Voltage Variation On Distribution Networks With Distributed Generation - Worst Case Scenario
Voltage Variation On Distribution Networks With Distributed Generation - Worst Case Scenario
Abstract—This paper presents an analytical approach to estab- of centralized control is introduced in [5] to increase the DG
lish a relationship between the voltage variation and distributed connection capacity. A centralized distribution management
generation (DG) integration for the planning and operation of system controller, similar to that used in transmission networks,
distribution networks with DG. The proposed approach is mainly
based on the derivation of a voltage variation formula for distri- is presented in [6] and [7] to maximize the DG penetration using
bution networks with DG and the consideration of the worst case a wide-area voltage control and reactive power management
scenario, which establishes a relationship between the amount of approach where state estimations are employed to assess the
voltage variation and maximum permissible DG. Some recommen- voltage level. However, the centralized approaches presented
dations are presented based on the worst case voltage variation in [5] and [7] require significant investment in sensors and
formula and DG integration to counteract the voltage variation
effect. The relationship between the connection cost and voltage communication assets, which make their application difficult to
level is also presented in this paper. The feasibility of the proposed increase the DG penetration.
approach is validated by comparing the voltage profile obtained There are several alternative approaches, which include to
from the derived formula to that with the existing power system ensure the maximum DG capacity with minimal voltage im-
simulation software. pacts in the distribution network. A distributed voltage con-
Index Terms—Distributed generation (DG), distribution trol approach is introduced in [8] to limit the voltage rise
systems, voltage variation, worst case scenario. in distribution feeders by considering continuously distributed
loads and generation. Some other distributed active manage-
I. I NTRODUCTION ment approaches are presented in [9]–[11] to accommodate
more DG units by controlling the power factor rather than the
MAHMUD et al.: VOLTAGE VARIATION ON DISTRIBUTION NETWORKS WITH DG: WORST CASE SCENARIO 3
ΔV = VGEN − VS ≈ R(PG − PL ) + X(±QC − QL ± QG ). ΔVji ≈ Rij (PGj − PLj ) + Xij (±QGj ± QCj − QLj ).
(6)
These voltage variation formulas can be used to determine
DERs always export active power (+PG ) and may export the relationship between the voltage variation and DG inte-
or import reactive power (±QG ), whereas the load consumes gration, which may suggest possible solutions to mitigate the
both active −PL and reactive −QL power and the compen- voltage variation. In this paper, the worst case scenario of the
sators may supply or absorb only reactive power ±QC . The distribution network is considered to investigate the relationship
reactive power capability of DERs depends on the nature of between the voltage variation and DG integration, which is
DERs connected to distribution networks. The present trend is not considered in [32]. The worst case scenario of distribution
to integrate synchronous machine-based combined heat power networks with DG is discussed in the following section.
This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination.
IV. E STIMATION OF VOLTAGE VARIATION AND supplied by DERs. Since there is a linear relationship between
DG C APACITY U SING W ORST C ASE S CENARIO the voltage variation and the amount of active power supplied
by DERs, the voltage variation is more onerous when there is
DERs are connected to the distribution system due to the
no demand on the system as the generation is exported back
technological innovations and changes in the economic and
to the primary distribution system. The voltage variation in the
regulatory environment, as well as to meet the increased load
distribution system also limits the amount of DG units that can
demand. From (6), we can write
be integrated into the distribution network, and this can be seen
VGEN − VS + RPL − X(±QC − QL ± QG ) in the following equation, which is obtained from (6):
PG ≈ (9)
R VGENmax − VS
PGmax ≈ . (12)
and for a large distribution network R
Vj − Vi + Rij PLj − Xij (±QCj − QLj ± QGj ) The capacity of the DG unit that can be accommodated in the
PGj ≈ . existing system is clearly limited by the maximum voltage at
Rij
the point of DG connection, which can be written as
From (9), it is clear that the level of DG connected to the
VGENmax − VS
distribution system depends on the voltage at the primary DS, PGmax ≤ (13)
the voltage level of the receiving end, the size of the conductors R
and the distance from the primary DS, the load demand on the and for a large distribution system, it can be written as
system, and the other generation on the system.
