Unit - 9
Unit - 9
Lecture Number 41
Widening of Gauge & Vertical Curves
RAJAT RASTOGI
CIVIL ENGINEERING
1
Discussed in Previous Lecture
• Transition curve
– Numerical
– Laying a Transition curve
– Compound curve
– Reverse curve
• Extra clearances
2
Today’s Discussion
• Widening of Gauge
• Gradients
• Vertical Curves
– Types
– Length
– Setting in Field
3
Widening of Gauge
4
Widening of Gauge
5
Widening of Gauge
6
Widening of Gauge
• Reasons summarized:
– Centrifugal force
– Rigidity of vehicle base
– Relative distance traveled by wheels
• Loss of contact between wheel and rail in trailing
position
– Slip of inner wheels backward/ Skid of outer
wheels forward
7
Widening of Gauge – Numerical 1
8
Widening of Gauge – Numerical 1
• Solution:
– Extra width of gauge = w = 13(B+L)2 / R
– w = 13*(6 + 0.446)2/168 = 3.21 cm or 32.1mm
• Gauge Tolerances as per IR
– Straight track including curves of radius 350 m for
BG: - 5mm to +3mm (tight to slack)
– For curves of radius less than 350 m for BG: up to
+10mm (slack)
9
Gradients
10
Gradients
• These need to be provided to:
– Connect various stations located at different
elevations
– Follow the natural contours on the ground to the
extent possible
– Reduce the cost of earthwork required
• Types:
– Ruling
– Pusher or Helper
– Momentum
– Gradient in station yards
11
Gradients
• Ruling Gradient
– Determined by maximum load that a locomotive
can haul with maximum permissible speed.
– Extra Pull required by a locomotive on a gradient
with degree inclination can be given as:
– P = W sin = W x gradient
– Ruling gradient with one locomotive in Plain area:
1 in 150 to 1 in 250
– Ruling gradient with one locomotive in Hilly area:
1 in 100 to 1 in 150
12
Gradients
• Ruling Gradient
– Once a ruling gradient is specified for a section,
then all other gradients provided in that section
should be flatter than the ruling gradient (after
making due compensation for curvature)
• Momentum Gradient
– Gradient steeper than ruling gradient that is
overcome by momentum gathered while having a
run in plain or on falling gradient in valleys
13
Gradients
• Momentum Gradient
– Uses additional kinetic energy received during run
on a section
– No obstruction like signals are provided on sections
with these gradients (which otherwise may bring the
train to a critical juncture)
• Pusher or Helper Gradient
– Gradient steeper than ruling gradient requiring extra
locomotive
• It reduces the length of a section
• It also reduces the overall cost
– E.g. Darjeeling Railway section
14
Gradients
15
Gradients - Compensation
16
Vertical Curves
17
Vertical Curves
• Solution:
– Connecting the two gradients by a smooth
vertical curve at the location of kink, eliminating
the rough run and providing a smooth
comfortable movement
– Based on the orientation of the two meeting
gradients, the vertical curve can take a shape of
summit (hog) curve or a valley (sag) curve
– Raising gradient is considered as positive and
falling gradient as negative
18
Vertical Curves
19
Vertical Curves
SUMMIT CURVES
20
Vertical Curves
VALLEY CURVES
21
Vertical Curves
22
Vertical Curves
23
Vertical Curves
24
Vertical Curves
25
Vertical Curves – Setting in Field
• Two methods:
– Tangent Correction method
– Chord Deflection method
– Tangent correction method is simpler and easy to
implement in the field
– Process:
• Calculate length of vertical curve
• Calculate RL of tangent point and apex
• Compute tangent correction
26
Vertical Curves – Setting in Field
• Two methods:
– Tangent Correction method
• Tangent correction: y = cx2
• Where, c = (g1 – g2)/4n
• y = vertical ordinate from chord
• g = gradient, positive or negative as per rise or fall
• n = number of chords up to half the length of the
curve
• Elevation of the stations on the curve are calculated
by algebraically adding the tangent corrections on
tangent
27
Vertical Curves – Setting in Field
• Chainages of Points
– Chainage of point ‘A’ = chainage of intersection
point (O) – L/2
– Chainage of point ‘B’ = chainage of intersection
point (O) + L/2
• Reduced Levels
– RL of point ‘A’ = RL of intersection point (O) –
L/2*(gi/100)
– RL of point ‘B’ = RL of intersection point (O) –
L/2*(- gj/100)
28
Vertical Curves – Setting in Field
30
Today we have discussed widening of gauge,
gradients used on tracks, vertical curves, their
types, calculation of length, setting in the field.
