Geometric Design Manual
Geometric Design Manual
The Ministry of Public Works, Housing and Water Resources (MOPHRH) in Mozambique is
responsible for the National Road Administration of Mozambique, Administração Nacional
de Estradas (ANE) and custodian of the standards and specifications for roads in the
Mozambique Road Sector. This manual provides guidance to all practitioners in the
provision of appropriately designed drainage systems for all roads and particularly high-
volume roads. The content adequately covers all relevant technical areas and where
more details are required users may consult other documents referenced by the author.
This manual is tailor-made for Mozambique and ANE will apply it as mandated by the
Ministry.
(i)
Preface
The procedures for the geometric design of roads presented in this manual are applicable
to roads carrying more than 300 motorised vehicles per day, or the design traffic
exceeding 1 million cumulative equivalent standard axles (MESA) over the design life of
the road. If the traffic is less than 300 vehicles per day or the design traffic is less than 1
MESA over the design life, then ANE’s Manual for the Provision of Low Volume Roads
must be used.
This manual covers three basic design situations. Upgrading from a lower class of road to
a higher class; designing a road to replace an existing track; and designing a completely
new road where nothing existed before. This manual does not deal in detail with the
design of major grade-separated interchanges between restricted-access freeways
(motorways) although the topic is introduced sufficiently for some of the simpler designs
to be carried out.
In order to improve road safety, the geometric design should take into account the road
environment, road characteristics and human factors which are explained under various
chapters. This holistic approach is aimed at reducing the probability of ‘failure’ to the
lowest possible level and should minimise the adverse consequences should failure
occur.
It is recognised that every highway project is unique. The characteristics of the area, the
values of the surrounding community, the needs of the highway users and the physical
challenges are unique factors that highway designers must consider. The corollary of this
is that designers must exercise flexibility and, most importantly, to understand the
safety and operational impacts of various design features and modifications.
(i)
Acknowledgements
This manual was prepared through the concerted effort from many stakeholders within
and outside Mozambique. The immense contributions from ANE, the Technical Working
Group (WG) members, the World Bank Expert Reviewer, the MOPHRH and other key
stakeholders which included academia, consultants, municipal engineers, Institute of
Meteorology, Ministry of Water Resources, etc. are acknowledged and greatly
appreciated. ANE provided leadership and guidance including management of the project
in general. They also provided information and support required for the successful
delivery of the manual. The WG members, World Bank reviewer, academia, consultants
and municipal engineers reviewed the manual in its different stages of development and
provided invaluable inputs through technical deliberations, comments, edits and
additions.
The production of this manual was financed by the Government of Mozambique through
the Ministry of Finance and the Road Fund with support from the World Bank.
ANE
Eng. Marcos Vaz Dos Anjos General Director
Eng. Luis Fernandes Director of Emergency Works and Project Coordinator
Eng. Irene Simeos Director of Maintenance
Eng. Migel Coanai Director of Planning
Eng. Rubina Normahomed Head of Maintenance
Eng. Anibal Nuvunga Head of Planning
Technical Working Group ANE Engineers, MOPHRH Engineers, Municipal Engineers,
Consultants, Academia,
Financiers
Gov. of Mozambique MOPHRH, Min of Finance, Road Fund
World Bank Representative Kulwinder S. Rao
World Bank Reviewer Eng. Carlos Matias Ramos
(ii)
Abbreviations
(iii)
PT Point of Tangency. Where a Circular Curve ends. Also
designated EC
RC Reverse Camber
SANRAL South African National Roads Agency Limited
SATCC Southern Africa Transport and Communications Commission
SC Spiral to Circular Curve Transition point
SE Super-Elevation
TC Telecommunications Corporations
TC Tangent to Curve. Also designated BC or PC
TRL Transport Research Laboratory
TS Tangent to Spiral Transition point
VPI Vertical Point of Intersection
vph Vehicles per Hour
(iv)
Glossary of Terms
Acceleration lane An auxiliary lane to enable a vehicle to increase its speed so
that it can merge safely with through traffic.
Access Control The condition where the road agency controls the right of
landowners to direct access to and from a public highway.
Auxiliary Lane Part of the roadway adjoining the carriageway for parking,
speed change, turning, storage for turning, weaving, truck
climbing, and for other purposes supplementary to through
traffic movement.
Average Annual The total yearly traffic volume in both directions divided by the
Daily Traffic number of days in the year.
(AADT)
Average Daily The total traffic volume during a given time period in whole days
Traffic (ADT) greater than one day and less than one year divided by the
number of days in that time period.
Average Running The total distance travelled by all the vehicles divided by the
Speed running time of all the vehicles; also referred to as the space
mean speed. [The time mean speed is the average of all
recorded speeds.
Axis of Rotation The line about which the pavement is rotated to super-elevate
the roadway. This line normally maintains the highway profile.
Catchwater Drain Located above a cut face to ensure that storm water does not
flow down the cut face causing erosion and deposition of silt on
the roadway.
(v)
motorcycles to a common unit for judging road width
requirement for safety purposes. Note that they are not the
same as PCU values that are used for capacity and congestion
estimates for heavily trafficked roads.
Climbing Lane An auxiliary lane in the upgrade direction for use by slow moving
vehicles and to facilitate overtaking, thereby maintaining
capacity and freedom of operation on the carriageway.
Clover-leaf An interchange with four loop ramps and four diagonal ramps,
interchange with no traffic control on either crossing roadway.
Coefficient of Ratio of the frictional force on the vehicle and the component of
Friction the weight of the vehicle perpendicular to the frictional force
Compound Curve Curve consisting of two or more arcs of different radii curving in
the same direction and having a common tangent or transition
curve where they meet.
Connector A collective term for interchange links, link roads, ramps and
loops.
Critical Slope Side slope on which a vehicle is likely to overturn. Slopes with
inclinations greater than 1V:3H are considered critical.
Cycle Lane A portion of the roadway which has been designated by road
markings, striping and signing as being exclusively for the use of
cyclists.
Cycle Path Also known as a bike way. A path physically separated from
(vi)
motorised traffic by an open space or barrier and located either
within the road reserve or an independent reserve.
Deceleration Lane An auxiliary lane to enable a vehicle leaving the through traffic
stream to reduce speed without interfering with other traffic.
Decision Sight Allows for circumstances where complex decisions are required
Distance by a driver or unusual manoeuvres have to be carried out. As
such, it is significantly longer than Stopping Sight Distance.
Deflection Angle Successive angles from a tangent subtending a chord and used
in setting out curves.
Design Capacity Maximum number of vehicles that can pass over a lane or a
roadway during a given time period without operating
conditions falling below a pre-selected design level.
Design Hour The hour in which the condition being designed for, typically the
anticipated flow is expected to occur. This is often the thirtieth
highest hour of flow in the design year.
Design Speed An index which links road function, traffic flow and terrain to the
design parameters of sight distance and curvature to ensure that
a driver is presented with a reasonably consistent speed
environment. It is now defined as the 85th percentile speed of
passenger cars travelling in free flow conditions. In practice,
most roads will only be constrained to minimum parameter
values over short sections or on specific geometric elements.
Design Traffic Number of vehicles that pass over a given section of a lane or
Volume roadway during a given time period.
Design Vehicle Vehicle whose physical characteristics and proportions are used
in setting geometric design.
Design Year The last year of the design life of the road or any other facility,
often taken as twenty years although, for costly structures such
as major bridges, a longer period is usually adopted.
Diverging The opposite of merging. When a traffic stream splits into two or
more streams.
(vii)
percentile speed road or highway.
Eye Height Assumed height of a driver's eyes above the surface of the
roadway used for the purpose of determining sight distances.
Gap The space or time between two vehicles, measured from the
rear bumper of the front vehicle to the front bumper of the
second vehicle.
Grade Line The line describing the vertical alignment of the road or
highway.
Gradient Rate of rise or fall on any length or road, with respect to the
horizontal. It is typically expressed as a percentage or as the
vertical rise or fall in m/100 m. In the direction of increasing
stake value, upgrades are taken as positive and downgrades as
negative.
Hairpin Curve A bend in a road with a very acute inner angle at or near
minimum radius, making it necessary for a vehicle to turn
sharply almost 180°. Sometimes also called switchback curves.
High Occupancy A special lane open only to vehicles carrying two or more
Vehicle (HOV) passengers.
Lane
(viii)
distance. the road and measured at the centre of the inside lane.
Left Hand Lane On a dual roadway, the traffic lane nearest to the verge or
shoulder (in countries where traffic moves on the left).
(ix)
stopping sight distances for the two vehicles plus a short safety
distance.
Normal Traffic Traffic which would pass along the existing road or track even if
no new pavement were provided.
Operating Speed Highest overall speed at which a driver can travel on a given
road under favourable weather conditions and under prevailing
traffic conditions without at any time exceeding the safe speed
as determined by the design speed on a section-by-section
basis, neither exceeding at any time the speed limit.
Outer separator Similar to the median but located between the travelled way of
the major road and the travelled way of parallel lanes serving a
local function if these lanes are contained within the reserve of
the major road. If they fall outside this reserve, reference is to
a frontage road.
Parking Bay Area provided for taxis and other vehicles to stop outside of the
roadway.
Partial Clover An interchange with loop ramps in one, two or three (but
Leaf Interchange usually only two) quadrants. A Par-Clo A Interchange has the
loops in advance of the structure and Par-Clo B Interchange has
the loops beyond the structure. A Par-Clo AB Interchange has
its loops on the same side of the crossing road.
Passenger car The number of passenger cars that will result in the same
equivalents operational conditions as a single heavy vehicle of a particular
(units) (PCE or type under specified roadway, traffic, and control conditions. In
(x)
PCU). studies involving capacity and LS at interceptions it might be
necessary to extend the PCU concept to motorcycles.
Passing Sight Minimum sight distance on two-way single roadway roads that
Distance must be available to enable the driver of one vehicle to pass
another vehicle safely and comfortably without interfering with
the speed of an oncoming vehicle travelling at the design
speed, should it come into view after the overtaking manoeuvre
is started.
Point of Vertical The point at which a grade ends and the vertical curve begins,
Curvature (PVC) often also referred to as BVC (Beginning of Vertical Curve).
Vertical Point of The point where the extension of two grades intersect.
Intersection (VPI)
Point of Vertical The point at which the vertical curve ends, and the grade begins.
Tangency (PVT) Also referred to as EVC (End of Vertical Curve).
Recoverable Side slope of limited grade such that a motorist can generally
Slope return to the roadway. (Slopes < 1:4)
(xi)
Relative Gradient The slope of the edge of the travelled way relative to the grade
line.
Right Hand Lane On a dual roadway, the traffic lane nearest to thecentral
reserve.
Road Reserve Strip of land legally awarded to the Roads Authority, specifically
for the provision of public right of way, in which the road is, or
will be, situated and where no other work or construction may
take place without permission from the Roads Authority.
Safety Rest Area Roadside area with parking facilities for the motorist to stop
and rest.
Shoulder The point on a cross section at which the extended flat planes
Breakpoint of the surface of the shoulder and the outside slope of the fill
and pavement intersect.
Side Drain Open longitudinal drain situated adjacent to and at the bottom of
(xii)
cut or fill slopes.
Side Slope Area between the outer edge of shoulder or hinge point and the
ditch bottom.
Sight Triangle The area in the quadrants of an intersection that must be kept
clear to ensure adequate sight distance between the opposing
legs of the intersection.
Spiral Curve Transition curves between straight (tangent) sections of road and
a circular curve.
(xiii)
Interchange
Tangent Runout The tangent runout section consists of the length of roadway
needed to accomplish a change in outside-lane cross slope from
the normal cross slope rate to zero (flat), or vice versa.
Traffic Lane Part of a travelled way intended for a single stream of traffic in
one direction, which has normally been demarcated as such by
road markings.
Transition Curve Curve whose radius changes continuously along its length, used
to connect a tangent with a circular arc or two circular areas of
different radii.
Travelled Way The lanes of the cross-section used for the movement of
vehicles. The travelled way excludes the shoulders, auxiliary
lanes, bus-bays, etc.
Turning Lanes Lanes which separate turning vehicles from the through traffic
lanes.
(xiv)
Underpass A grade separation where the subject highway passes under an
intersecting highway.
Verge The area between the edge of the road prism and the reserve
boundary.
(xv)
Contents
FOREWORD ........................................................................................................ I
PREFACE............................................................................................................. I
ACKNOWLEDGEMENTS ...................................................................................... II
ABBREVIATIONS ............................................................................................. III
GLOSSARY OF TERMS ......................................................................................... V
LIST OF TABLES ........................................................................................... XXII
LIST OF FIGURES .......................................................................................... XXV
1 INTRODUCTION ............................................................................................ 1
1.1 SCOPE ....................................................................................................... 1
1.2 FUNDAMENTAL PRINCIPLES ................................................................................ 1
1.2.1 Dealing with Human Factors .................................................................. 1
1.2.2 Other Road Users ................................................................................. 3
1.2.3 Flexibility in Design ............................................................................... 3
1.2.4 Design Speed ....................................................................................... 4
1.3 THE DESIGN DOMAIN CONCEPT ........................................................................... 4
1.4 ECONOMIC ANALYSIS ...................................................................................... 4
1.5 PRIMARY DESIGN CRITERIA ............................................................................... 5
1.5.1 Road Hierarchy .................................................................................... 5
1.5.2 Traffic Hierarchy ................................................................................... 5
1.5.3 Road environment ................................................................................ 6
1.6 DESIGN CLASSES........................................................................................... 6
1.7 DESIGN STEPS .............................................................................................. 7
2 DESIGN DATA COLLECTION AND ANALYSIS .................................................. 9
2.1 TOPOGRAPHIC SURVEY .................................................................................... 9
2.2 TRAFFIC SURVEY ........................................................................................... 9
2.2.1 Design Situations ................................................................................. 9
2.2.2 Conducting Traffic Surveys .................................................................. 10
2.3 INITIAL DATA REVIEW ................................................................................... 11
2.4 DATA ANALYSIS .......................................................................................... 11
2.4.1 Determine Non-motorised Traffic Composition ........................................ 11
2.4.2 Determine AADT ................................................................................. 12
2.4.3 Designing for Peak Flows ..................................................................... 12
2.4.4 Estimating Traffic Growth .................................................................... 12
2.5 SELECTION OF THE DESIGN TRAFFIC CLASS .......................................................... 13
3 DESIGN OF CROSS SECTION ELEMENTS ...................................................... 15
3.1 TERRAIN ................................................................................................... 15
3.2 CAPACITY AND LEVEL OF SERVICE. .................................................................... 16
3.2.1 Highway Capacity ............................................................................... 16
3.2.2 Level of Service .................................................................................. 17
3.3 ROAD WIDTHS ............................................................................................ 20
3.3.1 Additional Width for Mixed Vehicles ....................................................... 23
3.3.2 Additional Width Based on Surrounding Land Use ................................... 23
3.3.3 Auxiliary lanes.................................................................................... 23
3.4 SHOULDERS ............................................................................................... 23
3.4.1 Surfacing of Shoulders ........................................................................ 24
3.4.2 Edge Marking ..................................................................................... 24
3.4.3 Shoulders for Gravel Roads .................................................................. 24
3.5 NORMAL CROSSFALL ..................................................................................... 24
(xvi)
3.6 ROAD RESERVE ........................................................................................... 25
3.7 SIDE SLOPES AND BACK SLOPES ....................................................................... 25
3.8 ROADSIDE DITCHES...................................................................................... 27
3.8.1 Trapezoidal ........................................................................................ 28
3.8.2 V-Shape ............................................................................................ 28
3.8.3 Safer Ditches ..................................................................................... 28
3.9 CLEAR ZONE .............................................................................................. 28
3.10 FOUR-LANE AND DIVIDED ROADS ..................................................................... 29
3.11 MEDIANS .................................................................................................. 29
3.11.1 Depressed Medians ............................................................................. 30
3.12 OUTER SEPARATORS ..................................................................................... 30
3.13 BUS STOPS, LAY-BYS AND PARKING BAYS ............................................................ 31
3.14 REFUGE ISLANDS ......................................................................................... 32
3.15 SIDEWALKS ............................................................................................... 33
3.16 FOOTPATHS IN RURAL AREAS ........................................................................... 33
3.17 SLOPES .................................................................................................... 34
4 GENERAL DESIGN CRITERIA FOR ROAD ALIGNMENTS ................................ 35
4.1 DESIGN SPEED ........................................................................................... 35
4.1.1 Consistency ....................................................................................... 35
4.1.2 Changes of Design Speed .................................................................... 36
4.1.3 Speed Profiles .................................................................................... 36
4.1.4 Choice of Design Speed ....................................................................... 36
4.2 THE DESIGN VEHICLE.................................................................................... 36
4.3 SIGHT DISTANCES ....................................................................................... 39
4.3.1 Introduction ....................................................................................... 39
4.3.2 Friction between Tyres and Roadway .................................................... 39
4.3.3 Stopping Sight Distance ...................................................................... 40
4.3.4 Stopping Sight Distance for Single Lane Roads (Meeting Sight Distance) ... 42
4.3.5 Intersection Sight Distance .................................................................. 42
4.3.6 Decision Sight Distance ....................................................................... 43
4.3.7 Passing Sight Distance (PSD) ............................................................... 44
4.3.8 Passing Opportunities .......................................................................... 45
4.3.9 Headlight Sight Distance ..................................................................... 45
4.3.10 Control of Sight Distance ..................................................................... 46
5 DESIGN OF HORIZONTAL ALIGNMENT ........................................................ 47
5.1 MINIMUM HORIZONTAL RADIUS OF CURVATURE ..................................................... 47
5.2 CONSISTENCY ............................................................................................. 48
5.2.1 Length of Tangents ............................................................................. 51
5.2.2 Friction .............................................................................................. 52
5.2.3 Evaluation of Consistency .................................................................... 53
5.3 ISOLATED CURVES ....................................................................................... 53
5.4 LENGTH OF TANGENT SECTIONS AND CURVES........................................................ 54
5.4.1 Maximum Length of Tangents .............................................................. 54
5.4.2 Minimum Length of Tangent................................................................. 55
5.4.3 Minimum Length of Circular Curves ....................................................... 55
5.4.4 Maximum Length of Circular Curves ...................................................... 55
5.5 CROSS-FALL............................................................................................... 56
5.6 MINIMUM TURNING RADII ............................................................................... 56
5.7 PASSING LANES .......................................................................................... 56
5.7.1 Three-lane Designs ............................................................................. 57
5.7.2 Entry and Exit Tapers .......................................................................... 57
5.7.3 Use on Gradients ................................................................................ 57
5.8 WIDENING ON CURVES AND EMBANKMENTS .......................................................... 59
5.9 HAIRPIN CURVES ......................................................................................... 60
5.10 TRANSITION CURVES .................................................................................... 62
5.11 SUPER-ELEVATION........................................................................................ 63
(xvii)
5.11.1 Alignment with Spirals ........................................................................ 63
5.12 REVERSE CURVES, BROKEN-BACK CURVES, AND COMPOUND CURVES............................ 66
5.12.1 Reverse Curve.................................................................................... 67
5.12.2 Broken-back Curve ............................................................................. 67
5.12.3 Compound Curve ................................................................................ 68
5.13 SHOULDER SUPER-ELEVATION .......................................................................... 69
6 DESIGN OF VERTICAL ALIGNMENT ............................................................. 75
6.1 INTRODUCTION ........................................................................................... 75