Vjmax − Vi
DNSPs should consider the worst case operating scenarios PGjmax ≤ .
to demonstrate the relationship between the voltage variation Rij
and the amount of DG integration so that their networks and Therefore, from the worst case scenario, it is seen that the
customers will not be adversely affected. Generally, these worst resistance of the line, as well as the voltage variation within the
case scenarios are: system, is critical for the DG integration. From the worst case
1) minimum load maximum generation; scenario of distribution networks with DG, possible solutions to
2) maximum load minimum generation; the voltage variation due to the integration of the maximum DG
3) maximum load maximum generation. unit can be obtained easily, which is presented in the following
Since the aim of this paper is to find out the maximum section.
amount of DG units that can be integrated into the distribution
network under the worst condition, the minimum load max-
imum generation scenario is considered in this paper as the V. M ITIGATION OF VOLTAGE VARIATION BASED ON
worst case scenario. Under the considered worst case scenario W ORST C ASE S CENARIO
The integration of DERs may cause an excessive voltage
PL = 0 QL = 0 PG = PGmax . variation. Traditionally, the DS is equipped with an over- or
Now, for the sake of simplicity, if we consider that the system undervoltage protection relay to protect it. The voltage protec-
is operating at unity power factor, ±QG and ±QC will be zero. tion scheme may permanently disconnect DERs, or it may even
In this case, the worst case voltage variation for a two-bus disconnect the DS from the main grid, which may cause serious
distribution network can be obtained from (6) and written in economical damage for customers and DNSPs. The voltage
the following form: variation on the DS can be mitigated through the following
approaches:
ΔVworst = VGENmax − VS ≈ RPGmax . (10) 1) by using the resistance reduction;
2) by regulating primary DS voltage VS ;
For a large system, the worst case voltage variation is 3) by using the generation curtailment;
4) by using the reactive power compensation.
ΔVworstji = Vjmax − Vi ≈ Rij PGjmax .
From (10), it is clear that the voltage variation depends on the A. Mitigation of Voltage Variation by Using the
resistance of the distribution line and the power supplied by Resistance Reduction
DERs. If the resistance of the distribution line is constant, then
we can write If the amount of the DG connected to a distribution system is
constant, from (10), we can write
ΔVworst ∝ PGmax (11)
ΔVworst ∝ R. (14)
and that for a large system is
From (14), it is seen that the worst case voltage variation that
ΔVworstji ∝ PGjmax . considers the maximum DG penetration is directly proportional
to the resistance of the line. Therefore, the voltage variation
Therefore, the voltage variation in the distribution network with in distribution networks can be reduced by decreasing the line
DG is directly proportional to the amount of active power resistance. The resistance of a line can be reduced by increasing
This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination.
MAHMUD et al.: VOLTAGE VARIATION ON DISTRIBUTION NETWORKS WITH DG: WORST CASE SCENARIO 5
ΔVworstji ≈ Rij PGmaxj + Xij (+QGmaxj ± QCj ). (17) D. Mitigation of Voltage Variation by Using the
Generation Curtailment
From (16) and (17), it is seen that the second part of the right It is important to observe that the probability of the worst
side of these equations needs to be negative to mitigate the case scenario in distribution networks is generally low, and
voltage rise problem, and in this case, the compensator must hence, it may be beneficial to accommodate a larger DER and
absorb reactive power that should be greater than the maximum curtail it when the voltage at the busbar where it is connected
reactive power supplied by the generator. However, if there is a varies outside the specified limit. The effect of the generation
voltage dip within the network, the compensator should supply curtailment on the voltage variation can be obtained from the
reactive power to the system to keep the voltage within the following equation:
specified limit.
