Work Order 28
Work Order 28
Name of work: Repairs to ceiling at DCM/HWH chamber and DEN/II chamber toilet, changing
of old ,damaged sanitary fittings by new one and other ancillary works under AEN/HQ/HWH
(Site) DRM Bldg, Commercial at Yatri Niwas, DRM bldg back
Schedule of Drawings
Survey sheet
Authority ADRM/HWH/INFRA
Allocation 0441032
The Contractor ARINDAM GHOSH-KOLKATA is/are hereby ordered to carry out the following
works at percentage(s), above/below/At par the Schedule of Rates of Eastern Railway Corrected
upto latest correction slips of Howrah Division under Zone Contract Agreement here-in before
referred to:
The Works herein mentioned are required to be completed on or before 10/06/2024 (Date).The
quantities provided herein are approximinate and subject to variation Signature
under Clause 42 of the
Not Verified
Standard General condition of Contract corrected upto latest correction slips.
Digitally signed by SUDIPTA NANDI
Date: 2024.05.31 20:37:06 IST
Reason: For sanction of zonal work
order
Railway :Sr.DEN/HQ/HWH
(For President of india)
I agree to complete the works herin set forth on or before the date specified under the Zone
Contract Agreement herin before referred to in conformity with the drawings hereto annexed and
in accordance with the General and Special (if any ) Conditions of Contract Corrected upto latest
Correction Slips and the Standard Specification of Eastern Railway with up-to-date Correction
Slips.
I also agree to maintain such works for the period specified below from the date of
completion:
(a) Repair and maintaince work including white/color washing: three calendar months
from date of completion.
(b) All new works except earth work: Six calendar months from date of completion.
Signature Not Verified Signature Not Verified
Digitally signed by ARINDAM GHOSH Digitally signed by MUKESH KUMAR
Date: 2024.05.22 13:40:05 IST JHA RAKESH
Reason: For sanction of zonal work Date: 2024.05.24 15:38:48 IST
order Reason: For sanction of zonal work