Assignment2 Group14
Assignment2 Group14
MCQs:
Q1:
For a 4-bus system using DC power flow, the initial state estimates (θ) are:
0
−0.02
θ= −0.03
−0.04
−0.1
e = z − h, where h = H · θ
1
Soln:
State Estimates (θ):
0
−0.02
θ=
−0.03
−0.04
These represent the voltage angles at each bus.
Measurement Vector (z):
0.5
0.3
z= −0.2
−0.1
This is the actual power flow measured in the system.
Measurement Jacobian (H):
1 −1 0 0
0 1 −1 0
H=
0 0 1 −1
1 0 0 −1
The residual error (e) is defined as the difference between the measured values (z)
and the calculated values (h) based on the state estimates.
Now, the calculated power flow values (h) are given by:
h=H ·θ
Substitute H and θ:
1 −1 0 0 0
0 1 −1 0 −0.02
h= ·
0 0 1 −1 −0.03
1 0 0 −1 −0.04
Simplify:
0.02
0.01
h=
0.01
0.04
Residual error is given by:
e=z−h
2
Substitute z and h:
0.5 0.02
0.3 0.01
−0.2 − 0.01
e=
−0.1 0.04
Perform the subtraction:
0.5 − 0.02 0.48
0.3 − 0.01 0.29
e=
−0.2 − 0.01 = −0.21
Substitute e:
p
|e| = (0.48)2 + (0.29)2 + (−0.21)2 + (−0.14)2
Simplify: √
|e| = 0.3782
Final result:
|e| ≈ 0.615
Q2:
Problem: In a system with three thermal units, the optimal dispatch neglecting losses for
a 190 MW load is given. If the loss formula is applied, which of the following parameters
is critical to estimating incremental losses accurately?
3
Generation Shift Factors (GSFs): GSFs quantify how redispatch affects line
flows.
All three—GSFs, LDFs, and loss sensitivities—are essential for accurate incremental
loss calculations in systems.
Correct Answer:
(4) All of the above.
Soln:
Contingency analysis identifies insecure lines under stressed conditions by determining
the maximum permissible load increase at a bus before a line flow exceeds its limit. This is
done using Generation Shift Factors (GSFs), Line Outage Distribution Factors (LODFs),
and the initial power flows.
GSF (Generation Shift Factor): GSF quantifies how a change in generation at bus
i affects the flow on line k. Mathematically:
LODF (Line Outage Distribution Factor): LODF determines how the flow on line
l changes due to the outage of another line k. Mathematically:
Initial Flow: The initial flow on line l is Flpre , and its limit is Flmax . Under stressed
conditions:
Flpost = Flpre + ∆Fl ≤ Flmax
4
Flow Constraint: For line l under contingency:
Flpost = Flpre + GSFl,i · Pimax + Effect of other line outages.
Assuming a single generator change and a single contingency:
Flpost = Flpre + GSFl,i · Pimax + LODFl,k · Fkpre
Insecure Line Detection: If Pimax is small, the line is close to its limit and is flagged
as insecure under contingency conditions.
Stress Analysis: This formula helps identify buses where load or generation increases
have a significant impact on line flows, allowing for preemptive corrective actions.
Consider a 3-bus system with the following parameters:
Line l: Flmax = 100 MW, Flpre = 80 MW
Line k: Fkpre = 50 MW
LODF: LODFl,k = 0.1
GSF: GSFl,i = 0.2
Using the formula:
100 − 80 − 0.1 · 50
Pimax =
0.2
100 − 80 − 5 15
Pimax = = = 75 MW
0.2 0.2
The maximum permissible load increase at bus i is 75 MW.
Q4:
Problem: A multi-area system consists of two areas, each with a governor response of
R1 = 0.01 pu, R2 = 0.02 pu.
A 100 MW load increase in Area 1 is managed by both areas. How would you integrate
Load Frequency Control (LFC), Economic Dispatch (ED), and Unit Commitment (UC)
to ensure frequency regulation while minimizing costs?
