FORM H LOT 5 GWEMBE and KAZUNGULA

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 100

BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA

DISTRICT UNDER THE SCRALA PROJECT


APPENDIX
H: BILL OF
QUANTITI
ES LOT
5: ITEM DESCRIPTION UNIT QTY
KAZUNGU
LA 1.00 PRELIMINARIES AND GENERAL ITEMS

NOTE: The value of preliminaries and general items shall not exceed 5% of the value of
measured works of the project

i) Site Mobilization Item 1

The contractor shall set up the site working areas and storage facilities as may be
deemed necessary including all required site mobilization activities not mentioned below

ii) Site Billboard, Site hoarding and Site Meetings Item 1

The contractor shall fabricate and errect a project billboard, site hoarding during the
construction of the water tank stand, and shall allow for all expenses associated with
convening and attending site progress meetings with client's staff and stage inspection of
works quality and progress .

iv) Contractor's Demobilization and handover Item 1

The contractor shall upon completion of the works remove all equipment, tools and
remaining materials and clean the site as may be approved by the Project Engineer

TOTAL P&Gs CARRIED TO GENERAL SUMMARY

2.0 CONSTRUCTION OF WATER TANK AND STAND

Site: SIAKASIPA KAZUNGULA DISTRICT


A FOUNDATION AND EARTHWORKS

Site Preparation

1 Clear site of bushes, shrubs undergrowth and the like


including cutting down trees not exceeding 600mm
girth and grub up roots m2 100

2 Excavating Base Pit commencing at reduced level depth


not exceeding 1.5m starting from formation level m3 10

3 Extra over excavating in hard rock m3 3

Backfilling and Disposal

4 Backfilling around foundations and compacting loose


soils in 150mm layers upto 1.5m height on reduced level m3 9

5 Redig from spoil heap and remove off site m3 11

B CONCRETE WORKS

Preamble

All structral concrete shall vibrated reinforced concrete (reinforcement measured


separately); to specified classes for different member categories; 30MPa for foundation
members, (30MPa for stub columns; 20 mm maximum aggregate). Slump and cube
samples shall be taken for each batch for quality control.

Plain in-situ concrete Grade 15

1 50mm thick Blinding below column bases m2 12

Reinforced concrete C30 in

2 Column bases m3 6

Page 1
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY

3 Stub Columns m3 1

4 Ground beam m3 2

C STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement cut
to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.

1 8mm bars Kg 39

High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
and fixing.

2 16mm diameter bars Kg 452

Sl.No. ITEM UNIT QTY

D FORMWORK

Smooth off shutter concrete formwork including


making good exposed surfaces after removal as described
to:

1 Sides of stub column m2 8

2 Sides and soffits of ground beams m2 9

E STRUCTURAL STEELWORK

Preamble

All structural steel shall be Grade S275, in accordance with with B.S 5950, all welds to be
6mm continous weld or as described; in accordance with BS 1856 and 2642, and shall be
given a coat of SF Utra - Thin Fire Retardant.

All rates shall include the cost of fabrication, installation, assemby,errection and where
necessary testing; and all other associated costs to render the design functional as
described

1 IPE 160 Stanchions Kg 506

2 UB 254 x 146 x 31 Primary Beams Kg 273

3 IPE 200 x 22.4 for Secondary Beams Kg 667

4 80 x 80 x 6 for Ties Kg 245.00

5 70 x 70 x6 for Bracing Kg 864

6 70 x 70 x 6 RSA for railing support Kg 211

33.7mm dia. x 2.6mm CHS hand rails (2.4 Kg/m)


7 Kg
41

8 20mm base plate Kg 101

9 16mm base plates Kg 58

10 8mm MS Plates Kg 452

Page 2
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY


11 M20 x 60mm Gr. 8.8 Bolts & Nuts No. 24

12 M16 x 50mm Gr. 8.8 Bolts & Nuts No. 360

13 M20 x 1m Gr. 8.8 HD Bolts No. 16

14 150x75mm Tank decking HW timber m 19

15 Fabricate ladder and install as described (Provisional sum) m 1

16 484 Expanded diamond mesh for catwalk m2 13

Touch up approved anti corrosion paint primer, and two more coats on all steelworks;
17 General surfaces of steelwork in green colour (Provisional Sum) item 1

Sl.No. ITEM UNIT QTY

F WATER TANK

1 Supply and fix 10,000 litres capacity polycon water


tank hoisted on tank stand ( measured seperately)
complete with automatic float switch, ball valves, filters
and connecting pipes inlet and outlet and overflow No. 1

COLLECTION

SITE: SINDE KAZUNGULA DISTRICT


A FOUNDATION AND EARTHWORKS

Site Preparation

1 Clear site of bushes, shrubs undergrowth and the like


including cutting down trees not exceeding 600mm
girth and grub up roots m2 100

2 Excavating Base Pit commencing at reduced level depth


not exceeding 1.5m starting from formation level m3 10

3 Extra over excavating in hard rock m3 3

Backfilling and Disposal

4 Backfilling around foundations and compacting loose


soils in 150mm layers upto 1.5m height on reduced level m3 9

5 Redig from spoil heap and remove off site m3 11

B CONCRETE WORKS

Preamble

All structral concrete shall vibrated reinforced concrete (reinforcement measured


separately); to specified classes for different member categories; 30MPa for foundation
members, (30MPa for stub columns; 20 mm maximum aggregate). Slump and cube
samples shall be taken for each batch for quality control.

Plain in-situ concrete Grade 15

1 50mm thick Blinding below column bases m2 12

Page 3
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY


Reinforced concrete C30 in

2 Column bases m3 6

3 Stub Columns m3 1

4 Ground beam m3 2

C STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement cut
to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.

1 8mm bars Kg 39

High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
and fixing.

2 16mm diameter bars Kg 452

Sl.No. ITEM UNIT QTY

D FORMWORK

Smooth off shutter concrete formwork including


making good exposed surfaces after removal as described
to:

1 Sides of stub column m2 8

2 Sides and soffits of ground beams m2 9

E STRUCTURAL STEELWORK

Preamble

All structural steel shall be Grade S275, in accordance with with B.S 5950, all welds to be
6mm continous weld or as described; in accordance with BS 1856 and 2642, and shall be
given a coat of SF Utra - Thin Fire Retardant.

All rates shall include the cost of fabrication, installation, assemby,errection and where
necessary testing; and all other associated costs to render the design functional as
described

1 IPE 160 Stanchions Kg 506

2 UB 254 x 146 x 31 Primary Beams Kg 273

3 IPE 200 x 22.4 for Secondary Beams Kg 667

4 80 x 80 x 6 for Ties Kg 245.00

5 70 x 70 x6 for Bracing Kg 864

6 70 x 70 x 6 RSA for railing support Kg 211

33.7mm dia. x 2.6mm CHS hand rails (2.4 Kg/m)


7 Kg
41

8 20mm base plate Kg 101

9 16mm base plates Kg 58

Page 4
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY

10 8mm MS Plates Kg 452

11 M20 x 60mm Gr. 8.8 Bolts & Nuts No. 24

12 M16 x 50mm Gr. 8.8 Bolts & Nuts No. 360

13 M20 x 1m Gr. 8.8 HD Bolts No. 16

14 150x75mm Tank decking HW timber m 19

15 Fabricate ladder and install as described (Provisional sum) m 1

16 484 Expanded diamond mesh for catwalk m2 13

Touch up approved anti corrosion paint primer, and two more coats on all steelworks;
17 General surfaces of steelwork in green colour (Provisional Sum) item 1

Sl.No. ITEM UNIT QTY

F WATER TANK

1 Supply and fix 10,000 litres capacity polycon water


tank hoisted on tank stand ( measured seperately)
complete with automatic float switch, ball valves, filters
and connecting pipes inlet and outlet and overflow No. 1

COLLECTION

SITE: MANYEMUNYEMU KAZUNGULA DISTRICT


A FOUNDATION AND EARTHWORKS

Site Preparation

1 Clear site of bushes, shrubs undergrowth and the like


including cutting down trees not exceeding 600mm
girth and grub up roots m2 100

2 Excavating Base Pit commencing at reduced level depth


not exceeding 1.5m starting from formation level m3 10

3 Extra over excavating in hard rock m3 3

Backfilling and Disposal

4 Backfilling around foundations and compacting loose


soils in 150mm layers upto 1.5m height on reduced level m3 9

5 Redig from spoil heap and remove off site m3 11

B CONCRETE WORKS

Preamble

Page 5
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY

All structral concrete shall vibrated reinforced concrete (reinforcement measured


separately); to specified classes for different member categories; 30MPa for foundation
members, (30MPa for stub columns; 20 mm maximum aggregate). Slump and cube
samples shall be taken for each batch for quality control.

Plain in-situ concrete Grade 15

1 50mm thick Blinding below column bases m2 12

Reinforced concrete C30 in

2 Column bases m3 6

3 Stub Columns m3 1

4 Ground beam m3 2

C STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement cut
to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.

1 8mm bars Kg 39

High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
and fixing.

2 16mm diameter bars Kg 452

Sl.No. ITEM UNIT QTY

D FORMWORK

Smooth off shutter concrete formwork including


making good exposed surfaces after removal as described
to:

1 Sides of stub column m2 8

2 Sides and soffits of ground beams m2 9

E STRUCTURAL STEELWORK

Preamble

All structural steel shall be Grade S275, in accordance with with B.S 5950, all welds to be
6mm continous weld or as described; in accordance with BS 1856 and 2642, and shall be
given a coat of SF Utra - Thin Fire Retardant.

All rates shall include the cost of fabrication, installation, assemby,errection and where
necessary testing; and all other associated costs to render the design functional as
described

1 IPE 160 Stanchions Kg 506

2 UB 254 x 146 x 31 Primary Beams Kg 273

3 IPE 200 x 22.4 for Secondary Beams Kg 667

4 80 x 80 x 6 for Ties Kg 245.00

Page 6
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY

5 70 x 70 x6 for Bracing Kg 864

6 70 x 70 x 6 RSA for railing support Kg 211

33.7mm dia. x 2.6mm CHS hand rails (2.4 Kg/m)


7 Kg
41

8 20mm base plate Kg 101

9 16mm base plates Kg 58

10 8mm MS Plates Kg 452

11 M20 x 60mm Gr. 8.8 Bolts & Nuts No. 24

12 M16 x 50mm Gr. 8.8 Bolts & Nuts No. 360

13 M20 x 1m Gr. 8.8 HD Bolts No. 16

14 150x75mm Tank decking HW timber m 19

15 Fabricate ladder and install as described (Provisional sum) m 1

16 484 Expanded diamond mesh for catwalk m2 13

Touch up approved anti corrosion paint primer, and two more coats on all steelworks;
17 General surfaces of steelwork in green colour (Provisional Sum) item 1

Sl.No. ITEM UNIT QTY

F WATER TANK

1 Supply and fix 10,000 litres capacity polycon water


tank hoisted on tank stand ( measured seperately)
complete with automatic float switch, ball valves, filters
and connecting pipes inlet and outlet and overflow No. 1

COLLECTION

TO MAIN COLLECTION - WATER TANK STRUCTURE

3.0 CONSTRUCTION OF WATER KIOSKS

SINDE SITE
No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS

Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 140
cutting down trees not exceeding 600mm girth and grub
up roots

Unless otherwise stated excavations shall be in 'pickable' material.


Excavations and Earthworks

Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Kiosk apron, pipe trenches and soak pit m3 26

Page 7
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY


Refilling of foundation hardcore base with approved laterite in layers of 150mm thick
including compaction and consolidation etc., all complete as directed by the Engineer-in-
Charge.