Thank You
31
RAILWAY ENGINEERING
Lecture Number 42
Realignment of Curves
RAJAT RASTOGI
CIVIL ENGINEERING
1
Discussed in Previous Lecture
• Widening of Gauge
• Gradients
• Vertical Curves
– Types
– Length
– Setting in Field
2
Today’s Discussion
• Realignment of Curves
– Reasons
– Permissible limits
– String line operation
– Double and multiple tracks
– Rail cutting
– Check rails
3
Realignment of Curves
4
Realignment of Curves
Speed on curve Limits of station-to-station variation in
Versine, mm
160 kmph and up 10mm (15mm for speed of 110 kmph) OR
to 110 kmph 20% of average versine on circular
portion; whichever is more
Below 110 kmph 20mm OR 20% of average versine on
and up to 50 kmph circular portion; whichever is more IRPWM 2020
5
Realignment of Curves
6
Realignment of Curves
7
Realignment of Curves
• Reason of distortion:
– Large horizontal forces exerted on the rails by
passing trains tend to make the curve flatter at some
locations and sharper at other locations, thus
causing a change in the radius of the curve
• String Line Operation
– Survey of existing curve by measuring Versines
– Determining revised alignment and computing
slews, including correct superelevation
– Slewing of the curve to the revised alignment
8
Realignment of Curves
9
Realignment of Curves
10
Realignment of Curves
11
Realignment of Curves
12
Realignment of Curves
13
Realignment of Curves
Determination of
revised alignment
IRPWM 2020
14
Realignment of Curves
versine.
– The slew at the last station should be zero,
otherwise track beyond this point will be affected by
slew. To make it zero, correcting couples are applied
15
Realignment of Curves
• Computation of slews
– Calculate length of transition and determine the
versine gradient on the transition
– Calculate versine difference (as discussed before) for
first and second summations
– Review the proposed versines if necessary and IRPWM 2020
16
Realignment of Curves
• Computation of slews
– Maximum slew: At a station it is limited by
practical considerations
– At bridges, it may not be possible to slew the
curve at all
IRPWM 2020
– If stations on a long curve are more than 50, then
10 stations shall be considered at one time and
check be made that the sum of proposed versines
is approximately the same as that of the
corresponding old versines
17
Realignment of Curves
18
Realignment of Curves
19
Realignment of Curves
20
Realignment of Curves
21
Realignment of Curves
22
Realignment of Curves
23
Realignment of Curves
24
Check Rails on Curves
26
RAILWAY ENGINEERING
Lecture Number 43
Turnouts, Points & Crossings - I
RAJAT RASTOGI
CIVIL ENGINEERING
1
Discussed in Previous Lecture
• Realignment of Curves
– Reasons
– Permissible limits
– String line operation
– Double and multiple tracks
– Rail cutting
– Check rails
2
Today’s Discussion
• Turnouts
– Components
– Terminologies
• Points & Crossings
– Tongue rail
– Switch rail
3
Turnout
4
Turnout
5
Turnout - Components
6
Turnout - Components
crossing
• Switches
– Pair of stock rails, a pair of tongue rails, a pair of
heel blocks, slide chairs, stretcher bars, gauge tie
plate
• Crossing Lead Rail
– Nose consisting of a point rail and splice rail, two
wing rails and two check rails
• Lead rails
– Provided in four sets, two pairs of lead rails, one
each of straight and curved rail
7
Turnout – Components Tongue Rail
Stock Rail
• Tongue rail
– This is a tapered movable rail made of high
carbon or manganese steel to withstand wear.