6.2 VERTICAL CURVE FORMULA ............................................................................. 76
6.3 CREST CURVES ............................................................................................ 77
6.3.1 Minimum Length of Vertical Curve ........................................................ 78
6.4 SAG CURVES .............................................................................................. 79
6.5 GRADIENT ................................................................................................. 79
6.5.1 Maximum Gradients ............................................................................ 79
6.5.2 Gradient and Super-elevation ............................................................... 81
6.5.3 Maximum Gradients at Hairpin Curves ................................................... 81
6.5.4 Minimum Gradients ............................................................................. 81
6.5.5 Gradients through Villages ................................................................... 81
6.6 CLIMBING LANES ......................................................................................... 82
6.6.1 Criteria for Climbing Lanes ................................................................... 82
6.6.2 Geometric Properties of Climbing Lanes ................................................. 82
6.6.3 Safety Aspects of Climbing Lanes ......................................................... 83
7 DESIGN STANDARDS FOR ROAD ALIGNMENTS ........................................... 85
8 PHASING OF HORIZONTAL AND VERTICAL ALIGNMENTS ......................... 105
8.1 TYPES OF MIS-PHASING AND CORRECTIVE ACTION ................................................ 105
8.2 MINIMUM LENGTHS OF VERTICAL CURVES .......................................................... 105
8.3 CREST AND SAG CURVE HAVE A COMMON BEGINNING AND END ................................ 106
8.4 A SHORT DIP IN THE ALIGNMENT PRECEDING A HORIZONTAL CURVE .......................... 107
8.5 DISTORTED ALIGNMENT ............................................................................... 109
8.6 BROKEN BACK CURVES ................................................................................ 110
8.7 SAG CURVE AT THE START OF A HORIZONTAL CURVE .............................................. 111
8.8 VARIATIONS IN VERTICAL ALIGNMENT ON LONG HORIZONTAL CURVES ........................ 111
8.9 START OF HORIZONTAL CURVES NOT VISIBLE...................................................... 112
8.10 VERTICAL CURVE OVERLAPS ONE END OF THE HORIZONTAL CURVE ............................ 112
8.11 INSUFFICIENT SEPARATION BETWEEN THE CURVES ................................................ 113
8.12 BOTH ENDS OF THE VERTICAL CURVE LIE ON THE HORIZONTAL CURVE ........................ 113
8.13 VERTICAL CURVE OVERLAPS BOTH ENDS OF THE HORIZONTAL CURVE ......................... 113
8.14 THE ECONOMIC PENALTY DUE TO PHASING ......................................................... 114
8.15 VERTICAL CLEARANCES ................................................................................ 114
9 DESIGN OF AT-GRADE INTERSECTIONS .................................................... 116
9.1 INTRODUCTION ......................................................................................... 116
9.2 INTERSECTION TYPES .................................................................................. 116
9.2.1 Simple and Priority Crossroads and T-Intersections............................... 117
9.2.2 Skew Intersections ........................................................................... 120
9.2.3 Roundabouts .................................................................................... 121
9.2.4 Controlled Intersections .................................................................... 121
9.2.5 Intersection Design Speed ................................................................. 121
9.3 OTHER CONSIDERATIONS ............................................................................. 122
9.3.1 Non-motorised Traffic and Non-road Users .......................................... 122
9.3.2 Pedestrian Requirements ................................................................... 122
9.3.3 Traffic Control .................................................................................. 122
9.3.4 Shared Facilities ............................................................................... 122
9.4 FACTORS AFFECTING SELECTION OF INTERSECTION TYPE AND DESIGN ........................ 123
9.4.1 Principles of Intersection Design ......................................................... 123
(xviii)
9.4.2 Safety and Operational Comfort ......................................................... 124
9.4.3 Safety and Intersection Sight Distance ................................................ 125
9.4.4 Capacity .......................................................................................... 126
9.4.5 Vehicle Characteristics ...................................................................... 131
9.4.6 Design Speed ................................................................................... 132
9.4.7 Sight Distances ................................................................................ 132
9.4.8 Local Environment ............................................................................ 133
9.4.9 Functionality .................................................................................... 133
9.4.10 Economy ......................................................................................... 133
9.5 SELECTION OF INTERSECTION TYPE .................................................................. 134
9.5.1 Priority Intersections ......................................................................... 134
9.5.2 Control Intersections ......................................................................... 134
9.5.3 Steps in the Selection and Design Procedure ........................................ 135
9.6 DISTANCE BETWEEN ADJACENT INTERSECTIONS ................................................... 136
9.7 DESIGN OF THE ELEMENTS OF PRIORITY JUNCTIONS .............................................. 137
9.7.1 Horizontal and Vertical Alignment ....................................................... 138
9.7.2 Lane Widths and Shoulders ................................................................ 138
9.7.3 Ghost Islands ................................................................................... 138
9.7.4 Central Reserves .............................................................................. 139
9.7.5 Channelisation ................................................................................. 139
9.7.6 Medians .......................................................................................... 142
9.7.7 Splitter Islands ................................................................................. 143
9.7.8 Channelised Intersection Layout ......................................................... 144
9.7.9 Widening of the Major Road at the Intersection .................................... 145
9.7.10 Speed Change Lanes ......................................................................... 146
9.7.11 Decelerating Lane: Left Turn .............................................................. 147
9.7.12 Acceleration Lanes ............................................................................ 148
9.7.13 Right Turn Lanes .............................................................................. 149
9.7.14 Merging and Diverging ...................................................................... 150
9.7.15 Turning Roadway .............................................................................. 151
9.7.16 Private Access .................................................................................. 153
9.8 DESIGN OF SIGNALISED INTERSECTIONS ........................................................... 154
9.8.1 Control Strategy and Layout .............................................................. 155
9.8.2 Visibility .......................................................................................... 156
9.8.3 Lane Design ..................................................................................... 157
9.8.4 Swept Paths and Corner Curves ......................................................... 159
9.8.5 Signals ............................................................................................ 160
9.8.6 Pedestrian and Cyclist Facilities .......................................................... 162
9.9 CHECKLIST FOR INTERSECTION DESIGN............................................................. 163
10 ROUNDABOUTS ...................................................................................... 164
10.1 INTRODUCTION ......................................................................................... 164
10.1.1 Normal Roundabouts......................................................................... 164
10.1.2 Compact Roundabout ........................................................................ 165
10.1.3 Mini Roundabout .............................................................................. 166
10.1.4 Signalised Roundabout ...................................................................... 166
10.2 THE USE OF ROUNDABOUTS ........................................................................... 166
10.3 DESIGN REQUIREMENTS ............................................................................... 167
10.3.1 Safety and Speed Control .................................................................. 167
10.3.2 Key requirements ............................................................................. 168
10.3.3 Number and Alignment of Entry Roads ................................................ 168
10.3.4 Visibility and Sight Distances.............................................................. 169
10.4 DIMENSIONS OF ROUNDABOUTS ..................................................................... 170
10.4.1 Normal Roundabouts ......................................................................... 171
10.4.2 Small Roundabouts (Compact and Mini) .............................................. 173
10.5 ENTRIES ................................................................................................. 174
10.5.1 Number of Entry Lanes ...................................................................... 174
10.5.2 Approach Alignment .......................................................................... 175
(xix)
10.5.3 Splitter Islands ................................................................................. 175
10.5.4 Entry Design .................................................................................... 175
10.5.5 Entry Flaring .................................................................................... 178
10.5.6 Entry Path Radius ............................................................................. 178
10.6 DRIVING PATHS ........................................................................................ 179
10.7 EXIT WIDTH............................................................................................. 181
10.8 SIGNALISED ROUNDABOUTS .......................................................................... 182
10.9 CAPACITY OF ROUNDABOUTS ......................................................................... 183
10.10 PEDESTRIAN AND CYCLE CROSSINGS ............................................................. 183
10.11 TYPICAL STEP BY STEP DESIGN PROCEDURE..................................................... 184
11 GRADE SEPARATED INTERCHANGES ...................................................... 185
11.1 SCOPE ................................................................................................... 185
11.2 GENERAL ................................................................................................ 185
11.3 SPACING OF INTERCHANGES .......................................................................... 186
11.4 CHOICE OF SCHEME .................................................................................... 186
11.5 TYPES OF INTERCHANGES ............................................................................. 187
11.5.1 Three-way Interchanges (Layouts A and B).......................................... 188
11.5.2 Junctions of Major/Minor Roads (Layouts C and D) ............................... 189
11.5.3 Interchange between Two Major Roads ............................................... 190
11.5.4 Roundabout Layouts ......................................................................... 191
11.5.5 Junctions of more than Two Major Roads ............................................. 191
11.6 INTERCHANGES ON NON-FREEWAY ROADS.......................................................... 192
11.7 GEOMETRIC STANDARDS .............................................................................. 192
11.7.1 Design Speed ................................................................................... 192
11.7.2 Acceleration and Deceleration Lanes ................................................... 193
11.7.3 Horizontal Curves and Super-elevation ................................................ 193
11.7.4 Vertical Curves and Gradients ............................................................ 193
11.7.5 Widths and Gradients of Ramps .......................................................... 193
11.7.6 Clearances ....................................................................................... 194
11.7.7 Capacity .......................................................................................... 194
11.7.8 Basic Lanes and Lane Balance ............................................................ 194
11.8 DESIGN PRINCIPLES ................................................................................... 195
11.9 DESIGN PROCEDURES.................................................................................. 196
12 ADDITIONAL SAFETY AND MISCELLANEOUS DESIGN ITEMS .................. 199
12.1 THE ROAD ACCIDENT SITUATION .................................................................... 199
12.1.1 Pedestrians ...................................................................................... 199
12.1.2 Cyclists ........................................................................................... 200
12.2 IMPROVING SAFETY .................................................................................... 200
12.3 TRAFFIC CALMING ...................................................................................... 202
12.3.1 Chicanes ......................................................................................... 202
12.3.2 Rumble strips ................................................................................... 202
12.3.3 Speed Reduction Humps and Cushions ................................................ 203
12.3.4 Village Treatment ............................................................................. 204
12.4 BRAKE CHECK AREAS .................................................................................. 207
12.5 PARKING LANES ........................................................................................ 207
12.6 PASSING POINTS ....................................................................................... 207
12.7 SAFETY REST AREAS AND SCENIC OVERLOOKS .................................................... 208
12.8 SAFETY BARRIERS ...................................................................................... 208
12.8.1 General ........................................................................................... 208
12.8.2 Basic Principles ................................................................................ 209
12.8.3 Alternative Solutions to Safety Barriers ............................................... 210
12.8.4 Containment Requirements for Safety Barriers ..................................... 210
12.8.5 Design and Performance Criteria ........................................................ 210
12.8.6 Requirement for Using Safety Barriers ................................................. 211
12.8.7 Required Length of a Safety Barrier .................................................... 212
12.8.8 Steel Beam Strong Post Guardrail ....................................................... 213
(xx)
12.8.8.1 Installation of Steel Beam Strong Post Guardrail ................................ 214
12.8.9 Concrete Barriers ............................................................................. 215
12.8.10 Wire-Rope Barriers ........................................................................ 215
12.8.11 Jersey Barriers .............................................................................. 216
12.8.12 Grouted Rock Barrier ...................................................................... 216
12.8.13 Median Barriers ............................................................................. 216
12.8.14 Terminals ..................................................................................... 217
12.8.15 Transition from Guardrail to Bridge Parapets and Concrete Barriers ...... 219
12.8.16 Pedestrian Barriers and Parapets ..................................................... 219
12.8.17 Summary - Use and Placement of Barriers ........................................ 221
12.9 EMERGENCY ESCAPE RAMPS .......................................................................... 222
12.9.1 Types .............................................................................................. 222
12.9.2 Design Considerations ....................................................................... 223
12.9.3 Maintenance .................................................................................... 225
12.10 ROAD SAFETY RESEARCH AND AUDITS ........................................................... 225
12.11 PUBLIC UTILITIES.................................................................................... 225
12.11.1 Electricidade de Moçambique (EDM) ................................................. 226
12.11.2 Direcção Nacional de Aguas (DNA) ................................................... 227
12.11.3 Telecomunicações de Moçambique (TDM) ......................................... 227
12.12 RAILWAY GRADE CROSSINGS ...................................................................... 227
13 ROAD SIGNS, ROAD MARKINGS AND ROAD FURNITURE ........................ 229
13.1 ROAD SIGNS ............................................................................................ 229
13.2 ROAD MARKINGS ....................................................................................... 229
13.2.1 Pavement markings .......................................................................... 229
13.2.2 Object Markers ................................................................................. 229
13.3 ROAD STUDS............................................................................................ 230
13.4 MARKER POSTS ......................................................................................... 230
13.5 TRAFFIC LIGHT SIGNALS .............................................................................. 230
13.6 LIGHTING ................................................................................................ 231
14 DEPARTURES FROM STANDARDS ........................................................... 232
14.1 PROCEDURE ............................................................................................. 232
15 REFERENCES .......................................................................................... 235
APPENDIX A ESTIMATING DESIGN TRAFFIC (EXAMPLE) ................................ 238
APPENDIX B MEASURING SIGHT DISTANCE ON PLANS .................................. 240
APPENDIX C SIGHT DISTANCES AT INTERSECTIONS ..................................... 242
CASE A INTERSECTIONS WITH NO CONTROL ............................................... 244
CASE B INTERSECTIONS WITH STOP CONTROL ........................................... 245
CASE C INTERSECTIONS WITH YIELD CONTROL ON THE MINOR ROAD ........ 248
CASE D INTERSECTIONS WITH TRAFFIC SIGNAL CONTROL .......................... 250
CASE E INTERSECTIONS WITH ALL-WAY STOP CONTROL ............................ 250
CASE F RIGHT TURNS FROM A MAJOR ROAD .................................................. 251
APPENDIX D ROAD FRICTION ........................................................................ 253
APPENDIX E UTILITIES .................................................................................. 255
APPENDIX F COMPACT GRADE-SEPARATED INTERCHANGES......................... 257
APPENDIX G PASSING SIGHT DISTANCE ........................................................ 262
APPENDIX H ELEMENTS OF A CIRCULAR CURVE ............................................. 265
(xxi)
List of Tables
Table 1-1: Design Class Options .............................................................................................................. 6
Table 1-2: Steps in the Design Procedure .............................................................................................. 7
Table 2-1: Traffic Categories ................................................................................................................ 10
Table 2-2: Traffic Surveys ..................................................................................................................... 10
Table 2-3: Car Equivalency Factor ........................................................................................................ 11
Table 2-4: Methods of Estimating Traffic Growth ............................................................................... 13
Table 2-5: Design AADT (x103) for different traffic growth rates......................................................... 14
Table 3-1: Terrain Classification ........................................................................................................... 16
Table 3-2: Passenger Car Units ............................................................................................................ 17
Table 3-3: Level of Service for Base Conditions and Uninterrupted Flow ........................................... 18
Table 3-4: Dependence of Capacity on Directional Flow ..................................................................... 19
Table 3-5: Traffic Flow for Two-lane Rural Roads ................................................................................ 20
Table 3-6: Widths (m) for Paved Road Elements ................................................................................. 21
Table 3-7: Width and Crossfall for Unpaved Roads ............................................................................. 21
Table 3-8: Road Width Adjustments for Car Equivalence Factors (CEF) greater than 300 AADT ........ 23
Table 3-9: Recoverable and Non-recoverable Slopes .......................................................................... 26
Table 3-10: Slope Ratio Table – Vertical to Horizontal ........................................................................ 27
Table 3-11: Recommended Clear Zones (m) ........................................................................................ 29
Table 3-12: Pedestrian Sight Distances (m) ......................................................................................... 33
Table 3-13: Recommendations for Paved Footpaths in Rural Areas ................................................... 34
Table 4-1: Design Vehicle Characteristics ............................................................................................. 37
Table 4-2: Parameters Values Used for Calculating Sight Distances.................................................... 39
Table 4-3: Friction Factors.................................................................................................................... 40
Table 4-4: Minimum Stopping Sight Distances for Paved Roads ......................................................... 41
Table 4-5: Minimum Stopping Sight Distances for Unpaved Roads .................................................... 42
Table 4-6: Decision Sight Distances for Various Situations (m) ........................................................... 44
Table 4-7: Passing Sight Distances ....................................................................................................... 45
Table 4-8: Minimum Provision of Passing Sight Distance .................................................................... 45
Table 5-1: Minimum Radii for Horizontal Curves for Paved Roads (m) ............................................... 48
Table 5-2: Minimum Radii for Horizontal Curves for Unpaved Roads (m) .......................................... 48
Table 5-3: Variables required for evaluation of consistency ............................................................... 50
Table 5-4: Design Criteria ..................................................................................................................... 51
Table 5-5: Lengths of Tangents and Circular Curves ............................................................................ 54
Table 5-6: Widening on Curves and High Fills ...................................................................................... 59
Table 5-7: Transition Curve Requirements (m) .................................................................................... 63
Table 5-8: Minimum length of super-elevation run-off for two-lane roads ........................................ 65
Table 5-9: Super-elevation Rates for emax = 4.0% .............................................................................. 71
Table 5-10: Super-elevation Rates for emax = 6.0% ............................................................................ 72
Table 5-11: Super-elevation Rates for emax = 8.0%............................................................................... 73
Table 5-12: Super-elevation Rates for emax = 10.0% ............................................................................ 74
Table 6-1: Minimum Values of K for Crest Vertical Curves (Paved Roads) .......................................... 77
Table 6-2: Minimum Values for Crest Vertical Curves (Unpaved Roads) ............................................ 78
Table 6-3: Minimum Lengths of Vertical Curves .................................................................................. 78