3 i) Below Kiosk apron m3 15.0

FOUNDATION AND EARTHWORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


B STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement
cut to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
i)
and fixing.
For Substructure works:
3 i) 12mm dia. As Y12 in apron Kg 355

STEEL REINFORCEMENT FOR CONCRETE- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


C CONCRETE WORKS

All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R
cement, 20mm graded granite aggregated and quarry dust; thickness as required
including compacting, curing, formwork etc., complete as directed by the Resident
Engineer
i) Below Kiosk apron m3 2.00

All structral concrete shall vibrated reinforced concrete (reinforcement measured


separately); to specified classes for different member categories; 30MPa for foundation
members, (30MPa for stub columns; 20 mm maximum aggregate). Slump and cube
samples shall be taken for each batch for quality control. Rate should include all formwork
For Substructure works:
ii) in Apron and ramps m3 4.00

Formwork
Sawn formwork; to:
iii) Sides of apron concrete m2 4

CONCRETE WORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


D BRICKWORK AND MASONRY
Blockwork in concrete blocks not less than 10N/mm2 in crushing strength cement
mortar (1:3); and filled with C15 concrete in:
For Substructure works:
i) 200 mm Kiosk blockwork m2 6
ii) 200 mm Kiosk Soak Pit honeycomb m2 10

Two strand 3.25 mm diameter high tensile steel wire wall reinforcement; 100 mm laps
(measured net: no allowance made for laps); every course; in
Kiosk blockwork:
iii) 200 mm block wall. m 20
iv) 200 mm Kiosk Soak Pit honeycomb m2 38

BRICKWORK AND MASONRY - TOTAL CARRIED TO SUMMARY

E PLASTERING AND FLOORING

Page 8
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY

Cement mortar (1:4) plastering 10mm thick over concrete and blockwork surface and
concrete apron to be finished even and smooth with steel float trowel; all complete as
directed by the Resident Engineer.

i) Apron Flooring m2 23

ii) Kiosk Blockwork m2 9

iii) Kiosk Soak Pit honeycomb m2 45

PLASTERING AND FLOORING - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


1.1 PLUMBING INSTALLATION

Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)

Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.

Galvanised mild steel pipework, medium weight, imbeded in blockwork at construction

i) 19 mm Diameter pipe to walls and slab underside m 2


ii) 25 mm Diameter pipe to walls and slab underside m 15
iii) Allow for Extra for all fittings in diameter 19 mm No. 12
iv) Allow for Extra for all fittings in pipe diameter 25 mm No. 5

Equipment
Include for making chases and holes in walls, existing slab and breaking existing slab
v) Item 1
where necessary and making good walls, slab and finishings.

PLUMBING INSTALLATION - TOTAL CARRIED TO SUMMARY

SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
D BRICKWORK AND MASONRY
E PLASTERING AND FLOORING
F PLUMBING INSTALLATION
COLLECTION

SIAKASIPA SITE
No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS

Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 140
cutting down trees not exceeding 600mm girth and grub
up roots

Unless otherwise stated excavations shall be in 'pickable' material.


Excavations and Earthworks

Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Kiosk apron, pipe trenches and soak pit m3 26

Refilling of foundation hardcore base with approved laterite in layers of 150mm thick
including compaction and consolidation etc., all complete as directed by the Engineer-in-
Charge.

3 i) Below Kiosk apron m3 15.0

Page 9
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY

FOUNDATION AND EARTHWORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


B STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement
cut to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
i)
and fixing.
For Substructure works:
3 i) 12mm dia. As Y12 in apron Kg 355

STEEL REINFORCEMENT FOR CONCRETE- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


C CONCRETE WORKS

All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R
cement, 20mm graded granite aggregated and quarry dust; thickness as required
including compacting, curing, formwork etc., complete as directed by the Resident
Engineer
i) Below Kiosk apron m3 2.00

All structral concrete shall vibrated reinforced concrete (reinforcement measured


separately); to specified classes for different member categories; 30MPa for foundation
members, (30MPa for stub columns; 20 mm maximum aggregate). Slump and cube
samples shall be taken for each batch for quality control. Rate should include all formwork
For Substructure works:
ii) in Apron and ramps m3 4.00

Formwork
Sawn formwork; to:
iii) Sides of apron concrete m2 4

CONCRETE WORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


D BRICKWORK AND MASONRY
Blockwork in concrete blocks not less than 10N/mm2 in crushing strength cement
mortar (1:3); and filled with C15 concrete in:
For Substructure works:
i) 200 mm Kiosk blockwork m2 6
ii) 200 mm Kiosk Soak Pit honeycomb m2 10

Two strand 3.25 mm diameter high tensile steel wire wall reinforcement; 100 mm laps
(measured net: no allowance made for laps); every course; in
Kiosk blockwork:
iii) 200 mm block wall. m 20
iv) 200 mm Kiosk Soak Pit honeycomb m2 38

BRICKWORK AND MASONRY - TOTAL CARRIED TO SUMMARY

E PLASTERING AND FLOORING

Cement mortar (1:4) plastering 10mm thick over concrete and blockwork surface and
concrete apron to be finished even and smooth with steel float trowel; all complete as
directed by the Resident Engineer.

i) Apron Flooring m2 22.2

ii) Kiosk Blockwork m2 8.5

Page 10
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY

iii) Kiosk Soak Pit honeycomb m2 45

PLASTERING AND FLOORING - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


1.1 PLUMBING INSTALLATION

Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)

Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.

Galvanised mild steel pipework, medium weight, imbeded in blockwork at construction

i) 19 mm Diameter pipe to walls and slab underside m 2


ii) 25 mm Diameter pipe to walls and slab underside m 15
iii) Allow for Extra for all fittings in diameter 19 mm No. 12
iv) Allow for Extra for all fittings in pipe diameter 25 mm No. 5

Equipment
Include for making chases and holes in walls, existing slab and breaking existing slab
v) Item 1
where necessary and making good walls, slab and finishings.

PLUMBING INSTALLATION - TOTAL CARRIED TO SUMMARY

SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
D BRICKWORK AND MASONRY
E PLASTERING AND FLOORING
F PLUMBING INSTALLATION
TO COLLECTIONS

MANYEMUNYEMEU SITE
No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS

Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 140
cutting down trees not exceeding 600mm girth and grub
up roots

Unless otherwise stated excavations shall be in 'pickable' material.


Excavations and Earthworks

Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Kiosk apron, pipe trenches and soak pit m3 26

Refilling of foundation hardcore base with approved laterite in layers of 150mm thick
including compaction and consolidation etc., all complete as directed by the Engineer-in-
Charge.

3 i) Below Kiosk apron m3 15.0

FOUNDATION AND EARTHWORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


B STEEL REINFORCEMENT FOR CONCRETE

Page 11
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY

Supplying, bending and fixing in position as per approved design; steel reinforcement
cut to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
i)
and fixing.
For Substructure works:
3 i) 12mm dia. As Y12 in apron Kg 355

STEEL REINFORCEMENT FOR CONCRETE- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


C CONCRETE WORKS

All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R
cement, 20mm graded granite aggregated and quarry dust; thickness as required
including compacting, curing, formwork etc., complete as directed by the Resident
Engineer
i) Below Kiosk apron m3 2.00

All structral concrete shall vibrated reinforced concrete (reinforcement measured


separately); to specified classes for different member categories; 30MPa for foundation
members, (30MPa for stub columns; 20 mm maximum aggregate). Slump and cube
samples shall be taken for each batch for quality control. Rate should include all formwork
For Substructure works:
ii) in Apron and ramps m3 4.00

Formwork
Sawn formwork; to:
iii) Sides of apron concrete m2 4

CONCRETE WORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


D BRICKWORK AND MASONRY
Blockwork in concrete blocks not less than 10N/mm2 in crushing strength cement
mortar (1:3); and filled with C15 concrete in:
For Substructure works:
i) 200 mm Kiosk blockwork m2 6
ii) 200 mm Kiosk Soak Pit honeycomb m2 10

Two strand 3.25 mm diameter high tensile steel wire wall reinforcement; 100 mm laps
(measured net: no allowance made for laps); every course; in
Kiosk blockwork:
iii) 200 mm block wall. m 20
iv) 200 mm Kiosk Soak Pit honeycomb m2 38

BRICKWORK AND MASONRY - TOTAL CARRIED TO SUMMARY

E PLASTERING AND FLOORING

Cement mortar (1:4) plastering 10mm thick over concrete and blockwork surface and
concrete apron to be finished even and smooth with steel float trowel; all complete as
directed by the Resident Engineer.

i) Apron Flooring m2 22.2

ii) Kiosk Blockwork m2 8.5

iii) Kiosk Soak Pit honeycomb m2 45

PLASTERING AND FLOORING - TOTAL CARRIED TO SUMMARY

Page 12
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY


Sl.No. ITEM UNIT QTY
1.1 PLUMBING INSTALLATION

Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)

Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.

Galvanised mild steel pipework, medium weight, imbeded in blockwork at construction

i) 19 mm Diameter pipe to walls and slab underside m 2


ii) 25 mm Diameter pipe to walls and slab underside m 15
iii) Allow for Extra for all fittings in diameter 19 mm No. 12
iv) Allow for Extra for all fittings in pipe diameter 25 mm No. 5

Equipment
Include for making chases and holes in walls, existing slab and breaking existing slab
v) Item 1
where necessary and making good walls, slab and finishings.

PLUMBING INSTALLATION - TOTAL CARRIED TO SUMMARY

SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
D BRICKWORK AND MASONRY
E PLASTERING AND FLOORING
F PLUMBING INSTALLATION
TO COLLECTIONS

WATER KIOSKS TOTAL CARRIED TO MAIN SUMMARY

4.0 CONSTRUCTION OF WATER TROUGHS

SITE: SINDE KAZUNGULA DISTRICT


No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS

Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 384
cutting down trees not exceeding 600mm girth and grub
up roots

Unless otherwise stated excavations shall be in 'pickable' material.


Excavations and Earthworks

Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Cattle Water Trough apron and pipe trenches m3 40

Refilling of foundation hardcore base with approved laterite in layers of 150mm thick
including compaction and consolidation etc., all complete as directed by the Engineer-in-
Charge.

3 i) Below Cattle Water Trough apron m3 40.0

FOUNDATION AND EARTHWORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


B STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement
cut to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.

Page 13
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY


i) 3.2mm dia , 150 BRC heavy duty conforce wire in apron slab m2 120
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
ii)
and fixing.

3 i) 10mm dia. As Y10 in trough stem concrete Kg 586

STEEL REINFORCEMENT FOR CONCRETE- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


C CONCRETE WORKS

All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R
cement, 20mm graded granite aggregated and quarry dust; thickness as required
including compacting, curing, formwork etc., complete as directed by the Resident
Engineer
i) Below Cattle Water Trough apron m3 7.00

All structral concrete shall vibrated reinforced concrete (reinforcement measured


separately); to specified classes for different member categories; 30MPa for foundation
members, (30MPa for stub columns; 20 mm maximum aggregate). Slump and cube
samples shall be taken for each batch for quality control. Formwork rates to include all
supports and jointing to required to assemble sound formwork necessary to achieve and
form described concrete geometry
For Substructure works:
ii) in Cattle Water Trough Apron m3 23.00

Formwork
Sawn formwork; to:
iii) Sides of trough stem concrete m2 64

CONCRETE WORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


E TROUGH GROUTING AND SEALING
10mm thick Cement grouting mortar (1:2) to be rendered to the interior of the water
trough over concrete surface; smooth with steel float trowel; all complete as directed by
the Resident Engineer.

i) Grout to interior surfaces of water troughs m2 116

TROUGH GROUTING AND SEALING- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


F PLUMBING INSTALLATIONS

Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)

Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.

Galvanised mild steel pipework, medium weight, imbeded in blockwork at construction

i) 25 mm Diameter pipe to walls and slab underside m 20


ii) Allow for Extra for all fittings in pipe diameter 25 mm No. 5

Supply and installation of ball-floater automated water opening and closing mechanism,
iii) L.S. 1
including all associated fixture to render installation functional (Provisional Sum only)

Equipment
Include for making chases and holes in walls, existing slab and breaking slab where
iv) Item 1
necessary and making good walls, slab and finishings.