Again, if a DG unit imports reactive power, (15) can be VGENmax − VS
PGmax ≈ PGcur + . (20)
written as R
Equation (19) can be rewritten as
ΔVworst ≈ RPGmax + X(−QGmax ± QC ) (18)
ΔVworst ≈ RPGmax − RPGcur . (21)
and for large systems, it can be written as
From (21), it is seen that the voltage rise can be reduced through
ΔVworstji ≈ Rij PGmaxj + Xij (−QGmaxj ± QCj ). (19) the generation curtailment. The likelihood of the coincidence
of the minimum load with maximum generation will determine
From (18) and (19), it can be said that if there is a voltage rise the total annual energy that needs to be curtailed. As the price
within the system and the reactive power absorbed by DG is of electricity is primarily driven by the load demand and the
not sufficient, it is essential to absorb more reactive power and generation curtailment occurs typically during the period of low
the compensator should absorb reactive power to mitigate the load, the value of this energy to be curtailed is relatively low.
voltage rise problem. In case of a voltage dip, reactive power However, this approach is not suitable when there is a voltage
needs to be supplied from the compensator to compensate the drop within the system.
reactive power absorbed by the DG unit.
VI. VOLTAGE L EVEL AND DG C ONNECTION C OST
C. Mitigation of Voltage Variation by Regulating the Primary
From the analysis of the worst case voltage variation, it is
DS Voltage VS
seen that the voltage level at the point of the DG connection is
In conventional passive distribution networks, it is a common very important as it has a great impact on the overall profitabil-
practice for DNSPs to maintain the primary DS voltage above ity of both consumers and DNSPs. If a DG unit is connected to a
This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination.
TABLE I
VOLTAGE L EVEL AND DG C ONNECTION C OST
MAHMUD et al.: VOLTAGE VARIATION ON DISTRIBUTION NETWORKS WITH DG: WORST CASE SCENARIO 7
The voltage profile of the 15-bus test system is shown in [3] H. A. Gill and G. Joos, “Models for quantifying the economic benefits
Fig. 7 from where it is seen that the voltages at buses 6, 15, of distributed generation,” IEEE Trans. Power Syst., vol. 23, no. 2,
pp. 327–335, May 2008.
and 11 are below the considered specified limit ±6% because [4] J. A. P. Lopes, N. Hatziargyriou, J. Mutale, P. Djapic, and N. Jenkins,
these buses are far away from the main grid supply point. At “Integrating distributed generation into electric power systems: A review
this point, no DERs are connected to the distribution network. of drivers, challenges and opportunities,” Elect. Power Syst. Res., vol. 77,
no. 9, pp. 1189–1203, Jul. 2007.
The voltage profile obtained from a widely used simulation tool [5] S. Liew and G. Strbac, “Maximising penetration of wind generation in
in power industry, called PSSE, is shown by the solid line with existing distribution networks,” Proc. Inst. Elect. Eng.—Gener., Transm.
stars in Fig. 7. The voltage profile of this test system should Distrib., vol. 149, no. 3, pp. 256–262, May 2002.
[6] A. Shafiu, T. Bopp, I. Chilvers, and G. Strbac, “Active management and
be similar or close to that of obtained through PSSE when the protection of distribution networks with distributed generation,” in Proc.
derived voltage variation formula will be used. With the derived IEEE Power Eng. Soc. Gen. Meet., Jun. 2004, pp. 1098–1103.
voltage variation formula, the voltage profile of the 15-bus test [7] T. Bopp, A. Shafiu, I. Cobelo, I. C. Jenkins, N. Jenkins, G. Strbac,
H. Li, and P. Crossley, “Commercial and technical integration of dis-
system is also shown in Fig. 7 by the solid line with circles, tributed generation into distribution networks,” presented at the 17th Int.
which is very close that of obtained from PSSE. Conf. Electricity Distribution (CIRED), Barcelona, Spain, 2003, Paper 45.
