NOTE: The value of preliminaries and general items shall not exceed 5% of the value of
measured works of the project
The contractor shall set up the site working areas and storage facilities as may be
deemed necessary including all required site mobilization activities not mentioned below
The contractor shall fabricate and errect a project billboard, site hoarding during the
construction of the water tank stand, and shall allow for all expenses associated with
convening and attending site progress meetings with client's staff and stage inspection of
works quality and progress .
The contractor shall upon completion of the works remove all equipment, tools and
remaining materials and clean the site as may be approved by the Project Engineer
Site Preparation
B CONCRETE WORKS
Preamble
2 Column bases m3 6
Page 1
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
3 Stub Columns m3 1
4 Ground beam m3 2
Supplying, bending and fixing in position as per approved design; steel reinforcement cut
to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.
1 8mm bars Kg 39
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
and fixing.
D FORMWORK
E STRUCTURAL STEELWORK
Preamble
All structural steel shall be Grade S275, in accordance with with B.S 5950, all welds to be
6mm continous weld or as described; in accordance with BS 1856 and 2642, and shall be
given a coat of SF Utra - Thin Fire Retardant.
All rates shall include the cost of fabrication, installation, assemby,errection and where
necessary testing; and all other associated costs to render the design functional as
described
Page 2
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Touch up approved anti corrosion paint primer, and two more coats on all steelworks;
17 General surfaces of steelwork in green colour (Provisional Sum) item 1
F WATER TANK
COLLECTION
Site Preparation
B CONCRETE WORKS
Preamble
Page 3
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
2 Column bases m3 6
3 Stub Columns m3 1
4 Ground beam m3 2
Supplying, bending and fixing in position as per approved design; steel reinforcement cut
to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.
1 8mm bars Kg 39
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
and fixing.
D FORMWORK
E STRUCTURAL STEELWORK
Preamble
All structural steel shall be Grade S275, in accordance with with B.S 5950, all welds to be
6mm continous weld or as described; in accordance with BS 1856 and 2642, and shall be
given a coat of SF Utra - Thin Fire Retardant.
All rates shall include the cost of fabrication, installation, assemby,errection and where
necessary testing; and all other associated costs to render the design functional as
described
Page 4
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Touch up approved anti corrosion paint primer, and two more coats on all steelworks;
17 General surfaces of steelwork in green colour (Provisional Sum) item 1
F WATER TANK
COLLECTION
Site Preparation
B CONCRETE WORKS
Preamble
Page 5
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
2 Column bases m3 6
3 Stub Columns m3 1
4 Ground beam m3 2
Supplying, bending and fixing in position as per approved design; steel reinforcement cut
to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.
1 8mm bars Kg 39
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
and fixing.
D FORMWORK
E STRUCTURAL STEELWORK
Preamble
All structural steel shall be Grade S275, in accordance with with B.S 5950, all welds to be
6mm continous weld or as described; in accordance with BS 1856 and 2642, and shall be
given a coat of SF Utra - Thin Fire Retardant.
All rates shall include the cost of fabrication, installation, assemby,errection and where
necessary testing; and all other associated costs to render the design functional as
described
Page 6
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Touch up approved anti corrosion paint primer, and two more coats on all steelworks;
17 General surfaces of steelwork in green colour (Provisional Sum) item 1
F WATER TANK
COLLECTION
SINDE SITE
No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS
Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 140
cutting down trees not exceeding 600mm girth and grub
up roots
Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Kiosk apron, pipe trenches and soak pit m3 26
Page 7
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Supplying, bending and fixing in position as per approved design; steel reinforcement
cut to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
i)
and fixing.
For Substructure works:
3 i) 12mm dia. As Y12 in apron Kg 355
All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R
cement, 20mm graded granite aggregated and quarry dust; thickness as required
including compacting, curing, formwork etc., complete as directed by the Resident
Engineer
i) Below Kiosk apron m3 2.00
Formwork
Sawn formwork; to:
iii) Sides of apron concrete m2 4
Two strand 3.25 mm diameter high tensile steel wire wall reinforcement; 100 mm laps
(measured net: no allowance made for laps); every course; in
Kiosk blockwork:
iii) 200 mm block wall. m 20
iv) 200 mm Kiosk Soak Pit honeycomb m2 38
Page 8
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Cement mortar (1:4) plastering 10mm thick over concrete and blockwork surface and
concrete apron to be finished even and smooth with steel float trowel; all complete as
directed by the Resident Engineer.
i) Apron Flooring m2 23
Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.
Equipment
Include for making chases and holes in walls, existing slab and breaking existing slab
v) Item 1
where necessary and making good walls, slab and finishings.
SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
D BRICKWORK AND MASONRY
E PLASTERING AND FLOORING
F PLUMBING INSTALLATION
COLLECTION
SIAKASIPA SITE
No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS
Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 140
cutting down trees not exceeding 600mm girth and grub
up roots
Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Kiosk apron, pipe trenches and soak pit m3 26
Refilling of foundation hardcore base with approved laterite in layers of 150mm thick
including compaction and consolidation etc., all complete as directed by the Engineer-in-
Charge.
Page 9
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Supplying, bending and fixing in position as per approved design; steel reinforcement
cut to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
i)
and fixing.
