Relay Setting Calculation
Relay Setting Calculation
(CALCULATION)
10005-ESC-GPV105-002
ETP SUBSTATION
Copyright of all published material including photographs, drawings and images in this
document remains vested in Aker Solutions and third party contributors as appropriate.
Accordingly, neither the whole nor any part of this document shall be reproduced in any form
nor used in any manner without express prior permission and applicable acknowledgements.
No trademark, copyright or other notice shall be altered or removed from any reproduction.
Project No. :
INDEX
1. Scope............................................................................................................................................4
2. Reference Documents...................................................................................................................4
3. Reports Index................................................................................................................................5
4. Tag Convention............................................................................................................................6
5. Feeder Types................................................................................................................................6
6. Protection Types...........................................................................................................................6
7. Operating Conditions:..................................................................................................................7
8. General Protection Co-Ordination Philosophy.............................................................................7
9. Protection for Different Circuit Types.......................................................................................14
10. Formulae.....................................................................................................................................17
1. Scope
The intent of this document is to define the philosophy for Electrical Protection Co-
ordination for electrical network for ETP Substation & to verify the results using ETAP
software version 11.1.1.
The actual relay parameterization activities – that includes entering the parameters at
appropriate address in the relays & setting other default relay parameters - shall be done by
vendor at the time of commissioning based on the settings given in this document.
The Settings given in this document are applicable for plant commissioning & shall not be
used for substation charging purpose.
The parameterization of the following relays shall be carried out by operations team in
consultation with the agencies mentioned.
1. Settings for 11kV Incomer relay to ES-GPV105-01 & respective outgoing feeder relays
from HT-248 board at SS5 are recommended in this document. The Incomer Bus
coupler relay at HT-248 shall be accordingly coordinated by OTHERS.
This document provides the basis for parameterization & the current/time settings for the
following elements:
1. Phase over current elements I>, I>>, Ip
2. Ground over current elements IE>, IEp
3. Neutral over current elements SEF, REF
4. Phase under current element I< & Negative sequence element I2>
5. Differential current element I DIFF
6. Phase under & over voltage elements U<, U>
7. Other specific settings for REF, MComp & ProkDvs.
2. Reference Documents
a. APG Key SLD - 10005-E51-GPV105-008
b. Vendor schematic H09 series for ES0A01, ES0A02 & EC0A01
c. Protection philosophy Doc. No. 10080-1-SS-EL-039, Rev 0
d. Addendum email by core dated 03rd Dec 2013
Notes: The relay settings are first determined to give the shortest operating times at
maximum source fault levels and then checked to see if operation will also be satisfactory at
the minimum source fault current expected. Where significant differences between maximum
and minimum fault levels exist, it is essential to ensure that the selection of a current setting
does not result in the relay failing to operate under minimum fault current conditions.
3. Reports Index
TCC – 11kV
Phase Over Current Relay Coordination Curves / TCC for 11kV
2.1.1 Switchboard –
incomer, bus coupler & 2..5MVA Transformer outgoing feeder
Phase
TCC – 11kV
Ground Relay Coordination Curves / TCC for 11kV incomer, bus
2.1.2 Switchboard –
coupler & 2..5MVA Transformer outgoing feeder
Ground
TCC – 2.5MVA Ground Relay Coordination Curves / TCC for 2.5MVA Transformer
2.2.2 Transformer – outgoing feeder & Downstream PCC Incomer, Bus coupler &
Ground outgoing feeder to MCC
Parameterization Schedules
4. Tag Convention
All protective/switching devices are assigned unique tags of the form ‘X_Y’.
The first portion of the tag (‘X’) shall be derived as follows:
a. Relays: R_
b. Current transformers: C_
c. Contactors: CO_
d. Fuses: F_
The second portion of the tag (‘Y’) shall be derived from the tags of the equipment
associated with the protected devices.
For protective devices associated with a piece of equipment, ‘Y’ shall be
same as the equipment tag name.
For protective devices between two items of equipment, ‘Y’ shall be same as the tag
name of the first equipment, followed by underscore and then the tag name of the
second equipment
5. Feeder Types
Circuit Circuit
Application Application
Type Type
ZA Only SFU <=63A ZE SFU + Contactor DOL
ZB SFU + Contactor <=63A ZF SFU + Contactor DOL
ZC SFU + Contactor + ELR >63A ZG ACB Feeder DOL
ZD SFU + Contactor DOL ZH ACB Feeder upto 800A
6. Protection Types
Feeder
Circuit Type Protection Type Selected Relay Type
Type
0.415kV
Outgoing – to non-motor
ZA Fuse
consumers<=63A
Outgoing – to non-motor
ZC Fuse + ELR
consumers>63A
ZH & ZJ Outgoing – to Other Boards> & <=800A Feeder Protection Relay REF 615
- Incomer & Bus Coupler Feeder Protection Relay REF 615, REU 615
11kV
Z3 / Z4 Outgoing – to Motor NA
11kV
7. Operating Conditions:
7.1. Minimum – 250MVA (13.12kA @ 11kV)
7.2. Maximum – 501.1MVA (26.3kA @ 11kV)
7.3. Normal – 501.1MVA (26.3kA @ 11kV)
8.3. Fuses
The operating time of a fuse is a function of both the pre-arcing and arcing time of the
fusing element, which follows the I 2t law. To achieve proper co-ordination between two
fuses in series, it is necessary to ensure that the total I 2t taken by the smaller fuse is not
greater than the pre-arcing I2t value of the larger fuse. It has been established by tests that
satisfactory grading between the two fuses will generally be achieved if the current rating
ratio between them is greater than two.
