ITP For Etmam

Download as pdf or txt
Download as pdf or txt
You are on page 1of 46

Contractor Job Code 5360/B/2020

Contract No. 0-8494-20-000

Project Doc. No. SP-000-16700-****

[要約] Document Class X

South Refineries Company (SRC) - IRAQ


Basrah Refinery Upgrading Project

TRAINING CENTER

Rev. Date Description Prepared by Checked by Approved by

00 8-Sep-21 IFR W.J.Lim D.H.Lee T.K.Kang


Contractor Job Code 5360/B/2020

Contract No. 0-8494-20-000

Project Doc. No. SP-000-16700-****

[要約] Document Class X


Basrah Refinery Upgrading Project
TRAINING CENTER

CONTENTS

REVISION HISTORY ............................................................................................................ 4


REVISION DESCRIPTION ................................................................................................... 5
1 SCOPE ...................................................................................................................... 6
2 REFERENCES DOCUMENT ..................................................................................... 6
3 DEFINITIONS & ABBREVIATIONS .......................................................................... 6
3.1 Definitions ................................................................................................................................... 6
3.2 Abbreviations .............................................................................................................................. 8
4 CONSTRUCTION ITP, CCS AND ITR....................................................................... 8
5 INTERVENTION ABBREVIATION AND NOTIFICATION RULE ............................... 9
6 SUBCONTRACTOR RESPONSIBILITIES .............................................................. 10
7 CONTRACTOR RIGHTS ......................................................................................... 10
ATTACHMENT-1: INSPECTION AND TEST PLAN ........................................................... 10
ATTACHMENT-2: COMPLETION CHECK SHEET (CCS) & INSPECTION TEST REPORT
(ITR)
LIST ................................................................................................................................ 19
ATTACHMENT-3 COMPLETION CHECK SHEET (CCS) & INSPECTION TEST REPORT
(ITR) FORMAT ................................................................................................................... 22
Basrah Refinery Upgrading Project
TRAINING CENTER

REVISION HISTORY

Rev. Section Page Description

00 All All 1st Issuance for Review


Basrah Refinery Upgrading Project
TRAINING CENTER

REVISION DESCRIPTION

Description
Added/
Employer Doc
No. Deleted/ Section
No.
Modified
Basrah Refinery Upgrading Project
TRAINING CENTER

SCOPE

This document describes the Inspection and Test Plan (ITP) including its check sheets and inspection
report format for only to Training Center’s construction work for Basrah Refinery Upgrade Project.

REFERENCES DOCUMENT
The following documents shall be referred to where required.

Document Number Document Title

SP-000-16700-0001 PROJECT QUALITY CONTROL PLAN FOR CONSTRUCTION


WORK (CONSTRUCTION PHASE)

SP-000-16700-0002 QUALITY CONTROL REQUIREMENTS TO SUBCONTRACTOR


(CONSTRUCTION PHASE)

SP-000-16700-0101 NONCONFORMITY CONTROL PROCEDURE AT SITE

DEFINITIONS & ABBREVIATIONS


Definitions
Basrah Refinery Upgrading Project
TRAINING CENTER

The following definitions shall be applied for this project.

Project Basrah Refinery Upgrading Project

Employer The Ministry of Oil, South Refineries Company (SRC)

JGC Corporation who undertakes the Engineering, Procurement and


Contractor
Construction, Commissioning (EPCC) activity for the Project.

Hyundai Engineering & Construction Co., Ltd to whom Contractor has


EPC Subcontractor subcontracted any part of Engineering, Procurement and Construction,
Commissioning (EPCC) activity for the Project.

Any third party to whom Contractor and/or EPC Subcontractor has


Subcontractor
subcontracted any part of the work pursuant the contract.
Basrah Refinery Upgrading Project
TRAINING CENTER

Abbreviations
The following abbreviations shall be applied for this project.

Term Description

JGC JGC Corporation

HDEC Hyundai Engineering & Construction Co., Ltd

PIM Pre-Inspection Meeting

ITP Inspection and Test Plan

CCS Completion Check Sheet

ITR Inspection Test Report

EMP Employer

CTR / EPCS Contractor / EPC Subcontractor

SUB Subcontractor

MAR Material Approval Report

CONSTRUCTION ITP, CCS AND ITR


Basrah Refinery Upgrading Project
TRAINING CENTER

The following construction ITP shall be followed by Subcontractor and implement all inspection in
accordance with the ITP in Attachment 1.

