HOLD POINTS FOR MEP WORKS READINESS


Level : 2nd floor level (Office block) Pour : P1,P2 & P3(Grid no.(01'-09/A"-D'))
Sl. No Description of work Check

1 Removal of left out plywoods after deshuttering of slab soffits ¨


2 Removal of foam sheets in junctions of beams & Column ¨
3 Removal of dead concrete around the beams & column junction ¨
4 Removal of leaked cement slurry around the columns ¨
5 Removal of shuttering/masking tape in ceilings ¨
6 Tie rod holes packing in columns ¨
7 Removal of wall ties & PU sleeves in shear/core walls ¨
8 Grouting/Packing of wall ties in shear/core walls ¨
9 Rectification of damaged Column Captial edges ¨
10 Grouting/Packing of screw head impressions of table mould in slab soffits ¨
11 Rectification of honeycombs in column capital side surfaces ¨
12 Protruding nails from slab soffit/capitals/beam junctions removal. ¨
13 Protruding binding wires from slab/capitals/beam junctions removal. ¨
14 Pour strip soffits grinding & rectification ¨
15 PT stressing cut out soffit grinding & rectification ¨
16 Water Leakages rectification in Slab soffits ¨
17 Plumb out/bulged beam, columns and junctions rectification ¨
18 Water ponding test in pour strips joints and constrution joint areas in slab ¨
19 MEP sleeves foam removal ¨
20 Ramp & Staircase area electrical junction box exposing ¨
21 Duct/shaft sizes checking ¨
22 Lift pit cleaning (Not Applicable except Basement-3 level) ¨
23 Grinding of joints in slab soffits ¨
24 PT cable marking X & Y directions ¨
25 Blockworks for service rooms ¨
26 Plastering works for service rooms ¨
27 Upstands constructions ¨
28 Plum concrete filling in B3 ramps ¨
29 Overhead protection in duct/shaft openings above ¨
30 Painting in Walls in service rooms ¨
31 Painting (OBD) of Ceilings, Beams, Columns with primer & putty ¨
32 Housekeeping & Removal of unwanted materials from bay ¨
33 VDF Flooring ( Drain & Sump Gratings/ Plumbing conduits/Electrical conduits/etc) ¨
34 Lime coat in shafts ¨
35 Gutter/grating for drain /Catch basin ¨
Water proofing treatment/plaster in Catchbasin /UG sumps/Drain etc (Not
36 Applicable except Basement-3 level) ¨