ITP-001 Installation and Testing of Engine Generator
ITP-001 Installation and Testing of Engine Generator
Project:
MISK-Riyadh Schools, Boys ITP Reference No.:
Campus, KSA P-0058-PH01-D09-09C001-UNE-ITP-ELE-00009,
Rev: 00
MTS Ref. No.:
P-0058-PH01-D09-09C001-UNE-MTS-ELE-000009,
Project No.:
P-0058 Rev: 00
Date: 20 OCT 2024
Project Specs,
Prior to start Approved
Prequalification submittal IFC / Approved Project Specs, IFC & Vendor Project Manager/
1.2 work Prequalification
(Manufacturer / Supplier) Shop Dwgs. lists QA/QC Engineer
R R R Document
Vendor lists
Inspection & Test Plan (ITP) for Engine Generator Installation Page 1 of 7
P-0058-PH01-D08-08C001-UNE-ITP-ELE-00009, R00
INSPECTION AND TEST PLAN FOR
Engine Generator Installation
Project:
MISK-Riyadh Schools, Boys ITP Reference No.:
Campus, KSA P-0058-PH01-D09-09C001-UNE-ITP-ELE-00009,
Rev: 00
MTS Ref. No.:
P-0058-PH01-D09-09C001-UNE-MTS-ELE-000009,
Project No.:
P-0058 Rev: 00
Date: 20 OCT 2024
Approved
Material
Approval Site Engineer /
Per material Approved MAR/Test
Material receiving Inspection Request / Discipline
2.1 reports and Sample Approved MIR
and Storage at site. Manufacturer’ delivery Engineer / H H H ---
Approval
s QA/QC Engineer
recommendati
on
Inspection & Test Plan (ITP) for Engine Generator Installation Page 2 of 7
P-0058-PH01-D08-08C001-UNE-ITP-ELE-00009, R00
INSPECTION AND TEST PLAN FOR
Engine Generator Installation
Project:
MISK-Riyadh Schools, Boys ITP Reference No.:
Campus, KSA P-0058-PH01-D09-09C001-UNE-ITP-ELE-00009,
Rev: 00
MTS Ref. No.:
P-0058-PH01-D09-09C001-UNE-MTS-ELE-000009,
Project No.:
P-0058 Rev: 00
Date: 20 OCT 2024
Inspection & Test Plan (ITP) for Engine Generator Installation Page 3 of 7
P-0058-PH01-D08-08C001-UNE-ITP-ELE-00009, R00
INSPECTION AND TEST PLAN FOR
Engine Generator Installation
Project:
MISK-Riyadh Schools, Boys ITP Reference No.:
Campus, KSA P-0058-PH01-D09-09C001-UNE-ITP-ELE-00009,
Rev: 00
MTS Ref. No.:
P-0058-PH01-D09-09C001-UNE-MTS-ELE-000009,
Project No.:
P-0058 Rev: 00
Date: 20 OCT 2024
Project Spec;
Section, IFC
Visual Inspection of Diesel Site Engineer /
Drawing / Shop As per approved shop
Generator installation includes Visual Discipline
3.1 Drawing drawing, specs & Method of H H H S Shop Drawing
Elevation, Position and Inspection Engineer /
; Method Statement
Location QA/QC Engineer
Statement
Project Spec;
Visual Inspection of installed Section, IFC
Site Engineer /
Generator set accessories like Drawing / Shop As per approved shop
Visual Discipline
3.2 Batteries, Charger, Factory Drawing drawing, specs & Method of H H H S Shop Drawing
Inspection Engineer /
assembled Control Panel & ; Method Statement
QA/QC Engineer
Etc.. Statement
Project Spec;
Section, IFC
Site Engineer /
Drawing / Shop As per approved shop
Visual inspection of Diesel Visual Discipline
3.3 Drawing drawing, specs & Method of H H H S Shop Drawing
tank and fuel pipes Inspection Engineer /
; Method Statement
QA/QC Engineer
Statement
Inspection & Test Plan (ITP) for Engine Generator Installation Page 4 of 7
P-0058-PH01-D08-08C001-UNE-ITP-ELE-00009, R00
INSPECTION AND TEST PLAN FOR
Engine Generator Installation
Project:
