CONTRACT NO: TLC-14-2020 (LOT-III)

CIVIL WORKS, ERECTION, STRINGING, TESTING & COMMISSIONING OF 500KV D/C QUAD BUNDLE T/ LINE THAR - MATIARI
Tentative Planned Recovery Schedule
SR # Description Marking Jan-23 Feb-23 Mar-23
8-1 16-1 22-1 31-1 8-2 16-2 22-2 28-2 8-3 16-3 22-3 31-3
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
CIVIL WORKS Total Completed Balance
Conventional 117 116.00 1.00
Foundation
Planning For Work Location No. 588
Start Date End Date Days No. of Towers 1
Planned
09-01-2023 20-01-2023 11

Pile Foundation 74 71 3
Planning for work Location No. 669 661-New 661- A
A.
Start Date End Date Days No. of Towers
Planned
09-01-2023 31-01-2023 22

Pile Cap Foundation 75 68.00 7


Planning for work Location No. 658 662 657 654 669 661-New 661-A
Start Date End Date Days No. of Towers 1 1 1 1 1 1 1
Planned
09-01-2023 28-02-2023 50

587, 588, 606, 609, 618,619, 628,629, 645, 646, 654,655, 662,663,
550, 551, 559, 560, 637,638,
Tower Erection 191 102 89 Crew-2 589, 590, 610, 620, 630,631, 647, 648, 656, 664, 665,
552, 553 561, 562 639,640,
592 611, 612 621, 622 632 649, 657, 658 666
563, 565, 613, 614, 623, 624, 633,634, 641, 650,651, 659,
554, 555, 593, 601, 667,668,
Planning For Work Location No. Crew-1 581, 583, 615, 616, 625, 626, 635, 642, 643, 652, 660,661N,
B. 557, 558
586
'604, 605
617 627 636 644 653 661A
669

Start Date End Date Days No. of Towers 8 9 9 10 10 9 8 9 9 8


Planned
09-01-2023 25-03-2023 75

STRINGING WORK 64.00 16.22 47.79


CONDUCTOR, OPGW, Stretch Crew 1 498-480 546-550 550-583 583-609 609-644 644-Gantry
C. SHIELDWIRE
Start Date End Date Days Stringing (km) 6.19 1.40 11.00 8.80 12.10 8.30
Planned
09-01-2023 30-03-2023 80

Note:- This Recovery Scheduled work is based on the following terms & conditions:
1. Client NTDC should ensure that there will be no ROW on any of tower location and access road for a single minute.
2. Client NTDC should manage timely payment of crops compensation to avoid herdles.
3. Shutdown and approvals for crossings should be arranged before time schedule.
4. Allocation of Erection Material and availability from loadabale warehouses.
5. Allocation of Balance Stringing Hardware, Conductor, Shiledwire and OPGW.
6. Approval of pending Motorway crossings' release and entrance permission inside Matiari Converter Station.