For Substructure works:
3 i) 12mm dia. As Y12 in apron Kg 355
All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R
cement, 20mm graded granite aggregated and quarry dust; thickness as required
including compacting, curing, formwork etc., complete as directed by the Resident
Engineer
i) Below Kiosk apron m3 2.00
Formwork
Sawn formwork; to:
iii) Sides of apron concrete m2 4
Two strand 3.25 mm diameter high tensile steel wire wall reinforcement; 100 mm laps
(measured net: no allowance made for laps); every course; in
Kiosk blockwork:
iii) 200 mm block wall. m 20
iv) 200 mm Kiosk Soak Pit honeycomb m2 38
Cement mortar (1:4) plastering 10mm thick over concrete and blockwork surface and
concrete apron to be finished even and smooth with steel float trowel; all complete as
directed by the Resident Engineer.
Page 10
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.
Equipment
Include for making chases and holes in walls, existing slab and breaking existing slab
v) Item 1
where necessary and making good walls, slab and finishings.
SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
D BRICKWORK AND MASONRY
E PLASTERING AND FLOORING
F PLUMBING INSTALLATION
TO COLLECTIONS
MANYEMUNYEMEU SITE
No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS
Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 140
cutting down trees not exceeding 600mm girth and grub
up roots
Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Kiosk apron, pipe trenches and soak pit m3 26
Refilling of foundation hardcore base with approved laterite in layers of 150mm thick
including compaction and consolidation etc., all complete as directed by the Engineer-in-
Charge.
Page 11
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Supplying, bending and fixing in position as per approved design; steel reinforcement
cut to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
i)
and fixing.
For Substructure works:
3 i) 12mm dia. As Y12 in apron Kg 355
All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R
cement, 20mm graded granite aggregated and quarry dust; thickness as required
including compacting, curing, formwork etc., complete as directed by the Resident
Engineer
i) Below Kiosk apron m3 2.00
Formwork
Sawn formwork; to:
iii) Sides of apron concrete m2 4
Two strand 3.25 mm diameter high tensile steel wire wall reinforcement; 100 mm laps
(measured net: no allowance made for laps); every course; in
Kiosk blockwork:
iii) 200 mm block wall. m 20
iv) 200 mm Kiosk Soak Pit honeycomb m2 38
Cement mortar (1:4) plastering 10mm thick over concrete and blockwork surface and
concrete apron to be finished even and smooth with steel float trowel; all complete as
directed by the Resident Engineer.
Page 12
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.
Equipment
Include for making chases and holes in walls, existing slab and breaking existing slab
v) Item 1
where necessary and making good walls, slab and finishings.
SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
D BRICKWORK AND MASONRY
E PLASTERING AND FLOORING
F PLUMBING INSTALLATION
TO COLLECTIONS
Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 384
cutting down trees not exceeding 600mm girth and grub
up roots
Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Cattle Water Trough apron and pipe trenches m3 40
Refilling of foundation hardcore base with approved laterite in layers of 150mm thick
including compaction and consolidation etc., all complete as directed by the Engineer-in-
Charge.
Supplying, bending and fixing in position as per approved design; steel reinforcement
cut to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.
Page 13
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R
cement, 20mm graded granite aggregated and quarry dust; thickness as required
including compacting, curing, formwork etc., complete as directed by the Resident
Engineer
i) Below Cattle Water Trough apron m3 7.00
Formwork
Sawn formwork; to:
iii) Sides of trough stem concrete m2 64
Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.
Supply and installation of ball-floater automated water opening and closing mechanism,
iii) L.S. 1
including all associated fixture to render installation functional (Provisional Sum only)
Equipment
Include for making chases and holes in walls, existing slab and breaking slab where
iv) Item 1
necessary and making good walls, slab and finishings.
Page 14
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
E TROUGH GROUTING AND SEALING
F PLUMBING INSTALLATIONS
TO COLLECTIONS
Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 384
cutting down trees not exceeding 600mm girth and grub
up roots
Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Cattle Water Trough apron and pipe trenches m3 40
Supplying, bending and fixing in position as per approved design; steel reinforcement cut
to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.
i) 3.2mm dia , 150 BRC heavy duty conforce wire in apron slab m2 120
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
ii)
and fixing.
All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R
cement, 20mm graded granite aggregated and quarry dust; thickness as required
including compacting, curing, formwork etc., complete as directed by the Resident
Engineer
i) Below Cattle Water Trough apron m3 7.00
Page 15
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Formwork
Sawn formwork; to:
iii) Sides of trough stem concrete m2 64
Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.
Supply and installation of ball-floater automated water opening and closing mechanism,
iii) L.S. 1
including all associated fixture to render installation functional (Provisional Sum only)
Equipment
Include for making chases and holes in walls, existing slab and breaking slab where
iv) Item 1
necessary and making good walls, slab and finishings.
Supply and install, 50mm dia. uPVC pipes including all fittings to render the installation
v) functional as described; in accordance with ASMD - 1785 or equal and approved m 180
standard
SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
E TROUGH GROUTING AND SEALING
F PLUMBING INSTALLATIONS
TO COLLECTIONS
Page 16
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 384
cutting down trees not exceeding 600mm girth and grub
up roots
Excavate not exceeding 1500 mm deep starting from stripped level for;
2 Below Cattle Water Trough apron and pipe trenches m3 40
Supplying, bending and fixing in position as per approved design; steel reinforcement cut
to length, bent to shape required, cranking, hooking ends etc., including binding with
0.90mm dia (soft drawn) MS black binding wire etc., all complete as directed by Engineer-
in-Charge.
i) 3.2mm dia , 150 BRC heavy duty conforce wire in apron slab m2 120
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks
ii)
and fixing.