Subcontractor shall fill all related CCS and ITR as per Attachment 2 list and Attachment 3 formats.

These CCS and ITR shall be approved by Contractor/EPC Subcontractor to verify its compliance
against required acceptance criteria.

INTERVENTION ABBREVIATION AND NOTIFICATION RULE.

Intervention abbreviation and notification rule for each intervention level are shown in the following
table and notification requirements shall be followed by Sub-contractor.

Abbreviation Notification Description

Subcontractor Activity shall not continue without


H: Hold
shall submit designated party's presence at the inspection.
notification 24
hours prior to
start activity to Activity may continue
W: Witness Contractor/EPC without designated party’s
Subcontractor presence at the inspection.

Even though none


Contractor/EPC of designated
Subcontractor and/or party’s presence,
Employer inspector will review of test and
randomly monitor and/or inspection records
S: Surveillance Not required survey construction shall be done.
conditions, workmanship
and test/inspection during
his visit or periodical
inspection.

Subcontractor shall provide the Contractor/EPC


Subcontractor and/or Employer with certificates,
R: Record
Not required reports and records as applicable for
Review
Contractor’s/EPC Subcontractor’s review and
confirmation

Subcontractor shall be responsible for undertaking the inspection or


I: Inspection
test and generating the appropriate report and record
Basrah Refinery Upgrading Project
TRAINING CENTER

Subcontractor responsibilities
The witnessed inspections and document reviewed by Contractor/EPC Subcontractor does not relieve Subcontractor of his responsibilities or obligations
under the contract and governing statutory regulations / code.

contractor rights
Contractor/EPC Subcontractor reserve the rights to carry out more detailed inspection and modify this ITP as deemed necessary based on subcontractor
work performance.

ATTACHMENT-1: iNSPECTION AND TEST PLAN

Activity Reference / Applicable Verifying Scope of Inspection


Activities Acceptance Criteria Remarks
No. Specification Documents SUB JGC / HDEC
1. Receiving Material Check
1.1 Type, Size, free from damage Applicable Drawing No deviation CCS-4000-201 I R/S

2 Earth Work
Check for coordinate, elevation and CCS-3100-002 Survey
stability (Benchmark Installation & Report
2.1 Excavation) Applicable Drawing No deviation ITR-3100-002A I S
FDT
ITR-3100-003A Report
Check sand bedding, filling and Survey
structural soil backfilling CCS-3100-004 Report
2.2 Applicable Drawing No deviation I S
ITR-3100-004A FDT
Report
2.3 Conduct compaction test Applicable Drawing No deviation CCS-3100-003 I W
Basrah Refinery Upgrading Project
TRAINING CENTER

Activity Reference / Applicable Verifying Scope of Inspection


Activities Acceptance Criteria Remarks
No. Specification Documents SUB JGC / HDEC

3 Concrete
Slump / Lab test Lab Test
3.1 Applicable Drawing No deviation CCS-3200-002 I W
Record
Check Form work Survey
3.2 Applicable Drawing No deviation CCS-3200-002 I S
Report

3.3 Check Rebar work Applicable Drawing No deviation CCS-3200-002 I S


Check the other embedded items Survey
3.4 Applicable Drawing No deviation CCS-3200-004 I W
Report

3.5 Check fresh concrete condition Applicable Drawing No deviation CCS-3200-004 I W

3.6 Check pouring condition Applicable Drawing No deviation CCS-3200-004 I S


Check protection and curing after Survey
3.7 Applicable Drawing No deviation CCS-3200-004 I S
pouring Report
4 Masonry Concrete Block
4.1 Setting out Applicable Drawing No deviation CCS-4000-203 I S
Basrah Refinery Upgrading Project
TRAINING CENTER

