PLANT DESIGN LECTURE 9 - 2024
PLANT DESIGN LECTURE 9 - 2024
PLANT DESIGN LECTURE 9 - 2024
1. LECTURE 1 - INTRODUCTION
2. LECTURE 2 – PLANT DESIGN BASIS
3. LECTURE 3 – PROCESS EQUIPMENT
4. LECTURE 4 – INSTRUMENTS
5. LECTURE 5 – PIPING, PSV and P&ID
6. LECTURE 6 – INTRODUCTION OF REFINERY
INDEX
7. LECTURE 7 - HYDRAULICS
8. LECTURE 8 – COSTING & PROJ. EVALUATION I
9. LECTURE 9 – COSTING & PROJ. EVALUATION II
10. LECTURE 10 – HAZOP STUDY
11. LECTURE 11 - SAFETY
LECTURE 8
4
III. Estimating Capital Costs
3.1 Accuracy of Purpose of Cost Est.
5 Levels
1. Class 5 – “Ballpark estimate”, “guess estimate”
Ø Accuracy: ±30 − 50%
Ø Estimated based on the costs of similar processes and requiring
essentially no design information.
Ø Used in “Feasibility study” and screening purposes.
2. Class 4 – “Preliminary”, “approximate”, “study”, etc.
Ø Accuracy: ±30%
Ø Estimated based on limited cost data and design details
Ø Used in making coarse choices between design alternatives.
3. Class 3 – “Definitive”, “Authorization”, “Budgeting”, etc.
Ø Accuracy: ±10 − 15%
Ø Estimated based on rough P&ID and approximate sizes of major
equipment
Ø Used for authorization of funds to proceed with the design to more
detailed design.
3.1 Accuracy of Purpose of Cost Est.
5 Levels
4. Class 2 – “Detailed estimates”, “Quotation”, “tender”, etc.
Ø Accuracy: ±5 − 10%
Ø Estimated based on completed (or near complete) process design,
firm quotes for equipment, and detailed breakdown and estimation
of the construction cost.
Ø Used for “project cost control” and estimates for “fixed price
contract”
Where,
C2=ISBL capital cost of the plant with capacity S2
C1= ISBL capital cost of the plant with capacity S1
3.2 Rapid Cost Estimates
A. Historic Cost Data (Cont’d)
Values of exponents, n
Ø Processes that use a lot of mechanical work or gas
compression (e.g. methanol, paper pulping, solids-
handling plants): 0.8 – 0.9
Ø Typical chemical process: 0.7
Ø Averaged over the whole chemical process: 0.6, “six-tenth
rule”
Ø Small scale, highly instrumented process: 0.4 -0.5
3.2 Rapid Cost Estimates
A. Historic Cost Data (Cont’d)
Notes:
Ø A functional unit includes all equipment and ancillaries needed
for a significant process step or function, such as a reaction,
separation, or other major unit operation.
Ø Pumping and heat exchange are not normally considered as
functional units unless they have substantial cost, for example,
compressors, refrigeration systems, or process furnaces.
Exercise 1
Where,
C = total plant ISBL capital cost (including engineering costs);
Σ 𝐶𝑒 = total delivered cost of all the major equipment items: reactors, tanks,
columns, heat exchangers, furnaces, etc.
F = an installation factor, later widely known as a Lang factor.
3.3 The Factorial Method of Cost Est.
A. Lang Factors (Cont’d)
1. Lang originally proposed the following values of F,
based on 1940s economics:
Ø F = 3.1 for solids processing plant;
Ø F = 4.74 for fluids processing plant;
Ø F = 3.63 for mixed fluids-solids processing plant.
3. Calculate the ISBL installed capital cost, using the factors given in
Table 2 and correcting for materials of construction using expanded
Lang factor equations with the materials factors given in Table 3.
7. Add the fixed and working capital to get the total investment required.
3.4 Estimating Purchased Equipment Costs
The prices are all for carbon steel equipment except where
noted in the table.
Exercise 2
Notes:
1. For the total weight of distillation column:
Ø Shell mass = 𝜋 𝐷! 𝐿! 𝑡" 𝜌
where,
Dc = vessel diameter, m
Lc = vessel length, m
tw = wall thickness, m (i.e. use 20 mm for this case)
𝜌 = metal density (i.e. 𝜌 of stainless steel = 8,000 kg/m3)
2. For horizontal vessel, use Lc = 2Dc
use tw = 8mm
Exercise 2 (Cont’d)
3. Selection of Materials
• Carbon Steel: Distillation Column Shell, Horizontal vessel, Pump
drivers
• Alloy: The remaining items, including trays, pump itself
4. Installation Factors
• No need to apply installation factors to ‘spare pumps’, ‘spare drivers’
and ‘trays’.
• Installation factor of storage tanks = 2.5
3.5 Cost Escalation
Composite Index
Ø Chemical Engineering Journal
• Chemical Engineering Plant Cost Index (CEPCI, or CE)
• Marshall and Swift Index (M&S Equipment Cost Index)
Ø Oil and Gas Journal
• Nelson-Farrer Refinery Construction Index (NF Index)):
(Updated monthly and index for 40 types of equipment are
updated quarterly.)
Ø Engineering News Record Journal
• Based on Civil Engineering projects
3.5 Cost Escalation
Sol)
From Figure 3,
Index in 2003 = 1,123.6
Index in 2007 = 1,373.3
By extrapolation from the period 2003 to 2005, the M&S index for 2010
will be about 1,560.
So, estimated cost in January 2010 = $64,000 x 1,560/1,124 = $89,000
3.6 Location Factors
1. The cost of building a plant in any other location will
depend on
Ø Local fabrication and construction infrastructure;
Ø Local labor availability and cost;
Ø Costs of shipping or transporting equipment to site;
Ø Import duties or other local tariffs;
Ø Currency exchange rates, which affect the relative cost of locally
purchased
Ø items such as bulk materials, when converted to a conventional
pricing basis such as U.S. dollars.
Source: Aspen Richardson’s International Construction Cost Factor Location Manual (2003)
Exercise 4
From Table 5, the 2003 location factor for Germany was 1.11. The exchange
rate in 2003 averaged about 1 Euro = $1.15, and it averaged about 1 Euro =
$1.35 in 2006.
The 2006 location factor for Germany is thus 1.11 x 1.35/1.15 = 1.3.
The cost of building the acrolein plant in Germany in 2006 is US$ 80 MM x 1.3
= US$104MM.
Appendix A – Process Cost Correlations
Appendix A – Process Cost Correlations