The minimum grading interval t' between inverse time relays and fuses shall be set in
accordance with the formula:
t' = 0.4t + 0.10 seconds = 0.4 x 0.01 + 0.10 = 0.104s
where, t = nominal operating time of fuse = 10ms
When grading inverse time relays with fuses, it should be ensured that the relay backs up
the fuse and not vice versa, since it is very difficult to maintain correct discrimination at
high values of fault current because of the fast operation of the fuse.
The relay characteristic best suited for co-ordination with fuses is normally that of the
extremely inverse relay, which follows a similar I2t characteristic. For satisfactory co-
ordination between the extremely inverse relay and the fuse, the primary current setting
of the relay should be approximately three times the current rating of the fuse.
As fuse can reliably trip from their min breaking current i.e. 2.5 to 3 times their rated
current. For currents between their rated current & min breaking current, fuses can not
reliably operate
8.4. Switchboards have short time current withstand rating of 1 second. No short circuit
protection settings are therefore allowed to exceed 1s.
8.5. Protection discrimination and operational sensitivity shall be established for the maximum
and minimum three phase fault currents as shown in the Power System Study Report. The
minimum three phase fault currents are generally based upon the least number of
generators and a transformer outage, and excludes the short-circuit current contribution
from motors.
8.6. Based on the transformer data sheets furnished by the manufacturers, the transformer inrush
current shall be considered as follows:
8.8. The 415V system is solidly earthed. Discrimination shall be provided for earth fault
protection between incomer and outgoing feeders.
8.9. The 11kV system is resistance earthed with the earth fault current limited to 2000A.
Discrimination shall be provided for earth fault protection between incomer and outgoing
feeders.
8.10. Philosophy for Setting up Under voltage Protection
Motor Feeders
Under voltage protection shall be set to distinguish between normal transient under
voltage occurring due to the motor starting or load additions, and the severe under voltage
associated with system fault conditions. Transient voltage dips to 80% of nominal voltage
will be regarded as normal and values below 80% as abnormal. Motors shall be tripped
on abnormal under voltage in order to protect the motor from the transient torques that
occur when the voltage is depressed and restored in rapid succession.
The under voltage setting shall also be selected to ensure that the motor does not stall due
to load torque requirement exceeding the motor pull-out torque while operating at
reduced voltages.
The under voltage settings for motor feeders shall be selected as follows:
Voltage: 75% of nominal voltage (set below the minimum normal voltage limit of 80%)
Time: 0.8s (set above the operating time of the incomer/outgoing feeder overcurrent and
earth fault protections, thus preventing nuisance tripping of the motor feeders under
temporary under voltage conditions due to fault elsewhere in the electrical system).
Overcurrent and under voltage protection should be checked for coordination.
Generally, to avoid momentary overload on battery, max. 2 nos motor feeders are tripped
with the delay of 0.8s. Tripping of rest of the motors is staggered over next 0.2s.
However, battery vendor has confirmed that there’s no restriction on simultaneous
breaker closing hence under voltage element of all motors has been set identical.
Transformer Feeders/Bulk Feeders
It is not intended to trip non-motor feeders on occurrence of under voltage.
Incomers
The under voltage protection for the switchboard incomers is related to the operation of
the switchboard auto change over scheme.
8.11. Philosophy for Auto Change Over (ACO) Scheme
ACO schemes are provided for 11kV and 415V systems. This enables automatic closing
of the bus coupler circuit breaker on loss of normal supply to any of the bus sections. The
following conditions shall be fulfilled before the ACO scheme issues closing command to
the bus coupler Circuit Breaker:
All outgoing motor feeders connected to the de-energised bus are tripped on under
voltage. This will prevent simultaneous restarting of these motors on resumption of
power supply to the bus section.
One of the two incomers to the switchboard is tripped on under voltage protection.
The voltage at the de-energised bus is less than 20% of the nominal voltage.
The circuit breaker on the ‘healthy’ incomer is in the ‘service’ position and closed.
The voltage at the ‘healthy’ bus is more than 80% of the nominal voltage.
ACO schemes shall be blocked by high set over current and earth fault protection when
there is a bus fault.
In addition, the overcurrent protection on the HV side of the incomer transformer shall
be graded with the incomer overcurrent protection to ensure that the upstream relay does
not clear a switchboard bus fault before the incomer protection operates and inhibits the
ACO scheme.
Also, no trip - that is not related to the switchboard bus fault - shall hit the 86 of the
incomer relay.
(a) Under voltage protection settings for ACO scheme on 11kV Switchboards
The under voltage protection for the motor feeders shall be set at 75% of the nominal
voltage with a time delay of 0.8s.