4.2 Dowels and anchors location Applicable Drawing No deviation CCS-4000-203 I S


Pre-wetting of concrete block before
4.3 Applicable Drawing No deviation CCS-4000-203 I R/S
use
Mixing of grout / mortar using
4.4 approved proportion and gauge Applicable Drawing No deviation CCS-4000-203 I S
boxes
4.5 Alignment and plumb Walls Applicable Drawing No deviation CCS-4000-203 I S
Arrangement of stiffener columns
4.6 Applicable Drawing No deviation CCS-4000-203 I S
and bond beams
Size and location of joints, control
4.7 Applicable Drawing No deviation CCS-4000-203 I R/W
and expansion joints
4.8 Ties and bar / mesh arrangement Applicable Drawing No deviation CCS-4000-203 I R/S
Location and type of electrical
4.9 Applicable Drawing No deviation CCS-4000-203 I S
conduit, box and sleeve pipe etc.
Location and size of openings and
4.10 Applicable Drawing No deviation CCS-4000-203 I S
penetrations
4.11 Grouting Applicable Drawing No deviation CCS-4000-203 I S
4.12 Cleaning and Pointing Applicable Drawing No deviation CCS-4000-203 I S
4.13 Curing Applicable Drawing No deviation CCS-4000-203 I S
5 Ceiling Works
Marking and verification of ceiling
5.1 Applicable Drawing No deviation CCS-4000-202 I R
panel layout
Check M&E items above ceiling has
5.2 Applicable Drawing No deviation CCS-4000-202 I W
been completed
Type and elevation of edge
5.3 Applicable Drawing No deviation CCS-4000-202 I R/S
moldings
Basrah Refinery Upgrading Project
TRAINING CENTER

Type, size and spacing of ceiling


5.4 Applicable Drawing No deviation CCS-4000-202 I R/S
hangers
Verify the location and size of
5.5 ceiling mount M&E equipment / Applicable Drawing No deviation CCS-4000-202 I R/S
fixtures
Location, alignment and rigidity of
5.6 Applicable Drawing No deviation CCS-4000-202 I R/S
ceiling suspension system
Elevation of ceiling suspension CCS-4000-202
5.7 Applicable Drawing No deviation I R/S
system
Insulation board / blanket
5.8 Applicable Drawing No deviation CCS-4000-202 I W
installation(Acoustic / Moisture)
Type and thickness of ceiling panels
5.9 ` Applicable Drawing No deviation CCS-4000-202 I S
/ boards

5.10 Ceiling panels / boards installation Applicable Drawing No deviation CCS-4000-202 I S

Treatment of cut panel / board


5.11 Applicable Drawing No deviation CCS-4000-202 I S
edges and board joints
Surface condition for exposed
5.12 Applicable Drawing No deviation CCS-4000-202 I S
ceiling frame and panel boards

6 Tile Work (Wall)


Layout, marking and check of
6.1 Applicable Drawing No deviation CCS-4000-205 I S
substrate
Check location and size of
6.2 Applicable Drawing No deviation CCS-4000-205 I W
concealed M&E items
Verify the type, pattern and layout of
6.3 Applicable Drawing No deviation CCS-4000-205 I W
tiles

6.4 Corner and joint beads setting Applicable Drawing No deviation CCS-4000-205 I S
Basrah Refinery Upgrading Project
TRAINING CENTER

Method, type, mixing ratio and


6.5 application of bedding mortar / grout Applicable Drawing No deviation CCS-4000-205 I W
or adhesive
Alignment, level and flatness /
6.6 Applicable Drawing No deviation CCS-4000-205 I S
evenness of installed tiles
Conditions of cut tile edges and
6.7 projection around embedded pipes Applicable Drawing No deviation CCS-4000-205 I S
and fitting

6.8 Check adhesion of tiles by sounding Applicable Drawing No deviation CCS-4000-205 I S


Type, color and application of grout
6.9 Applicable Drawing No deviation CCS-4000-205 I S
for tile joints
Type, color and application of seal
6.10 for control joints Applicable Drawing No deviation CCS-4000-205 I S

6.11 Cleaning and polishing Applicable Drawing No deviation CCS-4000-205 I S

7 Gypsum board Partition

7.1 Layout and marking Applicable Drawing No deviation CCS-4000-206 I R

7.2 Location and size of Wall openings Applicable Drawing No deviation CCS-4000-206 I S
Location, alignment, spacing and
7.3 rigidity of runners / studs installed Applicable Drawing No deviation CCS-4000-206 I S
per manufacturer‘s recommendation
Reinforcement for wall openings,
7.4 Wall mounted M&E items, Applicable Drawing No deviation CCS-4000-206 I W
equipment, fixtures and fittings etc.
Check concealed M&E items has
7.5 Applicable Drawing No deviation CCS-4000-206 I W
been completed
Insulation board / blanket
7.6 Applicable Drawing No deviation CCS-4000-206 I W
installation