Table 6-4: Minimum Values of K for Sag Curves .................................................................................. 79
Table 6-5: Lengths of grade for a 15 km/h speed reduction ............................................................... 80
Table 6-6: Suggested Maximum Gradients for Paved Sections ........................................................... 81
Table 6-7: Traffic Volume and Gradient Criteria Justifying a Climbing Lane ....................................... 82
Table 7-1 Applicable Design standards ................................................................................................. 85
(xxii)
Table 7-2: Design Parameters for H1-T1-R .......................................................................................... 86
Table 7-3: Design Parameters for (H2-T1-R) ........................................................................................ 87
Table 7-4: Design Parameters for (H2-T2-R) ........................................................................................ 88
Table 7-5: Design Parameters for (H2-T3-R) ........................................................................................ 89
Table 7-6: Design Parameters for (H3-T3-R) ........................................................................................ 90
Table 7-7: Design Parameters for (H3-T4-R) ........................................................................................ 91
Table 7-8: Design Standards H4-T4-R................................................................................................... 92
Table 7-9: Design Parameters for (H1-T1–M) ...................................................................................... 93
Table 7-10: Design Parameters for (H2-T1-M) ..................................................................................... 94
Table 7-11: Design Parameters for (H2-T2-M) ..................................................................................... 95
Table 7-12: Design Parameters for (H2-T3-M) ..................................................................................... 96
Table 7-13: Design Parameters for (H2-T2-U) ...................................................................................... 97
Table 7-14: Design Parameters for (H2-T3-U) ...................................................................................... 98
Table 7-15: Design Parameters for (H3-T3-U) ...................................................................................... 99
Table 7-16: Design Standards for H3-T4-U......................................................................................... 100
Table 7-17: Design Standards H4-T4-U .............................................................................................. 101
Table 7-18: Design Standards for Unpaved H3-T3 and H3-T4 Rural .................................................. 102
Table 7-19: Design Standards for Unpaved H3-T3 and H3-T4 Urban ................................................ 103
Table 7-20: Design Standards for Unpaved H4-T4 Rural and Urban.................................................. 104
Table 8-1: Vertical Clearance from Superstructure to Design Flood Level ........................................ 115
Table 9-1: Basic Types of Intersections .............................................................................................. 116
Table 9-2: Types of Traffic Control for At-grade Intersections .......................................................... 117
Table 9-3: Minimum Radii for Location of Intersections on Curves ................................................... 124
Table 9-4: Features Contributing to Accidents at Intersections and Remedial Measures. ............... 124
Table 9-5: Human Factors for Intersection Design ............................................................................ 125
Table 9-6: Typical Maximum Traffic Volumes .................................................................................... 129
Table 9-7: Vehicle Factors for Intersection Design ............................................................................ 131
Table 9-8: Minimum Sight Distances for ‘Yield’ or ‘Approach’ Conditions ........................................ 133
Table 9-9: Minimum Sight Distances for ‘Stop’ or ‘Departure’ Conditions ........................................ 133
Table 9-10: Intersection Selection Based on Traffic Flow (1000 vpd)................................................ 135
Table 9-11: Steps in the Selection and Design Procedure ................................................................. 135
Table 9-12: Minimum Spacings (m) between Uncontrolled Intersections ........................................ 136
Table 9-13: Length of Left Turn Lane ................................................................................................. 148
Table 9-14: Taper Rates for Exit Lanes (or Ramps) ............................................................................ 148
Table 9-15: Length of Acceleration Lanes including Taper (m) .......................................................... 149
Table 9-16: Lengths of Storage Sections for Right Turn Lanes........................................................... 149
Table 9-17: Turning Roadway Widths ................................................................................................ 152
Table 9-18: Criteria for Traffic Signalisation of Cross Walks .............................................................. 156
Table 10-1 Roundabouts Dimensions ................................................................................................. 171
Table 10-2: Entry Widths.................................................................................................................... 177
Table 11-1: Characteristics of some common Grade Separated Interchanges ................................. 188
Table 11-2: Minimum Widths for Ramps ........................................................................................... 193
Table 12-1: Design of Circular Road Humps (Height = 0.1 m)............................................................. 203
Table 12-2: Design of Flat-topped Road Humps ................................................................................ 204
Table 12-3: Containment Level .......................................................................................................... 210
Table 12-4: Containment Level – Requirement of Design of Safety Barriers ..................................... 211
Table 12-5: Length of Safety Barriers ................................................................................................. 213
Table 12-6: Rolling Resistance of Roadway Surfacing Materials ....................................................... 225
Table 13-1: Spacing of Guide Posts at Curves .................................................................................... 230
Table A-1 Traffic Information for Estimating Design Traffic for the Example..................................... 238
Table A-2 Converting non-4 Wheel Traffic and Pedestrians ............................................................... 238
Table A-3 Results of Calculation Total AADT ...................................................................................... 239
(xxiii)
Table C-1 Case A: Recommended Sight Distances for Intersections with no Traffic Control ............ 245
Table C-2 Travel Times Used to Determine the Leg of the Departure Triangle along the Major Road
for Right and Left Turns from Stop-controlled Approaches ............................................................... 246
Table C-3 Travel Times Used to Determine the Leg of the Departure Triangle along the Major Road
for Crossing Manoeuvres from Stop-controlled Approaches ............................................................. 247
Table C-4 Leg of Approach Sight Triangle Along the Minor Road to Accommodate Crossing
Manoeuvres from Yield-controlled Approaches................................................................................. 249
Table C-5 Travel Times Used to Determine the Sight Distance along the Major Road to Accommodate
Right Turns from the Major Road (Case F).......................................................................................... 251
Table E-1 Minimum Vertical Clearance of Wires above Road Surface (in centimetres) .................... 255
Table E-2 Trench Dimensions for Water and Sewerage Pipe Culverts ............................................... 256
Table G-1 Clearance Distance (d3) for Different Ambient Speeds ...................................................... 263
Table G-2 Passing Sight Distances ....................................................................................................... 264
(xxiv)
List of Figures
Figure 3-1: Typical Road Cross Section Showing All Elements ............................................................. 15
Figure 3-2: Cross Section for H1 T2 in Rolling or Flat ........................................................................... 22
Figure 3-3: Cross Section for H2 T3 in Mountainous and Escarpment Terrain .................................... 22
Figure 3-4: Details of the road edge .................................................................................................... 25
Figure 3-5: Side Drain Ditch Location in Expansive Soils ...................................................................... 27
Figure 3-6: Bus Lay-Bys and Parking Bays ............................................................................................ 32
Figure 4-1: Dimensions and Turning Radius Path for Single Unit Truck (DV2) .................................... 37
Figure 4-2: Dimensions and Turning Radius Path for Single Unit Bus (DV3)........................................ 38
Figure 4-3: Dimensions and Turning Radius for a Semi-Trailer Combination ...................................... 38
Figure 4-4: Sight Distance for Horizontal Curves ................................................................................. 46
Figure 5-1: Ratio of Radii of Consecutive Horizontal Curves ............................................................... 49
Figure 5-2: Passing Lane Arrangements ............................................................................................... 56
Figure 5-3: Example of a Passing Lane ................................................................................................. 57
Figure 5-4: Layout for Passing Lane ..................................................................................................... 58
Figure 5-5: Hairpin Curve ..................................................................................................................... 61
Figure 5-6: Hairpin Curve for the Passage of Single DV4 Vehicle ........................................................ 62
Figure 5-7 Elements of Super-elevation............................................................................................... 64
Figure 5-8: Attainment of Super-elevation using the Transition Curve ................................................ 65
Figure 5-9: Reverse Curves, Broken-Back Curves, and Compound Curves .......................................... 67
Figure 5-10: Super-elevation of Reverse Curves .................................................................................. 68
Figure 5-11: Super-elevation of Broken-back Curves .......................................................................... 69
Figure 5-12: Shoulder Super-elevation (for Surfaced Roads) .............................................................. 70
Figure 6-1: Crest Curve.......................................................................................................................... 75
Figure 6-2: Sag Curve ............................................................................................................................ 75
Figure 6-3: Layout of Climbing Lanes ................................................................................................... 84
Figure 8-1: Hidden Dip (Roller Coaster) Profile .................................................................................. 106
Figure 8-2: Short Humps on Long Horizontal Curve........................................................................... 107
Figure 8-3: Short Vertical Curves Preceding a Long Horizontal Curve ............................................... 108
Figure 8-4: Distorted Alignment at Bridge Crossing........................................................................... 109
Figure 8-5: Replacement of Broken-Back Curve by Single Radius Long Curve. ................................. 110
Figure 8-6: Out-of-phase Vertical and Horizontal Alignments ........................................................... 111
Figure 8-7: Variable Gradients (Rolling Grade-line) ........................................................................... 111
Figure 8-8: Break in Horizontal Alignment ......................................................................................... 112
Figure 8-9: Well-coordinated Crest and Horizontal Curves ............................................................... 114
Figure 8-10: Well-coordinated Sag and Horizontal Curves ................................................................ 114
Figure 9-1: Crossroads with Stop Lines .............................................................................................. 118
Figure 9-2: Partly Channelised T-Intersection with Ghost Islands ..................................................... 119
Figure 9-3: T-Intersections with Channelisation ................................................................................ 119
Figure 9-4: Staggered Intersection...................................................................................................... 119
Figure 9-5: Partly Channelised Staggered Intersection with Ghost Islands ....................................... 120
Figure 9-6: Skew or Y Intersection with Ghost and Channelising Islands. ......................................... 121
Figure 9-7: Traffic Signal Controlled Cross Roads .............................................................................. 121
Figure 9-8: Selection of Intersection Types........................................................................................ 127
Figure 9-9: Peak Hour Capacity ........................................................................................................... 129
Figure 9-10: Example of a Signal-Controlled Crossroads ................................................................... 130
Figure 9-11: Signal-Controlled Crossroads with a Staggered Pedestrian Crossing and Refuge. ........ 131
Figure 9-12: Intersection Selection Based on Traffic Flows ............................................................... 134
Figure 9-13: Desirable Spacings of Controlled Intersections ............................................................. 137
(xxv)
Figure 9-14: Typical Traffic Islands ..................................................................................................... 140
Figure 9-15: Typical Triangular Island ................................................................................................ 142
Figure 9-16: Median End Treatment .................................................................................................. 143
Figure 9-17: Layout of a Channelised Intersection ............................................................................ 144
Figure 9-18: Layout of a Partially Channelised Intersection .............................................................. 145
Figure 9-19: Conditions Requiring a Right Turn Lane ........................................................................ 147
Figure 9-20: Layout for Left Turn Lane ............................................................................................... 147
Figure 9-21: Layout for Right Turn Lane, Single Carriageway ............................................................ 150
Figure 9-22: Layout for Right Turn Lane, Dual Carriageway .............................................................. 150
Figure 9-23: Examples of Merge and Diverge Lanes .......................................................................... 151
Figure 9-24: Typical Cross-road Intersection showing all Elements .................................................. 153
Figure 9-25: Typical Access ................................................................................................................ 154
Figure 9-26: Protected Right Turn Sequence ...................................................................................... 155
Figure 9-27: Inter-visibility Zone without Pedestrian Crossing .......................................................... 157
Figure 9-28: Right Turn Lane Design .................................................................................................. 157
Figure 9-29: Ghost Island Layout ........................................................................................................ 158
Figure 9-30: Left Turn Filter Lane with Taper to Facilitate Large Vehicles......................................... 158
Figure 9-31: Lane Drop Design Principles .......................................................................................... 159
Figure 9-32: Combinations of Tapers and Corner Radii ..................................................................... 159
Figure 9-33: Examples of Swept Path Checks .................................................................................... 160
Figure 9-34: Signal Location Advice .................................................................................................... 161
Figure 9-35: Alternative Signal Locations for Right Turn Lanes ......................................................... 161
Figure 9-36: Example of a Signal-Controlled Intersection with a Staggered Pedestrian Crossing .... 162
Figure 10-1: Basic Roundabout Showing Key Features....................................................................... 165
Figure 10-2: A Compact Roundabout ................................................................................................. 166
Figure 10-3: Vehicle Path through Roundabout ................................................................................ 168
Figure 10-4: Required visibility towards approaching vehicles from the right and required visibility
forwards to the left ............................................................................................................................. 169
Figure 10-5: Required Visibility for Drivers within a Roundabout. .................................................... 169
Figure 10-6: Nomenclature for Dimensions of Roundabouts Showing Design Vehicle. .................... 170
Figure 10-7: Minimum Width of Circulating Carriageway – One Lane .............................................. 172
Figure 10-8: Radius of Central Island and Circulating Carriageway for Normal Roundabouts. ......... 173
Figure 10-9: Roundabout Radii for Small Roundabouts .................................................................... 174
Figure 10-10: Number of Entry Lanes ................................................................................................ 174
Figure 10-11: Design of Approach Deflection. ................................................................................... 175
Figure 10-12: Approach Half Width and Entry Width ......................................................................... 176
Figure 10-13: Example Showing an Arc Projected Forwards from the Splitter Island and Tangential to
the Central Island. ............................................................................................................................... 177
Figure 10-14: Average Effective Flare Length ..................................................................................... 178
Figure 10-15: Determination of Entry Path Radius for Ahead Movement at a 4-arm Roundabout... 179
Figure 10-16: Driving Paths for Passenger Cars ................................................................................. 180
Figure 10-17: Alignment between entry and exit .............................................................................. 180
Figure 10-18: Staggering of East-West Arms to Increase Deflection .................................................. 181
Figure 10-19: Typical Single Carriageway Exit at a Normal Roundabout with a Long Splitter Island . 182
Figure 10-20: Example of a Signalised Roundabout........................................................................... 183
Figure 10-21: Location of pedestrian crossings ................................................................................. 183
Figure 11-1: Typical Layouts for Grade-Separated Interchanges....................................................... 189
Figure 11-2: Dumb-bell Layout (One Bridge, Two Roundabouts) ....................................................... 190
Figure 11-3: Use of a large roundabout ............................................................................................. 191
Figure 11-4: Jug Handle Interchange ................................................................................................. 192
Figure 11-5: Principles of Lane Balance ............................................................................................. 195
Figure 12-1: Engineering Design Features Affecting Road Safety ...................................................... 201
(xxvi)
Figure 12-2 Circular humps ................................................................................................................. 203
Figure 12-3 Flat-topped Humps .......................................................................................................... 204
Figure 12-4: Village Gateway Designs ................................................................................................. 206
Figure 12-5: Deformation of safety barriers ...................................................................................... 211
Figure 12-6: Guide for determining need for a guard rail.................................................................. 212
Figure 12-7: Length of Safety Barriers ............................................................................................... 213
Figure 12-8 Typical Post Details .......................................................................................................... 214
Figure 12-9: Various Barriers ............................................................................................................. 215
Figure 12-10: Different Types of Median Barrier ............................................................................... 217
Figure 12-11: Guardrail End Treatment ............................................................................................. 218
Figure 12-12: Typical Transition (W-beam Guard-rail to Rigid Object).............................................. 219
Figure 12-13: Details of a Vehicle/Pedestrian Parapet ...................................................................... 220
Figure 12-14: Basic Types of Emergency Escape Ramps .................................................................... 223
Figure 12-15: Utilities Placement Detail ............................................................................................ 227
Figure 12-16: Railway Crossing Details with Rumble Strips ............................................................... 228
Figure 12-17: Railway Crossings Details on Vertical Curve ................................................................ 228
Figure B-1 Scaling and Recording Sight Distances on Plans ............................................................... 241
Figure C-1 Departure Sight Triangles .................................................................................................. 243
Figure D-1 Longitudinal Friction for Various Tyre and Pavement Conditions .................................... 253
Figure D-2 Side Friction Factors .......................................................................................................... 254
Figure F-1 Grade Separation for a 4-Arm Junction Showing Merge and Diverge Tapers ................... 257
Figure F-2 Grade Separation for 4-Arm Junction Without Merge and Diverge Tapers ...................... 257
Figure F-3 Grade Separation for 4-Arm Junction with Compact Connector Road.............................. 258
Figure F-4 Grade separation for 3-arm junction with compact connector roads showing merge and
diverge tapers ..................................................................................................................................... 258
Figure F-5 A selection of schematic layouts indicating 4-arm compact grade separations on dual all-
purpose carriageways. ........................................................................................................................ 259
Figure F-6 A selection of schematic layouts indicating 4-arm compact grade separations on single all-
purpose carriageways. ........................................................................................................................ 260
Figure F-7 A selection of schematic layouts indicating 3-arm compact grade separations on dual all-
purpose carriageways. ........................................................................................................................ 260
Figure F-8 A selection of schematic layouts indicating 3-arm compact grade separations on single all-
purpose carriageways. ........................................................................................................................ 260
Figure F-9 Schematic example of compact grade separation and restricted junctions. .................... 261
Figure G-1 Passing Sight Distance ...................................................................................................... 263
Figure H-1 Curve Elements.................................................................................................................. 265
(xxvii)
1 Introduction
Geometric design is the process whereby the layout of the road through the terrain is
designed to meet the needs of all the road users. The geometric standards are
intended to meet two important objectives namely to provide satisfactory levels of
service, safety and comfort for drivers by provision of adequate sight distances and
road space for manoeuvres and to optimise or minimise earthworks volumes to reduce
construction costs.