All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R
cement, 20mm graded granite aggregated and quarry dust; thickness as required
including compacting, curing, formwork etc., complete as directed by the Resident
Engineer
i) Below Cattle Water Trough apron m3 7.00
Formwork
Sawn formwork; to:
iii) Sides of trough stem concrete m2 64
Page 17
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.
Supply and installation of ball-floater automated water opening and closing mechanism,
iii) L.S. 1
including all associated fixture to render installation functional (Provisional Sum only)
Equipment
Include for making chases and holes in walls, existing slab and breaking slab where
iv) Item 1
necessary and making good walls, slab and finishings.
Supply and install, 50mm dia. uPVC pipes including all fittings to render the installation
v) functional as described; in accordance with ASMD - 1785 or equal and approved m 180
standard
SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
E TROUGH GROUTING AND SEALING
F PLUMBING INSTALLATIONS
TO COLLECTIONS
FENCING
SITE: SINDE KAZUNGULA DISTRICT
Sl.No. ITEM UNIT QTY
G FENCING INSTALLATION
Game wire fencing shall be 1.88m x 300mm 14W Wire VELDSPAN brand or equal and
approved, with all posts, steys and Y sections well anchored in to the ground by
concreting with C20 concrete to resident Engineer's approval, all complete with fence
posts round 3.0m x 76mm MD, Fence Stey Round 3.0 x 38mm MD, all bolts, washers and
nuts to render installation functional, fence standards Y sections 3.05m at not more than
4.5m centres, Double 1.8 x 4.2m Fence Gate all complete with required Wire plains to
Engineers satisfaction
Supply and install 'game wire fencing' as described around the water tank and water
i) kiosk facility around 1 hactare plot m 500
Page 18
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Supply and install double gate as described to allow for controlled access around the
ii) water tank and water kiosk facility around 1 hactare plot No. 1
Game wire fencing shall be 1.88m x 300mm 14W Wire VELDSPAN brand or equal and
approved, with all posts, steys and Y sections well anchored in to the ground by
concreting with C20 concrete to resident Engineer's approval, all complete with fence
posts round 3.0m x 76mm MD, Fence Stey Round 3.0 x 38mm MD, all bolts, washers and
nuts to render installation functional, fence standards Y sections 3.05m at not more than
4.5m centres, Double 1.8 x 4.2m Fence Gate all complete with required Wire plains to
Engineers satisfaction
Supply and install 'game wire fencing' as described around the water tank and water
i) kiosk facility around 1 hactare plot m 500
Supply and install double gate as described to allow for controlled access around the
ii) water tank and water kiosk facility around 1 hactare plot No. 1
Game wire fencing shall be 1.88m x 300mm 14W Wire VELDSPAN brand or equal and
approved, with all posts, steys and Y sections well anchored in to the ground by
concreting with C20 concrete to resident Engineer's approval, all complete with fence
posts round 3.0m x 76mm MD, Fence Stey Round 3.0 x 38mm MD, all bolts, washers and
nuts to render installation functional, fence standards Y sections 3.05m at not more than
4.5m centres, Double 1.8 x 4.2m Fence Gate all complete with required Wire plains to
Engineers satisfaction
Supply and install 'game wire fencing' as described around the water tank and water
i) kiosk facility around 1 hactare plot m 200
Supply and install double gate as described to allow for controlled access around the
ii) water tank and water kiosk facility around 1 hactare plot No. 1
The contractor is expected to supply, construct, commission the 1ha drip irrigation system
Page 19
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
FILTER
1 DISC FILTER 130 MICRONS, 3" EA 1
2 ACCESSORIES incl valves, fittings, risers etc EA 1
3
DRIP SYSTEM
DRIP PIPE 1.0L/H @ 0.3CM SP, 0.60MM MIN WALL THICKNESS, VIRGIN MATERIAL,
1 4 YR WARRANTY MTR 10000
2 PE IRRIGATION PIPE 16/4 100M MTR 200
3 START CONN-PVC BARB 16 W/SEAL- MT EA 200
4 END LINE (DOUBLE O) 16/17 EA 200
5 BARB 16 COUPLING CONN. 1UNIT EA 200
6 BARB 16 W/FLARE COUPLING EA 200
7
COLLECTION
The contractor is expected to supply, construct, commission the 1ha drip irrigation system
FILTER
1 DISC FILTER 130 MICRONS, 3" EA 1
2 ACCESSORIES incl valves, fittings, risers etc EA 1
3 TOTAL PER GROUP
Page 20
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
DRIP SYSTEM
DRIP PIPE 1.0L/H @ 0.3CM SP, 0.60MM MIN WALL THICKNESS, VIRGIN MATERIAL,
1 4 YR WARRANTY MTR 10000
2 PE IRRIGATION PIPE 16/4 100M MTR 200
3 START CONN-PVC BARB 16 W/SEAL- MT EA 200
4 END LINE (DOUBLE O) 16/17 EA 200
5 BARB 16 COUPLING CONN. 1UNIT EA 200
6 BARB 16 W/FLARE COUPLING EA 200
7 TOTAL PER GROUP
To Collection
Excavation(Provisional)
Excavation including maintaining and supporting sides and keeping free from water, mud
and fallen materials by bailing, pumping or otherwise
A1 Prepare site by stripping top 200 mm of soil to remove all debris including sand (if any)
m2 70
from site and carting away spoil
A2 Pit excavation commencing at reduced levels depth not exceeding 1.50m deep
m3 2
Concrete work
Page 21
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Reinforcement
Sawn formwork
A7 Formwork to sides m 2
Structural steelwork
A8 Supply, fabricate and erect the following framed structural steelwork; complete with and