7.7 Type and thickness of Wall board Applicable Drawing No deviation CCS-4000-206 I S
Basrah Refinery Upgrading Project
TRAINING CENTER

Wall board layout, height, number


7.8 Applicable Drawing No deviation CCS-4000-206 I S
and spacing of tapping screws
Treatment of cut board edges,
7.9 Applicable Drawing No deviation CCS-4000-206 I S
board joints and corner beads

7.10 Straightness and flatness Applicable Drawing No deviation CCS-4000-206 I S

7.11 Expansion / control joint Applicable Drawing No deviation CCS-4000-206 I S


Seal for penetrations of fire rated
7.12 wall Applicable Drawing No deviation CCS-4000-206 I S

8 Floor Works
Layout, marking and check of
8.1 Applicable Drawing No deviation CCS-4000-207 I R
substrate
Check location and size of
8.2 Applicable Drawing No deviation CCS-4000-207 I W
concealed M&E items
Verify the type, pattern and layout of
8.3 Applicable Drawing No deviation CCS-4000-207 I S
tiles

8.4 Corner and joint beads setting Applicable Drawing No deviation CCS-4000-207 I S
Method, type, mixing ratio and
8.5 application of bedding mortar / grout Applicable Drawing No deviation CCS-4000-207 I R
or adhesive
Alignment, level and flatness /
8.6 Applicable Drawing No deviation CCS-4000-207 I S
evenness of installed tiles
Conditions of cut tile edges and
8.7 projection around embedded pipes Applicable Drawing No deviation CCS-4000-207 I S
and fitting

8.8 Check adhesion of tiles by sounding Applicable Drawing No deviation CCS-4000-207 I S


Type, color and application of grout
8.9 Applicable Drawing No deviation CCS-4000-207 I S
for tile joints
Basrah Refinery Upgrading Project
TRAINING CENTER

Type, color and application of seal


8.10 for control joints Applicable Drawing No deviation CCS-4000-207 I S

8.11 Cleaning and polishing Applicable Drawing No deviation CCS-4000-207 I S

9 Doors & windows

9.1 Setting out Applicable Drawing No deviation CCS-4000-208 I S


Location and size of structural
9.2 Applicable Drawing No deviation CCS-4000-208 I S
opening
Type, size, location and orientation
9.3 Applicable Drawing No deviation CCS-4000-208 I S
of door / window being installed

9.4 Conditions of anchors/fasteners Applicable Drawing No deviation CCS-4000-208 I S

9.5 Grouting for threshold Applicable Drawing No deviation CCS-4000-208 I S


Alignment plumb elevation and
9.6 Applicable Drawing No deviation CCS-4000-208 I S
orientation
Rigidity of frame fit-up / fixing with
9.7 Applicable Drawing No deviation CCS-4000-208 I S
structure
Grouting for gap between frame and
9.8 Applicable Drawing No deviation CCS-4000-208 I S
structure

9.9 Paint finish Applicable Drawing No deviation CCS-4000-208 I S


Type of glass and face direction for
9.10 installation Applicable Drawing No deviation CCS-4000-208 I S

Bead / Seal conditions for glass


9.11 panels Applicable Drawing No deviation CCS-4000-208 I S

Type, location and orientation of


9.12 Hardware fitting Applicable Drawing No deviation CCS-4000-208 I W

9.13 Earth bonding Applicable Drawing No deviation CCS-4000-208 I S

9.14 Labels for fire rated door Windows Applicable Drawing No deviation CCS-4000-208 I W
Basrah Refinery Upgrading Project
TRAINING CENTER

9.15 Functional / operational check Applicable Drawing No deviation CCS-4000-208 I S

10 Waterproofing
Location of up-stands, pipe
10 penetration, foundation bases, Applicable Drawing No deviation CCS-4000-302 I R
10.1 raisers, drain etc.