1.1 Scope
The procedures for the geometric design of roads presented in this manual are
applicable to roads carrying more than 300 motorised vehicles per day, or the design
traffic exceeding 1 million cumulative equivalent standard axles (MESA) over the
design life of the road. If the traffic is less than 300 vehicles per day or the design
traffic is less than 1 MESA over the design life, then the Low Volume Manual of ANE
must be used.
This manual covers three basic design situations. Upgrading from a lower class of road
to a higher class; designing a road to replace an existing track; and designing a
completely new road where nothing existed before. This manual does not deal in detail
with the design of major grade-separated interchanges between restricted-access
freeways (motorways) although the topic is introduced sufficiently for some of the
simpler designs to be carried out.
(1)
behaviour as expressed by the 85th percentile speed of cars under free-flow
conditions. The difference between the 85th percentile and the design speed on
an element such as a horizontal curve should be less than 20km/h.
• The information provided to the driver should be presented in sequence to
avoid presenting several alternatives at the same time.
• Clear sight lines and sight distances must be sufficient to allow time for good
decision making.
• Where possible, margins are allowed for recovery in case of error.
It is important that human factors are considered in many aspects of design, as
indicated in the details of design in this manual, but the subject is of such importance
that the fundamental principles are summarised here.
1.2.1.3 The logic rule: the road has to follow a driver’s perception logic.
Drivers follow the road with an expectation logic based on their experience and recent
perceptions. Unexpected abnormalities disturb a mostly automatic chain of actions and
may cause a driver to ‘stumble’ (to use an apt analogy). Several critical seconds can
pass before the disturbance can be processed. Designers should introduce inevitable
changes as early and clearly as possible and avoid sudden changes that would confuse
the driver.
Much of the information is best understood with visual examples. The publication
‘Human Factors Guidelines for a Safer Man-road Interface’ by The World Road
Association (PIARC) (available on their website http://www.piarc.org) from which
(2)
previous transcriptions were made provides many details and examples of good
practice.
1.2.2.1 Pedestrians
In Africa about 38% of all road fatalities are pedestrians therefore facilities that
improve pedestrian safety should be included wherever possible. In general,
pedestrian safety is enhanced by the provision of median refuge islands of sufficient
width at road junctions, and separate pedestrian footpaths (sidewalks) where
pedestrian traffic warrants it, for example, on approaches to villages. Indeed, the
design of rural roads through villages should encompasses a range of safety features
including traffic calming and well-designed village centres permitting trading in relative
safety, as described in Chapter 12. In metropolitan areas pedestrians’ facilities need to
be incorporated as a traffic stream in all facilities.
(3)
1.2.4 Design Speed
The design speed is an index which links road function, traffic flow and terrain to the
design parameters of sight distance and road curvature to ensure that a driver is
presented with a reasonably consistent speed environment. The current definition is
that the design speed is the speed selected as the basis for establishing appropriate
geometric elements for a section of road. These elements include horizontal and
vertical alignment, super-elevation and sight distance. Other elements such as lane
width, shoulder width and clearance from obstacles are indirectly related to design
speed. The chosen design speed should be consistent with the road function as
perceived by the driver and also one that takes into account the type of road, the
anticipated operating speed, and the terrain that the road traverses, as discussed in
Chapter 4. Recommended design speeds for each functional class of road are shown in
Table 7-1.
(4)
1.5 Primary Design Criteria
1.5.1.2 Secondary
The secondary road (H2 class) links locally important traffic generators with their rural
hinterland and provides service to the smaller communities. Travel speeds on the
secondary road network are generally not as high as those on primary roads; an
intermediate design speed and level of service is required.
1.5.1.3 Tertiary
Tertiary roads (H3 class) are intended to provide access to properties, i.e. they link
them to the higher order routes in the hierarchy. It follows that traffic volumes and
speeds on these roads tend to be low, so that tertiary roads are rarely surfaced.
Properties are also linked directly to secondary and primary routes, but the control of
access to a route is more stringently applied as the importance of the route in the
hierarchy increases.
(5)
1.5.3 Road environment
Roads can be located in rural areas with low population densities and also in
metropolitan areas, although not in residential urban areas. Each traffic class can
perform different functions and therefore the specifications within each road class (i.e.
traffic level) for different functionalities are not identical. For example, roads of the
same traffic class in Metropolitan, Urban or in Rural areas are not designed to the
same specifications because the functions are different. The traffic speed and the flow
of traffic depend on the road environment, therefore the road environment, whether it
is Metropolitan, Urban or Rural should be selected.
(6)
1.7 Design Steps
The design of road geometry can be carried out manually or using computer software
using the design standards and specifications provided in this manual.
The steps involved in the design are listed in Table 1-2 and explained further in the
relevant chapters. However, the process itself is essentially one of trial and error
because all the elements must fit together in ‘harmony’.
It is also vital that the public are involved at all points in the project where there are
opportunities for changes to be made in the design.
(7)
comprise the majority of junctions in Mozambique,
and the selection of junction type, sight distances;
and junction elements including turning lanes and
traffic islands.
Roundabouts Roundabouts have many advantages over other
types of road intersections over a wide range of
traffic flows. The main types of roundabout are
mini, compact, normal, signalised and grade 10
separated. The key elements are: entries and
exits; the circulatory roadway; the central island
and sight distances.
Grade-separated Designs for very high traffic flows require
Interchanges intersections at two or more levels of elevation so
that traffic on the main arteries can be routed
without the need to slow down significantly. Thus
11
high speed merging and turning facilities are
required. These grade-separated junctions are
expensive and used primarily on freeways and
major international routes.
Safety and Miscellaneous This includes traffic calming, the design of safety
Aspects rest areas and scenic overlooks, bus lay-bys and
parking bays, parking lanes, public utilities,
railway at-grade crossings, brake check areas, 12
road restraint systems, emergency escape ramps,
design of village centres, and safety auditing,
amongst other topics.
Road Furniture and Markings Traffic signs and signals, road marking, lighting
13
and so on.
Departures from Standards Procedures for dealing with situations where the
designer has to deviate from the standards
because it is impossible to meet them, mainly due
to severe terrain conditions. Typical examples of 14
departures from the standards include the use of a
gradient greater than the desirable value or use of
a lower design speed.
After carrying out the design, drawings or sketches should be prepared as follows:
a. Typical section of roadway showing geometric details.
b. Profile plot of existing centreline ground line. This can usually be plotted at a
scale of 1:1,000 or 1:2,000.
c. Cross section drawing for each section;
d. Junction details;
e. Details of ancillary structures
(8)
2 Design Data Collection and Analysis
The road alignment and its cross-sectional elements primarily depend on the
topography of the route and the estimated traffic that will use the road. These are
determined through topographic and traffic surveys.
(9)
2.2.2 Conducting Traffic Surveys
The initial traffic volume in terms of AADT for each vehicle class shown in Table 2-1
must be determined. AADT is defined as the total annual traffic summed for both
directions and divided by 365. It is usually obtained by recording actual traffic
volumes over a much shorter period, from which the AADT is then estimated. The two
commonly used methods of traffic survey are:
1. Automatic. Traffic counters with inductive loops and possibly weighing-in-
motion (WIM) sensors are installed in the road.
2. Manual.
(10)
If possible, consider 7 days counts twice a year, once during the peak season and
another during off-peak season.
Care should be exercised in selecting appropriate locations for conducting the traffic
counts to ensure a true reflection of the traffic using the road. If any significant
junctions occur along the road length, counts should also be conducted before and
after the junctions.
It is also necessary to count non-motorised and intermediate means of transport
including pedestrians, bicycles, animal transport, motorcycles, tractors and trailers.
The topography data should be checked for completeness against other maps
available to the designer. Topography data obtained by field ground surveys will
generally be collected electronically for downloading to appropriate computer-aided
design software.
(11)
2.4.2 Determine AADT
The AADT is the sum of the traffic in both directions. In the first year of analysis it
consists of the current traffic plus an estimate of the diverted traffic. If the total traffic
is denoted by AADT0 and the general growth rate is i % per annum, then the traffic in
any subsequent year, x, is given by the following equation:
x
AADTx = AADT0 (1+i/100) Equation 2.1
Traffic growth means that annual traffic is higher in late life than in early life. For
geometric design purposes the AADT should be estimated near the end of the design
life period to minimise the risk of reaching capacity. For most roads a design life of 20
years is recommended but a longer period should be selected for the most important
roads in the country for which traffic estimates indicate that there is a high probability
that 20 years will be insufficient. However, the function of the road needs to be taken
into account if sufficiently large variations in hourly flow are expected.
The design hourly volume, as a percentage of the ADT, is referred as the K-Factor and
typically varies between 12 and 18 %. A value of 15 % is normally assumed unless
actual traffic counts suggest another value.
On an annual basis, the directional split on most rural roads is approximately 50:50.
However, during any specific hour the volume in one direction may be much heavier
than in the other. The directional split is often in the ratio of 60:40, and the heavier
flow is the design criterion.
1. Normal traffic. Traffic which would pass along the existing road or track even if
no new geometry were provided. This increases naturally by virtue of normal
social and economic growth.
2. Diverted traffic. Traffic that changes from another route (or mode of transport)
to the project road because of the improved pavement, but still travels between
the same origin and destination. Diverted traffic should be considered when a
totally new road is to be provided or when an existing road is to be improved. To
estimate the volume of diverted traffic, the designer should conduct an origin
destination survey of all major junctions that adjoin to the project road. Road
users should specifically be asked for the origin and destination of their trips, the
purpose of the trip, whether they will change mode of travel upon completion of
the project road, whether truck drivers will change the truck class, and most
importantly, whether they will divert.
3. Generated traffic. Additional traffic which occurs in response to the provision or
improvement of the road. This is traffic generated by any extra economic growth
(12)
resulting from the road. It is likely to be greater than the increase expected from
normal regional economic growth. The initial volume of generated traffic must be
obtained by conducting interviews with the existing road users. The interviews
must focus on understanding whether upgrading the road would lead to an
increased number of trips immediately. Other planning factors must also be
considered. For example, if a farm is likely to increase its crop outputs as a result
of improved road conditions; the extra trips generated as result should be
considered in determining the generated traffic. For major projects such as those
involving addition of extra lanes, it is necessary to engage a traffic specialist for
estimating the generated traffic.
The survey for all three types of traffic can be conducted simultaneously.
There are several methods for estimating the traffic growth and each has its
advantages and disadvantages as summarised in Table 2-4. The methods will not all
give robust and reliable figures or, therefore, similar answers and so some degree of
judgement about the quality of the data will be required to obtain the best estimate.
Equation 2-1 can be used to calculate the traffic after 20 years. Alternatively, Table
2-5 can be used to estimate the design traffic based on different initial traffic levels
and different growth rates for a 20-year design. This AADT in the design year is used
to determine design traffic class.
(13)
If traffic in different traffic classes is expected to grow at different rates the calculation
must be done for each class and the total summed afterwards.
Where the expected traffic is within 10 percent of the maximum for the road class in
question, the higher classification should be adopted. For example, if the expected
traffic is over 9,000 (i.e. within 10% of 10,000) the design should be for the next
higher traffic class (i.e. >10,000). An example to calculate design traffic is provided in
Appendix A.
Table 2-5: Design AADT (x103) for different traffic growth rates
Current
Growth Rate (%)
AADT
X103 2 3 4 5 6 7 8 9 10 12 15
0.3 0.4 0.5 0.7 0.8 1.0 1.2 1.4 1.7 2.0 2.9 4.9
0.5 0.7 0.9 1.1 1.3 1.6 1.9 2.3 2.8 3.4 4.8 8.2
1 1.5 1.8 2.2 2.7 3.2 3.9 4.7 5.6 6.7 10 16
1.5 2.2 2.7 3.3 4.0 4.8 5.8 7.0 8.4 10 14 25
2 3.0 3.6 4.4 5.3 6.4 7.7 9.3 11 13 19 33
2.5 3.7 4.5 5.5 6.6 8.0 10 12 14 17 24 41
3 4.5 5.4 6.6 8.0 9.6 12 14 17 20 29 49
3.5 5.2 6.3 7.7 9.3 11 14 16 20 24 34
4 5.9 7.2 8.8 11 13 15 19 22 27 39
4.5 6.7 8.1 10 12 14 17 21 25 30 43
5 7.4 9.0 11 13 16 19 23 28 34 48
6 8.9 11 13 16 19 23 28 34 40
7 10 13 15 19 22 27 33 39 47
8 12 14 18 21 26 31 37 45
9 13 16 20 24 29 35 42 50
10 15 18 22 27 32 39 47
(14)
3 Design of Cross Section Elements
A cross-section normally consists of the carriageway, shoulders and/or kerbs, drainage
features, and earthwork profiles as in Figure 3-1.
1. The carriageway is the part of the road used by moving traffic, including traffic
lanes, auxiliary lanes such as acceleration and deceleration lanes, climbing
lanes, passing lanes, and bus bays and lay-bys.
2. A shoulder is the portion of the roadway contiguous to the carriageway. It
provides lateral support for the pavement layers and accommodation for
stopped vehicles; traditional and intermediate non-motorised traffic, animals,
and pedestrians; emergency use; and for the recovery of errant vehicles.
3. The Road Reserve is the strip of land legally awarded to the Roads Authority, in
which the road is, or will be, situated and where no other work or construction
may take place without permission from the Roads Authority. The width of the
road reserve is measured at right angles to the centreline and is 50 m wide for
all road classes.
4. Side slopes provide the stability of the roadway and can be designed to give
reasonable opportunity for recovery of an out-of-control vehicle (Section 3.7).
Earthwork profiles include side slopes and back slopes.
5. For urban cross-sections, the cross-section elements may also include facilities
for pedestrians, cyclists, or other specialist user groups. These include kerbs,
footpaths, and islands. It may also provide for parking lanes.
6. For dual carriageways, the cross-section will also include medians.
The length and slope of the cross-sectional elements vary depending on the design
class selected from the Table 1-1.
3.1 Terrain
Terrain has the greatest effect on road costs and, therefore, it is not economical to
apply the same standards in all terrains. Thus, terrain has a strong influence on the
level of service that can be provided. Terrain class needs to be established before a
road is designed and hence it is defined independently of the alignment that is finally
selected for the road. It is determined by counting the number of 5-m contours
crossed by a straight line connecting the two ends of the road section in question
according to the following definitions in Table 3-1.
(15)
Table 3-1: Terrain Classification
Terrain Definition
0-10 five-m contours per km. The transverse ground slopes
Flat
perpendicular to the ground contours are generally below 3%.
11-25 five-m contours per km. The transverse ground slopes
Rolling perpendicular to the ground contours are generally between
3% and 25%.
26-50 five-m contours per km. The transverse ground slopes
Mountainous perpendicular to the ground contours are generally above
25%.
Escarpments are geological features that require special
geometric standards because of the engineering problems
involved. They are characterised by more than 50 five-m
Escarpment
contours per km and the transverse ground slopes
perpendicular to the ground contours are generally greater
than 50%.
In mountain areas the geometric standard takes account of the constraints imposed
by the difficulty and stability of the terrain. This design standard may need to be
reduced locally in order to cope with exceptionally difficult terrain conditions. Every
effort should be made to design the road so that the maximum gradient does not
exceed the standards (Chapter 7). It is difficult to provide adequate compaction on
gradients of greater than 10% but, where higher gradients cannot be avoided, they
should be restricted in length. Gradients greater than 10% should not be longer than
250 m. Horizontal curve radii of as little as 13 m may also be unavoidable, even
though a minimum of 15 m is specified.
(16)
Table 3-2: Passenger Car Units
Terrain
Vehicle Type
Flat Rolling Mountainous
Passenger cars 1.0 1.0 1.5
Light goods vehicle 1.0 1.5 3.0
Medium goods vehicle GVW<8,500 kg 2.5 5.0 10
Heavy goods vehicle GVW>8,500 kg 3.5 8.0 20
Small bus <30 passengers 1.5 3.0 4.5
Large bus >30 passengers 2.5 5.0 7.5
Motor cycle 0.5 1.0 1.5
Pedal cycle 0.5 0.5 NA
(17)
Table 3-3: Level of Service for Base Conditions and Uninterrupted Flow
Level of Two-lane rural road without Multi-lane rural road without
service access control access control
A Average travel speed of ≥ 90km/h. Average travel speed ≥ 95 km/h.
Most passing manoeuvres can be Under ideal conditions, flow rate
made with little or no delay. is limited to 720 PCU/lane/h or
Service flow rate is a total of 490 33% of capacity.
PCU/h for both directions and about
15% of capacity can be achieved.
Maximum AADT is 2,800(1).
B Average travel speed of ≥ 80km/h. Reasonably free flow. Volume at
Flow rates may reach 27% of which actions of preceding vehicle
capacity with continuous passing will have some influence on
sight distance. Flow rate of 780 following vehicles. Flow rates will
PCU/h total for both directions. not exceed 55% of capacity or
Maximum AADT is about 5,200(1). 1,200 PCU/lane/h at 96 km/h
average travel speed under ideal
condition.
C Flow still stable. Average travel Stable flow to a flow rate not
speed of ≥ 70km/h. exceeding 75% of capacity or
Flow rates under ideal condition 1,650 PCU/lane/h, under ideal
equal to 43% of capacity with conditions maintaining at least a
continuous passing sight distance or 95 km/h average travel speed.
1,190 PCU/h total for both directions.
Maximum AADT is about 7,900(1).
D Approaching unstable flow. Average Approaching unstable flow at flow
travel speed of ≥ 60km/h. rates up to 89% of capacity or
Flow rates, two directions, at 64% of 1,940 PCU/lane/h at an average
capacity with continuous passing travel speed of about 92 km/h
opportunity, or a total of 1,830 under ideal condition.
PCU/h for both directions. Maximum
AADT is about 12,000(1).