MISK-Riyadh Schools, Boys ITP Reference No.:
Campus, KSA P-0058-PH01-D09-09C001-UNE-ITP-ELE-00009,
Rev: 00
MTS Ref. No.:
P-0058-PH01-D09-09C001-UNE-MTS-ELE-000009,
Project No.:
P-0058 Rev: 00
Date: 20 OCT 2024
Project Spec;
Section, IFC
Site Engineer /
Visual Inspection of Conduit, Drawing / Shop As per approved shop
Visual Discipline
3.4 Tray, Trunking and Fittings Drawing drawing, specs & Method of H H H S Shop Drawing
Inspection Engineer /
Installation ; Method Statement
QA/QC Engineer
Statement
Project Spec;
Section, IFC
Visual Inspection for Site Engineer /
Drawing / Shop As per approved shop
Laying/Pulling of Low Visual Discipline
3.5 Drawing drawing, specs & Method of H H H S Shop Drawing
Voltage Cable including Inspection Engineer /
; Method Statement
Accessories QA/QC Engineer
Statement
Project Spec;
Section, IFC
Visual Inspection for Site Engineer /
Drawing / Shop As per approved shop
Installation of Grounding Visual Discipline
3.6 Drawing drawing, specs & Method of H H H S Shop Drawing
system connected to Generator Inspection Engineer /
; Method Statement
including accessories QA/QC Engineer
Statement
Inspection & Test Plan (ITP) for Engine Generator Installation Page 5 of 7
P-0058-PH01-D08-08C001-UNE-ITP-ELE-00009, R00
INSPECTION AND TEST PLAN FOR
Engine Generator Installation
Project:
MISK-Riyadh Schools, Boys ITP Reference No.:
Campus, KSA P-0058-PH01-D09-09C001-UNE-ITP-ELE-00009,
Rev: 00
MTS Ref. No.:
P-0058-PH01-D09-09C001-UNE-MTS-ELE-000009,
Project No.:
P-0058 Rev: 00
Date: 20 OCT 2024
Project Spec;
Section, IFC
Site Engineer /
Visual Inspection of Cable Drawing / Shop As per approved shop
Visual Discipline
3.7 Gland, Cable Dressing, Cable Drawing drawing, specs & Method of H H H S Shop Drawing
Inspection Engineer /
Identification &Termination ; Method Statement
QA/QC Engineer
Statement
LEGEND: H - Hold Point; W - Witness Point; S - Surveillance Inspection; R - Review Documents Only.
H: Hold Point, work may not proceed without Approval or Acceptance by Authorized Party
W: Witness Point notified verification. Work may proceed with or without Approval and Acceptance by Authorized Party
S: Surveillance Point, verification on a random basis where work may proceed with or without Approval or Acceptance by Authorized Party
R: Record Review Point are verification points in an ITP used to confirm conformance of any inspection or test carried out with the project specifications.
Prepared By Approved By
Main Contractor’s Reviewed By
QA/QC Engineer Project Manager
Review & Approval: Sr. Electrical Engineer
Name: Eng. Salman Muzammil Eng. Anas Ashour Eng. Tauqir Ahmed
Signature:
Inspection & Test Plan (ITP) for Engine Generator Installation Page 6 of 7
P-0058-PH01-D08-08C001-UNE-ITP-ELE-00009, R00
INSPECTION AND TEST PLAN FOR
Engine Generator Installation
Project:
MISK-Riyadh Schools, Boys ITP Reference No.:
Campus, KSA P-0058-PH01-D09-09C001-UNE-ITP-ELE-00009,
Rev: 00
MTS Ref. No.:
P-0058-PH01-D09-09C001-UNE-MTS-ELE-000009,
Project No.:
P-0058 Rev: 00
Date: 20 OCT 2024
20 OCT 2024
Date:
Inspection & Test Plan (ITP) for Engine Generator Installation Page 7 of 7
P-0058-PH01-D08-08C001-UNE-ITP-ELE-00009, R00