Ref.

#:CMO-F-040
Rev.#: 1
Rev. Date: 26 May 2022

Weather Fair
Chart Cloudy
Rainy
Stormy
DAILY CONSTRUCTION REPORT

Project Name: Contract Package: Date:


HPI-PHASE II CONDO 5 (PLUMBING & SANITARY, FIRE 10-08-2024
PROTECTION WORKS)
Contractor: Package No.:
AGACONS CONSTRUCTION, INC. ACI-HPI-010224-423
Effects of Weather on Major Work Items
Affected
Affected
less than
No effect more than No work
Major and/or Controlling Works Item 50%
all day 50% work all Day
work
Days
Days
All Activities

Manpower Report
Description No. Hrs Description No. Hrs
Construction Supervisor 1 8
Project In Charge/ Site Engineer 1 8
QAQC Engineer 1 8
Safety Officer 1 0
DCC/Admin 1 8
CAD Operator 1 8
Electrician 1 8
Warehouseman 1 8
Foreman 2 16
Plumber 3 16
Pipe Fitter 2 16
Welder/Fabricator 3 24
Mason/Carpenter 2 16
Helper 4 24
Driver 1 8
Total 25 200

Equipment Report (Active or idle)


Ref. #:CMO-F-040
Rev.#: 1
Rev. Date: 26 May 2022

Description No. of Pcs No. of Use Total Hrs. Use


Picker 1 1 8
Shovel 2 2 8
Extension Cord 3 3 8
Grinder 2 2 8
Line Laser 1 1 8
Welding Machine 2 2 8

Work Activity
Description Location
DRYPIPE (FIREPRO) HYDROTEST GROUNDFLOOR
INSTALLATION OF FLOOR DRAIN 3RD FLOOR
INSTALLATION OF WATERLINE , HALLWAY 3RD FLOOR
INSTALLATION OF SUPPORT FOR FIREPRO MAINLINE 5TH FLOOR
INSTALLATION OF PIPE AND SUPPORT FOR WL/VENT PIPE/ SL 5TH FLOOR
FABRICATION OF HANGERS AND SUPPORT FABRICATION AREA

Materials Deliveries
Description Supplier Quantity

Accident Report
Accidents Day of Contract Total Days
Week Day
No Yes See Accident Report 2 189 189

Prepared by: Approved by:

Jerico T. Castillo Arlen T. Rutaquio


ACI – Site Engineer ACI – Construction Supervisor

Verified by: Noted by:

Allyza Joy Delin Alexander Andaya


DCCD Inspector DCCD CM