Page 14
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY


Supply and install, 50mm dia. uPVC pipes including all fittings to render the installation
v) functional as described; in accordance with ASMD - 1785 or equal and approved m 180
standard

PLUMBING INSTALLATIONS - TOTAL CARRIED TO SUMMARY

SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
E TROUGH GROUTING AND SEALING
F PLUMBING INSTALLATIONS
TO COLLECTIONS

SIAKASIPA KAZUNGULA DISTRICT


No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS

Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 384
cutting down trees not exceeding 600mm girth and grub
up roots

Unless otherwise stated excavations shall be in 'pickable' material.


Excavations and Earthworks

Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Cattle Water Trough apron and pipe trenches m3 40

Refilling of foundation hardcore base with approved laterite in layers of 150mm


thick including compaction and consolidation etc., all complete as directed by the
Engineer-in-Charge.

3 i) Below Cattle Water Trough apron m3 40.0

FOUNDATION AND EARTHWORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


B STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement cut
to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.
i) 3.2mm dia , 150 BRC heavy duty conforce wire in apron slab m2 120
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
ii)
and fixing.

3 i) 10mm dia. As Y10 in trough stem concrete Kg 586

STEEL REINFORCEMENT FOR CONCRETE- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


C CONCRETE WORKS

All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R
cement, 20mm graded granite aggregated and quarry dust; thickness as required
including compacting, curing, formwork etc., complete as directed by the Resident
Engineer
i) Below Cattle Water Trough apron m3 7.00

Page 15
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY

All structral concrete shall vibrated reinforced concrete (reinforcement measured


separately); to specified classes for different member categories; 30MPa for foundation
members, (30MPa for stub columns; 20 mm maximum aggregate). Slump and cube
samples shall be taken for each batch for quality control. Formwork rates to include all
supports and jointing to required to assemble sound formwork necessary to achieve and
form described concrete geometry
For Substructure works:
ii) in Cattle Water Trough Apron m3 23.00

Formwork
Sawn formwork; to:
iii) Sides of trough stem concrete m2 64

CONCRETE WORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


E TROUGH GROUTING AND SEALING
10mm thick Cement grouting mortar (1:2) to be rendered to the interior of the water
trough over concrete surface; smooth with steel float trowel; all complete as directed by
the Resident Engineer.

i) Grout to interior surfaces of water troughs m2 116

TROUGH GROUTING AND SEALING- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


F PLUMBING INSTALLATIONS

Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)

Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.

Galvanised mild steel pipework, medium weight, imbeded in blockwork at construction

i) 25 mm Diameter pipe to walls and slab underside m 20


ii) Allow for Extra for all fittings in pipe diameter 25 mm No. 5

Supply and installation of ball-floater automated water opening and closing mechanism,
iii) L.S. 1
including all associated fixture to render installation functional (Provisional Sum only)

Equipment
Include for making chases and holes in walls, existing slab and breaking slab where
iv) Item 1
necessary and making good walls, slab and finishings.

Supply and install, 50mm dia. uPVC pipes including all fittings to render the installation
v) functional as described; in accordance with ASMD - 1785 or equal and approved m 180
standard

PLUMBING INSTALLATIONS - TOTAL CARRIED TO SUMMARY

SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
E TROUGH GROUTING AND SEALING
F PLUMBING INSTALLATIONS
TO COLLECTIONS

MANYEMUNYEMU KAZUNGULA DISTRICT

Page 16
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY


No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS

Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 384
cutting down trees not exceeding 600mm girth and grub
up roots

Unless otherwise stated excavations shall be in 'pickable' material.


Excavations and Earthworks

Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Cattle Water Trough apron and pipe trenches m3 40

Refilling of foundation hardcore base with approved laterite in layers of 150mm


thick including compaction and consolidation etc., all complete as directed by the
Engineer-in-Charge.

3 i) Below Cattle Water Trough apron m3 40.0

FOUNDATION AND EARTHWORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


B STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement cut
to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.
i) 3.2mm dia , 150 BRC heavy duty conforce wire in apron slab m2 120
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
ii)
and fixing.

3 i) 10mm dia. As Y10 in trough stem concrete Kg 586

STEEL REINFORCEMENT FOR CONCRETE- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


C CONCRETE WORKS

All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R
cement, 20mm graded granite aggregated and quarry dust; thickness as required
including compacting, curing, formwork etc., complete as directed by the Resident
Engineer
i) Below Cattle Water Trough apron m3 7.00

All structral concrete shall vibrated reinforced concrete (reinforcement measured


separately); to specified classes for different member categories; 30MPa for foundation
members, (30MPa for stub columns; 20 mm maximum aggregate). Slump and cube
samples shall be taken for each batch for quality control. Formwork rates to include all
supports and jointing to required to assemble sound formwork necessary to achieve and
form described concrete geometry
For Substructure works:
ii) in Cattle Water Trough Apron m3 23.00

Formwork
Sawn formwork; to:
iii) Sides of trough stem concrete m2 64

CONCRETE WORKS - TOTAL CARRIED TO SUMMARY

Page 17
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY


Sl.No. ITEM UNIT QTY
E TROUGH GROUTING AND SEALING
10mm thick Cement grouting mortar (1:2) to be rendered to the interior of the water
trough over concrete surface; smooth with steel float trowel; all complete as directed by
the Resident Engineer.

i) Grout to interior surfaces of water troughs m2 116

TROUGH GROUTING AND SEALING- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


F PLUMBING INSTALLATIONS

Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)

Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.

Galvanised mild steel pipework, medium weight, imbeded in blockwork at construction

i) 25 mm Diameter pipe to walls and slab underside m 20


ii) Allow for Extra for all fittings in pipe diameter 25 mm No. 5

Supply and installation of ball-floater automated water opening and closing mechanism,
iii) L.S. 1
including all associated fixture to render installation functional (Provisional Sum only)

Equipment
Include for making chases and holes in walls, existing slab and breaking slab where
iv) Item 1
necessary and making good walls, slab and finishings.

Supply and install, 50mm dia. uPVC pipes including all fittings to render the installation
v) functional as described; in accordance with ASMD - 1785 or equal and approved m 180
standard

PLUMBING INSTALLATIONS - TOTAL CARRIED TO SUMMARY

SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
E TROUGH GROUTING AND SEALING
F PLUMBING INSTALLATIONS
TO COLLECTIONS

SUMMARY TO MAIN COLLECTIONS FOR TROUGHS

5.0 CONSTRUCTION OF FENCING

FENCING
SITE: SINDE KAZUNGULA DISTRICT
Sl.No. ITEM UNIT QTY
G FENCING INSTALLATION

Game wire fencing shall be 1.88m x 300mm 14W Wire VELDSPAN brand or equal and
approved, with all posts, steys and Y sections well anchored in to the ground by
concreting with C20 concrete to resident Engineer's approval, all complete with fence
posts round 3.0m x 76mm MD, Fence Stey Round 3.0 x 38mm MD, all bolts, washers and
nuts to render installation functional, fence standards Y sections 3.05m at not more than
4.5m centres, Double 1.8 x 4.2m Fence Gate all complete with required Wire plains to
Engineers satisfaction
Supply and install 'game wire fencing' as described around the water tank and water
i) kiosk facility around 1 hactare plot m 500

Page 18
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY

Supply and install double gate as described to allow for controlled access around the
ii) water tank and water kiosk facility around 1 hactare plot No. 1

FENCING INSTALLATION - TOTAL CARRIED TO SUMMARY

SITE: SIAKASIPA KAZUNGULA DISTRICT


Sl.No. ITEM UNIT QTY
G FENCING INSTALLATION

Game wire fencing shall be 1.88m x 300mm 14W Wire VELDSPAN brand or equal and
approved, with all posts, steys and Y sections well anchored in to the ground by
concreting with C20 concrete to resident Engineer's approval, all complete with fence
posts round 3.0m x 76mm MD, Fence Stey Round 3.0 x 38mm MD, all bolts, washers and
nuts to render installation functional, fence standards Y sections 3.05m at not more than
4.5m centres, Double 1.8 x 4.2m Fence Gate all complete with required Wire plains to
Engineers satisfaction
Supply and install 'game wire fencing' as described around the water tank and water
i) kiosk facility around 1 hactare plot m 500

Supply and install double gate as described to allow for controlled access around the
ii) water tank and water kiosk facility around 1 hactare plot No. 1

FENCING INSTALLATION - TOTAL CARRIED TO SUMMARY

SITE: MANYEMUNYEMU KAZUNGULA DISTRICT


Sl.No. ITEM UNIT QTY
G FENCING INSTALLATION

Game wire fencing shall be 1.88m x 300mm 14W Wire VELDSPAN brand or equal and
approved, with all posts, steys and Y sections well anchored in to the ground by
concreting with C20 concrete to resident Engineer's approval, all complete with fence
posts round 3.0m x 76mm MD, Fence Stey Round 3.0 x 38mm MD, all bolts, washers and
nuts to render installation functional, fence standards Y sections 3.05m at not more than
4.5m centres, Double 1.8 x 4.2m Fence Gate all complete with required Wire plains to
Engineers satisfaction
Supply and install 'game wire fencing' as described around the water tank and water
i) kiosk facility around 1 hactare plot m 200

Supply and install double gate as described to allow for controlled access around the
ii) water tank and water kiosk facility around 1 hactare plot No. 1

FENCING INSTALLATION - TOTAL CARRIED TO SUMMARY

COLLECTION FENCING TO MAIN SUMMARY

6.0 CONSTRUCTION OF DRIP IRRIGATION SYSTEM

SITE: SINDE KAZUNGULA DISTRICT

ITEM DESCRIPTION UNIT QTY

1 DRIP IRRIGATION SYSTEM 1ha

The contractor is expected to supply, construct, commission the 1ha drip irrigation system

A Excavating trenches not exceeding 0.80m deep and


average depth 600mm starting from existing ground level
to receive service pipes, including grading bottoms,
earthwork supports, backfilling with excavated material,
disposing of surplus excavated material off site m 400

Page 19
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY

B Extra over excavating in hard rock m³ 100

Polyvinyl Chloride class 6, PVC pipes, fittings


and jointing as described

FILTER
1 DISC FILTER 130 MICRONS, 3" EA 1
2 ACCESSORIES incl valves, fittings, risers etc EA 1
3

MAINLINE & SUBMAIN FITTINGS


1 PIPE PVC 63 W/SEAL CLASS 6 MTR 204
2 GALVANISED UNION WITH O-RING, HD 50MM EA 10
3 PVC VALVE PLAIN 50 EA 10
4 PVC 90 DEG TEE GLUE 63 EA 4
5 PVC ADAPTOR GLUE 50*63*2", PN16 EA 10
6 PVC END CAP PN16 EA 10
7 PVC 63MM SOCKET PN16 EA 8
8 NAVC 10 2" COMBINATION AV PN10 BSP EA 2
9 GALVANISED RISER 2" X 75MM, HD EA 30
10 GALVANISED EQUAL TEE, HD, 50MM EA 10
11 GALVANISED ELBOW, HD, 50MM EA 40
12 GALVANISED NIPPLE, HD, 50MM EA 60
13 PVC ADAPTOR-GLUE 63*75*2, PN16 EA 3
14 PVC ADAPTOR TEE-GLUE 63* 2", PN16 EA 3
15 ACCESSORIES EA 2
16

SUBMAIN PVC PIPES


1 PIPE UPVC 50 CLASS 6 MTR 240
2 ACCESSORIES fittings LS 1
3

DRIP SYSTEM
DRIP PIPE 1.0L/H @ 0.3CM SP, 0.60MM MIN WALL THICKNESS, VIRGIN MATERIAL,
1 4 YR WARRANTY MTR 10000
2 PE IRRIGATION PIPE 16/4 100M MTR 200
3 START CONN-PVC BARB 16 W/SEAL- MT EA 200
4 END LINE (DOUBLE O) 16/17 EA 200
5 BARB 16 COUPLING CONN. 1UNIT EA 200
6 BARB 16 W/FLARE COUPLING EA 200
7
COLLECTION

