Week 11
Week 11
CALCULATING EARNED
SCHEDULE
IEAC(t) = PD / SPI(t)
Summary:
Earned Schedule Concept
• Formula
• ES =C+I
where: C = number of time increments.
I = (EV – PVC) / (PVC+1 – PVC)
• Indicators
• Schedule Variance: SV(t)
= ES – AT
• Schedule Performance Index: SPI(t) = ES / AT
• IEAC(t) = PD / SPI(t)
Homework
For a project, the budget is 8000$ and the planned duration
is 8 months. Time now is end of June. The EV is 3200$. The
planned value in May was 3000$ and that of next month is
4100$.
Find the ES, SPI(t), SV(t) and IEAC(t) for this project.
Revised Homework Problem
Consider given monthly ES values for a 6-month project.
It means that you have earned 1.105 at end of month 1, and 2.063 at
end of month 2 and so on… This means you are going ahead of schedule
as evident from EV values also which are greater than PV values.
PV ($)
EV ($)
Adv Topics in PM
Spring 2024
Applied Mathematics 16
6 - 17
Applied Mathematics 18
Weighted Scoring Model
19
A weighted scoring model is a tool that provides a
systematic process for selecting between alternates
based on many criteria
First identify criteria important to the selection process
Then assign weights (percentages) to each criterion so they add
up to 100% or 1.0
Then assign scores to each criterion for each alternative
Multiply the scores by the weights and get the total weighted
scores
The higher the weighted score, the better
Scoring Model
Example 1
25
Exercise
Supplier Selection: Choose one supplier based upon given criteria.
Note that criteria 3 and 5 are on a different scale. These are large numbers
which will dominate the weighted sum.
Applied Mathematics