including all welded and bolted connections; and including one shop coat red oxide, zinc
chromate or similar and approved primer and 2 finishing coats of gloss oil paint after 1
erection: refer to DWG #1 attached
A9 Solar panels support structure constructed according to design including anti theft U-
channels 50mm x 50mm, including Aluminium U 3mm channel, 7mm angle lines, sum 1
Warranty (months): 12
A14 345W solar modules, voc 46.4v +/-3% OR alternative module combination
ea 24
A18 2" well seal complete (union, tee and Elbow etc) ea 4
Page 22
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Excavation(Provisional)
Excavation including maintaining and supporting sides and keeping free from water, mud
and fallen materials by bailing, pumping or otherwise
A1 Prepare site by stripping top 200 mm of soil to remove all debris including sand (if any)
m2 60
from site and carting away spoil
A2 Pit excavation commencing at reduced levels depth not exceeding 1.50m deep
m3 2
Concrete work
Reinforcement
Sawn formwork
A7 Formwork to sides m 2
Structural steelwork
A8 Supply, fabricate and erect the following framed structural steelwork; complete with and
including all welded and bolted connections; and including one shop coat red oxide, zinc
chromate or similar and approved primer and 2 finishing coats of gloss oil paint after 1
erection: refer to DWG #1 attached
A9 Solar panels support structure constructed according to design including anti theft U-
channels 50mm x 50mm, including Aluminium U 3mm channel, 7mm angle lines, sum 1
Warranty (months): 12
C Joint kit ea 3
Page 23
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
M Installation ea 1
N Borehole flushing ea 3
Excavation(Provisional)
Excavation including maintaining and supporting sides and keeping free from water, mud
and fallen materials by bailing, pumping or otherwise
A1 Prepare site by stripping top 200 mm of soil to remove all debris including sand (if any)
m2 10
from site and carting away spoil
A2 Pit excavation commencing at reduced levels depth not exceeding 1.50m deep
m3 2
Concrete work
Reinforcement
Sawn formwork
A7 Formwork to sides m 4
Structural steelwork
A8 Supply, fabricate and erect the following framed structural steelwork; complete with and
including all welded and bolted connections; and including one shop coat red oxide, zinc
chromate or similar and approved primer and 2 finishing coats of gloss oil paint after 1
erection: refer to DWG #1 attached
A9 Solar panels support structure constructed according to design including anti theft U-
channels 50mm x 50mm, including Aluminium U 3mm channel, 7mm angle lines, sum 1
Warranty (months): 12
Page 24
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
M Installation ea 1
N Borehole flushing ea 1
7.0 PRIME
COSTS
SUMMARY
Sl.No. ITEM
Page 25
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
4 WATER TROUGHS
5 FENCING
6 DRIP IRRIGATION
8 PRIME COSTS
9 TOTAL
Page 26
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Page 27
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Page 28
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Page 29
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Page 30
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Page 31
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Page 32
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Page 33
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
0
0
0
0
Page 34
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
0
0
0
0
0
0
0
0
0
0
0
Page 35
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
0
0
0
0
Page 36
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
0
0
0
0
0
0
0
0
0
0
0
Page 37
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
0
0
0
0
Page 38
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
0
0
0
0
0
0
0
0
0
0
0
Page 39
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Page 40
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
0
0
0
0
0
0
Page 41
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
0
0
0
0
0
0
Page 42
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Page 43
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
0
0
0
0
0
0
0
0
Page 44
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Page 45
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Page 46
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Page 47
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Page 48
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Page 49
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Page 50
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
RATE AMOUNT
AMOUNT
Page 51
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN KAZUNGULA
DISTRICT UNDER THE SCRALA PROJECT
Page 52
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
APPENDI THE SCRALA PROJECT
X H: BILL
OF
QUANTIT
IES LOT
5 ITEM DESCRIPTION UNIT QTY
GWEMB
E 1.00 PRELIMINARIES AND GENERAL ITEMS
NOTE: The value of preliminaries and general items shall not exceed 5% of the value of measured works
of the project
The contractor shall set up the site working areas and storage facilities as may be deemed necessary
including all required site mobilization activities not mentioned below
The contractor shall fabricate and errect a project billboard, site hoarding during the construction of the
water tank stand, and shall allow for all expenses associated with convening and attending site progress
meetings with client's staff and stage inspection of works quality and progress .