SITE: SIAKASIPA KAZUNGULA DISTRICT

ITEM DESCRIPTION UNIT QTY

1 DRIP IRRIGATION SYSTEM 1ha

The contractor is expected to supply, construct, commission the 1ha drip irrigation system

A Excavating trenches not exceeding 0.80m deep and


average depth 600mm starting from existing ground level
to receive service pipes, including grading bottoms,
earthwork supports, backfilling with excavated material,
disposing of surplus excavated material off site m 400

B Extra over excavating in hard rock m³ 100

Polyvinyl Chloride class 6, PVC pipes, fittings


and jointing as described

FILTER
1 DISC FILTER 130 MICRONS, 3" EA 1
2 ACCESSORIES incl valves, fittings, risers etc EA 1
3 TOTAL PER GROUP

Page 20
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY

MAINLINE & SUBMAIN FITTINGS


1 PIPE PVC 63 W/SEAL CLASS 6 MTR 204
2 GALVANISED UNION WITH O-RING, HD 50MM EA 10
3 PVC VALVE PLAIN 50 EA 10
4 PVC 90 DEG TEE GLUE 63 EA 4
5 PVC ADAPTOR GLUE 50*63*2", PN16 EA 10
6 PVC END CAP PN16 EA 10
7 PVC 63MM SOCKET PN16 EA 8
8 NAVC 10 2" COMBINATION AV PN10 BSP EA 2
9 GALVANISED RISER 2" X 75MM, HD EA 30
10 GALVANISED EQUAL TEE, HD, 50MM EA 10
11 GALVANISED ELBOW, HD, 50MM EA 40
12 GALVANISED NIPPLE, HD, 50MM EA 60
13 PVC ADAPTOR-GLUE 63*75*2, PN16 EA 3
14 PVC ADAPTOR TEE-GLUE 63* 2", PN16 EA 3
15 ACCESSORIES EA 2
16 TOTAL PER GROUP

SUBMAIN PVC PIPES


1 PIPE UPVC 50 CLASS 6 MTR 240
2 ACCESSORIES fittings LS 1
3 TOTAL PER GROUP

DRIP SYSTEM
DRIP PIPE 1.0L/H @ 0.3CM SP, 0.60MM MIN WALL THICKNESS, VIRGIN MATERIAL,
1 4 YR WARRANTY MTR 10000
2 PE IRRIGATION PIPE 16/4 100M MTR 200
3 START CONN-PVC BARB 16 W/SEAL- MT EA 200
4 END LINE (DOUBLE O) 16/17 EA 200
5 BARB 16 COUPLING CONN. 1UNIT EA 200
6 BARB 16 W/FLARE COUPLING EA 200
7 TOTAL PER GROUP
To Collection

COLLECTION DRIP IRRIGATION TO MAIN SUMMARY

7.0 CONSTRUCTION OF SOLAR SYSTEMS

SITE: SINDE KAZUNGULA DISTRICT


3 BOREHOLES
No. ITEM UNIT QTY

SOLAR PUMP STRUCTURE


Excavation(Provisional)

A SOLAR PUMP AND STRUCTURE

Excavation(Provisional)

Excavation including maintaining and supporting sides and keeping free from water, mud
and fallen materials by bailing, pumping or otherwise

A1 Prepare site by stripping top 200 mm of soil to remove all debris including sand (if any)
m2 70
from site and carting away spoil

A2 Pit excavation commencing at reduced levels depth not exceeding 1.50m deep
m3 2

A3 Remove surplus excavated material from site m3 0.50

A4 Backfill around foundation m3 2

Concrete work

Page 21
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY

Reinforced Concrete class 25

A5 Concrete pad with surface steel trowelled smooth m3 0.13

Reinforcement

A6 Reinforcement bars (all sizes) kg 35

Sawn formwork

A7 Formwork to sides m 2

Structural steelwork

A8 Supply, fabricate and erect the following framed structural steelwork; complete with and
including all welded and bolted connections; and including one shop coat red oxide, zinc
chromate or similar and approved primer and 2 finishing coats of gloss oil paint after 1
erection: refer to DWG #1 attached

A9 Solar panels support structure constructed according to design including anti theft U-
channels 50mm x 50mm, including Aluminium U 3mm channel, 7mm angle lines, sum 1

Warranty (months): 12

Supply and Installation of Solar Powered Pump


A10 2HP DC Solar Submersible Pump CW Control Panel ea 3

A11 4.0 mm submersible cable 3-core m 300

A12 Joint kit ea 3

A13 INVT prewired DC/AC controller w/protection ea 3

A14 345W solar modules, voc 46.4v +/-3% OR alternative module combination
ea 24

A15 40mm HDPE poly pipe class 9 x 100m ea 4

A16 40mm HDPE poly pipe class 6 x 100m ea 8

A17 40mm x 1.1/2" poly adapter ea 12

A18 2" well seal complete (union, tee and Elbow etc) ea 4

A19 Cable ties packets ea 4

A20 6mm earth wire m 40

A21 50mm compression couplers ea 16

A22 Miscelleaneous ( bolts, thread tape etc) items 3

A23 Installation of solar kit and pipework from borehole to tanks ea 3

A24 Borehole flushing and testing ea 3

TOTAL CARRIED TO SUMMARY

SITE: SIAKASIPA KAZUNGULA DISTRICT


3 BOREHOLES
No. ITEM UNIT QTY

SOLAR PUMP STRUCTURE


Excavation(Provisional)

Page 22
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY


A SOLAR PUMP AND STRUCTURE

Excavation(Provisional)

Excavation including maintaining and supporting sides and keeping free from water, mud
and fallen materials by bailing, pumping or otherwise

A1 Prepare site by stripping top 200 mm of soil to remove all debris including sand (if any)
m2 60
from site and carting away spoil

A2 Pit excavation commencing at reduced levels depth not exceeding 1.50m deep
m3 2

A3 Remove surplus excavated material from site m3 0.50

A4 Backfill around foundation m3 2

Concrete work

Reinforced Concrete class 25

A5 Concrete pad with surface steel trowelled smooth m3 0.13

Reinforcement

A6 Reinforcement bars (all sizes) kg 35

Sawn formwork

A7 Formwork to sides m 2

Structural steelwork

A8 Supply, fabricate and erect the following framed structural steelwork; complete with and
including all welded and bolted connections; and including one shop coat red oxide, zinc
chromate or similar and approved primer and 2 finishing coats of gloss oil paint after 1
erection: refer to DWG #1 attached

A9 Solar panels support structure constructed according to design including anti theft U-
channels 50mm x 50mm, including Aluminium U 3mm channel, 7mm angle lines, sum 1

Warranty (months): 12

Supply and Installation of Solar Powered Pump


A 2HP DC Solar Submersible Pump CW Control Panel ea 3

B 4.0mm submersible cable 3-core m 200

C Joint kit ea 3

D 550W solar modules, Monocrystalline, 49.9 VoC DC OR alternative module combination ea


8

E 40mm HDPE poly pipe class 9 x 100m ea 3

F 40mm HDPE poly pipe class 6 x 100m ea 4

G 40mm x 1 1/4" poly adapter ea 3

H 1 1/4" well seal complete (union, tee and Elbow etc) ea 3

I Cable ties packets ea 2

J 6mm earth wire m 30

K 32mm compression couplers ea 12

Page 23
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY


L Miscelleaneous ( i.e sundries, bolts, thread tape etc) items 2

M Installation ea 1

N Borehole flushing ea 3

O Borehole pump test ea 3

TOTAL CARRIED TO SUMMARY

SITE: MANYEMUNYEMU KAZUNGULA DISTRICT


1 BOREHOLES
No. ITEM UNIT QTY

SOLAR PUMP STRUCTURE


Excavation(Provisional)

A SOLAR PUMP AND STRUCTURE

Excavation(Provisional)

Excavation including maintaining and supporting sides and keeping free from water, mud
and fallen materials by bailing, pumping or otherwise

A1 Prepare site by stripping top 200 mm of soil to remove all debris including sand (if any)
m2 10
from site and carting away spoil

A2 Pit excavation commencing at reduced levels depth not exceeding 1.50m deep
m3 2

A3 Remove surplus excavated material from site m3 2.00

A4 Backfill around foundation m3 4

Concrete work

Reinforced Concrete class 25

A5 Concrete pad with surface steel trowelled smooth m3 0.26

Reinforcement

A6 Reinforcement bars (all sizes) kg 30

Sawn formwork

A7 Formwork to sides m 4

Structural steelwork

A8 Supply, fabricate and erect the following framed structural steelwork; complete with and
including all welded and bolted connections; and including one shop coat red oxide, zinc
chromate or similar and approved primer and 2 finishing coats of gloss oil paint after 1
erection: refer to DWG #1 attached

A9 Solar panels support structure constructed according to design including anti theft U-
channels 50mm x 50mm, including Aluminium U 3mm channel, 7mm angle lines, sum 1

Warranty (months): 12

Supply and Installation of Solar Powered Pump


A 1HP DC Solar Submersible Pump CW Control Panel ea 1

B 4 mm submersible cable 3-core m 100

Page 24
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY


C Joint kit ea 4

D 550W solar modules, Monocrystalline, 49.9 VoC DC OR alternative module combination ea


4

E 32mm HDPE poly pipe class 9 x 100m ea 1

F 32mm HDPE poly pipe class 6 x 100m ea 2

G 32mm x 1 1/4" poly adapter ea 4

H 1 1/4" well seal complete (union, tee and Elbow etc) ea 1

I Cable ties packets ea 2

J 6mm earth wire m 40

K 32mm compression couplers ea 12

L Miscelleaneous ( i.e sundries, bolts, thread tape etc) items 1

M Installation ea 1

N Borehole flushing ea 1

O Borehole pump test ea 1

TOTAL CARRIED TO SUMMARY

SOLAR SYSTEM - TOTAL CARRIED TO MAIN SUMMARY

7.0 PRIME
COSTS

DESCRIPTION UNIT QTY

Include the following NET Provisional Sums


to be expended by Ministry of Agriculture
or omitted if not expended without any claim for loss
of profit

1 ALLOW the provisional sum at K300,000 to cover incidentals, complete ea 1


cost of incorporating materials into the
works including delivery of materials to site,
off-loading, storing, checking replacing defective
items, establishment charges all transport and
for installation of materials on site and all
contractor's overheads and profit

2 To add contigency sum at 10% of the bill ea 1

PROVISIONAL AND PRIME COST SUMS


TOTAL CARRIED TO SUMMARY

SUMMARY

Sl.No. ITEM

1 PRELIMINARIES AND GENERAL ITEMS

2 CONSTRUCTION OF A STEEL WATER TANK TO HOIST LITRE POLY WATER TANK

Page 25
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

ITEM DESCRIPTION UNIT QTY

3 4 POINT WATER KIOSK

4 WATER TROUGHS

5 FENCING

6 DRIP IRRIGATION

7 SOLAR SYSTEM & STRUCTURE

8 PRIME COSTS

9 TOTAL

Page 26
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 27
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 28
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE


0

Page 29
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 30
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 31
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 32
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 33
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0

0
0

Page 34
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0
0
0

0
0
0
0
0
0
0

Page 35
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0

0
0

Page 36
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0
0
0

0
0
0
0
0
0
0

Page 37
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0

0
0

Page 38
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0
0
0

0
0
0
0
0
0
0

Page 39
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE


0

Page 40
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0
0
0
0
0

Page 41
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0
0
0
0
0

Page 42
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 43
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0

0
0
0
0
0
0

Page 44
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 45
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0

0
0
0
0
0
0

0
0

Page 46
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0

0
0
0
0
0
0

Page 47
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 48
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 49
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE


0

Page 50
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE


0

RATE AMOUNT

AMOUNT

Page 51
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 52
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
APPENDI THE SCRALA PROJECT
X H: BILL
OF
QUANTIT
IES LOT
5 ITEM DESCRIPTION UNIT QTY
GWEMB
E 1.00 PRELIMINARIES AND GENERAL ITEMS

NOTE: The value of preliminaries and general items shall not exceed 5% of the value of measured works
of the project

i) Site Mobilization Item 1

The contractor shall set up the site working areas and storage facilities as may be deemed necessary
including all required site mobilization activities not mentioned below

ii) Site Billboard, Site hoarding and Site Meetings Item 1

The contractor shall fabricate and errect a project billboard, site hoarding during the construction of the
water tank stand, and shall allow for all expenses associated with convening and attending site progress
meetings with client's staff and stage inspection of works quality and progress .

iv) Contractor's Demobilization and handover Item 1

The contractor shall upon completion of the works remove all equipment, tools and remaining materials
and clean the site as may be approved by the Project Engineer

TOTAL P&Gs CARRIED TO GENERAL SUMMARY

2.00 CONSTRUCTION OF A STEEL WATER TANK TO HOIST LITRE POLY WATER TANK
No. ITEM UNIT QTY

No. ITEM UNIT QTY


KASONDE GWEMBE DISTRICT

A FOUNDATION AND EARTHWORKS

Site Preparation

1 Clear site of bushes, shrubs undergrowth and the like


including cutting down trees not exceeding 600mm
girth and grub up roots m2 200

2 Excavating Base Pit commencing at reduced level depth


not exceeding 1.5m starting from formation level m3 20

3 Extra over excavating in hard rock m3 3

Backfilling and Disposal

4 Backfilling around foundations and compacting loose


soils in 150mm layers upto 1.5m height on reduced level m3 9

5 Redig from spoil heap and remove off site m3 11

B CONCRETE WORKS

Preamble

All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.