Now, if a 6-kW synchronous generator is connected at bus [8] M. H. J. Bollen and A. Sannino, “Voltage control with inverter-based
distributed generation,” IEEE Trans. Power Del., vol. 20, no. 1, pp. 519–
4, a 2-kW PV generator is connected at bus 13, and a 3-kW 520, Jan. 2005.
wind generator is connected at bus 10, the voltage profile of [9] C. M. Hird, H. Leite, N. Jenkins, and H. Li, “Network voltage controller
the distribution network is shown in Fig. 8. In this case, there for distributed generation,” Proc. Inst. Elect. Eng.—Gener., Transm. Dis-
trib., vol. 151, no. 2, pp. 150–156, Mar. 2004.
should be a voltage rise, as compared with the distribution [10] A. E. Kiprakis and A. R. Wallace, “Maximizing energy capture from
network without DG at buses 4 and 13, as well as their adjacent distributed generators in weak networks,” Proc. Inst. Elect. Eng.—Gener.,
buses and a voltage drop at bus 10 and its adjacent buses. This Transm. Distrib., vol. 151, no. 5, pp. 611–618, Sep. 2004.
[11] P. M. S. Carvalho, P. F. Correia, and L. A. F. M. Ferreira, “Distributed
happens as the synchronous generator supplies both active and reactive power generation control for voltage rise mitigation in distribu-
reactive power and the PV generator supplies active power to tion networks,” IEEE Trans. Power Syst., vol. 23, no. 2, pp. 766–772,
the system. Moreover, this portion of the system has enough May 2008.
[12] A. Keane, L. F. Ochoa, E. Vittal, C. J. Dent, and G. P. Harrison, “Enhanced
reactive power to supply loads. On the other hand, the region at utilization of voltage control resources with distributed generation,” IEEE
which the wind generator is connected is far from the main grid, Trans. Power Syst., vol. 26, no. 1, pp. 252–260, Feb. 2011.
and the reactive power available in this portion is not sufficient [13] G. Celli, E. Ghiani, S. Mocci, and F. Pilo, “A multiobjective evolutionary
algorithm for the sizing and siting of distributed generation,” IEEE Trans.
to meet the load demand. Moreover, the wind generator also Power Syst., vol. 20, no. 2, pp. 750–757, May 2005.
consumes reactive power, and this is why the voltage at bus 11, [14] L. F. Ochoa, A. Padilha-Feltrin, and G. P. Harrison, “Time-series-based
which is adjacent to bus 10, falls down outside the specified maximization of distributed wind power generation integration,” IEEE
Trans. Energy Convers., vol. 23, no. 3, pp. 968–974, Sep. 2008.
limit. In Fig. 8, it is shown that the voltage profile obtained [15] A. M. El-Zonkoly, “Optimal placement of multi-distributed generation
from the derived formula is very close to that of obtained from units including different load models using particle swarm optimisation,”
PSSE when DERs are integrated into the distribution system. IET Gener., Transm. Distrib., vol. 5, no. 7, pp. 760–771, Jul. 2011.
[16] A. Keane and M. OMalley, “Optimal allocation of embedded genera-
tion on distribution networks,” IEEE Trans. Power Syst., vol. 20, no. 3,
pp. 1640–1646, Aug. 2005.
VIII. C ONCLUSION [17] N. S. Rau and Y. H. Wan, “Optimum location of resources in dis-
tributed planning,” IEEE Trans. Power Syst., vol. 9, no. 4, pp. 2014–2020,
The voltage variation for a small and a large distribution Nov. 1994.
[18] G. P. Harrison and A. R. Wallace, “Optimal power flow evaluation of dis-
network has been estimated through an analytical approach, and tribution network capacity for the connection of distributed generation,”
the derived voltage variation formula is accurate for performing Proc. Inst. Elect. Eng.—Gener., Transm. Distrib., vol. 152, no. 1, pp. 115–
the analysis as it provides very similar results to that of the 122, Jan. 2005.