E Average travel speeds in Flow at 100% of capacity or
(capacity) neighbourhood of 60 km/h. 2,200 PCU/lane/h under ideal
Flow rates under ideal conditions, conditions. Average travel speeds
total two way, equal to 3200 PCU/h. about 88 km/h.
Maximum AADT is about 18,000(1)
Level E may never be attained.
Operation may go directly from Level
D directly to Level F.
F Forced congested flow with Forced flow congested condition
unpredictable characteristics. with widely varying volume
Operating speeds less than 72 km/h. characteristics. Average travel
speed of less than 50 km/h.
The speed is then adjusted according to the conditions that differ from the base
conditions for the road being evaluated. These are characterised as roadway, traffic or
control conditions.
(18)
Roadway conditions include the number of lanes, lane width, no passing lengths, and
design speed; the latter controlling the vertical and horizontal alignment. Traffic
conditions include vehicle types and directional distribution.
For interrupted flow, traffic control conditions are important and analysis quite
complex because of the range of conditions that can affect capacity. However, for
uninterrupted flow conditions the analysis of service level is relatively straightforward.
For a two-lane, two-way road in flat terrain, capacity is reached when the traffic level
(sum of both directions) approaches 2,800 PCU per hour (Harwood et al.; 1999). This
peak traffic (per hour) is usually between 12 and 18% of the AADT and a value of
15% is a reasonable average. The capacity also depends on directional split as shown
in Table 3-4.
Capacity is reduced if the physical features of the road are deficient in some way:
• Lane widths of 3.65 m are the minimum necessary for heavy volumes of mixed
traffic, i.e. before capacity of the lane is reduced.
• Narrow shoulders cause vehicles to travel closer to the centre of the
carriageway, and vehicles making emergency stops must park on the
carriageway. This causes a substantial reduction in the effective width of the
road, thereby reducing capacity.
• Side obstructions such as poles, bridge abutments, retaining walls or parked
cars that are located within about 1.5 m of the edge of the carriageway
contribute towards a reduction in the effective width of the outside traffic lane.
• Imperfect horizontal or vertical curvature.
• Long and/or steep hills and sharp bends result in restricted sight distances.
Drivers have reduced opportunities to pass and so the capacity of the road is
reduced.
• The capacities of some rural roads and the great majority of urban roads are
controlled by the layouts of intersections.
Table 3-5 provides guidance for a realistic example. Based on different types of terrain
and with the following typical conditions or assumptions, the Table illustrates that for
more severe terrain and for the lower traffic classes, the expected speeds, traffic flows
and resulting LoS are controlled by geometric design factors and not by capacity or
traffic flow:
a. Traffic mix is 14% trucks;
b. Directional split is 60/40;
c. No-passing zones,
• Level terrain 20%
• Rolling terrain 40%
(19)
• Mountainous terrain 60%
• Ratio of Highest Hourly Volume to AADT = 0.15
Care is required if a particular level of service must be achieved because the traffic
levels are such that the capacity of the road for a particular service level is likely to be
exceeded before the end of the design period.
Source: Harwood et al. Capacity and Quality of Service of Two-lane Highways. NCHRP
Project 3-55(3), Geometric Design Guidelines (2003), South African National Roads Agency
Limited
On the basis that the maximum PCU/h is between 0.1 and 0.15 times the AADT, traffic
class TC2 is potentially commensurate with LoS B at the lower traffic level and LoS D
at the higher end of the traffic range for TC2.
Constructing extra capacity in the future by adding an additional lane is often difficult
and also very costly. A whole life cost analysis might prove useful to justify the costs
but, in general, if capacity is expected to be exceeded towards the end of the design
period it is usually better to design for it in the beginning.
Where computations indicate that a two-lane road is not adequate for existing or
projected demands, various multi-lane options must be considered and analysed.
(20)
Table 3-6: Widths (m) for Paved Road Elements
Design
Road Class Flat Rolling Mountain Escarp’t
element
Carriageway 7.3 7.3 7.0 6.5
H1-T1- R
Shoulders 3.0 3.0 1.5 (1.0) 2.0
H1-T1-M/U Carriageway 7.3 7.3 7.0 6.5
Carriageway 7.3 7.3 7.0 6.5
H2-T2-R
Shoulders 3.0 1.5-2.0 1.0-1.5 (0.5)-1.5
H2-T2-M Carriageway 7.3 7.3 7.0 6.5
H2-T2-U Carriageway 7.0 7.0 7.0 6.5
Carriageway 7.0 7.0 7.0 6.5
H2-T3-R
Shoulders 2.0-3.0 1.5 1.0 (0.5)-1.0
Carriageway 7.0 7.0 7.0 6.3
H2-T3-M
Shoulders 3.0 1.5 1.0 (0.5)-1.0
Carriageway 6.8 6.8 6.8 6.3
H2-T3-U
Shoulder 3.0 1.5 1.0 (0.5)-1.0
Carriageway 6.8 6.8 6.8 6.3
H3-T3-R
Shoulders 2.5 1.5 1.0 (0.5)-1.0
Carriageway 6.5 6.5 6.5 6.3
H3-T3-U
Shoulders 2.5 1.5 1.0 (0.5)-1.0
Carriageway 6.5 6.5 6.5 6.3
H3-T4 R
Shoulders 2.0 1.5 1.0 (0.5)-1.0
Carriageway 6.0 6.0 6.0 6.0
H3-T4 U
Shoulders(4) 2.0 1.5 1.0 (0.5)-1.0
Carriageway 6.0 6.0 6.0 6.0
H4-T4 U
Shoulders(4) 2.0 1.5 1.0 (0.5)-1.0
H3-T4 and Carriageway
H4-T4 + 7.0 – 7.5 7.0 – 7.5 7.0 – 7.5 7.0 – 7.5
Unpaved Shoulders
Notes 1 Dependant on local environment
2 Figures in brackets are minima
3 Road reserve is 50 m.
4 In urban/metropolitan areas the edge of the carriageway/running surface will
not usually be a shoulder but will be kerbed with a sidewalk. However the
minimum
Notes 1 If the number of CEF is high the width should be increased to 11.0 m.
2 If the number of CEF is high the width should be increased to 10.0 m
(21)
3 Cross-fall can be reduced to 4% where warranted (e.g. poor gravel - for safety,
low rainfall).
Figure 3-2 and Figure 3-3 illustrate examples of cross section elements for three
different terrains.
(22)
3.3.1 Additional Width for Mixed Vehicles
For the lower road standards, modifications to the standards are made for high
volumes of non-motorised vehicles, motor cycles, pedestrians (and other forms of
intermediate transport). CEF are defined for this purpose as shown in Table 2-3 and
the modifications to specifications are summarised in Table 3-8, where it should be
noticed that the width increases are directed at the shoulders and not the
carriageways. The modifications are not possible on escarpments. In mountainous
terrain they are only possible along relatively flat sections. In these circumstances the
CEF values are only likely to be high where the population is high, and this is likely to
be defined as a populated area where widening is justified for that reason alone.
Table 3-8: Road Width Adjustments for Car Equivalence Factors (CEF)
greater than 300 AADT
Standard AADT Modification
Paved T1 None
Paved T2 None
Paved T3 Shoulder width increased to 2.5 m each side
Unpaved T3 Increase width to 11.0m
Paved T4 Shoulder width increased to 2.0 m each side
Unpaved T4 Increase width to 10.0m
The additional width depends on the status of the populated area that the road is
passing through. If the road is passing through a town or a larger populated area, an
extra carriageway of 3.5 m width is provided in each direction for parking and for
passenger pick-up and a 2.5 m pedestrian footpath is also specified. The latter is
essentially the shoulder. In addition, the main running surface is paved and is
increased to at least 7.0 m wide if the AADT is 1000 - 3000. However, village design
for road safety is essential and is described in Chapter 12.
When passing through a village, a 2.5 m paved shoulder is specified but no additional
footpath although one could easily be provided if required (Section 3.16).
3.4 Shoulders
Shoulder widths are shown in Table 3-6. The shoulder breakpoint is usually between
500 and 750 mm beyond the edge of the useable shoulder to allow for shoulder
(23)
rounding. Where vehicle restraint systems or other roadside furniture need to be
provided, they should be located beyond the limit of the useable shoulder and the
shoulder breakpoint should be a further 500mm beyond the furniture.
(24)
Normal crossfall (or camber) should be sufficient to provide adequate surface drainage
whilst not being so great as to make steering difficult. The ability of a surface to shed
water varies with its smoothness and integrity. On unpaved roads the minimum
acceptable value of crossfall should be related to the need to carry surface water away
from the pavement structure effectively, with a maximum value above which erosion
of material starts to become a problem.
Hinge point
Carriageway
Back slope
Shoulder
Side slope
Toe of slope
(25)
The selection of a side slope and back slope is dependent on safety considerations,
height of cut or fill, and economic considerations. The guidance in this chapter is
mainly applicable to new construction or major reconstruction. On maintenance and
rehabilitation projects, the primary emphasis is placed on the roadway itself. Because
of environmental impacts or limited road reserve it may not be cost-effective or
practical to bring these projects into full compliance with the side slope
recommendations provided.
Table 3-10 indicates the side slope ratios recommended for use in the design
according to the height of fill and cut, the material, and practical experience of the
costs of construction. It will be noted that with the single exception of roads in areas
of black cotton soils, the recommended slopes are too steep to meet the
recommendations for adequate safety. Achieving a good safety design is clearly a
function of overall cost and at the present time is only likely to be viable for the
highest classes of road.
(26)
Table 3-10: Slope Ratio Table – Vertical to Horizontal
This Table should be used as a guide only, particularly because applicable standards in
rock cuts are highly dependent on costs. Also, certain soils that may be present at
subgrade level may be unstable at 1:2 side slopes and therefore a higher standard will
need to be applied for these soils. Slope configuration and treatments in areas with
identified slope stability problems should be addressed as a final design issue.
(27)
3.8.1 Trapezoidal
Under normal circumstances the adoption of a trapezoidal cross-section will facilitate
maintenance and will be acceptable from the point of view of traffic safety. It is much
easier and appropriate to dig and clean a trapezoidal drain with hand tools and the
risk of erosion is lower. The minimum recommended width of the side drain is 0.5 m.
This shape has high flow capacity and, by carefully selecting the gradients of its side
slopes, it will resist erosion.
3.8.2 V-Shape
The V-shape is the standard shape for a drainage ditch constructed by a motor-
grader. It can be easily maintained by heavy equipment, but it has relatively low
capacity necessitating more frequent structures for emptying it. Furthermore, the
shape concentrates flow at the invert and encourages erosion. Using a V-shaped ditch
the minimum depth should be 0.6 m in mountainous and escarpment terrain, and 1.0
m elsewhere.
For the detailed design of roadside ditches, the Drainage Design Manual, 2017 and
CEDR: Forgiving Roadsides Design Guide (2012) should be used.
(28)
depends on the traffic level and whether the road is in cut or fill. The values
recommended are shown in Table 3-11.
For traffic that is low for the traffic class under consideration these values can be
reduced. The zone should extend beyond the toe of the slope. Lateral clearances
between roadside objects and obstructions and the edge of the carriageway should
normally be not less than 1.5 m. At existing pipe culverts, box culverts and bridges
the clearance cannot be less than the carriageway width; if this clearance is not met,
the structure must be widened. New pipe and box culvert installations, and extensions
to them, must be designed with a 1.5 m clearance from the edge of the shoulder.
For the horizontal clearance to road signs, marker posts, etc. an absolute minimum of
0.5 m from the edge of the carriageway is legally required.
Elements such as side slopes, fixed objects and water are features that a vehicle
might encounter when it leaves the roadway. The safety measures that can be taken
depend on the probability of an accident occurring, the likely severity, and the
available resources (Section 12.8). In order of priority, these measures are:
1. Removal.
2. Relocation.
3. Reduction of impact severity (using breakaway features – e.g. supports of
large vertical signs - or making it traversable – e.g. culvert ends).
4. Shielding with a road restraint system.
3.11 Medians
The median is the total area between the inner edges of the inside traffic lanes of a
divided road, and includes the inner shoulders and central islands. Medians separate
opposing streams of traffic. Medians as narrow as 1.5 m can be used where there are
(29)
severe space limitations, but a safety barrier will be required to ensure the separation
of vehicles. In contrast, a wide median (> 9.0 m) eliminates most cross-median
accidents and such accidents decrease as median width increases. Planting shrubs on
the central area of the median can also reduce the nuisance of headlight glare and
dazzle. A maximum stem thickness of 100 mm is recommended. Medians should not,
as far as possible, be obstructed by street furniture. If absolutely necessary, a median
of 5.0 m width can accommodate a right turn lane with provision for a pedestrian
refuge but would also require safety barrier protection to separate the opposing flows
of traffic. Such an arrangement is inherently unsafe unless controlled by traffic lights
and should be avoided.
For a raised median, kerbing offers a modest degree of protection to pedestrians who
may be on the median while crossing the road. In addition, kerbing can, to a very
limited extent, redirect errant vehicles back into their own lanes.
(30)
3.13 Bus Stops, Lay-bys and Parking Bays
Lay-bys clear of the lanes for through traffic considerably reduce the interference
between buses, taxis and other traffic. Bus lay-bys serve to remove buses from the
traffic lanes and parking bays are provided space for taxis and other vehicles to stop
outside of the roadway.
Pedestrian accidents at bus stops are common but can be reduced significantly by
good design of the bus stop area. Ideally a bus stop or a lay-by should be designed as
a short auxiliary lane with adequate entry and exit tapers and separated from the
travelled way by means of a separator from the through lanes. A further safeguard is
the use of pedestrian guardrails to prevent passengers from crossing the road until
they are well clear of the bus and have a clear vision of the road.
The location and design of lay-bys should provide ready access in the safest and most
efficient manner possible. To be fully effective, lay-bys should incorporate;
i) A deceleration lane or taper to permit easy entrance to the loading area.
ii) A standing space sufficiently long to accommodate the maximum number of
vehicles expected to occupy the space at one time.
iii) A merging lane to enable easy re-entry into the through-traffic lanes.
The deceleration lane should be tapered at an angle flat enough to encourage the bus
or taxi operator to pull completely clear of the through lane as in Figure 3-6. A taper
of 10:1, longitudinal to transverse, is a desirable minimum.
A loading area should provide 15 m of length for each bus. The width should be at
least 3.5 m and preferably 4.0 m. The merging or re-entry taper may be somewhat
more abrupt than the deceleration taper but, preferably, should not be sharper than
6:1.
(31)
Figure 3-6: Bus Lay-Bys and Parking Bays
The total length of lay-bys for a two-bus loading area of minimum design should be as
shown in Figure 3-6 and in the Standard Detail Drawings. These lengths of lay-bys
expedite bus manoeuvres, encourage full compliance on the part of bus and taxi
drivers, and lessen interference with through traffic. Sufficient footpaths should be
provided at bus lay-bys.
Bus stops should not be located immediately in advance of an intersection because of
the restriction of sight distance that this would impose on drivers approaching the
intersection. On the other hand, they should not be too far away because many
passengers may want access to the roads forming the intersection. Ideally the bus
stop should, except near roundabouts, be located after the intersection but not more
than 50 m from it.
(32)
Table 3-12: Pedestrian Sight Distances (m)
Design Speed Road Cross Section
(km/h) 2-Lane 3-Lane 4-Lane
60 85 130 170
70 100 150 200
80 115 170 230
90 130 190 255
100 140 215 285
110 155 235 310
120 170 255 340
Refuge islands should be at least 1.5 m wide (preferably 2.0 m) and may take the
form either of raised islands or of marked refuges with oblique parallel lines. If raised,
the sides should be semi-mountable. In addition, the approaches to the refuge island
should be tapered and clearly demarcated with the necessary road signs and
markings. The road markings together with retroreflective road studs should
channelise vehicular traffic away from the refuge island. A ‘pass this side’ (left) should
also be displayed prominently to safeguard drivers.
3.15 Sidewalks
On urban streets, it is necessary to provide sidewalks for pedestrian traffic. In
commercial areas or areas where the road reserve width is restricted, sidewalks may
extend from the kerb to the road reserve boundary. The width of a sidewalk should
not be less than 1.5 m and a minimum width of 2.0 m should be provided near
hospitals and residential homes where wheelchair traffic could be expected. If the
sidewalk is immediately adjacent to the kerbing, the minimum width should be
increased by 0.6 to 1 m. This is to make provision for fire hydrants, street lighting and
other road furniture. It also allows for the proximity of moving vehicles and the
opening of car doors.
Pedestrian paths must be continuous, not too sinuous and be unimpeded by
obstructions. The width of the path should not be less than 1.2 m, measured at
pavement level, to preserve the mobility of wheel chairs.
The normal cross-slope on a sidewalk should be 2 %. Steeper cross-slopes present
problems for disabled people. Sidewalks that cross driveway entrances may need a
steeper cross-slope to match the gradient of the driveways but should not exceed a
cross slope of 5 %.
Kerbs, raised medians and channelising islands can be major obstructions to the
elderly and people with disabilities, particularly those in wheelchairs. The most
common method for minimising the impact of these obstacles is to provide ramps,
also referred to as kerb cuts or dropped kerbs. Ramps should have a slope of not more
than about 6 %. A kerb height of 150 mm would thus require a ramp length of 2.5 m.
Ideally there should be a clear sidewalk width of 1.5 m beyond the top end of the
ramp so that, where a ramp is provided, the overall sidewalk width should be not less
than 4 m. Wheel chairs may be 0.75 m wide so that two would require a ramp width
of 2 to 2.5 m. If it is not possible to provide this width, a width of not less than 1.5 m
should be considered.
(33)
recommended. Footways can be as little as 1.0 m wide, but a width of 1.8 m allows
two people to walk side by side.
The safest location for footways is at the edge of the road reserve. In rolling or
mountainous terrain through cuts and fills, such a footway is not comfortable for
walking and so pedestrians often prefer to walk on the more level surface of the
shoulder. In level terrain, the footway should, if possible, be situated at least 3.0 m
away from the travelled way. In the case of a high-volume high-speed road this
unfortunately corresponds to a location immediately outside the edge of the usable
shoulder.