Plain in-situ concrete Grade 15

1 50mm thick Blinding below column bases m2 12

Reinforced concrete C30 in

2 Column bases m3 6

Page 53
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY


3 Stub Columns m3 1

4 Ground beam m3 2

C STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.

1 8mm bars Kg 81

High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.

2 16mm diameter bars Kg 793

Sl.No. ITEM UNIT QTY

D FORMWORK

Smooth off shutter concrete formwork including


making good exposed surfaces after removal as described
to:

1 Sides of stub column m2 13

2 Sides and soffits of ground beams m2 17

E STRUCTURAL STEELWORK

Preamble

All structural steel shall be Grade S275, in accordance with with B.S 5950, all welds to be 6mm
continous weld or as described; in accordance with BS 1856 and 2642, and shall be given a coat of SF
Utra - Thin Fire Retardant.

All rates shall include the cost of fabrication, installation, assemby,errection and where necessary testing;
and all other associated costs to render the design functional as described

1 IPE 160 Stanchions Kg 758

2 UB 254 x 146 x 31 Primary Beams Kg 434

3 IPE 200 x 22.4 for Secondary Beams Kg 1047

4 80 x 80 x 6 for Ties Kg 299

5 70 x 70 x6 for Bracing Kg 1213

6 70 x 70 x 6 RSA for railing support Kg 295

33.7mm dia. x 2.6mm CHS hand rails (2.4 Kg/m)


7 Kg 108

8 20mm base plate Kg 151

9 16mm base plates Kg 86

10 8mm MS Plates Kg 784

11 M20 x 60mm Gr. 8.8 Bolts & Nuts No. 36

12 M16 x 50mm Gr. 8.8 Bolts & Nuts No. 420

13 M20 x 1m Gr. 8.8 HD Bolts No. 24

Page 54
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY


14 150x75mm Tank decking HW timber m 37

15 Fabricate ladder and install as described (Provisional sum) m 1

16 484 Expanded diamond mesh for catwalk m2 18

Touch up approved anti corrosion paint primer, and two more coats on all steelworks;
17 General surfaces of steelwork in green colour (Provisional Sum) item 1

F WATER TANK

1 Supply and fix 10,000 litres capacity polycon water


tank hoisted on tank stand ( measured seperately)
complete with automatic float switch, ball valves, filters
and connecting pipes inlet and outlet and overflow No. 2

CONSTRUCTION OF TANK STAND AND 2NO POLY


TANKS- TOTAL CARRIED TO SUMMARY

ULIGOKEZYA SITE

A FOUNDATION AND EARTHWORKS

Site Preparation

1 Clear site of bushes, shrubs undergrowth and the like


including cutting down trees not exceeding 600mm
girth and grub up roots m2 200

2 Excavating Base Pit commencing at reduced level depth


not exceeding 1.5m starting from formation level m3 20

3 Extra over excavating in hard rock m3 3

Backfilling and Disposal

4 Backfilling around foundations and compacting loose


soils in 150mm layers upto 1.5m height on reduced level m3 9

5 Redig from spoil heap and remove off site m3 11

B CONCRETE WORKS

Preamble

All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.

Plain in-situ concrete Grade 15

1 50mm thick Blinding below column bases m2 12

Reinforced concrete C30 in

2 Column bases m3 6

3 Stub Columns m3 1

4 Ground beam m3 2

C STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.

Page 55
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY


1 8mm bars Kg 81

High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.

2 16mm diameter bars Kg 793

Sl.No. ITEM UNIT QTY

D FORMWORK

Smooth off shutter concrete formwork including


making good exposed surfaces after removal as described
to:

1 Sides of stub column m2 13

2 Sides and soffits of ground beams m2 17

E STRUCTURAL STEELWORK

Preamble

All structural steel shall be Grade S275, in accordance with with B.S 5950, all welds to be 6mm
continous weld or as described; in accordance with BS 1856 and 2642, and shall be given a coat of SF
Utra - Thin Fire Retardant.

All rates shall include the cost of fabrication, installation, assemby,errection and where necessary testing;
and all other associated costs to render the design functional as described

1 IPE 160 Stanchions Kg 758

2 UB 254 x 146 x 31 Primary Beams Kg 434

3 IPE 200 x 22.4 for Secondary Beams Kg 1047

4 80 x 80 x 6 for Ties Kg 299

5 70 x 70 x6 for Bracing Kg 1213

6 70 x 70 x 6 RSA for railing support Kg 295

33.7mm dia. x 2.6mm CHS hand rails (2.4 Kg/m)


7 Kg 108

8 20mm base plate Kg 151

9 16mm base plates Kg 86

10 8mm MS Plates Kg 784

11 M20 x 60mm Gr. 8.8 Bolts & Nuts No. 36

12 M16 x 50mm Gr. 8.8 Bolts & Nuts No. 420

13 M20 x 1m Gr. 8.8 HD Bolts No. 24

14 150x75mm Tank decking HW timber m 37

15 Fabricate ladder and install as described (Provisional sum) m 1

16 484 Expanded diamond mesh for catwalk m2 18

Touch up approved anti corrosion paint primer, and two more coats on all steelworks;
17 General surfaces of steelwork in green colour (Provisional Sum) item 1

Page 56
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY


F WATER TANK

1 Supply and fix 10,000 litres capacity polycon water


tank hoisted on tank stand ( measured seperately)
complete with automatic float switch, ball valves, filters
and connecting pipes inlet and outlet and overflow No. 2

CONSTRUCTION OF TANK STAND AND 2NO POLY


TANKS- TOTAL CARRIED TO SUMMARY

TEBE SITE

A FOUNDATION AND EARTHWORKS

Site Preparation

1 Clear site of bushes, shrubs undergrowth and the like


including cutting down trees not exceeding 600mm
girth and grub up roots m2 200

2 Excavating Base Pit commencing at reduced level depth


not exceeding 1.5m starting from formation level m3 20

3 Extra over excavating in hard rock m3 3

Backfilling and Disposal

4 Backfilling around foundations and compacting loose


soils in 150mm layers upto 1.5m height on reduced level m3 9

5 Redig from spoil heap and remove off site m3 11

B CONCRETE WORKS

Preamble

All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.

Plain in-situ concrete Grade 15

1 50mm thick Blinding below column bases m2 12

Reinforced concrete C30 in

2 Column bases m3 6

3 Stub Columns m3 1

4 Ground beam m3 2

C STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.

1 8mm bars Kg 81

High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.

2 16mm diameter bars Kg 793

Page 57
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY

Sl.No. ITEM UNIT QTY

D FORMWORK

Smooth off shutter concrete formwork including


making good exposed surfaces after removal as described
to:

1 Sides of stub column m2 13

2 Sides and soffits of ground beams m2 17

E STRUCTURAL STEELWORK

Preamble

All structural steel shall be Grade S275, in accordance with with B.S 5950, all welds to be 6mm
continous weld or as described; in accordance with BS 1856 and 2642, and shall be given a coat of SF
Utra - Thin Fire Retardant.

All rates shall include the cost of fabrication, installation, assemby,errection and where necessary testing;
and all other associated costs to render the design functional as described

1 IPE 160 Stanchions Kg 758

2 UB 254 x 146 x 31 Primary Beams Kg 434

3 IPE 200 x 22.4 for Secondary Beams Kg 1047

4 80 x 80 x 6 for Ties Kg 299

5 70 x 70 x6 for Bracing Kg 1213

6 70 x 70 x 6 RSA for railing support Kg 295

33.7mm dia. x 2.6mm CHS hand rails (2.4 Kg/m)


7 Kg 108

8 20mm base plate Kg 151

9 16mm base plates Kg 86

10 8mm MS Plates Kg 784

11 M20 x 60mm Gr. 8.8 Bolts & Nuts No. 36

12 M16 x 50mm Gr. 8.8 Bolts & Nuts No. 420

13 M20 x 1m Gr. 8.8 HD Bolts No. 24

14 150x75mm Tank decking HW timber m 37

15 Fabricate ladder and install as described (Provisional sum) m 1

16 484 Expanded diamond mesh for catwalk m2 18

Touch up approved anti corrosion paint primer, and two more coats on all steelworks;
17 General surfaces of steelwork in green colour (Provisional Sum) item 1

F WATER TANK

1 Supply and fix 10,000 litres capacity polycon water


tank hoisted on tank stand ( measured seperately)
complete with automatic float switch, ball valves, filters
and connecting pipes inlet and outlet and overflow No. 2

Page 58
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY


CONSTRUCTION OF TANK STAND AND 2NO POLY
TANKS- TOTAL CARRIED TO SUMMARY

3.0 CONSTRUCTION OF WATER KIOSKS

TEBE SITE
No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS

Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 140
cutting down trees not exceeding 600mm girth and grub
up roots

Unless otherwise stated excavations shall be in 'pickable' material.


Excavations and Earthworks
Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Kiosk apron, pipe trenches and soak pit m3 26

Refilling of foundation hardcore base with approved laterite in layers of 150mm thick including
compaction and consolidation etc., all complete as directed by the Engineer-in-Charge.

3 i) Below Kiosk apron m3 15.0

FOUNDATION AND EARTHWORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


B STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
i)
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.
For Substructure works:
3 i) 12mm dia. As Y12 in apron Kg 355

STEEL REINFORCEMENT FOR CONCRETE- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


C CONCRETE WORKS

All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R cement, 20mm graded
granite aggregated and quarry dust; thickness as required including compacting, curing, formwork etc.,
complete as directed by the Resident Engineer
i) Below Kiosk apron m3 2.00

All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
Rate should include all formwork
For Substructure works:
ii) in Apron and ramps m3 4.00

Formwork
Sawn formwork; to:
iii) Sides of apron concrete m2 4

CONCRETE WORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


D BRICKWORK AND MASONRY
Blockwork in concrete blocks not less than 10N/mm2 in crushing strength cement mortar (1:3); and
filled with C15 concrete in:
For Substructure works:
i) 200 mm Kiosk blockwork m2 6

Page 59
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY


ii) 200 mm Kiosk Soak Pit honeycomb m2 10

Two strand 3.25 mm diameter high tensile steel wire wall reinforcement; 100 mm laps (measured net: no
allowance made for laps); every course; in
Kiosk blockwork:
iii) 200 mm block wall. m 20
iv) 200 mm Kiosk Soak Pit honeycomb m2 38
BRICKWORK AND MASONRY - TOTAL CARRIED TO SUMMARY

E PLASTERING AND FLOORING


Cement mortar (1:4) plastering 10mm thick over concrete and blockwork surface and concrete apron to
be finished even and smooth with steel float trowel; all complete as directed by the Resident Engineer.
i) Apron Flooring m2 23

ii) Kiosk Blockwork m2 9

iii) Kiosk Soak Pit honeycomb m2 45

PLASTERING AND FLOORING - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


1.1 PLUMBING INSTALLATION

Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)

Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.

