No.4 PERMIT TO DIG

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

PALM JUMEIRAH

CENTRAL SAFETY TEAM 050-558-5135

SSp15/F04 – Permit To Dig

PERMIT TO DIG
SSP15/F04

Prepared and Issued by:

Steve Storey, H&S Manager, Palm Jumeirah Central Safety Team

Reviewed by:

Robert Whent, H&S Manager, Palm Jumeirah Central Safety Team

Authorised by:

Mark Warrington, Assistant Manager, Al Nakheel Safety

Revision History:
Revision Date Description

Palm Jumeirah Central Safety Team Revision: 0


SSP15/F04 Date : 01/06/05
Issue No: 01 Page : Page 1 of 3
PALM JUMEIRAH
CENTRAL SAFETY TEAM 050-558-5135

SSp15/F04 – Permit To Dig

PERMIT TO DIG
SSP15/F04

PERMIT TO DIG
PROJECT/SITE: PERMIT NO:

TO: (competent person) CONTRACTOR:


LOCATION OF WORKS: DESCRIPTION OF WORKS:

Approved Method Statement and Risk Assessment in place YES NO


Risk Assessment ref.no:
The competent person or his supervisor should tick as appropriate
PRECAUTIONS: precautions which have been taken
Have all services been located and proved to location GENERAL
UNDERGROUND SERVICES: All necessary drawings/ sketches received

Trial holes Suitable protection barriers available

Records of location Are sufficient ladders on hand for access to & from
Services protected excavation

CAT survey Adequate lighting available

Services isolated Is Supervisor fully experienced and competent in the support


OVERHEAD SERVICES: of excavations

Records of location Confined space work permit

Services protected

ADDITIONAL PRECAUTIONS/ COMMENTS:

PERMIT VALIDITY:
This permit is valid from: am/pm on / / Until: am/pm on / /

ISSUE OF PERMIT- AUTHORISATION/ RECEIPT


The responsible person: The competent person (Contractor)

I have examined the area specified and permission is given for I have read and agree to the conditions of this permit.
the work to start, subject to the conditions stated above.

Name: Name:
(print) (print)

Signed: Date: Signed: Date:

Palm Jumeirah Central Safety Team Revision: 0


SSP15/F04 Date : 01/06/05
Issue No: 01 Page : Page 2 of 3
PALM JUMEIRAH
CENTRAL SAFETY TEAM 050-558-5135

SSp15/F04 – Permit To Dig

PERMIT TO DIG
SSP15/F04

COMPLETION OF WORKS/ CLOSING OF PERMIT


The competent person: The responsible person:

Time work completed/ suspended: am/pm THIS PERMIT IS NOW CANCELLED

Name: Name:
(print) (print)

Signature: Signature:
Date: Time: am/pm
This permit must be returned to the responsible person on completion or suspension of the hot work.
A record of permits issued must be maintained.

Palm Jumeirah Central Safety Team Revision: 0


SSP15/F04 Date : 01/06/05
Issue No: 01 Page : Page 3 of 3