In cases where footways are not warranted but where many pedestrians walk
alongside the road; the road shoulder should be upgraded to cater for them. The
minimum width of these shoulders should be 3.0 m. If the shoulders are not surfaced,
they should be bladed and compacted regularly to provide pedestrians with a hard
surface to walk on. In high rainfall areas, a portion at least of the shoulder should be
paved, with this paved area being at least 1.5 m wide.
3.17 Slopes
The slopes of the sides of the road prism should be shallow for reasons of safety;
slopes of 1:4 are considered the steepest acceptable. See also Section 3.7. If steeper
slopes are necessary, then vehicle restraint systems might be needed, and the design
of the slope will need to take account of the geotechnical properties of the material
(Reference: Geotechnical Design Manual).
(34)
4 General Design Criteria for Road Alignments
The design of the road alignment is concerned with selecting the parameters of the
geometric features of the road so that they provide a safe, comfortable and efficient
conduit for transporting people and goods to wherever they need to be. Thus,
designing the road alignment is concerned with the application of methods of
achieving safety and efficiency in the road transport system.
The principal components are the horizontal alignment, which is essentially the road in
plan, and the vertical alignment, which is the road in longitudinal cross section. The
separate slopes and curves of the road must satisfy certain criteria based on how
vehicles and humans interact with them. This chapter is concerned with those criteria
for the horizontal and vertical curves. Some of these are specific to either horizontal or
vertical alignment while some are common to both. Once the criteria have been
defined, they are used to design the horizontal alignment (Chapter 5) and the vertical
alignment (Chapter 6).
4.1.1 Consistency
Design speed is significant only when the physical road characteristics limit the speed
of travel. However, the design speed concept alone does not ensure sufficient
coordination among individual geometric features to ensure consistency. It controls
only the minimum value of the maximum speeds for the individual features along an
alignment. For example, a road with an 80 km/h design speed may have only one
curve with a design speed of 80 km/h and all other features may have design speeds
of 120 km/h or greater. As a result, operating speeds approaching the critical curve
are likely to exceed the 80 km/h design speed. Such an alignment would comply with
an 80 km/h design speed, but it would violate a driver's expectancy and result in an
undesirable alignment.
Thus, the various design elements must be combined in a balanced way, avoiding the
application of minimum values for one, or a few, of the elements at a particular
location when the other elements are considerably above the minimum requirements.
Thus, the radii of curves within a section should be consistent, not merely greater than
the minimum value.
When a substantial length of road is being designed, a constant design speed should
be adopted to maintain consistency. In practice the speed of motorised vehicles on
many roads in flat and rolling terrain will only be constrained by the road geometry
over relatively short sections but it is important that the level of constraint is
consistent for each road class and set of conditions.
(35)
4.1.2 Changes of Design Speed
Changes in terrain and other physical controls may dictate a change in design speed
on certain sections. Each such section, however, should be relatively long, greater
than 2 km, and compatible with the general terrain or the development through which
the road passes. The justification for introducing a reduced design speed should be
obvious to the driver; for example, where a road leaves relatively level terrain and
starts to traverse hilly or mountainous terrain. It is often found that the physical
terrain changes quite quickly (e.g. by twosteps, typically, from mountainous to flat
terrain). However, change in design speed caused by a change in terrain class should
not occur abruptly but over sufficient distances to enable drivers to change speed
gradually. The change in design speed between successive speeds should be limited to
10 km/h when the design speed is 90 km/h or greater and to 20 km/h when the
design speed is below 80 km/h.
In view of the low density of roads (and, hence, lack of alternative routes) together
with the limited choice of vehicle for many transporters, it is prudent to be
conservative in choosing the design vehicle for each class of road so that the
maximum number of vehicle types can use them. Table 4-1 shows typical design
vehicles that are often used, but, for high volume roads in Mozambique, the design
vehicle should be a truck and trailer except for very severe escarpment terrain.
The maximum turning path for a single unit truck, a single unit bus, and a semi-trailer
combination are shown Figure 4-1, Figure 4-2 and Figure 4-3 respectively.
(36)
Table 4-1: Design Vehicle Characteristics
Minimum
Front Rear Wheel-
Design Height Width Length turning
Code overhang overhang base
vehicle (m) (m) (m) radius
(m) (m) (m)
(m)
4x4 Utility DV1 1.3 2.1 5.8 0.9 1.5 3.4 7.3
Single
unit truck
DV2 4.3 2.6 11.0 1.5 3.0 6.5 12.8
Single
unit bus
DV3 4.3 2.6 12.1 2.1 2.6 7.6 12.8
Truck +
semi- DV4 4.3 2.6 15.2 1.2 1.8 13.2 13.7
trailer
Typical 5-
axle truck
DV5 4.3 2.6 20.9 1.2 1.8 18.9 22.9
Typical 6-
axle truck DV6 4.3 2.6 22.0 1.2 1.8 20.4 13.7
trailer
* Distance between rear wheels of SU tractor vehicle and front wheels of trailer to be
added ((3.5m)
Figure 4-1: Dimensions and Turning Radius Path for Single Unit Truck (DV2)
(37)
Figure 4-2: Dimensions and Turning Radius Path for Single Unit Bus (DV3)
(38)
4.3 Sight Distances
4.3.1 Introduction
Drivers must be able to see objects in the road with sufficient time to either stop or to
manoeuvre round them. There are several situations requiring different sight distances
thus:
• Stopping sight distance.
• Intersection sight distance.
• Decision sight distance.
• Passing sight distance.
Each depends on the initial speed of the vehicle and the factors listed in Table 4-2
(39)
common, and the climate varies from wet to arid with the time of year. Gravel roads
can have particularly low friction characteristics.
Side friction coefficients are also dependent on vehicle speed, type, condition and
texture of roadway surface, weather conditions, and type and condition of tyres.
Appendix D illustrates some values obtained by various researchers.
The coefficient of friction values chosen are shown in Table 4-3 using the lowest
results of friction tests. The values allow a reasonable safety factor to cater for the
wide range of conditions. For unpaved roads a systematic reduction in the values used
for paved roads has also been used.
Longitudinal Paved 0.40 0.37 0.35 0.33 0.32 0.305 0.295 0.285 0.29 0.28
friction
factors Unpaved 0.32 0.30 0.28 0.26 0.25 0.24 0.235 0.23 0.23 0.23
Side friction Paved 0.21 0.19 0.17 0.16 0.14 0.13 0.12 0.10 0.10 0.095
factors Unpaved 0.165 0.15 0.135 0.125 0.12 0.11 0.10 0.095 0.09 0.09
V2
d = (0.278)(t )(V ) +
(254( f + g / 100) )
where,
d = stopping distance (m)
t = driver reaction time
V = initial speed (km/h)
f = longitudinal coefficient of friction between tyres and roadway.
g = gradient of road as a percentage (downhill is negative).
On a flat road the value of g is zero. On a 5 % downhill gradient the stopping distance
at 120 km/hr is typically 16 % longer. At a 10 % gradient it is nearly 40 percent
longer. For speeds above 50 km/h, the gradient of the road makes a significant
difference and must be taken into account in establishing safe sight distances.
Table 4-4 applies to cars and trucks with anti-lock braking systems. Trucks with
conventional braking systems require longer stopping distances. Although the driver’s
eye height is greater than that of a car driver, hence the driver can see objects
sooner, this does not always compensate for the poorer braking system. However,
separate stopping sight distances for trucks and passenger cars are not generally used
in highway design.
Table 4-5 is for unpaved roads where the coefficients of friction are lower and much
more variable, depending on the properties of the gravel or soil.
(40)
It is important to note that the values in the Tables are for dry weather conditions.
Stopping sight distances can be much longer in unfavourable wet conditions but are
not generally used in design. Driving at the design speed with worn tyres and very wet
conditions is not a common activity - drivers slow down until they feel safe - but
accident rates increase in wet weather.
Full adherence to the required sight distances is essential for safety reasons. On the
inside of horizontal curves, it may be necessary to remove trees, buildings or other
obstacles to obtain the necessary sight distances. If this cannot be done, the
alignment must be changed. In rare cases where it is not possible and a change in
design speed is necessary, adequate and permanent signage must be provided.
(41)
Table 4-5: Minimum Stopping Sight Distances for Unpaved Roads
4.3.4 Stopping Sight Distance for Single Lane Roads (Meeting Sight
Distance)
Meeting Sight Distance (sometimes called Barrier Sight Distance) is the distance that
needs to be provided on a single-lane road to allow vehicles travelling in the opposite
direction, usually because one vehicle is executing a passing manoeuvre, to see each
other and to stop safely if necessary.
It is measured for an object height of 1.3 m (i.e. the height of an approaching
passenger car) and an eye height of 1.05 m. This distance is normally set at twice the
stopping sight distance for a vehicle that is stopping to avoid a stationary object in the
road. An extra safety margin of 20-30 m is also sometimes added. Although a vehicle
is a much larger object than is usually considered when calculating stopping distances,
these added safety margins are used partly because of the very severe consequences
of a head-on collision and partly because it is difficult to judge the speed of an
approaching vehicle, which could be considerably greater than the design speed.
It is particularly important to check this on existing roads that have a poor vertical
alignment that may contain hidden dips that restrict sight distances. However, single
lane roads have a relatively low design speed, hence meeting sight distances should
not be too difficult to achieve.
(42)
4.3.6 Decision Sight Distance
Stopping sight distances are usually sufficient to allow reasonably competent drivers
to stop under ordinary circumstances. However, these distances are often inadequate
when drivers need to make complex decisions or when unusual or unexpected
manoeuvres are required. The driving task is constrained or limited by the human
factors involved (see Section 1.2.1).
Decision sight distance, sometimes termed ‘anticipatory sight distance’, is the distance
required for a driver to:
• detect an unexpected or otherwise ‘difficult-to-perceive’ information source or
hazard in a roadway environment that may be visually cluttered;
• recognize the hazard or its potential threat;
• select an appropriate speed and path; and
• complete the required safety manoeuvre safely and efficiently.
Critical locations where errors are likely to occur and where it is desirable to provide
decision sight distance include:
• Areas of concentrated demand where sources of information such as
roadway elements, opposing traffic, traffic control devices, advertising signs
and construction zones, compete for attention (i.e. visual noise).
• Approaches to interchanges and intersections;
• Railway crossings, bus stops, bicycle paths, entrances of villages and towns;
• Newly upgraded road sections or the change of road hierarchy;
• Changes in cross-section such as at toll plazas and lane drops;
• Design speed reductions.
The minimum decision sight distances that should be provided for specific situations
are shown in Table 4-6. If it is not feasible to provide these distances because of
horizontal or vertical curvature, or if relocation is not possible, special attention should
be given to the use of suitable traffic control devices for advance warning.
Although a sight distance is shown in the Table for the right side (off-side) exit, exiting
from the right side, except on LVRs, is undesirable because, to be safe, crossing a
fast-moving traffic stream requires traffic control; the efficiency of the junction is thus
severely reduced. Furthermore, a right-side exit is also in conflict with the expectancy
of most drivers and this further compromises safety. The reason for providing this
value is to allow for the possibility that an off-side (right side) exit might be necessary
sometimes, usually with traffic control.
In measuring decision sight distances, the 1.05 m eye height and 0 mm object height
have been adopted.
(43)
Table 4-6: Decision Sight Distances for Various Situations (m)
Situations
Lane drop,
Interchanges. Lane shift Intersections.
Design merge
Speed Sight distance to
km/h nose Sight Sight distance
Sight distance
distance to to beginning of
Near- Off-side to turn lane
taper area shift
side exit exit
50 NA NA 150 85 150
60 200 275 200 100 200
80 250 340 250 150 250
100 350 430 350 200 350
120 400 500 400 250 400
Source: SANRAL. Geometric Design Guidelines.
(44)
Table 4-7: Passing Sight Distances
30 115 195
40 135 275
50 155 345
60 180 420
70 210 485
80 240 550
90 275 615
100 310 670
110 350 730
120 395 780
130 440 830
Note 1 Manual on Uniform Traffic Control Devices (MUTCD) and Harwood et al. (2008).
NCHRP Report 605,
2 SATCC (2001). Code of Practice for the Geometric Design of Trunk Roads.
(45)
speeds above 80 km/h, only large, light coloured objects can be perceived at the
generally accepted stopping sight distances.
Example:
Radius = 1000 m, Δ = 200;
S = 2R sin(/2) M = R (1 – cos(/2)
= 2(1000)(sin(10o) = 1000(1- cos(10o)
= 347 m = 15.2 m
(46)
5 Design of Horizontal Alignment
The horizontal alignment consists of a series of straight sections (tangents), circular
curves and transition curves (spirals) between the tangents and the circular curves.
In order for a vehicle to move in a circular path, an inward radial force is required to
provide the necessary centripetal acceleration or, in other words, to counteract the
centrifugal force. This radial force is provided by the sideways friction between the tyres
and the road surface assisted by the super-elevation.
The objective is to provide a safe road which can be driven at a reasonably constant
speed. Therefore, sharp changes in the geometric characteristics of both horizontal and
vertical alignments, must be avoided. A transition curve whose radius changes
continuously between a straight section of road and a circular curve is used to reduce the
abrupt introduction of centripetal acceleration that occurs on entering the circular curve.
Transition curves are not required when the radius of the horizontal curve is large and are
not normally used on the lower classes of road.
VD 2
Rmin = Equation 5.1
127(e + f )
Where
VD = design speed (km/h)
e = maximum super-elevation (%/100)
f = side friction coefficient (Section 4.3.2)
The minimum radii of curvature for different design speeds and super-elevations based on
this formula and pragmatic coefficients of friction are shown in Table 5-1 for paved roads
and Table 5-2 for unpaved roads. For convenience they are also included in the summary
of specifications for each` road class in the Tables in Chapter 7. As the radius increases,
the accident rate decreases hence the minimum values should be used only under the
most critical conditions and the deviation angle of each curve should be as small as the
physical conditions permit.
(47)
Table 5-1: Minimum Radii for Horizontal Curves for Paved Roads (m)
Design
speed 30 40 50 60 70 80 85 90 100 110 120
(km/h)
Side
Friction 0.21 0.19 0.17 0.16 0.15 0.13 0.13 0.12 0.11 0.10 0.09
Factor (f)
Super-
elevation 30 55 95 150 220 300 350 400 520 660 810
= 4%
Super-
elevation 27 53 85 135 190 265 305 350 455 580 720
= 6%
Super-
elevation 25 50 80 120 175 240 280 320 415 530 660
= 8%
Super-
elevation 25 50 75 110 155 210 245 285 370 475 605
= 10%
For unpaved roads the friction is usually considerably less than on paved roads. In these
calculations it has been assumed that it is 80% of the value for paved roads but this is
dependent on a tightly knit and dry surface of good quality gravel with no loose stones; in
other words a surface on which the design speed can be maintained. A poorly bound
surface with many loose particles has a very low value of friction and it must be assumed
that vehicles will be driven on such a surface at a speed that is much lower than the
nominal design speed dictated by the sight distances and radii of curvature.
Table 5-2: Minimum Radii for Horizontal Curves for Unpaved Roads (m)
Design speed
20 30 40 50 60 70 80 85 90 100
(km/h)
Side Friction Factor 0.19 0.165 0.15 0.14 0.12 0.12 0.10 0.10 0.10 0.09
Super-elevation=4% 15 35 65 115 175 255 355 415 475 610
5.2 Consistency
Under normal circumstances sections of road will contain many curves whose radii are
larger than the minimum radii specified in the design standards. For reasons of safety and
driver comfort it is not advisable for two consecutive curves to differ in radius by a large
amount even though they are both greater than the minimum. Figure 5-1 shows the
required ratio of radii for consecutive curves. Consecutive horizontal curves are defined as
curves where the distance between the end of one and the beginning of the next is less
than the radius of the larger curve. The best result will be achieved when the two radii
are similar (labelled ‘very good’ in the diagram). If the ratio of radii falls outside the
‘good’ category but inside into the ‘useable’ category some discomfort or inconvenience
will be felt because of the increase in centripetal force when entering the tighter curve.
However, it is not merely the ratio of curve radii that affect consistency. In particular, the
length of connecting tangents and the friction between tyre and road surface are also
important because these affect speed. Thus for consistency all the various design
elements must be combined in a balanced way, avoiding the application of minimum
(48)
values for one or a few elements at a particular location when other elements are
considerably above the minimum requirements.
(Source: German Road and Transportation Research Association, Cologne, Germany (1973).
Guidelines for the design of rural roads (RAL), Part II.
Of the numerous techniques for the evaluation of consistency, the ratio between the
horizontal radius of a curve and that of the preceding curve or tangent (described as a
curve of infinite radius) is the most reliable indicator. This indicator is described as the
Curvature Change Rate (CCR) and has been adopted as the preferred option for the
evaluation of consistency of design (Lamm et al. (1999)):
(49)
R = Radius of the circular curve (m)
LC = Length of the circular portion of the curve
LT1 and LT2 = Length of the transition curves (m)
L = total length of the curve (m) = LT1 +LC + LT2
Tmin Tangent length necessary to achieve V852 from an initial speed of V851
Consistency of design is divided into three groups namely Good, Tolerable and Poor based
on the following three criteria.
• Design consistency – this relates to the difference in CCRs of successive curves
calculated according to the equations above;
• Operating speed consistency – this is a measure of the uniformity of 85 percentile
speeds through successive elements of the road.
• Consistency of driving dynamics – this relates the side friction assumed with
respect to the design speed, to that demanded at the 85 percentile speed.
(50)
Table 5-4: Design Criteria
Quality of Design Design Consistency
Good CCR1 – CCR2 ≤ 180
Tolerable 180 < CCR1 – CCR2 < 360
Poor 360 < CCR1 – CCR2
Speed Consistency
Good V851 – V852 <10
Tolerable 10 < V851 – V852 <20
Poor < 20V851 – V852
Frictional Difference
Good +0.01 ≤ f2 – f1
Tolerable -0.04 ≤ f2 – f1 ≤ +0.01
Poor f2 – f1 < - 0.04
The operating speed on each curve in the alignment is taken to be the observed 85 th
percentile speed.