– Its movement with respect to the stock rail
defines the direction of movement of the rolling
stock.
• Stock rail
– It is a running rail against which tongue rail
operates
8
Turnout – Components
Tongue Rail
9
Turnout – Components
• Point Rail
– This is a rail which ends at Actual Nose of a
Crossing (ANC). It has a blunt end.
• Splice Rail
– This is a cut (spliced) rail which buts against the
point rail
10
Turnout – Components
• Check Rail
– Flared rails provided opposite to crossing and
running parallel to the lead rails with a purpose of:
• Guiding the wheel flange
• Preventing wear and rocking of wheels
• Preventing derailment at level crossing
11
Turnout – Components
12
Turnout – Components
• Slide chairs
– These are provided under tongue rails to allow them
to move laterally. These are different for ordinary Tongue Rail
14
Turnout – Terminologies
• Points
– A pair of tongue rails with stock rails. Train diverting
from the main track will negotiate the points first.
Trains magazine
15
Turnout – Terminologies
• Crossing Throw of
Switch
16
Turnout – Terminologies
• Throat
Throw of
Switch
17
Turnout – Terminologies
crossing
• Curve Lead (CL)
– This is the distance from tangent point to the
theoretical nose of crossing (TNC) measured
along the length of the main track
• Switch Lead (SL) Lead Rail
18
Turnout – Terminologies
• Facing points
Throw of
Switch
19
Turnout – Terminologies
20
Turnout – Terminologies
21
Turnout – Terminologies Points &
Switches
• Switch angle
– Angle between gauge face of the stock rail and
tongue rail at the theoretical toe of the switch in
its closed position
– It is the function of heel divergence and the
length of the tongue rail
– It also depends upon whether the thickness of
tongue rail is considered or not
– If thickness of tongue rail is not considered:
• β = Sin-1(Heel divergence/Length of tongue rail)
22
Turnout – Terminologies Points &
Switches
• Switch angle
– If thickness is considered:
• β = Sin-1(Thickness/Difference in theoretical and
actual length of tongue rail)
• Throw of the switch
– Distance through which tongue rail moves
laterally at the toe of the switch to allow the
movement of train
– Limiting values for BG track: 95 – 115mm
23
Turnout – Terminologies
• Heel Divergence
– Distance between the gauge face of stock rail and Tongue Rail
24
Turnout – Terminologies
25
Turnout – Terminologies
26
Points and Crossings - Arrangement
Throw of Switch
27
Today we have discussed the turnouts, their
components and important terminologies
related to the turnouts. We also discussed the
points and crossings, especially the tongue rail
and arrangement of the points and crossings.
Thank You
28
RAILWAY ENGINEERING
Lecture Number 44
Turnouts, Points & Crossings - II
RAJAT RASTOGI
CIVIL ENGINEERING
1
Discussed in Previous Lecture
• Turnouts
– Components
– Terminologies
• Points & Crossings
– Tongue rail
– Switch rail
2
Today’s Discussion
3
Points & Crossings
Crossing
4
Points & Crossings
• Tongue rail
– Tapered section having thickness at the top same
as lead rail at the heel of switch and 0.64 cm to
0.95 cm at the toe of the switch
– Does not bear any load
– Half thickness of the rail should closely fit within
the stock rail at the toe
– Tongue rail should be about 6mm higher than
stock rail at the center
– It can be straight or curved
5
Points & Crossings
• Tongue rail
– Straight tongue rail can be used for right-hand as
well as left-hand turnout
– Straight tongue rails are usually used on a 1 in 8.5 or
1 in 12 turnouts on IR
– Curved tongue rails are shaped as per the curvature
of the track
– Curved tongue rails are usually used on 1 in 16 and 1
in 20 turnouts on IR. These are also used for 1 in 8.5
and 1 in 12 turnouts on important routes
6
Points & Crossings
7
Points & Crossings
9