The contractor shall upon completion of the works remove all equipment, tools and remaining materials
and clean the site as may be approved by the Project Engineer
2.00 CONSTRUCTION OF A STEEL WATER TANK TO HOIST LITRE POLY WATER TANK
No. ITEM UNIT QTY
Site Preparation
B CONCRETE WORKS
Preamble
All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
2 Column bases m3 6
Page 53
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
4 Ground beam m3 2
Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
1 8mm bars Kg 81
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.
D FORMWORK
E STRUCTURAL STEELWORK
Preamble
All structural steel shall be Grade S275, in accordance with with B.S 5950, all welds to be 6mm
continous weld or as described; in accordance with BS 1856 and 2642, and shall be given a coat of SF
Utra - Thin Fire Retardant.
All rates shall include the cost of fabrication, installation, assemby,errection and where necessary testing;
and all other associated costs to render the design functional as described
Page 54
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Touch up approved anti corrosion paint primer, and two more coats on all steelworks;
17 General surfaces of steelwork in green colour (Provisional Sum) item 1
F WATER TANK
ULIGOKEZYA SITE
Site Preparation
B CONCRETE WORKS
Preamble
All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
2 Column bases m3 6
3 Stub Columns m3 1
4 Ground beam m3 2
Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
Page 55
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.
D FORMWORK
E STRUCTURAL STEELWORK
Preamble
All structural steel shall be Grade S275, in accordance with with B.S 5950, all welds to be 6mm
continous weld or as described; in accordance with BS 1856 and 2642, and shall be given a coat of SF
Utra - Thin Fire Retardant.
All rates shall include the cost of fabrication, installation, assemby,errection and where necessary testing;
and all other associated costs to render the design functional as described
Touch up approved anti corrosion paint primer, and two more coats on all steelworks;
17 General surfaces of steelwork in green colour (Provisional Sum) item 1
Page 56
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
TEBE SITE
Site Preparation
B CONCRETE WORKS
Preamble
All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
2 Column bases m3 6
3 Stub Columns m3 1
4 Ground beam m3 2
Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
1 8mm bars Kg 81
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.
Page 57
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
D FORMWORK
E STRUCTURAL STEELWORK
Preamble
All structural steel shall be Grade S275, in accordance with with B.S 5950, all welds to be 6mm
continous weld or as described; in accordance with BS 1856 and 2642, and shall be given a coat of SF
Utra - Thin Fire Retardant.
All rates shall include the cost of fabrication, installation, assemby,errection and where necessary testing;
and all other associated costs to render the design functional as described
Touch up approved anti corrosion paint primer, and two more coats on all steelworks;
17 General surfaces of steelwork in green colour (Provisional Sum) item 1
F WATER TANK
Page 58
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
TEBE SITE
No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS
Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 140
cutting down trees not exceeding 600mm girth and grub
up roots
Refilling of foundation hardcore base with approved laterite in layers of 150mm thick including
compaction and consolidation etc., all complete as directed by the Engineer-in-Charge.
Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
i)
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.
For Substructure works:
3 i) 12mm dia. As Y12 in apron Kg 355
All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R cement, 20mm graded
granite aggregated and quarry dust; thickness as required including compacting, curing, formwork etc.,
complete as directed by the Resident Engineer
i) Below Kiosk apron m3 2.00
All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
Rate should include all formwork
For Substructure works:
ii) in Apron and ramps m3 4.00
Formwork
Sawn formwork; to:
iii) Sides of apron concrete m2 4
Page 59
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Two strand 3.25 mm diameter high tensile steel wire wall reinforcement; 100 mm laps (measured net: no
allowance made for laps); every course; in
Kiosk blockwork:
iii) 200 mm block wall. m 20
iv) 200 mm Kiosk Soak Pit honeycomb m2 38
BRICKWORK AND MASONRY - TOTAL CARRIED TO SUMMARY
Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.
Equipment
Include for making chases and holes in walls, existing slab and breaking existing slab where necessary
v) Item 1
and making good walls, slab and finishings.
SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
D BRICKWORK AND MASONRY
E PLASTERING AND FLOORING
F PLUMBING INSTALLATION
TO COLLECTIONS
Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 140
cutting down trees not exceeding 600mm girth and grub
up roots
Refilling of foundation hardcore base with approved laterite in layers of 150mm thick including
compaction and consolidation etc., all complete as directed by the Engineer-in-Charge.
Page 60
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
i)
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.
For Substructure works:
3 i) 12mm dia. As Y12 in apron Kg 355
All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R cement, 20mm graded
granite aggregated and quarry dust; thickness as required including compacting, curing, formwork etc.,
complete as directed by the Resident Engineer
i) Below Kiosk apron m3 2.00
All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
Rate should include all formwork
For Substructure works:
ii) in Apron and ramps m3 4.00
Formwork
Sawn formwork; to:
iii) Sides of apron concrete m2 4
Two strand 3.25 mm diameter high tensile steel wire wall reinforcement; 100 mm laps (measured net: no
allowance made for laps); every course; in
Kiosk blockwork:
iii) 200 mm block wall. m 20
iv) 200 mm Kiosk Soak Pit honeycomb m2 38
BRICKWORK AND MASONRY - TOTAL CARRIED TO SUMMARY
Page 61
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.
Equipment
Include for making chases and holes in walls, existing slab and breaking existing slab where necessary
v) Item 1
and making good walls, slab and finishings.
SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
C CONCRETE WORKS
D BRICKWORK AND MASONRY
E PLASTERING AND FLOORING
F PLUMBING INSTALLATION
TO COLLECTIONS
ULIGOKEZYA SITE
No. ITEM UNIT QTY
A FOUNDATION AND EARTHWORKS
Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including
cutting down trees not exceeding 600mm girth and grub
up roots m2 140
Refilling of foundation hardcore base with approved laterite in layers of 150mm thick including
compaction and consolidation etc., all complete as directed by the Engineer-in-Charge.
Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
i)
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.
For Substructure works:
3 i) 12mm dia. As Y12 in apron Kg 355
Page 62
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R cement, 20mm graded
granite aggregated and quarry dust; thickness as required including compacting, curing, formwork etc.,
complete as directed by the Resident Engineer
i) Below Kiosk apron m3 2.00
All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
Rate should include all formwork
For Substructure works:
ii) in Apron and ramps m3 4.00
Formwork
Sawn formwork; to:
iii) Sides of apron concrete m2 4
Two strand 3.25 mm diameter high tensile steel wire wall reinforcement; 100 mm laps (measured net: no
allowance made for laps); every course; in
Kiosk blockwork:
iii) 200 mm block wall. m 20
iv) 200 mm Kiosk Soak Pit honeycomb m2 38
BRICKWORK AND MASONRY - TOTAL CARRIED TO SUMMARY
Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.
Equipment
Include for making chases and holes in walls, existing slab and breaking existing slab where necessary
v) Item 1
and making good walls, slab and finishings.
SUMMARY
Sl.No. ITEM
A FOUNDATION AND EARTHWORKS
B STEEL REINFORCEMENT FOR CONCRETE
Page 63
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 384
cutting down trees not exceeding 600mm girth and grub
up roots
Refilling of foundation hardcore base with approved laterite in layers of 150mm thick including
compaction and consolidation etc., all complete as directed by the Engineer-in-Charge.
Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
i) 3.2mm dia , 150 BRC heavy duty conforce wire in apron slab m2 120
ii)
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.
All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R cement, 20mm graded
granite aggregated and quarry dust; thickness as required including compacting, curing, formwork etc.,
complete as directed by the Resident Engineer
i) Below Cattle Water Trough apron m3 7.00
All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
Formwork rates to include all supports and jointing to required to assemble sound formwork necessary to
achieve and form described concrete geometry
For Substructure works:
ii) in Cattle Water Trough Apron m3 23.00
Formwork
Sawn formwork; to:
iii) Sides of trough stem concrete m2 64
Page 64
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
F PLUMBING INSTALLATIONS
Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.
Supply and installation of ball-floater automated water opening and closing mechanism, including all
iii) L.S.
associated fixture to render installation functional (Provisional Sum only)
1
Equipment
iv) Include for making chases and holes in walls, existing slab and breaking slab where necessary and making Item 1
Supply and install, 50mm dia. uPVC pipes including all fittings to render the installation functional as
v) m 180
described; in accordance with ASMD - 1785 or equal and approved standard
SUMMARY
Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 384
cutting down trees not exceeding 600mm girth and grub
up roots
Refilling of foundation hardcore base with approved laterite in layers of 150mm thick including
compaction and consolidation etc., all complete as directed by the Engineer-in-Charge.
Page 65
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
i) 3.2mm dia , 150 BRC heavy duty conforce wire in apron slab m2 120
ii)
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.
All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R cement, 20mm graded
granite aggregated and quarry dust; thickness as required including compacting, curing, formwork etc.,
complete as directed by the Resident Engineer
i) Below Cattle Water Trough apron m3 7.00
All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
Formwork rates to include all supports and jointing to required to assemble sound formwork necessary to
achieve and form described concrete geometry
For Substructure works:
ii) in Cattle Water Trough Apron m3 23.00
Formwork
Sawn formwork; to:
iii) Sides of trough stem concrete m2 64
F PLUMBING INSTALLATIONS
Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.
Supply and installation of ball-floater automated water opening and closing mechanism, including all
iii) L.S.
associated fixture to render installation functional (Provisional Sum only)
1
Equipment
iv) Include for making chases and holes in walls, existing slab and breaking slab where necessary and making Item 1
Supply and install, 50mm dia. uPVC pipes including all fittings to render the installation functional as
v) m 180
described; in accordance with ASMD - 1785 or equal and approved standard
Page 66
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Site Preparation
1 Clear site of bushes, shrubs undergrowth and the like including m2 384
cutting down trees not exceeding 600mm girth and grub
up roots
Refilling of foundation hardcore base with approved laterite in layers of 150mm thick including
compaction and consolidation etc., all complete as directed by the Engineer-in-Charge.
Supplying, bending and fixing in position as per approved design; steel reinforcement cut to length, bent
to shape required, cranking, hooking ends etc., including binding with 0.90mm dia (soft drawn) MS black
binding wire etc., all complete as directed by Engineer-in-Charge.
i) 3.2mm dia , 150 BRC heavy duty conforce wire in apron slab m2 120
ii)
High tensile steel bar reinforcement; gr. 460N/mm2 including tying wire and space blocks and fixing.