Galvanised mild steel pipework, medium weight, imbeded in blockwork at construction

i) 19 mm Diameter pipe to walls and slab underside m 2


ii) 25 mm Diameter pipe to walls and slab underside m 15
iii) Allow for Extra for all fittings in diameter 19 mm No. 12
iv) Allow for Extra for all fittings in pipe diameter 25 mm No. 5

Equipment
Include for making chases and holes in walls, existing slab and breaking existing slab where necessary
v) Item 1
and making good walls, slab and finishings.

PLUMBING INSTALLATION - TOTAL CARRIED TO SUMMARY

SUMMARY

Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
D BRICKWORK AND MASONRY
E PLASTERING AND FLOORING
F PLUMBING INSTALLATION
TO COLLECTIONS

SITE: KASONDE GWEMBE DISTRICT


No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS

Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 140
cutting down trees not exceeding 600mm girth and grub
up roots

Unless otherwise stated excavations shall be in 'pickable' material.


Excavations and Earthworks
Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Kiosk apron, pipe trenches and soak pit m3 26

Refilling of foundation hardcore base with approved laterite in layers of 150mm thick including
compaction and consolidation etc., all complete as directed by the Engineer-in-Charge.

Page 60
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY

3 i) Below Kiosk apron m3 15.0

FOUNDATION AND EARTHWORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


B STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
i)
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.
For Substructure works:
3 i) 12mm dia. As Y12 in apron Kg 355

STEEL REINFORCEMENT FOR CONCRETE- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


C CONCRETE WORKS

All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R cement, 20mm graded
granite aggregated and quarry dust; thickness as required including compacting, curing, formwork etc.,
complete as directed by the Resident Engineer
i) Below Kiosk apron m3 2.00

All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
Rate should include all formwork
For Substructure works:
ii) in Apron and ramps m3 4.00

Formwork
Sawn formwork; to:
iii) Sides of apron concrete m2 4

CONCRETE WORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


D BRICKWORK AND MASONRY
Blockwork in concrete blocks not less than 10N/mm2 in crushing strength cement mortar (1:3); and
filled with C15 concrete in:
For Substructure works:
i) 200 mm Kiosk blockwork m2 6
ii) 200 mm Kiosk Soak Pit honeycomb m2 10

Two strand 3.25 mm diameter high tensile steel wire wall reinforcement; 100 mm laps (measured net: no
allowance made for laps); every course; in
Kiosk blockwork:
iii) 200 mm block wall. m 20
iv) 200 mm Kiosk Soak Pit honeycomb m2 38
BRICKWORK AND MASONRY - TOTAL CARRIED TO SUMMARY

E PLASTERING AND FLOORING


Cement mortar (1:4) plastering 10mm thick over concrete and blockwork surface and concrete apron to
be finished even and smooth with steel float trowel; all complete as directed by the Resident Engineer.
i) Apron Flooring m2 23

ii) Kiosk Blockwork m2 9

iii) Kiosk Soak Pit honeycomb m2 45

PLASTERING AND FLOORING - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


1.1 PLUMBING INSTALLATION

Page 61
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY


Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)

Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.

Galvanised mild steel pipework, medium weight, imbeded in blockwork at construction

i) 19 mm Diameter pipe to walls and slab underside m 2


ii) 25 mm Diameter pipe to walls and slab underside m 15
iii) Allow for Extra for all fittings in diameter 19 mm No. 12
iv) Allow for Extra for all fittings in pipe diameter 25 mm No. 5

Equipment
Include for making chases and holes in walls, existing slab and breaking existing slab where necessary
v) Item 1
and making good walls, slab and finishings.

PLUMBING INSTALLATION - TOTAL CARRIED TO SUMMARY

SUMMARY

Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
D BRICKWORK AND MASONRY
E PLASTERING AND FLOORING
F PLUMBING INSTALLATION
TO COLLECTIONS

ULIGOKEZYA SITE
No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS

Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including
cutting down trees not exceeding 600mm girth and grub
up roots m2 140

Unless otherwise stated excavations shall be in 'pickable' material.


Excavations and Earthworks
Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Kiosk apron, pipe trenches and soak pit m3 26

Refilling of foundation hardcore base with approved laterite in layers of 150mm thick including
compaction and consolidation etc., all complete as directed by the Engineer-in-Charge.

3 i) Below Kiosk apron m3 15.0

FOUNDATION AND EARTHWORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


B STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
i)
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.
For Substructure works:
3 i) 12mm dia. As Y12 in apron Kg 355

STEEL REINFORCEMENT FOR CONCRETE- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


C CONCRETE WORKS

Page 62
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY

All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R cement, 20mm graded
granite aggregated and quarry dust; thickness as required including compacting, curing, formwork etc.,
complete as directed by the Resident Engineer
i) Below Kiosk apron m3 2.00

All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
Rate should include all formwork
For Substructure works:
ii) in Apron and ramps m3 4.00

Formwork
Sawn formwork; to:
iii) Sides of apron concrete m2 4

CONCRETE WORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


D BRICKWORK AND MASONRY
Blockwork in concrete blocks not less than 10N/mm2 in crushing strength cement mortar (1:3); and
filled with C15 concrete in:
For Substructure works:
i) 200 mm Kiosk blockwork m2 6
ii) 200 mm Kiosk Soak Pit honeycomb m2 10

Two strand 3.25 mm diameter high tensile steel wire wall reinforcement; 100 mm laps (measured net: no
allowance made for laps); every course; in
Kiosk blockwork:
iii) 200 mm block wall. m 20
iv) 200 mm Kiosk Soak Pit honeycomb m2 38
BRICKWORK AND MASONRY - TOTAL CARRIED TO SUMMARY

E PLASTERING AND FLOORING


Cement mortar (1:4) plastering 10mm thick over concrete and blockwork surface and concrete apron to
be finished even and smooth with steel float trowel; all complete as directed by the Resident Engineer.
i) Apron Flooring m2 23

ii) Kiosk Blockwork m2 9

iii) Kiosk Soak Pit honeycomb m2 45

PLASTERING AND FLOORING - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


1.1 PLUMBING INSTALLATION

Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)

Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.

Galvanised mild steel pipework, medium weight, imbeded in blockwork at construction

i) 19 mm Diameter pipe to walls and slab underside m 2


ii) 25 mm Diameter pipe to walls and slab underside m 15
iii) Allow for Extra for all fittings in diameter 19 mm No. 12
iv) Allow for Extra for all fittings in pipe diameter 25 mm No. 5

Equipment
Include for making chases and holes in walls, existing slab and breaking existing slab where necessary
v) Item 1
and making good walls, slab and finishings.

PLUMBING INSTALLATION - TOTAL CARRIED TO SUMMARY

SUMMARY

Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE

Page 63
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY


C CONCRETE WORKS
D BRICKWORK AND MASONRY
E PLASTERING AND FLOORING
F PLUMBING INSTALLATION
TO COLLECTIONS

SUMMARY TO MAIN - KIOSKS

4.0 CONSTRUCTION OF WATER TROUGHS

SITE: KASONDE GWEMBE DISTRICT


No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS

Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 384
cutting down trees not exceeding 600mm girth and grub
up roots

Unless otherwise stated excavations shall be in 'pickable' material.


Excavations and Earthworks
Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Cattle Water Trough apron and pipe trenches m3 40

Refilling of foundation hardcore base with approved laterite in layers of 150mm thick including
compaction and consolidation etc., all complete as directed by the Engineer-in-Charge.

3 i) Below Cattle Water Trough apron m3 40.0

FOUNDATION AND EARTHWORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


B STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
i) 3.2mm dia , 150 BRC heavy duty conforce wire in apron slab m2 120
ii)
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.

3 i) 10mm dia. As Y10 in trough stem concrete Kg 586

STEEL REINFORCEMENT FOR CONCRETE- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


C CONCRETE WORKS

All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R cement, 20mm graded
granite aggregated and quarry dust; thickness as required including compacting, curing, formwork etc.,
complete as directed by the Resident Engineer
i) Below Cattle Water Trough apron m3 7.00

All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
Formwork rates to include all supports and jointing to required to assemble sound formwork necessary to
achieve and form described concrete geometry
For Substructure works:
ii) in Cattle Water Trough Apron m3 23.00

Formwork
Sawn formwork; to:
iii) Sides of trough stem concrete m2 64

CONCRETE WORKS - TOTAL CARRIED TO SUMMARY

Page 64
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY

Sl.No. ITEM UNIT QTY


E TROUGH GROUTING AND SEALING
10mm thick Cement grouting mortar (1:2) to be rendered to the interior of the water trough over concrete
surface; smooth with steel float trowel; all complete as directed by the Resident Engineer.

i) Grout to interior surfaces of water troughs m2 116

TROUGH GROUTING AND SEALING- TOTAL CARRIED TO SUMMARY

F PLUMBING INSTALLATIONS

Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.

Galvanised mild steel pipework, medium weight, imbeded in blockwork at construction

i) 25 mm Diameter pipe to walls and slab underside m 20


ii) Allow for Extra for all fittings in pipe diameter 25 mm No. 5

Supply and installation of ball-floater automated water opening and closing mechanism, including all
iii) L.S.
associated fixture to render installation functional (Provisional Sum only)
1

Equipment
iv) Include for making chases and holes in walls, existing slab and breaking slab where necessary and making Item 1

Supply and install, 50mm dia. uPVC pipes including all fittings to render the installation functional as
v) m 180
described; in accordance with ASMD - 1785 or equal and approved standard

PLUMBING INSTALLATIONS - TOTAL CARRIED TO SUMMARY

SUMMARY

A FOUNDATION AND EARTHWORKS


B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
E TROUGH GROUTING AND SEALING
F PLUMBING INSTALLATIONS
To collections

ULIGOKEZYA SITE GWEMBE DISTRICT


No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS

Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 384
cutting down trees not exceeding 600mm girth and grub
up roots

Unless otherwise stated excavations shall be in 'pickable' material.


Excavations and Earthworks
Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Cattle Water Trough apron and pipe trenches m3 40

Refilling of foundation hardcore base with approved laterite in layers of 150mm thick including
compaction and consolidation etc., all complete as directed by the Engineer-in-Charge.

3 i) Below Cattle Water Trough apron m3 40.0

FOUNDATION AND EARTHWORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY

Page 65
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY


B STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
i) 3.2mm dia , 150 BRC heavy duty conforce wire in apron slab m2 120
ii)
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.

3 i) 10mm dia. As Y10 in trough stem concrete Kg 586

STEEL REINFORCEMENT FOR CONCRETE- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


C CONCRETE WORKS

All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R cement, 20mm graded
granite aggregated and quarry dust; thickness as required including compacting, curing, formwork etc.,
complete as directed by the Resident Engineer
i) Below Cattle Water Trough apron m3 7.00

All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
Formwork rates to include all supports and jointing to required to assemble sound formwork necessary to
achieve and form described concrete geometry
For Substructure works:
ii) in Cattle Water Trough Apron m3 23.00

Formwork
Sawn formwork; to:
iii) Sides of trough stem concrete m2 64

CONCRETE WORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


E TROUGH GROUTING AND SEALING
10mm thick Cement grouting mortar (1:2) to be rendered to the interior of the water trough over concrete
surface; smooth with steel float trowel; all complete as directed by the Resident Engineer.

i) Grout to interior surfaces of water troughs m2 116

TROUGH GROUTING AND SEALING- TOTAL CARRIED TO SUMMARY

F PLUMBING INSTALLATIONS

Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.