Switches
10
Switches
11
Switches – Types
12
Switches – Split Type at Heel
13
Switches – Split Type at Heel
14
Switches – Types at Toe
• Overriding Switch
– Stock rail section at the toe remains full
– Tongue rail in planed to 6mm thickness at toe and
overrides the foot of the stock rail
– Tongue rail is kept 6mm higher than the stock rail
from the heel to the point where planning starts Railway Engineering by Chandra and Agarwal
15
Switches – Overriding
• Overriding Switch
16
Switches – Types at Toe
• Undercut Switch
– In this arrangement the foot of the stock rail is cut
to accommodate the tongue rail (switch rail)
– Tongue rail is planed to the thickness of 6mm at
the toe
Railway Engineering by Chandra and Agarwal
– As both the rail sections are cut, it becomes a
weak section
– Both the rails need to be manufactured to size
which increases the cost
17
Crossings
18
Crossings
19
Crossings – Components
• Point rail:
– Machined manufactured, used to form the nose of
the crossing
– It ends at the nose, as a thinner section, but so thin
only that it may not break off under the movement
of vehicles
Railway Engineering by Chandra and Agarwal
– Therefore, its end is made blunt by cutting the rail to
the thickness of 6mm
– Toe of the blunt edge is called Actual Nose of The
Crossing (ANC) and pointed toe is called Theoretical
Nose of the Crossing (TNC)
20
Crossings – Components
• Splice rail:
– Splice rail buts against the point rail at a distance
behind the nose
– It is also cut at the end to fit with the point rail
• ‘V’ rail section so formed has a depth of 6mm at
the nose and runs out in 89mm in the facing Railway Engineering by Chandra and Agarwal
direction
• Wing rail:
– These are two in numbers, right-hand and left-hand
wing rail
21
Crossings – Components
• Wing rail
– These form the throat at the crossing
– After that they diverge along the point rail and splice
rail and get flared at the ends
– This facilitates the entry and exit of the wheels with
flange in a smooth and protected manner Railway Engineering by Chandra and Agarwal
• Check rails
– These are also two in numbers, and guide the wheel
flanges without moving sideways
– This also protects the nose from hitting by the wheel
22
Crossings – Types
• Based on shape of crossing
– Acute angle crossing / ‘V’ crossing / Frog
– Obtuse angle crossing (Diamond crossing)
– Square crossing
• Based on manufacturing process
– Built-up crossing
– Cast Steel crossing
– Combined rail and cast crossing
– CMS crossing
• Based on assembly of crossing
– Spring or movable wing crossing
23
Crossings – Types
24
Crossings – Types
• Square crossing
– In this case the two tracks crosses each other at
right angle
25
Crossings – Types
• Built-up crossing
– In this crossing, two wing rails and ‘V’ section
consisting of a point and splice rail are assembled
using bolts and distance blocks
– It is economical, easy to repair or replace
– This becomes unserviceable if wear becomes
more than 10mm
– It lacks rigidity and bolts need to be checked
periodically
26
Crossings – Types
27
Crossings – Types
• CMS crossing
– This type of crossing is suitable for heavy traffic
tracks or tracks bearing heavy axle loads, suburban
sections with electric tractions, high speed tracks
– It has longer life, usually four times of built-up
crossing
– Maintenance is economical as it is free of bolts and
other components which tend to loose, and need to
be checked periodically
– It has higher strength, higher resistance to wear
– Mainly provided on Group-A tracks and tracks with
traffic density over 20 GMT
28
Crossings – Types
29
Crossings – Types
30
Today we have discussed the tongue rails as a part
of points and switches, determination of its
length, switches and their types, crossings, its
components and its types.
