TYBMS PM3 Module 1 Chapter 3 Project Selection Questions.
TYBMS PM3 Module 1 Chapter 3 Project Selection Questions.
B. PBDT/PBT is given
C. PAT is given
b. Cash inflows
Year Rupees
1 1.60,000
2 1,50,000
3 1,40,000
4 1,55,000
5 2,00,000
The cost of capital is 10%. Present value at 10% for
years 1 to 5 is 0.91, 0.83, 0.75, 0.68, 0.62
Problem No 2
1 35,000 1,18,000
2 80,000 60,000
3 90,000 40,000
4 75,000 14,000
5 20,000 13,000
B. PBDT/PBT is given
PBT
1 89,000 1,25,000
2 94,000 1,31,000
3 1,04,000 1,43,000
4 1,23,000 1,59,000
5 1,55,000 1,93,000
6 2,36,000 2,27,000
C. PAT is given
Year PAT
1 1,20,000
2 2,00,000
3 2,10,000
4 2,90,000
5 1,80,000
2. M/s OCM Ltd is considering purchasing a machine.
Two machines A and B under under consideration.
PAT
1 14,000 15,000
2 14,000 30,000
3 40,000 40,000
4 20,000 40,000
5 15,000 20,000
Calculate
1. Payback period
2. Discounted payback period assuming discount
factor of 10%. Pv factors being 0.91, 0.83, 0.75,
0.68 and 0.62
Problem no 2
Problem no 3
Formula
• Average investment
= (cash outflows – scrap) + additional wkg capital +
scrap
2
Note
Particulars Amount
Cost 5,20,000
PAT
1 30,000
2 60,000
3 70,000
4 90,000
5 1,10,000
Particulars Amount
Cost 1,20,000
PAT
1 10,000
2 30,000
3 40,000
4 60,000
5 40,000
1 25,000 10,000
2 15,000 12,000
3 10,000 18,000
4 12,000 25,000
5 6,000 12,000
Both the machines will have a cash outflow of Rs
50,000/-. Calculate the ARR of both these machines.
Problems on ARR method
1 25,000 22,000
2 20,000 22,000
3 30,000 38,000
4 42,000 45,000
5 16,000 10,000
&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&&
&&&
p/v factors
Work out the IRR by taking help of 12% and 14% p/v
factors table.
Combined sums
Problem No. 1
Year PBT
1 1,20,000
2 2,00,000
3 2,10,000
4 2,90,000
5 1,80,000
Calculate