All lean and blinding concrete shall be mixed on site as C15 concrete using 42.5R cement, 20mm graded
granite aggregated and quarry dust; thickness as required including compacting, curing, formwork etc.,
complete as directed by the Resident Engineer
i) Below Cattle Water Trough apron m3 7.00
All structral concrete shall vibrated reinforced concrete (reinforcement measured separately); to specified
classes for different member categories; 30MPa for foundation members, (30MPa for stub columns; 20
mm maximum aggregate). Slump and cube samples shall be taken for each batch for quality control.
Formwork rates to include all supports and jointing to required to assemble sound formwork necessary to
achieve and form described concrete geometry
For Substructure works:
ii) in Cattle Water Trough Apron m3 23.00
Formwork
Sawn formwork; to:
iii) Sides of trough stem concrete m2 64
Page 67
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
F PLUMBING INSTALLATIONS
Galvanized mild steel pipes and fittings to B.S 1387 Table 2 and 1256 (Medium gauge)
Note: The rates for pipes not exceeding 63 mm diameter shall include all jointing fittings.
Supply and installation of ball-floater automated water opening and closing mechanism, including all
iii) L.S.
associated fixture to render installation functional (Provisional Sum only)
1
Equipment
iv) Include for making chases and holes in walls, existing slab and breaking slab where necessary and making Item 1
Supply and install, 50mm dia. uPVC pipes including all fittings to render the installation functional as
v) m 180
described; in accordance with ASMD - 1785 or equal and approved standard
SUMMARY
Game wire fencing shall be 2.11m x 300mm 14W Wire VELDSPAN brand or equal and approved, with all
posts, steys and Y sections well anchored in to the ground by concreting with C20 concrete to resident
Engineer's approval, all complete with fence posts round 3.0m x 76mm MD, Fence Stey Round 3.0 x
38mm MD, all bolts, washers and nuts to render installation functional, fence standards Y sections 3.05m
at not more than 4.5m centres, Double 1.8 x 4.2m Fence Gate all complete with required Wire plains to
Engineers satisfaction
Supply and install 'game wire fencing' as described around the water tank and water kiosk facility around
i) 5 hactare plot m 1000
Supply and install double gate as described to allow for controlled access around the water tank and
ii) water kiosk facility around 5 hactare plot No. 1
Page 68
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Game wire fencing shall be 2.11m x 300mm 14W Wire VELDSPAN brand or equal and approved, with all
posts, steys and Y sections well anchored in to the ground by concreting with C20 concrete to resident
Engineer's approval, all complete with fence posts round 3.0m x 76mm MD, Fence Stey Round 3.0 x
38mm MD, all bolts, washers and nuts to render installation functional, fence standards Y sections 3.05m
at not more than 4.5m centres, Double 1.8 x 4.2m Fence Gate all complete with required Wire plains to
Engineers satisfaction
Supply and install 'game wire fencing' as described around the water tank and water kiosk facility around
i) 5 hactare plot m 1000
Supply and install double gate as described to allow for controlled access around the water tank and
ii) water kiosk facility around 5 hactare plot No. 1
Game wire fencing shall be 2.11m x 300mm 14W Wire VELDSPAN brand or equal and approved, with all
posts, steys and Y sections well anchored in to the ground by concreting with C20 concrete to resident
Engineer's approval, all complete with fence posts round 3.0m x 76mm MD, Fence Stey Round 3.0 x
38mm MD, all bolts, washers and nuts to render installation functional, fence standards Y sections 3.05m
at not more than 4.5m centres, Double 1.8 x 4.2m Fence Gate all complete with required Wire plains to
Engineers satisfaction
Supply and install 'game wire fencing' as described around the water tank and water kiosk facility around
i) 5 hactare plot m 1000
Supply and install double gate as described to allow for controlled access around the water tank and
ii) water kiosk facility around 5 hactare plot No. 1
CONSTRUCTION OF FENCING
TOTAL CARRIED TO SUMMARY
The contractor is expected to supply, construct, commission the 2.5ha drip irrigation system
A Excavating trenches not exceeding 0.80m deep and
average depth 600mm starting from existing ground level
to receive service pipes, including grading bottoms,
earthwork supports, backfilling with excavated material,
disposing of surplus excavated material off site m 800
FILTER
1 DISC FILTER 130 MICRONS, 3" EA 2
2 ACCESSORIES incl valves, fittings, risers etc EA 1
3
Page 69
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
DRIP SYSTEM
DRIP PIPE 1.0L/H @ 0.3CM SP, 0.60MM MIN WALL THICKNESS, VIRGIN MATERIAL, 4 YR
1 WARRANTY MTR 25,000
2 PE IRRIGATION PIPE 16/4 100M EA 10
3 START CONN-PVC BARB 16 W/SEAL- MT EA 1,100
4 END LINE (DOUBLE O) 16/17 EA 1,100
5 BARB 16 COUPLING CONN. 1UNIT EA 1,000
6 BARB 16 W/FLARE COUPLING EA 1,100
7
To Collection
The contractor is expected to supply, construct, commission the 2.0ha drip irrigation system
FILTER
1 DISC FILTER 130 MICRONS, 3" EA 2
2 ACCESSORIES incl valves, fittings, risers etc EA 1
3
DRIP SYSTEM
Page 70
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
To Collection
The contractor is expected to supply, construct, commission the 2.5ha drip irrigation system
FILTER
1 DISC FILTER 130 MICRONS, 3" EA 2
2 ACCESSORIES incl valves, fittings, risers etc EA 1
3 TOTAL PER GROUP
DRIP SYSTEM
DRIP PIPE 1.0L/H @ 0.3CM SP, 0.60MM MIN WALL THICKNESS, VIRGIN MATERIAL, 4 YR
1 WARRANTY MTR 25000