For new designs it is necessary to estimate this. Lamm et al. (1999) have shown that the
average V85 is related to the average CCR (Equations 5.4 and 5.5), hence the average
value of V85 and the average design speed can be calculated from the average CCR. The
equation for use when longitudinal gradients are less than 6% is:
The relationships are country dependant hence local data are needed to develop a local
equation for greater accuracy.
Note that CCR is zero for a tangent and the relationships are applicable from a CCR of 0
to 1600.
(51)
3) The tangent length is such that it is possible to achieve an operating speed
higher than that of the following curve but not as high as that achieved without
the constraint of nearby curves; Tmin < T < Tmax
The values of Tmin and Tmax are calculated from the following equation which is based on
an acceleration rate of 0.85 m/s2:
Equation 5.6
Where,
V851 and V852 are the 85 percentile speeds (km/h);
‘a’ is the acceleration (m/sec2); and
V85Tmax = operating speed on a long tangent
This equation means that the existing tangent is long enough to allow acceleration up to
the maximum operating speed (V85Tmax) on tangents.
Where the length of the tangent falls between Tmin and Tmax, the V85 on the curve of
interest must be recalculated on the basis of the V85 of the preceding curve plus the
acceleration on the tangent from:
Where:
A = acceleration (m/sec2) is 0.85 m/sec2 for acceleration and deceleration.
Although the tangent is not long enough to allow accelerations up to the highest
operating speed (V85Tmax), a speed higher than that of the following curve can be
achieved. In this case, for the evaluation of the Speed Criterion, equation 5.9 must be
used to calculate the realizable tangent speed (V85T).
5.2.2 Friction
In addition to consistency of geometry and speed, for safety there must also be
consistency in the driving dynamics of each curve. This is controlled by the friction
between tyre and road surface and its effect is quantified in Table 5-3.
(52)
5.2.3 Evaluation of Consistency
Three steps required:
Step 1. Calculate the CCR of all the curves from Equation 5.3.
Step 2. Obtain the V85 for the tangents and all the curves. It is unlikely that these will be
known from direct measurements hence Equations 5.4 and 5.5 must be used.
Step 3. From the average V85, compute the average design speed.
Step 4. Calculate Tmin and Tmax for the tangents between each pair of curves (Equations
5.6 and 5.7). Where the actual or proposed tangent length falls between these two values
it will be necessary to calculate the V85 achieved using equation 5.9.
Step 5. Calculate the difference between the side friction demanded by the design speed
and that required for the operating speed (Table 5-1).
The differences in CCR values for each row of Table 5-4 correspond to speed differences
Vdif of about 10km/h:
It is important to note that all criteria must be met for the design of an element to be
considered to be ‘good’ or ‘tolerable’. If any criteria are not met, it provides a pointer as
to the actions required to upgrade to a satisfactory state.
(53)
5.4 Length of Tangent Sections and Curves
Table 5-5 shows the minimum and maximum lengths of tangents and circular curves.
Notes A The minimum length of Tangent is equal to the super-elevation run off of the
preceding circular curve followed by the development of that for the following curve.
B The maximum length of Circular Curve is 800 – 1000 m.
1 This value or the length of the circular curve plus half the total length of the
transitions, whichever is the longest.
2 If space is restricted, this can be reduced by 30m for every degree less than 5 0 that
the curve deflects.
3 Reduce this if there is a significant amount of traffic at night
(54)
Design Speeds less than 120 km/h
At lower design speeds, maximum lengths considerably shorter than 8 km should be
used. Drivers should be encouraged to maintain a speed which is close to the design
speed to reduce the possibility of an error of judgment leading to an accident. A
maximum tangent length, measured in metres, of 15-20 times the design speed in km/h,
achieves this effect. For example, a design speed of 100 km/h suggests that tangents
should, ideally, not be longer than 1.5 – 2.0 km.
If the achievable maximum length of tangent across the length of the route is regularly
greater than this guideline value, a higher design speed should be considered.
(55)
5.5 Cross-fall
For both paved and unpaved roads there are constraints on the maximum cross-fall, as
summarised in the Chapter 3.
Passing lanes are normally provided in areas where construction costs are relatively low
and where there is an absence of passing opportunities. A passing lane length of about
one km is adequate for this purpose. Numerous short passing lanes are preferable to few
long passing lanes (Figure 5-2) and it is recommended that they be located at two, four
and eight kilometre spacing. Where traffic volumes are low, the longest spacing can be
used and, as traffic volumes increase, the intervening lanes can be added in a logical
manner with one-km passing lanes provided at two-km intervals. They potentially provide
safer passing opportunities for drivers who are uncomfortable in using the opposing traffic
lane and for those who become frustrated when few passing opportunities exist owing to
terrain or traffic density.
(56)
5.7.1 Three-lane Designs
The next level of upgrading is a continuous three-lane cross section, two lanes in one
direction (one for overtaking) and a single lane in the opposing direction (often called the
2 + 1 design) (Figure 5-3). The centre lane is alternately allocated to each of the
opposing directions of flow. The switch in the direction of flow in the centre lane should be
at about two-km intervals. A minimum shoulder width is required as discussed in Section
6.6.
(57)
traffic. The disadvantage is that unless the fast traffic does so it will face traffic from the
opposite direction travelling towards it in the central lane. The key is good road layout
and road signing. Reference should be made to the Road and Traffic Signs Manual for the
recommended signage and road markings. Driver experience and expectations also play
an important role.
Neither a passing lane nor a climbing lane are ideal solutions and each case needs to be
examined on its merits.
(58)
5.8 Widening on Curves and Embankments
The use of long curves of low radii should be avoided where possible because drivers
following the design speed will find it difficult to remain in the traffic lane. Widening of the
carriageway where the horizontal curve is tight is usually necessary to ensure that the
rear wheels of the largest vehicles remain on the road when negotiating the curve and,
for two-lane roads, to ensure that the front overhang of the vehicle does not encroach on
the opposite lane. Widening is therefore also important for safety reasons. Curve
widening is required on all standards of roads and should be sufficient to cater for the
design vehicle. Table 5-6 shows the values to be used.
• Curve widening is generally not applied to curves with a radius greater than 250 m
regardless of the design speed or the lane width.
• Vehicles need to remain centred in their lane to reduce the likelihood of colliding
with an oncoming vehicle or driving on the shoulder.
• Sight distances should be maintained as discussed above.
• Widening on high embankments is recommended for design classes H1 through to
H3. The steep drops from high embankments unnerve some drivers and the
widening is primarily for psychological comfort although it also has a positive effect
on safety. Widening for curvature and for high embankments should be added
where both cases apply.
• Widening should transition gradually on the approaches to the curve so that the
full additional width is available at the start of the curve.
• Although a long transition is desirable to ensure that the whole of the travelled
way is fully usable, for the improvement of existing roads this results in narrow
pavement slivers that are difficult, and correspondingly expensive, to construct in
existing roads. In practice curve widening is thus applied over no more than the
length of the super-elevation runoff preceding the curve.
• For ease of construction, the widening is normally applied only on one side of the
road. This is usually on the inside of the curve to match the tendency for drivers to
cut the inside edge of the travelled way.
(59)
• Widening is provided to make driving on a curve comparable with that on a
tangent. On older roads with narrow cross-sections and low design speeds and
hence sharp curves, there was a considerable need for widening on curves.
Because of the inconvenience attached to widening the surfacing of a lane, it
follows that the required widening may not always have been provided. Where a
road has to be rehabilitated and it is not possible to increase the radius of
curvature, the designer should consider the need for curve widening.
Figure 5-5 illustrates a hairpin curve. The abbreviations are defined at the beginning of
the manual.
(60)
Figure 5-5: Hairpin Curve
As an example, consider a road standard which allows for only the passage of a single
DV4 vehicle. By superimposing Figure 4-2 for design vehicle DV4 over Figure 5-5 at the
same scale, the additional requirements can be identified. The normal carriageway width
will usually need to be increased at the hairpin curve. Requirements vary depending on
passage requirements, radius, deflection angle, and design standard, and a template
should be used based on the turning radii of the design vehicle to ensure that the vehicles
can negotiate each hairpin.
(61)
Figure 5-6: Hairpin Curve for the Passage of Single DV4 Vehicle
It is also important to provide relief from a severe gradient through the hairpin. Gradient
parameters associated with a hairpin curve are discussed in Section 6.5.
(62)
Table 5-7: Transition Curve Requirements (m)
Transition required if Radius
Design Speed (km/hr)
of Curve is less than:
70 290
80 380
85 428
90 480
100 590
110 720
120 850
Source: AASHTO. A Policy on Geometric Design of Highways and Streets, (2011).
If a transition curve is required, the Euler spiral, which is also known as the clothoid,
should be used. The radius varies from infinity at the tangent end of the spiral to the
radius of the circular arc at the circular curve end. By definition, the radius at any point of
the spiral varies inversely with the distance measured along the spiral. The equation is:
R = A/L
where R is the curve radius, L is the distance from the start of the spiral and A is a
constant, called the spiral parameter, and has units of length.
5.11 Super-elevation
On all roads except those with the lowest design speed (i.e the lowest classes) a vehicle
negotiating a horizontal curve at the design speed requires more than just the friction
between wheels and road surface to prevent sliding. The additional force is provided from
the component of the vehicle’s weight that acts towards the centre of the curve when the
vehicle is tilted by means of super-elevation. The required force depends on the speed of
the vehicle and the radius of the horizontal curve hence the degree of tilting, or super-
elevation, also depends on these same parameters.
(63)
3) The next section of the road is called the Super-elevation Runoff. It is the length
of road needed to accomplish the change in cross slope from the first section in
which the adverse crown was removed to the fully super-elevated section and is
effected over the whole length of the spiral transition curve. Its end point is the
beginning of the circular curve itself which is denoted by SC (the Spiral to Curve
transition point) or, alternatively called PC (the Point of Curvature i.e the point
where the circular curve begins).
4) The length of runoff, as can be seen on Figure 5-7 and Figure 5-8, is the spiral
length with the tangent to spiral point (TS) at the beginning and the spiral to
curve point (SC) at the end.
(64)
Figure 5-8: Attainment of Super-elevation using the Transition Curve
5) The length of the transition curve is proportional to the total super-elevation and
should not be less than the values shown in Table 5-8. A simple practical rule is
that it must not be less than the distance travelled in 2 seconds at the design
speed.
6) At any design speed the degree of super-elevation that is necessary for curves
of radii greater than the minimum is less than that required for the minimum
radius. Thus higher values than strictly necessary can be used ranging up to the
maximum value (i.e. that value required for the minimum radius). In this
situation there are five different models for relating the super elevation to the
(65)
radius of the circular curve (AASHTO, 2002). The recommended method gives
the super-elevation values shown in Table 5-9 to Table 5-12. The values also
depend on the maximum super-elevation on the road in question. This produces
a uniform range of circular curves and super-elevation and therefore no curves
of unexpected characteristics that might surprise drivers. [For convenience the
minimum length of the super-elevation runoff (excluding the tangent runout) is
included in Table 5-9 to Table 5-12 for the respective design speed, radius of
curve, and maximum super-elevation].
7) The length of tangent runout is determined by the amount of adverse cross
slope and the rate at which it is removed. This rate of removal should preferably
be the same as the rate used to effect the super-elevation runoff. Between the
TS and SC (the super-elevation runoff) the travelled way is rotated to reach the
full super-elevation at the SC.
8) Not all circular curves require a spiral transition (Table 5-5). Current design
practice is to place approximately two-thirds of the runoff on the tangent
approach and one-third on the curve.
9) A tighter curve can be designed if higher values of super-elevation are used, but
high values of super-elevation are not recommended especially if the friction is
low, such as in locations where mud is likely to contaminate the road surface
regularly. High values are also not recommended where mixed traffic and/or
roadside development severely limit the speed of vehicles. In urban areas an
upper limit of 4 % should be used except on a high speed urban road where 6 %
is acceptable. Either a low maximum rate of super-elevation or no super-
elevation at all should be used within important intersection areas or where
there is a tendency to drive slowly because of turning and crossing movements,
warning devices, and signals. Super-elevation is, however, a requirement for all
standards of roads and, whatever value is selected as the maximum, it should
be applied consistently on a regional basis.
(66)
Figure 5-9: Reverse Curves, Broken-Back Curves, and Compound Curves
(67)
Figure 5-10: Super-elevation of Reverse Curves
(68)
Figure 5-11: Super-elevation of Broken-back Curves
(69)
Figure 5-12: Shoulder Super-elevation (for Surfaced Roads)
For design classes H3 and lower the shoulder may be sloped with the carriageway, but
the shoulder should then be surfaced on the outside of the curve.
(70)
Table 5-9: Super-elevation Rates for emax = 4.0%
Radius Design Speed (km/h)
(m) 40 50 60 70 80 90 100 110 120
7000 n n n n n n n
5000 n n n n n n n
4000 n n n n n n n
3000 n n n n n n rc
2000 n n n n rc rc rc
1500 n n n rc rc rc 2.2
1400 n n n rc rc rc 2.3
1300 n n n rc rc rc 2.45
Design speeds
1200 n n n rc rc 2.1 2.6 above 100
1000 n n rc rc rc 2.5 3 km/h
are not suitable
900 n n rc rc 2.1 2.7 3.2
800 n n rc rc 2.3 2.95 3.4
700 n rc rc rc 2.6 3.2 3.6
600 n rc rc 2.3 2.9 3.45 3.8
500 n rc 2.1 2.7 3.25 3.7
400 rc rc 2.6 3.1 3.6
300 rc 2.3 3.1 3.6
250 rc 2.6 3.4 3.8
200 2.1 3 3.7
180 2.3 3.2 3.8
160 2.5 3.4
140 2.8 3.6
120 3.1 3.8
100 3.4 4.0
80 3.7
60 4.0
Notes
1 n = normal crown
2 rc = remove adverse camber
(71)
Table 5-10: Super-elevation Rates for emax = 6.0%
Radius Design Speed (km/h)
(m) 40 50 60 70 80 90 100 110 120
7000 n n n n n n n n rc
5000 n n n n n n n rc rc
4000 n n n n n n rc rc rc
3000 n n n n n rc rc 2.0 24
2000 n n n rc rc 2.2 2.6 3.0 3.4
1500 n n rc rc 2.3 2.8 3.2 3.7 4.2
1400 n n rc rc 2.5 3.0 3.4 3.9 4.4
1300 n n rc 2.1 2.6 3.1 3.6 4.1 4.6
1200 n n rc 2.3 2.8 3.3 3.8 4.3 4.8
1000 n rc 2.1 2.7 3.2 3.7 4.2 4.8 5.3
900 n rc 2.3 2.9 3.4 3.9 4.4 5.1 5.6
800 n rc 2.5 3.1 3.6 4.2 4.7 5.4 5.9
700 n 2.1 2.7 3.4 3.9 4.5 5.0 5.7
600 n 2.4 3.0 3.7 4.2 4.8 5.4
500 rc 2.7 3.4 4.1 4.6 5.2 5.9
400 2.3 3.1 3.8 4.5 5.1 5.7
300 2.8 3.7 4.4 5.1 5.7
250 3.1 4.0 4.8 5.5
200 3.6 4.5 5.2 5.9
180 3.8 4.7 5.4
160 4.0 4.9 5.6
140 4.3 5.2 5.9
120 4.6 5.5
100 4.9 5.8
80 5.4
60 5.9
Notes
1 n = normal crown
2 rc = remove adverse camber
(72)
Table 5-11: Super-elevation Rates for emax = 8.0%
Radius Design Speed (km/h)
(m) 40 50 60 70 80 90 100 110 120
7000 n n n n n n n rc rc
5000 n n n n n n rc rc rc
4000 n n n n n n rc rc 2.2
3000 n n n n n rc rc 2.3 2.9
2000 n n n rc rc 2.4 2.9 3.5 4.1
1500 n n rc rc 2.6 3.2 3.7 4.3 5.1
1400 n n rc 2.1 2.8 3.4 3.9 4.6 5.3
1300 n n rc 2.3 3.0 3.6 4.2 4.8 5.6
1200 n n rc 2.5 3.2 3.8 4.4 5.1 5.9
1000 n rc 2.1 2.9 3.6 4.3 4.9 5.8 6.6
900 n rc 2.4 3.2 3.9 4.6 5.2 6.2 6.9
800 n 2.0 2.7 3.5 4.2 4.9 5.6 6.6 7.3
700 n 2.3 3.0 3.8 4.6 5.3 6.1 7.1 7.8
600 rc 2.6 3.4 4.2 5.0 5.8 6.7 7.6
500 2.1 3.0 3.9 4.8 5.6 6.4 7.3
400 2.5 3.5 4.5 5.4 6.3 7.1
300 3.1 4.2 5.3 6.3 7.2
250 3.5 4.7 5.9 6.9 7.8
200 4.0 5.4 6.5 7.5
180 4.4 5.7 6.8 7.8
160 4.7 6.0 7.2
140 5.1 6.4 7.6
120 5.6 6.9 8.0
100 6.1 7.4
80 6.7 8.0
60 8.0
Notes
1 n = normal crown
2 rc = remove adverse camber
(73)
Table 5-12: Super-elevation Rates for emax = 10.0%
Radius Design Speed (km/h)
(m) 40 50 60 70 80 90 100 110 120
7000 n n n n n n n n n
5000 n n n n n n n n rc
4000 n n n n n n rc rc rc
3000 n n n n n rc 2.0 2.2 2.5
2000 n n n n rc 2.2 2.7 3.1 3.6
1500 n n n rc 2.4 2.9 3.5 4.1 4.8
1400 n n rc 2.1 2.6 3.1 3.8 4.3 5.1
1300 n n rc 2.3 2.8 3.3 4.0 4.6 5.5
1200 n n rc 2.4 3.0 3.6 4.3 5.0 5.9
1000 n rc 2.2 2.9 3.5 4.2 5.1 5.9 7.0
900 n rc 2.5 3.2 3.9 4.6 5.6 6.5 7.7
800 n rc 2.7 3.5 4.3 5.1 6.2 7.2 8.5
700 rc 2.3 3.1 4.0 4.8 5.8 6.9 8.0 9.3
600 rc 2.7 3.6 4.5 5.5 6.5 7.8 8.9
500 2.3 3.1 4.2 5.3 6.4 7.6 8.8
400 2.8 3.8 5.0 6.3 7.5 8.7 9.7
300 3.6 4.8 6.3 7.8 8.9 9.8
250 4.2 5.6 7.1 8.7 9.5
200 5.0 6.6 8.2 9.5
180 5.5 7.1 8.7 9.8
160 6.0 7.6 9.2
140 6.4 8.1 9.6
120 7.0 8.7
100 7.7 9.3
80 8.6
60 9.6
50 10.0
Notes
1 n = normal crown
2 rc = remove adverse camber
(74)
6 Design of Vertical Alignment
6.1 Introduction
On rural and high-speed roads a smooth grade line is required rather than a series of
successive short lengths of grades and curvature. Vertical alignment is the
combination of parabolic vertical curves and tangent sections of a particular slope
designed to achieve this objective. Thus, the design of vertical alignment is concerned
with crest and sag curves. A crest curve is a convex vertical curve. A sag curve is a
concave vertical curve. These are as shown in Figure 6-1 and Figure 6-2, respectively.