Thank You
31
RAILWAY ENGINEERING
Lecture Number 45
Crossings and Turnout Design
RAJAT RASTOGI
CIVIL ENGINEERING
1
Discussed in Previous Lecture
2
Today’s Discussion
• Number of Crossings
• Turnout Design
– Coles method
– Method 2
– IRS method
3
Number of Crossing
5
Number of Crossing
6
Number of Crossing
7
Number of Crossing – Numerical 1
8
Number of Crossing – Numerical 2
9
Number of Crossing
• Use of crossings
– 1 in 8.5 Station yards, sharp turnouts
– 1 in 12 station yards of main lines, flat
turnouts
– 1 in 16 High-speed turnouts
– 1 in 20 very high-speed turnouts
10
Number of Crossing – Standard Details
Turnout Crossing Crossing Switch Permissible speed
No angle angle
1 in 8.5 8.5 6o42’35’ 1o34’37’’ 10 for straight switch
15 for curved switch
0o27’35’’ 30 for straight switch
30 for curved switch
1 in 12 12 4o45’49’’ 1008’00’’ 15 for straight switch
0o27’35’’ 40 for curved switch
1 in 16 16 3034’35’’ 0o24’27’’ 50 or 60+
1 in 20 20 2o51’45’’ 0o24’27’’ 50 or 60+
1 in 24 24 2o23’09’’ 0o10’00’’ 100
11
Turnout Design – Coles method
12
Turnout Design – Coles method
13
Turnout Design – Coles method
Curve Lead (CL) = AE = TE’
Radius of Curve (R) = OE = OT
Switch Lead (SL) = TL
Lead of crossing (L) = LE’
Heel Divergence (d) = LM
Angle of crossing (α) = CEA
Gauge (G) = AT = EE’
N = cot α
14
Turnout Design – Coles method
16
Turnout Design – Coles method
17
Turnout Design – Coles method
18
Turnout Design – Coles method: Numerical 3
19
Turnout Design – Coles method: Numerical 3
• Solution:
– Radius = R = 1.5G + 2GN2
– R = 1.5*1.676 + 2*1.676*8.52 = 245 m
– Switch Lead = SL = (2Rd – d2)
– SL = (2*245*0.12 – (0.12)2) = 7.67 m Railway Engineering by Chandra and Agarwal
– Lead = L = CL – SL
– L = 28.6 – 7.67 = 20.93 m
20
Turnout Design – Alternate method
22
Turnout Design – Alternate method
• Radius Ro = OC = OT
• At heel, TD = G – d
• Considering the symmetry of triangles
• Radius Ro = (G – d)/[Cos β – Cos α]
23
Turnout Design – Alternate method: Numerical 4
24
Turnout Design – Alternate method: Numerical 4
• Solution
– L = 1.556*Cot (3.5764 + 0.4075)/2
– L = 1.556*Cot 1.99195 = 1.556*28.752
– L = 44.74 m
– Radius Ro = (G – d)/[Cos β – Cos α]
– Ro = (1.676 – 0.12)/[Cos 0.4075 – Cos 3.5764]
– Ro = 1.556/[0.9999 – 0.9980] = 818.95 m
– Radius Rc = Ro – G/2 = 818.95 – 1.676/2
– R = 818.112 m
25
Turnout Design – IRS method
• This is the standard layout used on IR
• Curvature starts from the heel of the switch and
ends at a distance ahead of the toe of the
crossing
• Crossing is straight and hence no kink is
experienced at this point
Railway Engineering by Chandra and Agarwal
• Only kink in the layout is at toe of the switch
• Calculations are a bit complicated
• In this method the lead of the crossing and the
radius of the turnout curve are calculated
26
Turnout Design – IRS method
• AD = G = gauge of the track
• AB = d = heel divergence
• HE = h = distance ahead of
TNC at which curve ends
• BC = BD – CD = BD – PH
• BD = G – d and PH = h*Sinα
27
Turnout Design – IRS method
• Design:
– Lead of crossing = L = DP = CH
– From triangle BCH, angle CHB = (α+β)/2
– CH = BC*Cot (α+β)/2
– BC = BD – CD = BD – PH = (G – d) – h*Sinα Railway Engineering by Chandra and Agarwal
28
Turnout Design – IRS method
• Design:
– Radius of curve = R = OB = OH
– From triangle OBH, angle BOH = (α - β)
– BH = 2R*Sin (α - β)/2
– From triangle BHC, BC = BH*Sin (α+β)/2 Railway Engineering by Chandra and Agarwal
29
Today we have discussed the Number of crossings,
three methods to find the number, the turnout
design, three methods namely Coles method,
an alternate method and IRS method.
Thank You
30