Cant installation / Corner fillet sand


10.2 cement mortar Applicable Drawing No deviation CCS-4000-302 I S

Surface conditions (dry, clean,


10.3 smooth etc.) Applicable Drawing No deviation CCS-4000-302 I W

10.4 Application of Waterproofing primer Applicable Drawing No deviation CCS-4000-302 I W


Waterproofing membrane direction,
10.5 lap length, joint treatment etc. Applicable Drawing No deviation CCS-4000-302 I W

Installation of Waterproofing
10.6 membrane at corners, risers, end Applicable Drawing No deviation CCS-4000-302 I W
stop, penetrations and drain

10.7 Water leak test: Applicable Drawing No deviation CCS-4000-302 I W

10.8 ` Applicable Drawing No deviation CCS-4000-302 I S


Seal for joints and gaps,
Protection gravel / Con’c / mortar
10.9 Applicable Drawing No deviation CCS-4000-302 I S

11 Painting
Verification of Paint Material and MAR with
11.1 Certificate Applicable Drawing No deviation CCS-3930-001 I S Supplier’s
certificate

11.2 Storage Conditions Applicable Drawing No deviation CCS-3930-001 I S


Basrah Refinery Upgrading Project
TRAINING CENTER

Ambient Temperature and Relative


11.3 Applicable Drawing No deviation CCS-3930-002 I S
Humidity
Surface Temperature and Dew
11.4 Applicable Drawing No deviation CCS-3930-002 I S
Point
Check for Surface Preparation /
11.5 Applicable Drawing No deviation CCS-3930-002 I S
Check Surface Dust Level

11.6 Final Inspection Applicable Drawing No deviation CCS-3930-006 I S

11.7 Touch up Paint Applicable Drawing No deviation CCS-3930-006 I S

12 Steel Structural & Misc. steel


Verify that the quantity of the bolts
12.1 for each grade, dia. and length are Applicable Drawing No deviation CCS-3300-001 I S
same as erection documents
Verify the member piece marks with
erection drawings, and visual check Applicable Drawing No deviation CCS-3300-001 I
12.2 S
for damage of members and its
coating
Check Foundation(Chipping, Applicable Drawing No deviation CCS-3300-002 I
12.3 S
padding, Anchor bolt, etc.)
CCS-3300-004
12.4 Bolt Tightening / Welding Applicable Drawing No deviation I W
CCS-3300-005

12.5 Confirmation of Grouting Material Applicable Drawing No deviation CCS-3300-008 I S


Visual Inspection of Grout (No Applicable Drawing No deviation CCS-3300-008 I
12.6 W
Cracks and No Voids)
13 Electrical work
13.1 Electrical System Installation Applicable Drawing No deviation CCS-4000-401 I R/S
13.2 Electrical Equipment System Applicable Drawing No deviation CCS-4000-402 I R/S
14 Plumbing work
14.1 Plumbing Installation Applicable Drawing No deviation CCS-4000-501 I S
Basrah Refinery Upgrading Project
TRAINING CENTER

Performance Check for Plumbing Applicable Drawing No deviation CCS-4000-502 I


14.2 W
Equipment

ATTACHMENT-2: Completion check sheet (CCS) & inspection test report (itr) list

CCS & ITR Form


No Title Remarks
Number

1. CCS-4000-201 Completion Check Sheet for Receiving Material Check

2. CCS-4000-202 Completion Check Sheet for Ceiling Works

3. CCS-4000-203 Completion Check Sheet for Masonry Concrete Block

4. CCS-3200-002 Completion Check Sheet for Design mix & Trial mix Approval

5. CCS-3200-004 Completion Check Sheet for Pre-pour Inspection

6. CCS-4000-205 Completion Check Sheet for Tile Work (Wall)

7. CCS-4000-206 Completion Check Sheet for Gypsum board Partition

8. CCS-4000-207
Completion Check Sheet for Floor Works

9. CCS-4000-208
Completion Check Sheet for Doors & Windows

10. CCS-3100-002 Completion Check Sheet for Benchmark Installation


Basrah Refinery Upgrading Project
TRAINING CENTER

11. CCS-3100-003 Completion Check Sheet for Excavation Work

12. CCS-3100-004 Completion Check Sheet for Filling and Compaction

13. CCS-4000-302 Completion Check Sheet for Waterproofing

14. CCS-3930-001 Completion Check Sheet for MATERIAL INSPECTION

15. CCS-3930-002
Completion Check Sheet for Surface Preparation & Paint Application

16. CCS-3930-006 Completion Check Sheet for Final Inspection

17. CCS-3300-001
Completion Check Sheet for Material Inspection
18. CCS-3300-002 Completion Check Sheet for Base Connection

