence and the
severity or the potential loss to the project is the next step in the risk management process
2. The project management team will assign the appropriate resources to the technology managers
to assure the accomplishment of project goals. The more complex the technology, the more
resources the technology manager typically needs to meet project goals, and each of those
resources could face unexpected problems.
3. Risk evaluation often occurs in a workshop setting. Building on the identification of the risks,
each risk event is analyzed to determine the likelihood of occurring and the potential cost if it did
occur. The likelihood and impact are both rated ashigh, medium, or low. A risk mitigation plan
addresses the items that have high ratings on both factors—likelihood and impact
Each of these mitigation techniques can be an effective tool in reducing individual risks and the
risk profile of the project. The risk mitigation plan captures the risk mitigation approach for each
identified risk event and the actions the project management team will take to reduce or eliminate
the risk.
Risk avoidance usually involves developing an alternative strategy that has a higher probability
of success but usually at a higher cost associated with accomplishing a project task.
Risk sharing involves partnering with others to share responsibility for the risk activities. Many
organizations that work on international projects will reduce political, legal, labor, and others
risk types associated with international projects by developing a joint venture with a company
located in that country.
Risk reduction is an investment of funds to reduce the risk on a project. On international projects,
companies will often purchase the guarantee of a currency rate to reduce the risk associated with
fluctuations in the currency exchange rate. A project manager may hire an expert to review the
technical plans or the cost estimate on a project to increase the confidence in that plan and reduce
the project risk.
Risk transfer is a risk reduction method that shifts the risk from the project to another party. The
purchase of insurance on certain items is a risk transfer method. The risk is transferred from the
project to the insurance company
3.Write short notes on Resource Allocation and Cost Schedule/ What are the seven
categories of resources and explain.
Resource allocation is the assignment of available resources to various uses. In the context
of an entire economy, resources can be allocated by various means, such as markets or central
planning. In project management, resource allocation or resource management is the scheduling
of activities and the resources required by those activities while taking into consideration both
the resource availability and the project time.
Nature of Resources
Labor – Members of the project team
Equipment – Workstations and other communicating and office equipments
Material – Items that are consumed
Space – Office space
Services – Some specialist services telecommunicating
Time – Offset against the other primary resource
Scheduling Resources
Allocating resources for one activity limits flexibility for resource allocationand
scheduling of other activities
Priorities resource allocation
Total float priority
Activities are ordered according to their total float .Those with the smallest float are
assigned the highest priority
Map on activity plan to assess the distribution of resources required over the duration of
the project
Recruiting staff has cost
Smooth the histogram by delaying the start of some activities
Examples
Allocating resources is fairly self-explanatory. If allocating stone for building a house, the project
manager must ensure that she procures enough stone to complete the project. Regarding leveling,
if renting equipment, the project manager must ensure it will be used steadily rather than
sporadically rented and returned. If contracting carpenters, the project manager should aim to
strive to keep a set number of carpenters working at a set number of hours for the duration of the
project to ensure consistency. Carpenters may have difficulty scheduling more sporadic hours
into their schedule, meaning the firm might then have to contract more workers, leading to
inconsistent results. Meanwhile, materials don't necessarily need to be leveled as they have been
purchased rather than rented or paid by the hour.
Cost Schedules
Calculating cost is straightforward where organization has standard cost figures for staff and
other resources. Staff costs includes not just salary, but also social security contributions by the
employer, holiday pay etc. Timesheets are often used to record actual hours spent on each project
by an individual. One issue can be how time when a staff member is allocated and available to
the project, but is not actually working on the project, is dealt with. Overheads e.g. space rental,
service charges etc. Some overheads might be directly attributable to the project, in other cases a
percentage of departmental overheads may be allocated to project costs. Usage charges are some
charges can be on a ‘pay as you go’ basis e.g. telephone charges, postage, car mileage – at the
planning stage an estimate of these may have to be made.
Cost profile
This shows how much is going to be spent in each week. This could be important where an
organization allocates project budgets by financial year or quarter and the project straddles more
than one of these financial periods
Accumulative costs
The project manager will also be concerned about planned accumulative costs. This chart can be
compared to the actual accumulative costs when controlling the project to assess whether the
project is likely to meet its cost targets.
Balancing concerns
Successful project scheduling is not a simple sequence. Because of the inter-linking of different
concerns project planning will need to be iterative. The consequences of decisions
will need to carefully assessed and plans adjusted accordingly