1
1
NED UNIVERSITY.
STANDARD FORM OF CONTRACTS: FIDIC is the most common one but we also other
form of contracts use in different places.
iv. LOGIC: Leadership Oil and Gas Industry competence, used for offshore
works.
History of FIDIC:
2. PUBLICATION OF FIDIC:
Red Book: Conditional contracts for Buildings and engineering works by employer.
Edition: 1957 (ICE UK version) 1987 (4th Edition), 1999 (Rainbow suit), 2017
(Latest).
Green Book: Short form of contract for minor works with two main drivers
i). 0.5 Million dollar ii) Time frame = 06 Months. May be used for contracts in higher
values than mention.
Pink Book: FIDIC MDB (Multi Development Banks) Edition, having conditions of
contracts for B & E works for funding institution like World Bank.
Yellow Book: is about Electrical and Mechanical Plants but not limit to E & M now
used in wide range of works. Focus more on procurement type.
Gold Book: Gold Book for Design Build and operate (DBO) contracts, include
function of operation by contractor as inked in contract. Used for infrastructural
project like roads, airport or port. Differ from BOT (Build Operate and Transfer),
BOOT (Build Own Operate and Transfer), and PPP (Public Private Partnership) in of
function fund: funding in BOT, BOOT & PPP is handled by Contractor/Investors but
in Gold Book the Fund function is lies with owner of the project.
The FIDIC contract is inked between parties: (i) Employer (Client) (ii) The
Engineer/Employer’s Representative (iii) The Contractor.
Similarly the FIDIC book of contract imposed some obligations on both contractor
and Employers and it varies from type/format of book used in the contract for specific
project.
E.g. in yellow and silver form of contract in FIDIC, the risk associated with designed
is the responsibility of the contractor while the Red Book give and any other form
give the responsibility to Employer.
The Employer’s obligations as per FIDIC Red book (2017) Edition is as below
Site accessibility to the contactor, this way contractor will plan efficient work plan.
Site data like underground utilities and other necessary data provision is also
obligation of Employer.
Cooperation and facilitation of contractor in way that able the contactor to work
smoothly. Employer or representative of employer must cooperate with the contractor,
that contractor is required.
Funding and Financing well on time make the contractor able to work efficiently.
Funding has vital role in project.
Attend all the requisite meeting and keep records may be MOM of meeting, IPC of
Payment etc. (all contemporary records)
The contractor has highest number of obligations in all form of contract and on FIDIC
too, some of which are mention below:
Contactor has General obligation like plant and equipment, documents, safety etc.
Performance security/Bond
Appointment of representative.
Cooperate with Employer and other Contractor who are working in same project.
Protection of environment.
The engineer should carry duties not impartially/neutral but shall deem to act for
employer. Master Slave Relation, in this case no trust will be developed which will
affect the project. Most of employer follows the rule to execute the project which
definitely is not a way to handle project. This will make many dispute between
Employer and Contractor which will affect the project
The Engineer should not follow the above be the one to avoid the possible dispute
and should act as dispute resolver.
The unclear and ambiguous measurement may arise possible dispute, any suitable
methods RICS etc. should be used as reference materials.
Generally an illogical review time is given in contract which also leads to disputes.
This should be avoided; considerable time should be given in contract.
The DAB/DAAB work as second dispute resolver after the Engineer. Removing the
DAB/DAAB will prolong the dispute if any.
HOW TO MITIGATE:
To mitigate the situation Golden Principles prepared by the FIDIC should be followed:
The particular condition must not change the balance of risk/reward allocation.
LESSON LEARNED: