10-08-2024
10-08-2024
10-08-2024
#:CMO-F-040
Rev.#: 1
Rev. Date: 26 May 2022
Weather Fair
Chart Cloudy
Rainy
Stormy
DAILY CONSTRUCTION REPORT
Manpower Report
Description No. Hrs Description No. Hrs
Construction Supervisor 1 8
Project In Charge/ Site Engineer 1 8
QAQC Engineer 1 8
Safety Officer 1 0
DCC/Admin 1 8
CAD Operator 1 8
Electrician 1 8
Warehouseman 1 8
Foreman 2 16
Plumber 3 16
Pipe Fitter 2 16
Welder/Fabricator 3 24
Mason/Carpenter 2 16
Helper 4 24
Driver 1 8
Total 25 200
Work Activity
Description Location
DRYPIPE (FIREPRO) HYDROTEST GROUNDFLOOR
INSTALLATION OF FLOOR DRAIN 3RD FLOOR
INSTALLATION OF WATERLINE , HALLWAY 3RD FLOOR
INSTALLATION OF SUPPORT FOR FIREPRO MAINLINE 5TH FLOOR
INSTALLATION OF PIPE AND SUPPORT FOR WL/VENT PIPE/ SL 5TH FLOOR
FABRICATION OF HANGERS AND SUPPORT FABRICATION AREA
Materials Deliveries
Description Supplier Quantity
Accident Report
Accidents Day of Contract Total Days
Week Day
No Yes See Accident Report 2 189 189