[19] P. N. Vovos, G. Harrison, A. R. Wallace, and J. W. Bialek, “Optimal power
existing power system simulation software. The worst case flow as a tool for fault level constrained network capacity analysis,” IEEE
scenario of the distribution network is considered based on the Trans. Power Syst., vol. 20, no. 2, pp. 734–741, May 2005.
derived formula in order to build up a relationship between the [20] P. N. Vovos and J. W. Bialek, “Direct incorporation of fault level con-
straints in optimal power flow as a tool for network capacity analysis,”
voltage variation and maximum DG capacity. The relationship IEEE Trans. Power Syst., vol. 20, no. 4, pp. 2125–2134, Nov. 2005.
among voltage level, voltage variation, and DG connection cost [21] L. F. Ochoa, C. J. Dent, and G. P. Harrison, “Distribution network capacity
is built using an example. The approach presented in this paper assessment: Variable DG and active networks,” IEEE Trans. Power Syst.,
vol. 25, no. 1, pp. 87–95, Feb. 2010.
is useful for the future planning and operation of distribution [22] C. J. Dent, L. F. Ochoa, G. P. Harrison, and J. W. Bialek, “Efficient secure
networks, as well as for the voltage control of the existing AC OPF for network generation capacity assessment,” IEEE Trans. Power
distribution network with DG. Future works will deal with the Syst., vol. 25, no. 1, pp. 575–583, Feb. 2010.
[23] C. J. Dent, L. F. Ochoa, and G. P. Harrison, “Network distributed gen-
detailed analysis of the voltage control with different types of eration capacity analysis using OPF with voltage step constraints,” IEEE
DG such as CHP, wind generators, and PV. Trans. Power Syst., vol. 25, no. 1, pp. 296–304, Feb. 2010.
[24] G. P. Harrisona, A. Piccolo, P. Siano, and A. R. Wallacen, “Hybrid
GA and OPF evaluation of network capacity for distributed genera-
R EFERENCES tion connections,” Elect. Power Syst. Res., vol. 78, no. 3, pp. 392–398,
Mar. 2008.
[1] P. Chiradeja and R. Ramakumar, “An approach to quantify the technical [25] M. Gomez-Gonzaleza, A. Lopez, and F. Jurado, “Optimization of dis-
benefits of distributed generation,” IEEE Trans. Energy Convers., vol. 19, tributed generation systems using a new discrete PSO and OPF,” Elect.
no. 4, pp. 764–773, Dec. 2004. Power Syst. Res., vol. 84, no. 1, pp. 174–180, Mar. 2012.
[2] A. G. Tsikalakis and N. D. Hatziagyriou, “Environmental benefits of [26] C. Wang and M. H. Nehrir, “Analytical approaches for optimal placement
distributed generation with and without emissions trading,” Energy Policy, of distributed generation sources in power systems,” IEEE Trans. Power
vol. 35, no. 6, pp. 3395–3409, Jun. 2007. Syst., vol. 19, no. 4, pp. 2068–2076, Nov. 2004.
This article has been accepted for inclusion in a future issue of this journal. Content is final as presented, with the exception of pagination.
[27] N. Acharya, P. Mahat, and N. Mithulananthan, “An analytical approach M. J. Hossain (M’11–SM’13) received the B.Sc.
for DG allocation in primary distribution network,” Int. J. Elect. Power and M.Sc.Eng. degrees from Rajshahi University
Energy Syst., vol. 28, no. 10, pp. 669–678, Dec. 2006. of Engineering and Technology (RUET), Rajshahi,
[28] T. Gozel and M. H. Hocaoglu, “An analytical method for the sizing and Bangladesh, in 2001 and 2005, respectively, and the
siting of distributed generators in radial systems,” Elect. Power Syst. Res., Ph.D. degree from The University of New South
vol. 79, no. 6, pp. 912–918, Jun. 2009. Wales, Canberra, Australia, in 2010, all in electrical
[29] D. Q. Hung, N. Mithulananthan, and R. C. Bansal, “Analytical expressions and electronic engineering.
