PROJECT: Port Arabia Rendundancy Emergency Power Project Proposal

CLIENT : BVGI BILL OF QUANTITY

BOQ -

UNIT COST TOTAL Profit Margin


ITEM DESCRIPTION UNIT QTY
(SR) AMOUNT (SR) 20%

DIV. 1 Civil, Mechanical and Electrical Works

1.2
1 New Generator 500KVA Work Load
Supply 500KVA Set, 3Ph, 230V/120V Set 1 230000 230000 276000
Supply ATS 800 A with controllers Set 1 35000 35000 42000
Installation of new generator and ATS includes the termination of cables Lot 1 5500 5500 6600
Testing and Commissioning Lot 1 5500 5500 6600
2 Existing Generator 70KVA Work Load
Supply ATS 200 A with controllers Set 1 15000 15000 18000
Installation of old generator and ATS includes the termination of cables Lot 1 4000 4000 4800
Testing and Commissioning Lot 1 5500 5500 6600
3 New 500 KVA Transformer Work Load
Supply 500KVA, 13.8KV/230/120V oil type transformer Set 1 96000 96000 115200
Dismantling of old 500KVA transformer, includes the removal of cables Lot 1 3500 3500 4200
Installation of new transformer includes the termination of cables Lot 1 6000 6000 7200
Testing and Commissioning Lot 1 5000 5000 6000
4 Cable and Wires
4C-185mm2 CU/XLPE/PVC includes lugs LM 100 380 38000 45600
3C-70mm2 CU/XLPE/PVC includes lugs LM 50 150 7500 9000
5 Civil Works
Generator concrete foundation lot 2 10000 20000 24000
Transformer concrete foundation lot 1 15000 15000 18000
ATS Support foundation lot 2 3000 6000 7200
Excavation and backfilling lot 1 6500 6500 7800
Lifting Equipment lot 1 8000 8000 9600

Total 504000 604800