Project Management Gantt Chart Type 2

New toy production Project Management Gantt Chart type 2

Uploaded by

champa.hapangama
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views2 pages

Project Management Gantt Chart Type 2

New toy production Project Management Gantt Chart type 2

Uploaded by

champa.hapangama
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

New Toy Introduction Project Project start: Tue, 12/3/2024

Display week: 1

September October November December January February March

3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29
TASK START END
Duration (Days) T

Project Initiation 18 Days

Define project objectives and scope 6 Days 12/3/24 12/9/24

Identify Stakeholders 4 Days 12/10/24 12/14/24

Prepare project charter 4 Days 12/15/24 12/19/24

Develop project management plan 4 Days 12/20/24 12/24/24

Conduct market research 44 Days

Design market research strategy 7 Days 12/25/24 12/31/24

Collect and analysze data 30 Days 1/1/25 1/31/25

Prepare market research report 7 Days 2/1/25 2/8/25

Product Design 74 Days

Create initial design concepts 30 Days 12/25/24 1/24/25

Finalize design 30 Days 1/25/25 2/23/25

Document design specifications 14 Days 2/24/25 3/10/25

Prototype Development 45 Days

Build Prototype 30 Days 2/9/25 3/10/25

Prototype testing preparatio 15 Days 3/11/25 3/26/25

Protype testing in lab environment 28 Days

Perform safety and durability test 13 Days 3/28/25 4/10/25

Document and evaluate results 15 Days 4/11/25 4/26/25

Market Acceptance testing 25 Days

Select target audience for market testing 6 Days 4/27/25 5/3/25

Distribute prototype for user testing 6 Days 5/4/25 5/10/25

Collect feedback and analyze results 13 Days 5/11/25 5/24/25


September October November December January February March

3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29
TASK START END
Duration (Days) T

Bulk Production for the launch 6 Days

Secure production materials 3 Days 5/25/25 5/28/25

Begin mass production 3 Days 5/28/25 5/31/25

Launch and monitor the Toy 2 Days

Launch product in the market 1 Day 6/1/25 6/1/25

Monitor customer feedback and sales 1 Day 6/2/25 6/2/25

Insert new rows ABOVE this one