Considerations:
Tie-line constraints
Time-dependent Unit Commitment (UC) decisions
5
Soln:
The goal is to manage a 100 MW load increase in Area 1 using:
The total equivalent governor response Req for the system is:
R1 R2
Req = .
R1 + R2
The frequency deviation ∆f due to the 100 MW load change in Area 1 is:
∆Pload
∆f = .
Req
Substituting:
100
∆f = ≈ 15.0 Hz.
0.00667
Area 1 and Area 2 share the load change based on their individual governor re-
sponses:
R2 R1
∆P1 = ∆Pload , ∆P2 = ∆Pload .
R1 + R2 R1 + R2
Substituting:
0.02
∆P1 = · 100 = 66.67 MW,
0.01 + 0.02
0.01
∆P2 = · 100 = 33.33 MW.
0.01 + 0.02
Thus:
6
Economic dispatch minimizes the total cost of generation while meeting demand and
respecting operational constraints.
Cost Functions: Let the cost functions of generators in Areas 1 and 2 be:
Lagrangian Function:
Optimality Conditions:
∂L
1. ∂P1
= b1 + 2c1 P1 − λ = 0,
∂L
2. ∂P2
= b2 + 2c2 P2 − λ = 0,
3. P1 + P2 = 100, MW
Solving these equations provides the optimal generation values P1∗ and P2∗ .
Unit Commitment decides which generating units to turn on or off based on system
constraints and time-dependent operational decisions.
Constraints:
Minimum Up/Down Time: Units must remain online or offline for a minimum
duration,
Tie-Line Capacity: Power flow through the tie-line must not exceed its thermal
limit:
Ptie = ∆P2 = 33.33 MW.
LFC: Immediate response to load change ensures frequency stability and power-
sharing between areas.
Final Result
Frequency deviation after LFC: ∆f = 15.0 Hz,
Power shared:
Area 1: 66.67 MW, Area 2: 33.33 MW,
7
Analytical Question
Q5:
Consider a 4-bus power system with the following line reactances (in per unit):
X12 = 0.1
X23 = 0.15
X34 = 0.12
X14 = 0.2
Power flow measurements at the following locations with their respective values and
standard deviations (σ):
P12 = 0.8 pu, σ1 = 0.02
Assuming θ1 = 0 as reference:
b) State Estimation
Calculate the state estimate x̂ = (H T R−1 H)−1 H T R−1 z where R is the measurement
covariance matrix
Solution
Given Data:
Line reactances (pu):
– X12 = 0.1
– X23 = 0.15
– X34 = 0.12
– X14 = 0.2
Measurements:
8
– P12 = 0.8 pu, σ1 = 0.02
– P23 = 0.5 pu, σ2 = 0.02
– P34 = 0.3 pu, σ3 = 0.02
H Matrix Formation:
For DC power flow:
θi − θj
Pij =
Xij
1) For P12 measurement:
θ1 − θ2 0 − θ2
P12 = =
X12 0.1
∂P12 1
=− = −10
∂θ2 0.1
∂P12
=0
∂θ3
∂P12
=0
∂θ4
2) For P23 measurement:
θ2 − θ3
P23 =
X23
∂P23 1
= ≈ 6.67
∂θ2 0.15
∂P23 1
=− ≈ −6.67
∂θ3 0.15
∂P23
=0
∂θ4
3) For P34 measurement:
θ3 − θ4
P34 =
X34
∂P34
=0
∂θ2
∂P34 1
= ≈ 8.33
∂θ3 0.12
∂P34 1
=− ≈ −8.33
∂θ4 0.12
9
Therefore:
−10.0 0.0 0.0
H = 6.67 −6.67 0.0
0.0 8.33 −8.33
Measurement Error Covariance Matrix (R):
R = diag([σ12 , σ22 , σ32 ])
R = diag([0.022 , 0.022 , 0.022 ])
R = diag([0.0004, 0.0004, 0.0004])
10
Power Flow Check:
Conclusion:
The solution is physically reasonable and mathematically consistent, with power flows
matching the measurements and angle differences within typical ranges for power systems.
11