Galvanised mild steel pipework, medium weight, imbeded in blockwork at construction

i) 25 mm Diameter pipe to walls and slab underside m 20


ii) Allow for Extra for all fittings in pipe diameter 25 mm No. 5

Supply and installation of ball-floater automated water opening and closing mechanism, including all
iii) L.S.
associated fixture to render installation functional (Provisional Sum only)
1

Equipment
iv) Include for making chases and holes in walls, existing slab and breaking slab where necessary and making Item 1

Supply and install, 50mm dia. uPVC pipes including all fittings to render the installation functional as
v) m 180
described; in accordance with ASMD - 1785 or equal and approved standard

PLUMBING INSTALLATIONS - TOTAL CARRIED TO SUMMARY

Page 66
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY


SUMMARY

A FOUNDATION AND EARTHWORKS


B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
E TROUGH GROUTING AND SEALING
F PLUMBING INSTALLATIONS
To collections

TEBE SITE GWEMBE


No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS

Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 384
cutting down trees not exceeding 600mm girth and grub
up roots

Unless otherwise stated excavations shall be in 'pickable' material.


Excavations and Earthworks
Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Cattle Water Trough apron and pipe trenches m3 40

Refilling of foundation hardcore base with approved laterite in layers of 150mm thick including
compaction and consolidation etc., all complete as directed by the Engineer-in-Charge.

3 i) Below Cattle Water Trough apron m3 40.0

FOUNDATION AND EARTHWORKS - TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


B STEEL REINFORCEMENT FOR CONCRETE

Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
i) 3.2mm dia , 150 BRC heavy duty conforce wire in apron slab m2 120
ii)
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.

3 i) 10mm dia. As Y10 in trough stem concrete Kg 586

STEEL REINFORCEMENT FOR CONCRETE- TOTAL CARRIED TO SUMMARY

Sl.No. ITEM UNIT QTY


C CONCRETE WORKS

All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R cement, 20mm graded
granite aggregated and quarry dust; thickness as required including compacting, curing, formwork etc.,
complete as directed by the Resident Engineer
i) Below Cattle Water Trough apron m3 7.00

All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
Formwork rates to include all supports and jointing to required to assemble sound formwork necessary to
achieve and form described concrete geometry
For Substructure works:
ii) in Cattle Water Trough Apron m3 23.00

Formwork
Sawn formwork; to:
iii) Sides of trough stem concrete m2 64

CONCRETE WORKS - TOTAL CARRIED TO SUMMARY

Page 67
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY

Sl.No. ITEM UNIT QTY


E TROUGH GROUTING AND SEALING
10mm thick Cement grouting mortar (1:2) to be rendered to the interior of the water trough over concrete
surface; smooth with steel float trowel; all complete as directed by the Resident Engineer.

i) Grout to interior surfaces of water troughs m2 116

TROUGH GROUTING AND SEALING- TOTAL CARRIED TO SUMMARY

F PLUMBING INSTALLATIONS

Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.

Galvanised mild steel pipework, medium weight, imbeded in blockwork at construction

i) 25 mm Diameter pipe to walls and slab underside m 20


ii) Allow for Extra for all fittings in pipe diameter 25 mm No. 5

Supply and installation of ball-floater automated water opening and closing mechanism, including all
iii) L.S.
associated fixture to render installation functional (Provisional Sum only)
1

Equipment
iv) Include for making chases and holes in walls, existing slab and breaking slab where necessary and making Item 1

Supply and install, 50mm dia. uPVC pipes including all fittings to render the installation functional as
v) m 180
described; in accordance with ASMD - 1785 or equal and approved standard

PLUMBING INSTALLATIONS - TOTAL CARRIED TO SUMMARY

SUMMARY

A FOUNDATION AND EARTHWORKS


B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
E TROUGH GROUTING AND SEALING
F PLUMBING INSTALLATIONS
To collections

MAIN SUMMARY CATTLE TROUGHS

5.0 CONSTRUCTION OF FENCING

SITE: ULIGOKEZYA GWEMBE DISTRICT


Sl.No. ITEM UNIT QTY
G FENCING INSTALLATION

Game wire fencing shall be 2.11m x 300mm 14W Wire VELDSPAN brand or equal and approved, with all
posts, steys and Y sections well anchored in to the ground by concreting with C20 concrete to resident
Engineer's approval, all complete with fence posts round 3.0m x 76mm MD, Fence Stey Round 3.0 x
38mm MD, all bolts, washers and nuts to render installation functional, fence standards Y sections 3.05m
at not more than 4.5m centres, Double 1.8 x 4.2m Fence Gate all complete with required Wire plains to
Engineers satisfaction
Supply and install 'game wire fencing' as described around the water tank and water kiosk facility around
i) 5 hactare plot m 1000
Supply and install double gate as described to allow for controlled access around the water tank and
ii) water kiosk facility around 5 hactare plot No. 1

FENCING INSTALLATION - TOTAL CARRIED TO SUMMARY

SITE: TEBE GWEMBE DISTRICT


Sl.No. ITEM UNIT QTY
G FENCING INSTALLATION

Page 68
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY

Game wire fencing shall be 2.11m x 300mm 14W Wire VELDSPAN brand or equal and approved, with all
posts, steys and Y sections well anchored in to the ground by concreting with C20 concrete to resident
Engineer's approval, all complete with fence posts round 3.0m x 76mm MD, Fence Stey Round 3.0 x
38mm MD, all bolts, washers and nuts to render installation functional, fence standards Y sections 3.05m
at not more than 4.5m centres, Double 1.8 x 4.2m Fence Gate all complete with required Wire plains to
Engineers satisfaction
Supply and install 'game wire fencing' as described around the water tank and water kiosk facility around
i) 5 hactare plot m 1000
Supply and install double gate as described to allow for controlled access around the water tank and
ii) water kiosk facility around 5 hactare plot No. 1

FENCING INSTALLATION - TOTAL CARRIED TO SUMMARY

SITE: KASONDE GWEMBE DISTRICT


Sl.No. ITEM UNIT QTY
G FENCING INSTALLATION

Game wire fencing shall be 2.11m x 300mm 14W Wire VELDSPAN brand or equal and approved, with all
posts, steys and Y sections well anchored in to the ground by concreting with C20 concrete to resident
Engineer's approval, all complete with fence posts round 3.0m x 76mm MD, Fence Stey Round 3.0 x
38mm MD, all bolts, washers and nuts to render installation functional, fence standards Y sections 3.05m
at not more than 4.5m centres, Double 1.8 x 4.2m Fence Gate all complete with required Wire plains to
Engineers satisfaction
Supply and install 'game wire fencing' as described around the water tank and water kiosk facility around
i) 5 hactare plot m 1000
Supply and install double gate as described to allow for controlled access around the water tank and
ii) water kiosk facility around 5 hactare plot No. 1

FENCING INSTALLATION - TOTAL CARRIED TO SUMMARY

CONSTRUCTION OF FENCING
TOTAL CARRIED TO SUMMARY

6.0 CONSTRUCTION OF IRRIGATION SYSTEMS

SITE: ULIGOKEZYA GWEMBE DISTRICT

ITEM DESCRIPTION UNIT QTY

1 DRIP IRRIGATION SYSTEM 2,5ha

The contractor is expected to supply, construct, commission the 2.5ha drip irrigation system
A Excavating trenches not exceeding 0.80m deep and
average depth 600mm starting from existing ground level
to receive service pipes, including grading bottoms,
earthwork supports, backfilling with excavated material,
disposing of surplus excavated material off site m 800

B Extra over excavating in hard rock m³ 100

Polyvinyl Chloride class 6, PVC pipes, fittings


and jointing as described

FILTER
1 DISC FILTER 130 MICRONS, 3" EA 2
2 ACCESSORIES incl valves, fittings, risers etc EA 1
3

MAINLINE & SUBMAIN FITTINGS


1 PIPE PVC 63 W/SEAL CLASS 6 MTR 300
2 GALVANISED UNION WITH O-RING, HD 50MM EA 10
3 GALVANISED VALVE 50MM COBRA OR EQUIVALENT EA 10
4 PVC 90 DEG TEE GLUE 63 EA 4
5 PVC ADAPTOR GLUE 50*63*2", PN16 EA 10
6 PVC END CAP PN16 EA 10
7 PVC 63MM SOCKET PN16 EA 8
8 NAVC 10 2" COMBINATION AV PN10 BSP EA 2
9 GALVANISED RISER 2" X 75MM, HD EA 30

Page 69
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY


10 GALVANISED EQUAL TEE, HD, 50MM EA 10
11 GALVANISED ELBOW, HD, 50MM EA 40
12 GALVANISED NIPPLE, HD, 50MM EA 60
13 PVC ADAPTOR-GLUE 63*75*2, PN16 EA 3
14 PVC ADAPTOR TEE-GLUE 63* 2", PN16 EA 3
15 ACCESSORIES EA 2
16

SUBMAIN PVC PIPES


1 PIPE UPVC 50 CLASS 6 MTR 520
2 ACCESSORIES fittings LS 1
3

DRIP SYSTEM
DRIP PIPE 1.0L/H @ 0.3CM SP, 0.60MM MIN WALL THICKNESS, VIRGIN MATERIAL, 4 YR
1 WARRANTY MTR 25,000
2 PE IRRIGATION PIPE 16/4 100M EA 10
3 START CONN-PVC BARB 16 W/SEAL- MT EA 1,100
4 END LINE (DOUBLE O) 16/17 EA 1,100
5 BARB 16 COUPLING CONN. 1UNIT EA 1,000
6 BARB 16 W/FLARE COUPLING EA 1,100
7

To Collection

SITE: TEBE GWEMBE DISTRICT

ITEM DESCRIPTION UNIT QTY

1 DRIP IRRIGATION SYSTEM 2.0ha

The contractor is expected to supply, construct, commission the 2.0ha drip irrigation system

A Excavating trenches not exceeding 0.80m deep and


average depth 600mm starting from existing ground level
to receive service pipes, including grading bottoms,
earthwork supports, backfilling with excavated material,
disposing of surplus excavated material off site m 800

B Extra over excavating in hard rock m³ 100

Polyvinyl Chloride class 6, PVC pipes, fittings


and jointing as described

FILTER
1 DISC FILTER 130 MICRONS, 3" EA 2
2 ACCESSORIES incl valves, fittings, risers etc EA 1
3

MAINLINE & SUBMAIN FITTINGS


1 PIPE PVC 63 W/SEAL CLASS 6 MTR 300
2 GALVANISED UNION WITH O-RING, HD 50MM EA 10
3 PVC VALVE PLAIN 50 EA 10
4 PVC 90 DEG TEE GLUE 63 EA 4
5 PVC ADAPTOR GLUE 50*63*2", PN16 EA 10
6 PVC END CAP PN16 EA 10
7 PVC 63MM SOCKET PN16 EA 8
8 NAVC 10 2" COMBINATION AV PN10 BSP EA 2
9 GALVANISED RISER 2" X 75MM, HD EA 30
10 GALVANISED EQUAL TEE, HD, 50MM EA 10
11 GALVANISED ELBOW, HD, 50MM EA 40
12 GALVANISED NIPPLE, HD, 50MM EA 60
13 PVC ADAPTOR-GLUE 63*75*2, PN16 EA 3
14 PVC ADAPTOR TEE-GLUE 63* 2", PN16 EA 3
15 ACCESSORIES EA 2
16

SUBMAIN PVC PIPES


1 PIPE UPVC 50 CLASS 6 MTR 520
2 ACCESSORIES fittings LS 1
3

DRIP SYSTEM

Page 70
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY


DRIP PIPE 1.0L/H @ 0.3CM SP, 0.60MM MIN WALL THICKNESS, VIRGIN MATERIAL, 4 YR
1 WARRANTY MTR 20000
2 PE IRRIGATION PIPE 16/4 100M EA 8
3 START CONN-PVC BARB 16 W/SEAL- MT EA 800
4 END LINE (DOUBLE O) 16/17 EA 800
5 BARB 16 COUPLING CONN. 1UNIT EA 800
6 BARB 16 W/FLARE COUPLING EA 800
7