2 PE IRRIGATION PIPE 16/4 100M EA 5
3 START CONN-PVC BARB 16 W/SEAL- MT EA 800
4 END LINE (DOUBLE O) 16/17 EA 800
5 BARB 16 COUPLING CONN. 1UNIT EA 800
6 BARB 16 W/FLARE COUPLING EA 800
7 TOTAL PER GROUP
To Collection
Page 71
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Excavation(Provisional)
Excavation including maintaining and supporting sides and keeping free from water, mud and fallen
materials by bailing, pumping or otherwise
Prepare site by stripping top 200 mm of soil to remove all debris including sand (if any) from site and
A1 carting away spoil m2 60
A2 Pit excavation commencing at reduced levels depth not exceeding 1.50m deep m3 2
Concrete work
Reinforcement
Sawn formwork
A7 Formwork to sides m 2
Structural steelwork
Supply, fabricate and erect the following framed structural steelwork; complete with and including all
welded and bolted connections; and including one shop coat red oxide, zinc chromate or similar and
A8 approved primer and 2 finishing coats of gloss oil paint after erection: refer to DWG #1 attached ea 1
Solar panels support structure constructed according to design including anti theft U-channels 50mm x
A9 50mm, including Aluminium U 3mm channel, 7mm angle lines, sum 1
Warranty (months): 12
A14 345W solar modules, voc 46.4v +/-3% OR alternative module combination ea 24
A18 2" well seal complete (union, tee and Elbow etc) ea 4
Page 72
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
To Collection
Excavation(Provisional)
Excavation including maintaining and supporting sides and keeping free from water, mud and fallen
materials by bailing, pumping or otherwise
Prepare site by stripping top 200 mm of soil to remove all debris including sand (if any) from site and
A1 carting away spoil m2 40
A2 Pit excavation commencing at reduced levels depth not exceeding 1.50m deep m3 2
Concrete work
Reinforcement
Sawn formwork
A7 Formwork to sides m 2
Structural steelwork
Supply, fabricate and erect the following framed structural steelwork; complete with and including all
welded and bolted connections; and including one shop coat red oxide, zinc chromate or similar and
A8 approved primer and 2 finishing coats of gloss oil paint after erection: refer to DWG #1 attached 1
Solar panels support structure constructed according to design including anti theft U-channels 50mm x
A9 50mm, including Aluminium U 3mm channel, 7mm angle lines, sum 1
Warranty (months): 12
Page 73
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
A14 345W solar modules, voc 46.4v +/-3% OR alternative module combination ea 24
A18 2" well seal complete (union, tee and Elbow etc) ea 4
To Collection
Excavation(Provisional)
Excavation including maintaining and supporting sides and keeping free from water, mud and fallen
materials by bailing, pumping or otherwise
Prepare site by stripping top 200 mm of soil to remove all debris including sand (if any) from site and
A1 carting away spoil m2 70
A2 Pit excavation commencing at reduced levels depth not exceeding 1.50m deep m3 2
Concrete work
Reinforcement
Sawn formwork
A7 Formwork to sides m 2
Structural steelwork
Supply, fabricate and erect the following framed structural steelwork; complete with and including all
welded and bolted connections; and including one shop coat red oxide, zinc chromate or similar and
A8 approved primer and 2 finishing coats of gloss oil paint after erection: refer to DWG #1 attached 1
Page 74
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Solar panels support structure constructed according to design including anti theft U-channels 50mm x
A9 50mm, including Aluminium U 3mm channel, 7mm angle lines, sum 1
Warranty (months): 12
A14 345W solar modules, voc 46.4v +/-3% OR alternative module combination ea 36
A18 2" well seal complete (union, tee and Elbow etc) ea 6
To Collection
SUMMARY
Page 75
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
4 WATER TROUGHS
5 FENCING
6 DRIP IRRIGATION
8 PRIME COSTS
9 TOTAL
Page 76
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Page 77
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Page 78
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Page 79
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Page 80
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Page 81
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Page 82
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Page 83
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Page 84
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
0
0
0
0
0
Page 85
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
0
0
0
0
0
0
0
0
0
0
0
Page 86
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
0
0
0
0
0
0
0
0
0
0
0
Page 87
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Page 88
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
0
0
0
0
0
0
0
0
Page 89
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
0
0
Page 90
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
0
0
0
0
0
0
Page 91
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
0
0
0
0
0
0
0
0
Page 92
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
0
0
0
0
0
0
0
0
0
0
0
Page 93
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Page 94
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Page 95
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Page 96
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Page 97
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Page 98
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
RATE AMOUNT
Page 99
BILL OF QUANTITIES FOR THE PROPOSED CONSTRUCTION OF IRRIGATION SCHEMES IN GWEMBE DISTRICT UNDER
THE SCRALA PROJECT
Page 100