for DG allocation in primary distribution networks,” IEEE Trans. Energy He served as a Research Fellow in the School of
Convers., vol. 25, no. 3, pp. 814–820, Sep. 2010. Information Technology and Electrical Engineering,
[30] D. Q. Hung, N. Mithulananthan, and R. Bansal, “Multiple distributed The University of Queensland, Brisbane, Australia.
generators placement in primary distribution networks for loss reduction,” He was also an Assistant Professor and a Lecturer
IEEE Trans. Ind. Electron, vol. 60, no. 4, pp. 1700–1708, Apr. 2013. at RUET for six years. He is currently a Lecturer in Griffith School of
[31] K. Zou, A. P. Agalgaonkar, K. M. Muttaqi, and S. Perera, “Distribution Engineering, Griffith University, Gold Coast, Australia. His research interests
system planning with incorporating DG reactive capability and system are power systems, renewable energy integration and stabilization, voltage
uncertainties,” IEEE Trans. Sustain. Energy, vol. 3, no. 1, pp. 112–123, stability, microgrids, robust control, electrical machine, flexible alternating
Jan. 2012. current transmission system devices, and energy storage systems.
[32] M. L. Doumbia and K. Agbossou, “Voltage variation analysis in inter-
connected electrical network—Distributed generation,” in Proc. IEEE
Canada Elect. Power Conf., 2007, pp. 525–530.
[33] W. H. Kersting, Distribution System Modeling and Analysis, 2nd ed.
London, U.K.: CRC Press, 2007.
[34] “Report ‘Network pricing list’,” Energy Australia, Melbourne, VIC,
Australia, 2010.
[35] C. L. Masters, “Voltage rise: The big issue when connecting embedded
generation to long 11 kV overhead lines,” Power Eng. J., vol. 16, no. 1,
pp. 5–12, Feb. 2002.
[36] F. M. Gonzalez-Longatt, “Impact of distributed generation over power
losses on distribution system,” in Proc. 9th Int. Conf. Elect. Power Qual.
Utilisation, Oct. 2007, pp. 1–6.
H. R. Pota received the B.E. degree from Sardar
Vallabhbhai Regional College of Engineering and
M. A. Mahmud (S’10–M’13) received the Bache- Technology, Surat, India, in 1979; the M.E. degree
lor’s degree (with honours, first class first position) in from the Indian Institute of Science, Bangalore,
electrical and electronic engineering from Rajshahi India, in 1981; and the Ph.D. degree from The Uni-
University of Engineering and Technology (RUET), versity of Newcastle, Callaghan, Australia, in 1985,
Rajshahi, Bangladesh, in 2008 and the Ph.D. de- all in electrical engineering.
gree (with best thesis award) in electrical engi- He is currently an Associate Professor at The
neering from The University of New South Wales, University of New South Wales at the Australian
Canberra, Australia, in 2012. Defence Force Academy, Canberra, Australia. He
He served as a Radio Network Planning Engineer has held visiting appointments at the University of
at Huawei Technologies (BD) Ltd. After that, he be- Delaware, Newark, DE, USA; Iowa State University, Ames, IA, USA; Kansas
came a Lecturer at Khulna University of Engineering State University, Manhattan, KS, USA; Old Dominion University, Norfolk, VA,
and Technology, Khulna, Bangladesh, and in the Department of Electrical USA; the University of California at San Diego, La Jolla, CA, USA; and the
and Electronic Engineering, RUET. He is currently a Research Fellow at Centre for Artificial Intelligence and Robotics, Bangalore. He has a continuing
The University of Melbourne, Melbourne, Australia. His research interests are interest in the area of power system dynamics and control and modeling and
dynamic stability of power systems, renewable energy integration, smart grids, control of mechanical systems such as flexible structures, acoustical systems,
nonlinear control theory, and electrical machine. and unmanned aerial vehicles.