Office Memorandum Subject: Guidelines For Implementation of Feeder Level Solarisation Under Component-C of PM-KUSUM Scheme
Office Memorandum Subject: Guidelines For Implementation of Feeder Level Solarisation Under Component-C of PM-KUSUM Scheme
32/645/2017-SPV Division
Government of India
Ministry of New and Renewable Energy
***
Office Memorandum
Subject: Guidelines for Implementation of Feeder Level Solarisation under Component-
C of PM-KUSUM Scheme
Vide OM of even number dated 04.11.2020, Ministry had issued scale-up and
expansion of Pradhan Mantri Urja Suraksha evam Utthaan Mahabhiyaan (PM KUSUM)
Scheme. Under the scaled up Scheme, a target of solarization of 7.5 lakh existing agricultural
pumps has been kept through feeder level solarization under Component-C.
2. Under the above mentioned Order, it was also informed that guidelines for feeder
level solarization under Component-C will be issued separately. Accordingly, in continuation
of the above mentioned Order and Guidelines for PM KUSUM Scheme dated 22.07.2019
along with amendments and additions thereof, undersigned is directed to issue the Guidelines
for implementation of feeder level solarisation under Component-C of PM-KUSUM Scheme.
(Shobhit Srivastava)
Scientist-D
To
All concerned
Guidelines for Implementation of Feeder Level Solarisation under Component-C of
PM-KUSUM Scheme
1. Background
Ministry had issued detailed Guidelines for implementation of Component-C of PM-KUSUM
Scheme on 8 November 2019. As per provisions of the PM-KUSUM Scheme, the grid
connected agriculture pumps can be solarised with central and state subsidy of 30% each and
farmer’s contribution of 40%. The solar capacity allowed is up to two times of the pump
capacity in kW and surplus power will be purchased by DISCOM. Since this component was
to be implemented on pilot mode, flexibility was given to states for using different models
like net-metering, replacing pump with BLDC pump or any other innovative model as
deemed fit by the states.
Based on discussions held with states it has been decided to also include feeder level
solarisation under Component-C of PM-KUSUM Scheme. Accordingly, these guidelines are
being issued to provide broad implementation framework for feeder level solarisation.
2. Implementation Methodology
The Distribution Company (DISCOM)/Power Department will be the implementing agency
for feeder level solarisation in their respective areas. However, state Government may
appoint any other expert agency to help DISCOM for tendering and other related activities of
installation of solar power plant for feeder level solarisation.
Where agriculture feeders have already been separated the feeders may be solarised under the
scheme. This will lead to lower cost both in terms of lower capital cost and cost of power.
Feeders having major load for agriculture may also be considered for solarisation under the
Scheme. The requirement of total annual power for an agriculture feeder will be assessed and
a solar power plant of capacity that can cater to the requirement of annual power for that
agriculture feeder can be installed either through CAPEX mode or RESCO mode, which will
supply solar power to that feeder.
For example, a feeder having annual power requirement of say 10 lakh units, the power can
be supplied by solar power plant of capacity around 600 kW with CUF of 19%. Higher or
lower CUF, depending upon the average solar insolation available in the areas, may be
considered for assessing solar power capacity.
Feeder level solar power plant may be installed to cater to the requirement of power for a
single feeder or for multiple agriculture feeders emanating from a distribution sub-station
(DSS) to feed power at 11 kV or at the higher voltage level side of the DSS depending upon
on factors like availability of land, technical feasibility, etc., and there is no cap of the
capacity of solar power plant for feeder level solarisation.
The DISCOMs may identify land near DSS, get ownership of land or its lease rights, provide
connectivity at DSS and lay sub-transmission line between DSS and solar power plant.
For the purpose of calculating CFA, the cost of installation of solar power plant has been
estimated as Rs. 3.5 Cr/MW. Under the Scheme solarisation of pumps of any capacity is
allowed, however, in case of pumps of capacity above 7.5 HP, the CFA will be limited to
solar capacity for 7.5 HP pumps.
Advance CFA up to 40% of the total eligible CFA will be released to DISCOMs on
completion of tendering process and signing of work agreement with EPC contractor selected
for installation of solar power plant. Balance CFA will be released on successful
commissioning of solar power plant and plant starts supplying power to agriculture feeder(s).
The process of tendering and signing of work agreement with EPC contractor should
normally be completed by implementing agency within six months from the date of issuance
of sanction by MNRE.
The DISCOM may carry-out operation and maintenance of the solar power plant.
Alternatively, the EPC contractor who install the solar power plant may also be given task for
O&M of plant and supply guaranteed solar power for 25 years. Payment for O&M of solar
plant can be linked with energy production. In case of failure of solar power plant to supply
required solar power for the complete 25 years of project life, the MNRE may direct the
DISCOM to refund the CFA amount on prorata basis. An undertaking to this effect will be
submitted by DISCOM to MNRE.
B. Implementation under RESCO Model
For installation of feeder level solar power plants through RESCO model, the developers will
be selected on the basis of lowest tariff offered for supply of required solar power for a period
of 25 years. The developer will get CFA @ 30% of the estimated cost of installation of solar
power plant i.e. Rs. 1.05 Cr/MW (30% of Rs. 3.5 Cr/MW). The solar power supplied by
RESCO developer would much cheaper than present cost of power delivered at distribution
sub-station and therefore, DISCOM will save the amount equal to difference between the
two. In the RESCO model the burden of electricity subsidy for agriculture will be reduced to
the extent of difference mentioned above and not become zero as in case of CAPEX model,
where once the loan is repaid, subsidy support from state Government is no longer required.
States may choose to provide upfront subsidy in lieu of electricity subsidy being given to
agriculture consumers. This upfront subsidy from state could be in the form of VGF to
RESCO developer, in addition to 30% CFA, to supply power to farmers of an agriculture
feeder at present subsidised rates or any other rate fixed by state Government. For example, if
present subsidised rate for agriculture is Rs. 1.50/kWh, the RESCO developer will be selected
on the basis of lowest VGF bidded for supply of solar power at Rs. 1.50/kWh.
CFA up to 100% of the total eligible CFA will be released to the RESCO developer through
DISCOM on successful commissioning and declaration of Commercial Operation Date
(COD) of solar power plant. The release of CFA to RESCO developer is subject to
submission of bank guarantee equivalent to CFA amount. Bank Guarantee will be released in
four lots of 25% each on successful operation of plant after 2.5 yrs, 5 yrs, 7.5 yrs and 10 yrs
from CoD. For selection of RESCO developer and PPA, the Guidelines and model PPA
issued by MNRE for implementation of Component-A of PM-KUSUM Scheme may be used,
with suitable modifications. The maximum timeline allowed for commissioning of solar
power plant by RESCO Developer will be nine months from the date of signing of PPA. The
process of selection of RESCO Developer and signing of PPA should normally be completed
by implementing agency within six months from the date of issuance of sanction by MNRE.
3. Feeder Separation:
Where agriculture feeders are not separated, loan for feeder separation will be available from
NABARD/PFC/REC. Ministry of Power is also in process of finalising a Scheme to provide
assistance for feeder separation. The savings on account of electricity subsidy on agriculture
and the possible income from the surplus electricity generated by the solar power plant when
it is not being used for irrigation can also be used to pay off the loan taken for feeder
separation.