19. CCS-3300-004 Completion Check Sheet for Erection of Steel Structure

20. CCS-3300-005 Completion Check Sheet for Visual Check of Field Weld

21. CCS-3300-008 Completion Check Sheet for Grout of steel structure

22. CCS-4000-401 Completion Check Sheet for Electrical System Installation

23. CCS-4000-402 Completion Check Sheet for Electrical Equipment System

24. CCS-4000-501 Completion Check Sheet for Plumbing Installation


Basrah Refinery Upgrading Project
TRAINING CENTER

25. CCS-4000-502 Completion Check Sheet for Performance Check for Plumbing Equipment

26. ITR-3100-002A ITR for Benchmark Installation(Survey Verification Report)

27. ITR-3100-003A ITR for Excavation Work(Survey Verification Report)

28. ITR-3100-004A ITR for Filling & Compaction(Survey Verification Report)


Basrah Refinery Upgrading Project
TRAINING CENTER

Attachment-3 Completion CHECK SHEET (CCS) & INSPECTION TEST REPORT (ITR) FORMAT

CCS No.:4000-201

Completion Check Sheet for Receiving Material Check

Project Job Code

TAG No / ID TAG / ID Description

Drawing No. Rev No.

PCWBS FWBS

System No. Sub System No.

Report No. Report Rev. No.

Items to be Checked Results


ITP Item Punch
Accepted
No. Activity / Description List(Y/N)
Y/N/NA

1 Receiving Material Check

1.1 Type, Size, free from damage

General Remarks:

SUB JGC / HDEC

SIGNATURE

PRINT NAME

DATE

COMPANY
Basrah Refinery Upgrading Project
TRAINING CENTER

CCS No.:4000-202

Completion Check Sheet for Ceiling Works

Project Job Code

TAG No / ID TAG / ID Description

Drawing No. Rev No.

PCWBS FWBS

System No. Sub System No.

Report No. Report Rev. No.

Items to be Checked Results


ITP Item Punch
Accepted
No. Activity / Description List(Y/N)
Y/N/NA

2 Ceiling Works

2.1 Marking and verification of ceiling panel layout

2.2 Check M&E items above ceiling has been completed

2.3 Type and elevation of edge moldings

2.4 Type, size and spacing of ceiling hangers

Verify the location and size of ceiling mount M&E equipment /


2.5
fixtures

2.6 Location, alignment and rigidity of ceiling suspension system

2.7 Elevation of ceiling suspension system

2.8 Insulation board / blanket installation

2.9 Type and thickness of ceiling panels / boards

2.10 Ceiling panels / boards installation

2.11 Treatment of cut panel / board edges and board joints

2.12 Sealing / Caulking to unnecessary gaps for edge molding

2.13 Surface condition for exposed ceiling frame and panel boards

General Remarks:

SUB JGC / HDEC

SIGNATURE

PRINT NAME

DATE

COMPANY
Basrah Refinery Upgrading Project
TRAINING CENTER

CCS No.:4000-203

Completion Check Sheet for Masonry Concrete Block

Project Job Code

TAG No / ID TAG / ID Description

Drawing No. Rev No.

PCWBS FWBS

System No. Sub System No.

Report No. Report Rev. No.

Items to be Checked Results


ITP Item Punch
Accepted
No. Activity / Description List(Y/N)
Y/N/NA

3 Masonry Concrete Block

3.1 Setting out

3.2 Dowels and anchors location

3.3 Pre-wetting of concrete block before use

Mixing of grout / mortar using approved proportion and gauge


3.4
boxes

3.5 Alignment and plumb Walls

3.6 Arrangement of stiffener columns and bond beams

3.7 Size and location of joints, control and expansion joints

3.8 Ties and bar / mesh arrangement

3.9 Location and type of electrical conduit, box and sleeve pipe etc

3.10 Location and size of openings and penetrations

3.11 Grouting

3.12 Cleaning and Pointing

3.13 Curing

General Remarks:

SUB JGC / HDEC

SIGNATURE

PRINT NAME

DATE

COMPANY
Basrah Refinery Upgrading Project
TRAINING CENTER

CCS No.: 3200-002

Completion Check Sheet for


Design mix & Trial mix Approval

Project Job Code

TAG No / ID TAG / ID
Description

Drawing No. Rev No.