To Collection

SITE: KASONDE GWEMBE DISTRICT

ITEM DESCRIPTION UNIT QTY

1 DRIP IRRIGATION SYSTEM 2.5ha

The contractor is expected to supply, construct, commission the 2.5ha drip irrigation system

A Excavating trenches not exceeding 0.80m deep and


average depth 600mm starting from existing ground level
to receive service pipes, including grading bottoms,
earthwork supports, backfilling with excavated material,
disposing of surplus excavated material off site m 800

B Extra over excavating in hard rock m³ 100

Polyvinyl Chloride class 6, PVC pipes, fittings


and jointing as described

FILTER
1 DISC FILTER 130 MICRONS, 3" EA 2
2 ACCESSORIES incl valves, fittings, risers etc EA 1
3 TOTAL PER GROUP

MAINLINE & SUBMAIN FITTINGS


1 PIPE PVC 63 W/SEAL CLASS 6 MTR 300
2 GALVANISED UNION WITH O-RING, HD 50MM EA 10
3 PVC VALVE PLAIN 50 EA 10
4 PVC 90 DEG TEE GLUE 63 EA 4
5 PVC ADAPTOR GLUE 50*63*2", PN16 EA 10
6 PVC END CAP PN16 EA 10
7 PVC 63MM SOCKET PN16 EA 8
8 NAVC 10 2" COMBINATION AV PN10 BSP EA 2
9 GALVANISED RISER 2" X 75MM, HD EA 30
10 GALVANISED EQUAL TEE, HD, 50MM EA 10
11 GALVANISED ELBOW, HD, 50MM EA 40
12 GALVANISED NIPPLE, HD, 50MM EA 60
13 PVC ADAPTOR-GLUE 63*75*2, PN16 EA 3
14 PVC ADAPTOR TEE-GLUE 63* 2", PN16 EA 3
15 ACCESSORIES EA 2
16 TOTAL PER GROUP

SUBMAIN PVC PIPES


1 PIPE UPVC 50 CLASS 6 MTR 520
2 ACCESSORIES fittings LS 1
3 TOTAL PER GROUP

DRIP SYSTEM
DRIP PIPE 1.0L/H @ 0.3CM SP, 0.60MM MIN WALL THICKNESS, VIRGIN MATERIAL, 4 YR
1 WARRANTY MTR 25000
2 PE IRRIGATION PIPE 16/4 100M EA 5
3 START CONN-PVC BARB 16 W/SEAL- MT EA 800
4 END LINE (DOUBLE O) 16/17 EA 800
5 BARB 16 COUPLING CONN. 1UNIT EA 800
6 BARB 16 W/FLARE COUPLING EA 800
7 TOTAL PER GROUP

To Collection

CONSTRUCTION OF DRIP IRRIGATION


TOTAL CARRIED TO SUMMARY

Page 71
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY


7.0 CONSTRUCTION OF SOLAR STRUCTURES

SITE: ULIGOKEZYA GWEMBE DISTRICT


4 BOREHOLES
No. ITEM UNIT QTY

SOLAR PUMP STRUCTURE


Excavation(Provisional)

A SOLAR PUMP AND STRUCTURE

Excavation(Provisional)

Excavation including maintaining and supporting sides and keeping free from water, mud and fallen
materials by bailing, pumping or otherwise

Prepare site by stripping top 200 mm of soil to remove all debris including sand (if any) from site and
A1 carting away spoil m2 60

A2 Pit excavation commencing at reduced levels depth not exceeding 1.50m deep m3 2

A3 Remove surplus excavated material from site m3 0.50

A4 Backfill around foundation m3 2

Concrete work

Reinforced Concrete class 25

A5 Concrete pad with surface steel trowelled smooth m3 0.13

Reinforcement

A6 Reinforcement bars (all sizes) kg 35

Sawn formwork

A7 Formwork to sides m 2

Structural steelwork

Supply, fabricate and erect the following framed structural steelwork; complete with and including all
welded and bolted connections; and including one shop coat red oxide, zinc chromate or similar and
A8 approved primer and 2 finishing coats of gloss oil paint after erection: refer to DWG #1 attached ea 1

Solar panels support structure constructed according to design including anti theft U-channels 50mm x
A9 50mm, including Aluminium U 3mm channel, 7mm angle lines, sum 1

Warranty (months): 12

Supply and Installation of Solar Powered Pump


A10 2HP Submersible, average yield 2L/S ea 4

A11 4.0 mm submersible cable 3-core m 400

A12 Joint kit ea 4

A13 INVT prewired DC/AC controller w/protection ea 4

A14 345W solar modules, voc 46.4v +/-3% OR alternative module combination ea 24

A15 50mm HDPE poly pipe class 9 x 100m ea 4

A16 50mm HDPE poly pipe class 6 x 100m ea 8

A17 50mm x 2" poly adapter ea 12

A18 2" well seal complete (union, tee and Elbow etc) ea 4

A19 Cable ties packets ea 4

Page 72
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY

A20 6mm earth wire m 20

A21 50mm compression couplers ea 16

A22 Miscelleaneous ( bolts, thread tape etc) items 4

A23 Installation of solar kit and pipework from borehole to tanks ea 4

A25 Borehole flushing and testing ea 4

To Collection

SITE: TEBE GWEMBE DISTRICT


4 BOREHOLES
No. ITEM UNIT QTY

SOLAR PUMP STRUCTURE


Excavation(Provisional)

A SOLAR PUMP AND STRUCTURE

Excavation(Provisional)

Excavation including maintaining and supporting sides and keeping free from water, mud and fallen
materials by bailing, pumping or otherwise

Prepare site by stripping top 200 mm of soil to remove all debris including sand (if any) from site and
A1 carting away spoil m2 40

A2 Pit excavation commencing at reduced levels depth not exceeding 1.50m deep m3 2

A3 Remove surplus excavated material from site m3 0.50

A4 Backfill around foundation m3 2

Concrete work

Reinforced Concrete class 25

A5 Concrete pad with surface steel trowelled smooth m3 0.13

Reinforcement

A6 Reinforcement bars (all sizes) kg 35

Sawn formwork

A7 Formwork to sides m 2

Structural steelwork

Supply, fabricate and erect the following framed structural steelwork; complete with and including all
welded and bolted connections; and including one shop coat red oxide, zinc chromate or similar and
A8 approved primer and 2 finishing coats of gloss oil paint after erection: refer to DWG #1 attached 1

Solar panels support structure constructed according to design including anti theft U-channels 50mm x
A9 50mm, including Aluminium U 3mm channel, 7mm angle lines, sum 1

Warranty (months): 12

Supply and Installation of Solar Powered Pump


A10 2hp Submersible, average yield 2l/s ea 4

A11 4.0 mm submersible cable 3-core m 400

A12 Joint kit ea 4

A13 INVT prewired DC/AC controller w/protection ea 4

Page 73
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY

A14 345W solar modules, voc 46.4v +/-3% OR alternative module combination ea 24

A15 50mm HDPE poly pipe class 9 x 100m ea 4

A16 50mm HDPE poly pipe class 6 x 100m ea 8

A17 50mm x 2" poly adapter ea 12

A18 2" well seal complete (union, tee and Elbow etc) ea 4

A19 Cable ties packets ea 4

A20 6mm earth wire m 20

A21 50mm compression couplers ea 16

A22 Miscelleaneous ( bolts, thread tape etc) items 4

A23 Installation of solar kit and pipework from borehole to tanks ea 4

A24 Borehole flushing and testing ea 4

To Collection

SITE: KASONDE GWEMBE DISTRICT


4 BOREHOLES
No. ITEM UNIT QTY

SOLAR PUMP STRUCTURE


Excavation(Provisional)

A SOLAR PUMP AND STRUCTURE

Excavation(Provisional)

Excavation including maintaining and supporting sides and keeping free from water, mud and fallen
materials by bailing, pumping or otherwise

Prepare site by stripping top 200 mm of soil to remove all debris including sand (if any) from site and
A1 carting away spoil m2 70

A2 Pit excavation commencing at reduced levels depth not exceeding 1.50m deep m3 2

A3 Remove surplus excavated material from site m3 0.50

A4 Backfill around foundation m3 2

Concrete work

Reinforced Concrete class 25

A5 Concrete pad with surface steel trowelled smooth m3 0.13

Reinforcement

A6 Reinforcement bars (all sizes) kg 35

Sawn formwork

A7 Formwork to sides m 2

Structural steelwork

Supply, fabricate and erect the following framed structural steelwork; complete with and including all
welded and bolted connections; and including one shop coat red oxide, zinc chromate or similar and
A8 approved primer and 2 finishing coats of gloss oil paint after erection: refer to DWG #1 attached 1

Page 74
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY

Solar panels support structure constructed according to design including anti theft U-channels 50mm x
A9 50mm, including Aluminium U 3mm channel, 7mm angle lines, sum 1

Warranty (months): 12

Supply and Installation of Solar Powered Pump


A10 2hp Submersible, average yield 2l/s ea 6

A11 4.0 mm submersible cable 3-core m 500

A12 Joint kit ea 6

A13 INVT prewired DC/AC controller w/protection ea 6

A14 345W solar modules, voc 46.4v +/-3% OR alternative module combination ea 36

A15 50mm HDPE poly pipe class 9 x 100m ea 6

A16 50mm HDPE poly pipe class 6 x 100m ea 10

A17 50mm x 2" poly adapter ea 12

A18 2" well seal complete (union, tee and Elbow etc) ea 6

A19 Cable ties packets ea 6

A20 6mm earth wire m 36

A21 50mm compression couplers ea 16

A22 Miscelleaneous ( bolts, thread tape etc) items 4

A23 Installation of solar kit and pipework from borehole to tanks ea 4

A24 Borehole flushing and testing ea 4

A25 Borehole drilling and development, ACCEPTABLE YIELD 1.5l/s ea 2

To Collection

CONSTRUCTION OF SOLAR AND PUMP


TOTAL CARRIED TO SUMMARY

8.0 PRIME COSTS

DESCRIPTION UNIT QTY

Include the following NET Provisional Sums


to be expended by Ministry of Agriculture
or omitted if not expended without any claim for loss
of profit

1 ALLOW the provisional sum at K300,000 to cover incidentals, complete ea 1


cost of incorporating materials into the
works including delivery of materials to site,
off-loading, storing, checking replacing defective
items, establishment charges all transport and
for installation of materials on site and all
contractor's overheads and profit

2 To add contigency sum at 10% of the bill ea 1

PROVISIONAL AND PRIME COST SUMS


TOTAL CARRIED TO SUMMARY

SUMMARY

Page 75
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

No. ITEM UNIT QTY


Sl.No. ITEM

1 PRELIMINARIES AND GENERAL ITEMS

2 CONSTRUCTION OF A STEEL WATER TANK TO HOIST LITRE POLY WATER TANK

3 4 POINT WATER KIOSK

4 WATER TROUGHS

5 FENCING

6 DRIP IRRIGATION

7 SOLAR SYSTEM & STRUCTURE

8 PRIME COSTS

9 TOTAL

Page 76
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

UNIT PRICE TOTAL PRICE

Page 77
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE


0

Page 78
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE


0

Page 79
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE


0

Page 80
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 81
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 82
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 83
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE


0

0
0
0

0
0
0
0

0
0
0
0
0
0
0

Page 84
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0

0
0
0

Page 85
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0
0
0

0
0
0
0
0
0
0

Page 86
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0

0
0
0

0
0
0
0

0
0

Page 87
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE


0
0
0
0
0

Page 88
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0

0
0
0
0
0
0

Page 89
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0

Page 90
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0
0
0
0
0

Page 91
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0

0
0
0
0
0
0

Page 92
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0

0
0
0
0
0
0
0
0
0

Page 93
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE


0
0
0
0
0
0

0
0

0
0
0
0
0
0

0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0

Page 94
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

0
0
0
0
0
0

0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0

0
0
0
0
0
0

Page 95
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 96
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 97
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

Page 98
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE

RATE AMOUNT

Page 99
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT

UNIT PRICE TOTAL PRICE


AMOUNT

Page 100