Module 1 - Btech413-Reviewer
Module 1 - Btech413-Reviewer
1. Cast-in-place/PRE-CAST Construction
2. Prestressed Concrete
3. Composite
4. Cable/Tensile
FLAT PLATES
5. Membrane
6. Shell - Erected as one-way or two-way slabs
7. Pre-engineered - Support is provided directly through
8. Geodesic columns or walls
- Easy and simple formworks
ALTERNATIVE BUILDING CONSTRUCTION
- Length of 6 to 8m; Live loads among 3 and
Cast-in-place - cast in situ construction 5KN/m2
- Pre-stressed flat plates remain among 8 to
- a.k.a poured-in-place
12 m.
- concreting technique which undertaken in
- can also be erected as post-tensioned
concrete component’s finished position.
slabs
- Preferred choice for concrete slabs.
- low-cost formwork, uncovered flat ceilings,
Floor slab – also called plate slab/ filigree slab rapid construction
- low shear strength
- Is a reinforced concreted slab with min.
thickness of 5-6cm. CONVENTIONAL SLAB
- Made into solid or monolithic
- supported on beams and columns
- Standard residential construction: 4inches
- thickness is small; depth of beam is large;
- 5 to 6 inches recommended for occasional
load is transferred onto the beam and then
heavy loads
the column
DIFFERENT TYPES OF CONCRETE SLABS IN - requires extra formwork
CONSTRUCTION - no column cap, thickness is 10cm
- 5 to 6 inches recommended for
FLAT SLAB – supported directly by a occasionally heavy loads
concrete/caps
TYPES OF CONVENTIONAL SLABS
- Known as a beam-less slabs
- Gives attractive appearance 1. ONE WAY SLAB
- Less sensitive of fire - Supported by a beam on two opposite side
- Easy to construct and require less formwork - Horizontal=main reinforcement bars;
- Min. thickness of 0.2m vertical=distribution bars
- spans of 6 to 9m - All cantilever slabs are usually one-way
- Square in shape and 4 m in size - ability to create monolithic concrete slabs
2. TWO-WAY SLAB makes lift slab construction technique
- Supported by beams from all sides useful in quickly creating structures with
- Length and width of slabs is more than 4m repetitive form works like parking ramps.
ADVANTAGES:
WAFFLE SLABS
o Only formwork for the edges of the slab
- made of reinforced concrete with holes is required; no centering to the soffit of
underneath slabs is needed.
- preferred for large spans greater than 12m o Slabs are cast monolithically and
- used to avoid columns interfering the space designed to span continuously between
- flat on top, grid-like surface in bottom points of support, allowing for the use of
- grid is created by removal of molds minimal slab thickness.
- composed by intricate formwork, more o The lift-slab construction method is
expensive than other slabs advantageous in buildings with similar
- ribs are constructed perpendicular to each floor plans throughout the height of the
other building, especially where a flush slab
- provide good aesthetic features is desired.
- depth slab varies: from 85 to 100 mm o The lift-slab method can be used with
- width of inside beams range: from 110 to ribbed slabs, not just flat slabs, though
200 mm it may compromise the ease of casting.
DISADVANTAGES:
MODULE 1.2 o If not properly handled, precast units may
be damaged.
LIFT SLAB – also called youtz-slick method
o It can be challenging to produce
- constructing concrete building by casting satisfactory connections between precast
the floor or roof slab on top of the previous members.
and then raising the slab up with hydraulic o Special equipment is necessary for lifting
jacks and moving the precast units.
- allows for large portion of the work to o The economy achieved in precast
completed at ground level construction is partially offset by the costs
of transport and handling of precast - Also, T-joist slab system requires less
members. concrete on site, reduced steel
o It is essential to locate the precast factory in reinforcement
a location that minimizes transport and - 20% savings compared to conventional
handling charges as much as possible. system
- Speeds up construction
EQUIPMENT USED FOR LIFT SLABS
- No exposed metal parts, durable and minimal to
HYDRAULIC JACKS maintain
- Clean and safe jobsite
- Is a Hydraulic piece of equipment
- Can lift slabs on columns loaded up to T-JOIST - precast pre-stressed Inverted T-beams
100,000 pounds at speeds of up to 14 ft./hr. and roof slab system
- cores can function as service ducts and Holds vertical forms in place; supports platforms
significantly reduce the self-weight of the and scaffolding; transmits lifting force.
slabs, maximizing structural efficiency.
3. Yokes
DOUBLE TEE FLOORS
Attach/support wales; transmit lifting forces; resist
- Load-bearing structure that resembles two lateral force from concrete.
5- beams connected to each other side by
4. Jacks
side.
Mounted on jack rods; lift the slip form system;
enable lifting of entire formwork.
MODULE 1.4
5. Jack Rods
SLIP FORMWORKS - construction method in which
Support jacks; essential for climbing the formwork
formwork continuously rises vertically as a work
system.
process.
ADVANTAGES
DISADVANTAGES