Under voltage protection for incoming feeders shall be set at 75% of the nominal voltage
with time delay of 0.9s. This allows tripping of the outgoing motor feeders on under
voltage protection prior to tripping of incomer Circuit Breaker and initiation of the ACO
scheme.
Under voltage protection for the bus sections shall be set at 20% nominal voltage with no
time delay to indicate “dead bus” conditions, permitting operation of the ACO scheme.
The total operation time of the ACO scheme at 11kV switchboards shall be 0.9s (Incomer
under voltage protection time delay) + 0.06s (Incomer CB opening time) + 0.06s (Bus
coupler CB closing time) = 1.02s
(b) Under voltage protection settings for ACO scheme on 415V Switchboards
The ACO scheme for the 415V PCCs shall be time-delayed to take place only if the
operation of the ACO scheme at the upstream 11kV Switchboards has not occurred.
The under voltage protection for motor feeders shall be set at 75% of the nominal voltage
with 0.8s time delay.
Under voltage protection for the incomer feeder shall be set at 75% of the nominal
voltage with 1.2s time delay (graded with the time delay settings of the upstream 6.6kV
Switchboard ACO scheme).
Under voltage protection for the bus sections shall be set at 20% nominal voltage with no
time delay to indicate “dead bus” conditions, permitting operation of the ACO scheme.
The total operation time of the ACO scheme at 415V switchboards shall be 1.2s (Incomer
under voltage protection time delay) + 0.05s (Incomer CB opening time) + 0.05s (Bus
coupler CB closing time) = 1.3s
For PMCCs with 2 incomers connected to upstream PCC and one incomer from DG (i.e.
with incomer configuration of PCC-PCC-DG), the ACO scheme shall be time-delayed to
take place only if the operation of the ACO scheme at the upstream 415V PCC has not
occurred. Hence, the under voltage protection for the PMCC incomers fed from upstream
PCC shall be set at 75% of the nominal voltage with 1.5s time delay (graded with the
time delay settings of the upstream 415V PCC ACO scheme).
For PMCCs with 1 incomer each from upstream PCC and PMCC (i.e. with incomer
configuration of PCC-PMCC), the ACO scheme shall be time-delayed to take place only
if the operation of the ACO scheme at the upstream 415V PCC/PMCC has not occurred.
Hence, the under voltage protection for the PMCC incomers shall be set at 75% of the
nominal voltage with 1.8s time delay (graded with the time delay settings of the upstream
415V PMCC ACO scheme).
(c) It shall be ensured that the over current protection does not operate during the starting
of the largest connected motor with the maximum possible standing load & the group
restart load.
(d) The earth fault protection shall be IDMT type, set at 30% and graded with the outgoing
feeder to provide backup protection to the outgoing feeders.
(e) Standby earth fault protection shall be IDMT type, set at 30% and graded with the
incomer earth fault protection. This protection shall trip the circuit breakers on both
11kV and 415V sides of the transformer.
(c) For breaker-controlled motors, IDMT negative phase sequence protection shall be set
as per the I22t value indicated by the motor manufacturer. In case this is not available,
I22t = 20 as indicated in IEC 60034 shall be used as the basis for the relay setting. In
addition to the IDMT negative phase sequence protection, the high-set negative phase
sequence protection shall be used to achieve fast clearance for severe unbalances like
loss-of-phase conditions.
(d) Earth fault protection
For contactor-controlled motor feeders rated upto 15kW, earth fault protection shall be
provided by the M Comp relay (as part of the unbalance protection). time delay is
provided with the earth fault protection to ensure the fuse operates before the contactor
opens for fault currents beyond its capability.
For contactor-controlled motor feeders rated 15kW & above and breaker-controlled
motor feeders, CBCT-fed earth fault protection is provided. The sensitivity of the
CBCT and the minimum settings available on the associated relay allow earth fault
current of the order of 1A to be detected and reliably tripped. For contactor-controlled
motor feeders, the operation of the relay shall be time delayed (3 seconds) to ensure
the fuse operates before the contactor opens for fault currents beyond its capability.
(e) Where required (e.g., pumps requiring dry run protection), under current protection shall
be provided set at 40% of FLC with time delay of 10s. This shall be reconfirmed from
the rotary equipment manufacturer.
(f) Other motor protection settings shall be set in accordance with recommendation by
motor manufacturer.
9.8. Low Voltage (415V) contactor-controlled Switch-Fuse Feeder – ZA / ZB / ZC
(a) Short circuit protection
Short circuit protection for contactor-controlled Switch-fuse feeders shall be provided
by the fuse.
(b) Earth fault protection
415V contactor-controlled Switch-fuse feeders are provided with CBCT-fed earth fault
relay set at 1A. The operation of the relay shall be time delayed (3 seconds) to ensure
the fuse operates before the contactor opens for fault currents beyond its capability
10. Formulae
Curve Type IEC Equation for TMS evaluation
Where,
t = Relay Tripping Time
Tp = TMS (Time Multiplier Setting)
MOC (Multiple Of Current) = fault current/pick up current