PCWBS FWBS

System No. Sub System No.

Report No. Report Rev. No.

Items to be Checked Results


ITP Item Punch
Accepted
No. Activity / Description List(Y/N)
Y/N/NA

2 Design mix & Trial mix approval

2.1 Slump test

Lab test

- Mix density & Cement content

2.2 - Air content

- Chloride content

- SO3 content

2.3 Compression cube (cylinder) test (7days, 28days)

General Remarks:

SUB JGC / HDEC

SIGNATURE

PRINT NAME

DATE

COMPANY
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER

CCS No.:4000-206

COMPLETION CHECK SHEET FOR GYPSUM BOARD


PARTITION

Project Job Code


TAG No / ID TAG / ID Description
Drawing No. Rev No.
PCWBS FWBS
System No. Sub System No.
Report No. Report Rev. No.
Items to be Checked Results
ITP Item Punch
Accepted
No. Activity / Description List(Y/N)
Y/N/NA

6 Gypsum board Partition

6.1 Layout and marking

6.2 Location and size of Wall openings


Location, alignment, spacing and rigidity of runners / studs installed per
6.3 manufacturer‘s recommendation
Reinforcement for wall openings, Wall mounted M&E items, equipment,
6.4 fixtures and fittings etc.

6.5 Check concealed M&E items has been completed

6.6 Insulation board / blanket installation

6.7 Type and thickness of Wall board

6.8 Wall board layout, height, number and spacing of tapping screws

6.9 Treatment of cut board edges, board joints and corner beads

6.10 Straightness and flatness

6.11 Expansion / control joint

6.12 Seal for penetrations of fire rated wall


General Remarks:

SUB JGC / HDEC

SIGNATURE

PRINT NAME

DATE

COMPANY
Basrah Refinery Upgrading Project
TRAINING CENTER

CCS No.:4000-207

Completion Check Sheet for Floor Works

Project Job Code

TAG No / ID TAG / ID Description

Drawing No. Rev No.

PCWBS FWBS

System No. Sub System No.

Report No. Report Rev. No.

ITP Items to be Checked Results


Punch
Item Accepted
Activity / Description List(Y/N)
No. Y/N/NA

7 Floor Works

7.1 Layout, marking and check of substrate

7.2 Check location and size of concealed M&E items

7.3 Verify the type, pattern and layout of tiles

7.4 Corner and joint beads setting

Method, type, mixing ratio and application of bedding mortar / grout or


7.5
adhesive

7.6 Alignment, level and flatness / evenness of installed tiles

Conditions of cut tile edges and projection around embedded pipes


7.7
and fitting

7.8 Check adhesion of tiles by sounding

7.9 Type, color and application of grout for tile joints

7.10 Type, color and application of seal for control joints

7.11 Cleaning and polishing

General Remarks:

SUB JGC / HDEC

SIGNATURE

PRINT NAME

DATE

COMPANY
Basrah Refinery Upgrading Project
TRAINING CENTER

CCS No.:4000-208

Completion Check Sheet for Doors & Windows

Project Job Code

TAG No / ID TAG / ID Description

Drawing No. Rev No.

PCWBS FWBS

System No. Sub System No.

Report No. Report Rev. No.

Items to be Checked Results


ITP Item Punch
Accepted
No. Activity / Description List(Y/N)
Y/N/NA

8 Doors & windows

8.1 Setting out

8.2 Location and size of structural opening

8.3 Type, size, location and orientation of door / window being installed

8.4 Conditions of anchors/fasteners

8.5 Grouting for threshold

8.6 Alignment plumb elevation and orientation

8.7 Rigidity of frame fit-up / fixing with structure

8.8 Grouting for gap between frame and structure

8.9 Paint finish

8.10 Type of glass and face direction for installation

8.11 Bead / Seal conditions for glass panels

8.12 Type, location and orientation of Hardware fitting

8.13 Earth bonding

8.14 Labels for fire rated door Windows

8.15 Functional / operational check

General Remarks:

SUB JGC / HDEC

SIGNATURE

PRINT NAME

DATE

COMPANY
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER
Basrah Refinery Upgrading Project
TRAINING CENTER