This chapter describes the mathematical concepts for defining the vertical curvature of
the road; defines the limiting characteristics for each road class; recommends
maximum and minimum gradients; indicates gradient requirements through villages;
and develops the criteria for incorporation of a climbing lane or a passing lane.
(75)
6.2 Vertical Curve Formula
Vertical curves are required to provide smooth transitions between consecutive
gradients. The parabola is specified for these because the parabola provides a
constant rate of change of curvature and, hence, acceleration and visibility, along its
length. Equations relating the various aspects of the vertical curve (both crest and
sag) are as follows:
The Vertical Point of Intersection (VPI) always occurs at an x coordinate of 0.5L hence,
from equation 6.1, the elevation is always;
Example:
For the crest curve shown in Figure 6.1 the two tangent grade lines are +6% and -
3%. The Beginning of the Vertical Curve is at chainage 0.000 and its elevation
100.0m. The length of the vertical curve is 400m. Compute the End of the Vertical
Curve and the coordinates of the Intersection Point.
(76)
6.3 Crest curves
Two conditions exist when considering the minimum sight distance criteria on vertical
curves. The first is where the sight distance (S) is less than the length of the vertical
curve (L), and the second is where sight distance extends beyond the vertical curve.
Consideration of the properties of the parabola results in the following relationships for
minimum curve length to achieve the required sight distances:
For S < L (the most common situation in practice):
Lm = K.G
where
Lm = minimum length of vertical crest curve (m)
S = required sight distance (m)
h1 = driver eye height (m)
h2 = object height (m)
K = is a constant for given values of h 1 and h2 and stopping sight distance
(S) and therefore speed and surface friction.
For S > L
Lm = 2S - [200.(h10.5 + h20.5)2]/G
Eye height (h1) has been taken as 1.05 m, and object heights h 2 of 0.2 m and 0.6 m
above the road surface. Minimum values of K for crest curves are shown in Table 6-1
and Table 6-2.
Table 6-1: Minimum Values of K for Crest Vertical Curves (Paved Roads)
K for Stopping K for Minimum
Design Speed Sight Distance (g = 0%) Passing Sight
(km/h)
h2 = 0m h2 = 0.2m h2 = 0.6m Distance
25 3 1 1 30
30 5 2 1 50
40 10 5 3 90
50 20 10 7 130
60 35 17 12 180
70 60 30 20 245
80 95 45 30 315
85 115 55 37 350
90 140 67 45 390
100 205 100 67 480
110 285 140 95 580
120 385 185 125 680
(77)
Table 6-2: Minimum Values for Crest Vertical Curves (Unpaved Roads)
K for Stopping K for Minimum
Design Speed Sight Distance Passing Sight
(km/h)
h2 = 0m h2 = 0.2m h2 = 0.6m Distance
25 3 1 1 30
30 5 2 2 50
40 11 6 4 90
50 25 11 8 135
60 45 20 15 185
70 75 35 25 245
80 120 58 40 315
85 150 72 50 350
90 185 90 60 390
100 270 130 88 480
Similar calculations can be carried out based on passing sight distance (Section 4.3.7)
rather than stopping sight distance. High values of K are obtained (Table 6-1 and
Table 6-2) and therefore, to achieve the passing sight distance, the volume of
earthworks required may also be large. Although as much passing sight distance as
possible should be provided along the length of the road, it may be impossible to
achieve passing sight distance over the crest curve itself. Encouraging drivers to
overtake when sight distances have not been fully achieved is dangerous hence
shortening the crest curve in order to increase the lengths of the grades on either side
is a better option.
Where a crest curve and a succeeding sag curve have a common end and beginning of
curve, the visual effect created is that the road has suddenly dropped away. In the
reverse case, the illusion of a hump is created. Either effect is removed by inserting a
short length of straight grade between the two curves. Typically, 60 m to 100 m is
adequate for this purpose.
(78)
6.4 Sag Curves
During daylight hours or on well-lit streets sag curves do not present any problems
concerning sight distances. For such situations it is recommended that sag curves are
designed using a driver comfort criterion of vertical acceleration. A maximum
acceleration of 0.3 m/s2 is often used. This translates into
K > V2/395
6.5 Gradient
Gradient is the rate of rise or fall on any length or road, with respect to the horizontal.
The slope of the grade between two adjacent Vertical Points of Intersection (VPI), is
usually expressed in percentage form as the vertical rise or fall in m/100m. In the
direction of increasing chainage, up-grades are taken as positive and down-grades as
negative.
(79)
The frequency of accidents increases when the speed differential between trucks and
cars increases. If truck speeds decrease by more than about 15 km/h, accidents
increase rapidly hence the ‘critical length of grade’ is the length over which a speed
reduction of 15 km/h occurs. It is important to note that truck speeds in flat terrain
are already lower, on average, than car speeds by, typically, 17 km/h, so another 15
km/h reduction means that the speed differential on uphill grades is of order 32 km/h.
The initial speed of the truck on the grade, which depends on characteristics of the
truck and the gradient of the approach (a downhill approach will allow vehicles to gain
momentum) affect the critical length over which a 15 km/h decrease in speed occurs.
Also some authorities use a different speed reduction (e.g. 20 km/h) to define critical
lengths of grade, hence Table 6-5, which indicates the critical lengths for a vehicle
with a mass/power ratio of 185 kg/kW and one of mass/power ratio of 275 kg/kW,
should be considered as a guide only.
If gradients on which the truck speed reduction is less than 15 km/h cannot be
achieved economically it may be necessary to provide auxiliary (climbing) lanes for the
slower-moving vehicles or passing lanes for the fast-moving vehicles (Sections 5.6 and
6.6). A solution often suggested whereby relief gradients of low gradient are provided
between steeper sections has proved ineffective because truck drivers prefer to
maintain a crawl speed rather than to change gear up and down frequently.
The effect of gradient on traffic flow is not limited to upgrades. Truck drivers
frequently adapt their speeds on downgrades to be of similar values to their speeds on
upgrades for better control and safety.
The maximum ‘absolute’ gradient and maximum ‘desirable’ gradient shown in Table
6-6 are therefore important criteria that greatly affect both the serviceability and cost
of the road. A whole life costing exercise can be an effective method of calculating the
trade-off between construction and maintenance costs and road user costs.
(80)
Table 6-6: Suggested Maximum Gradients for Paved Sections
Maximum Gradient (%), for Paved Sections
Terrain H1 and H2 H3
Desirable Absolute Desirable Absolute
Flat 3 5 4 6
Rolling 5 (1)
7 6 8
Mountainous 7 (1)
9 8 10
Escarpment 7 (1)
9 8 10
Urban 6 (1)
9 8 10
Notes: 1 On freeways a maximum gradient should not exceed 4%
Standards for desirable maximum gradients were set to assure user comfort and to
avoid severe reductions in vehicle speeds. If the occasional terrain anomaly is
encountered that requires excessive earthworks to reduce the vertical alignment to
the desirable standard, or when these earthworks prove to be incompatible with the
surrounding environment in urban areas, an absolute maximum gradient can be used.
Employment of a gradient in excess of the desirable maximum can only be authorized
through a formal Departure from Standard as described in Chapter 14.
(81)
6.6 Climbing Lanes
A climbing lane, also called a truck lane or crawler lane (but not a passing lane), is an
auxiliary lane added outside the continuous lanes on a gradient. It reduces congestion
by removing slower-moving vehicles from the traffic stream. If the traffic reduction is
sufficient, the Level of Service (LOS) (Section 3.2) on the grade will match that on the
preceding and succeeding grades. Road safety is also improved by the reduction of
speed differentials in the through lane. The requirements for climbing lanes are
therefore based on road standard, traffic volume and safety.
A passing lane is also an auxiliary lane that can be provided for the fast traffic on a
gradient, but it is also used on level sections of the route to increase passing
opportunities. Thus, it is used to raise the overall LOS and capacity of the route.
Passing lanes are described in more detail in Section 5.6.
Table 6-7: Traffic Volume and Gradient Criteria Justifying a Climbing Lane
Traffic volume in design hour
Gradient (%)
5 % trucks 10 % trucks
4 630 485
6 470 315
8 380 245
10 325 200
Source: SANRAL. Geometric Design Guidelines.
Any grade which exceeds the critical lengths given in Table 6-5 will normally cause
truck speeds to be reduced by more than 15 km/h. For an existing road a truck speed
profile could be prepared for each direction of flow. It will then be possible to identify
those sections of the road where speed reductions of 15 km/h or more may warrant
the provision of climbing lanes.
An alternative to these general criteria for justifying a climbing lane is to consider
some form of economic analysis. For example, software has been developed that
relates the cost of construction of the climbing lane to the value of time saved by its
provision. The analysis is based on calculation of delay that would ensue over the
design life of the road if the climbing lane was not provided.
(82)
low speeds and lane occupancy of vehicles in the climbing lane. In addition, the
shoulder width may also be reduced, but to not less than 1.5 m. If the shoulders
elsewhere on the road are 3 m wide, the additional construction width required to
accommodate the climbing lane and reduced shoulder is thus only 1.6 m.
In mountainous terrain, where trucks are reduced to crawl speeds over extended
distances and relatively few opportunities for overtaking exist, the cost of construction
of climbing lanes may be prohibitive. An alternative solution is to construct short
lengths of climbing lane (termed passing bays or partial climbing lanes) instead of a
continuous lane over the length of the grade. They are typically 100 to 200 m long.
Because vehicles entering the turnout do so at crawl speeds, the tapers can be short
(20 to 30m long).
(83)
Figure 6-3: Layout of Climbing Lanes
(84)
7 Design Standards for Road Alignments
The main characteristics that determine many of the design specifications are in Table
7-1. There are over 70 standards based on traffic, main functionality and topography.
In addition to these basic standards, additional variations are introduced for:
• High proportions of heavy vehicles on roads of Traffic Classes T3 and T4,
• Numbers of non-motorised traffic,
• Numbers of pedestrians,
*Justification is required for 4- lane standard which may include capacity benefits, safety
considerations, desirable level of service, value of time and effect of tidal flow and the counterfactual
arguments
Standards for both the horizontal and vertical alignments for the various design
classes are shown in Table 7-2 to Table 7-20.
The relevant parameters for calculating the standards in these Tables are described in
Chapters 3, 4, 5 and 6. Use of different parameters, and therefore different standards
requires ANE’s approval.
The design speed on escarpments may be constrained by the severity of the terrain
and the curve radius (plus curve widening) that can be achieved on the hairpin bends.
The Minimum Passing Sight distance allows the passing manoeuvre to be aborted.
(85)
For isolated curves, the minimum horizontal curve radius shown in the Tables should
be increased by 50 %.
(86)
Table 7-3: Design Parameters for (H2-T1-R)
Design Element Unit Flat Rolling Mountain Escarp’t
Design Speed km/h 110 90 70 50
g = 0% m 245 170 110 64
Minimum.
Stopping Sight g = 5% m 285 195 120 68
Distance (2)
g = 10% m 340 230 140 75
(87)
Table 7-4: Design Parameters for (H2-T2-R)
Design Element Unit Flat Rolling Mountain Escarp’t
Design Speed km/h 110 85 65 50
g = 0% m 245 155 97 64
Minimum.
Stopping Sight g = 5% m 285 175 107 68
Distance (2)
g = 10% m 340 205 122 75
(88)
Table 7-5: Design Parameters for (H2-T3-R)
Design Element Unit Flat Rolling Mountain Escarp’t
Design Speed km/h 100 80 60 45
g = 0% m 205 140 85 55
Minimum.
Stopping Sight g = 5% m 237 155 95 58
Distance (2)
g = 10% m 282 182 105 62
% Passing Opportunity % 50 50 25
Maximum Super-elevation % 8 8 8 8
(89)
Table 7-6: Design Parameters for (H3-T3-R)
Design Element Unit Flat Rolling Mountain Escarp’t
Design Speed km/h 90 70 55 40
g = 0% m 170 110 75 45
Minimum.
Stopping Sight g = 5% m 195 120 82 47
Distance (2)
g = 10% m 230 140 90 51
Min. Passing Sight Distance m 275 210 167 135
% Passing Opportunity % 33 50 25 -
SE = 4% m 400 220 121 55
Minimum
Horizontal SE = 6% m 350 190 108 53
Curve Radius(4)
SE = 8% m 320 175 100 50
Transition Curves Required Yes Yes Yes Yes
Max. Gradient (desirable) % 5 3 7 7
Max. Gradient (absolute) % 7 5 9 9
Minimum Gradient % 0.5 0.5 0.5 0.5
Maximum Super-elevation % 8 8 8 8
Min. Crest Vertical Curve -K m/% 67 30 14 5
Min. Sag Vertical Curve – K
m/% 20 12 8 4
Comfort criterion
Min. Sag Vertical Curve - K
m/% 40 25 17 9
Headlights criterion
(90)
Table 7-7: Design Parameters for (H3-T4-R)
Design Element Unit Flat Rolling Mountain Escarp’t
Design Speed km/h 80 60 50 40
g = 0% m 140 85 64 45
Minimum.
Stopping Sight g = 5% m 155 95 68 47
Distance (2)
g = 10% m 182 105 75 50
(91)
Table 7-8: Design Standards H4-T4-R
Design Element Unit Flat Rolling Mountain Escarp’t
Design Speed km/h 70 55 40 40
g = 0% m 110 75 45 45
Minimum.
Stopping Sight g = 5% m 120 82 47 47
Distance (2)
g = 10% m 140 90 50 50
(92)
Table 7-9: Design Parameters for (H1-T1–M)
Design Element Unit Flat Rolling Mountain
Design Speed km/h 100 90 70
g = 0% m 205 170 110
Minimum. Stopping Sight
g = 5% m 237 195 120
Distance
g = 10% m 282 230 140
(93)
Table 7-10: Design Parameters for (H2-T1-M)
Design Element Unit Flat Rolling Mountain
Design Speed km/h 95 80 65
g = 0% m 188 140 97
Minimum.
Stopping Sight g = 5% m 215 155 107
Distance (2)
g = 10% m 255 182 122
(94)
Table 7-11: Design Parameters for (H2-T2-M)
Design Element Unit Flat Rolling Mountain
Design Speed km/h 90 75 60
g = 0% m 170 125 85
Minimum.
Stopping Sight g = 5% m 195 137 95
Distance (2)
g = 10% m 230 160 105
(95)
Table 7-12: Design Parameters for (H2-T3-M)
Design Element Unit Flat Rolling Mountain
Design Speed km/h 80 70 55
g = 0% m 140 110 75
Minimum.
Stopping Sight g = 5% m 155 120 82
Distance (2)
g = 10% m 182 140 90
(96)
Table 7-13: Design Parameters for (H2-T2-U)
Design Element Unit Flat Rolling Mountain
Design Speed km/h 80 65 55
g = 0% m 140 97 75
45Minimum.
Stopping Sight g = 5% m 155 107 82
Distance (2)
g = 10% m 182 122 90
(97)
Table 7-14: Design Parameters for (H2-T3-U)
Design Element Unit Flat Rolling Mountain
Design Speed km/h 75 60 50
g = 0% M 125 85 65
Minimum.
Stopping Sight g = 5% M 137 95 70
Distance (2)
g = 10% M 160 105 75
(98)
Table 7-15: Design Parameters for (H3-T3-U)
Design Element Unit Flat Rolling Mountain
Design Speed km/h 75 60 45
g = 0% m 125 85 55
Minimum.
Stopping Sight g = 5% m 137 95 58
Distance (2)
g = 10% m 160 105 63
Min. Passing Sight Distance m 225 180 145
% Passing Opportunity % 50 33 25
SE = 4% m 260 150 75
Minimum
Horizontal SE = 6% m 225 135 69
Curve Radius(4)
SE = 8% m 205 120 65
Transition Curves Required Yes Yes Yes
Max. Gradient (desirable) % 3 3 7
Max. Gradient (absolute) % 5 5 9
Minimum Gradient % 0.5 0.5 0.5
Maximum Super-elevation % 8 8 8
Min. Crest Vertical Curve -K m/% 37 17 7
Min. Sag Vertical Curve – K
m/% 14 9 6
Comfort criterion
Min. Sag Vertical Curve - K
m/% 28 19 12
Headlights criterion
(99)
Table 7-16: Design Standards for H3-T4-U
Design Element Unit Flat Rolling Mountain
Design Speed km/h 65 50 45
g = 0% m 97 65 55
Minimum.
Stopping Sight g = 5% m 107 70 58
Distance (2)
g = 10% m 122 75 63
Min. Passing Sight Distance m 195 155 135
% Passing Opportunity % 50 33 25
SE = 4% m 185 95 55
Minimum
Horizontal SE = 6% m 162 85 50
Curve Radius(4)
SE = 8% m 147 80 50
Transition Curves Required Yes Yes Yes
Max. Gradient (desirable) % 3 5 7
Max. Gradient (absolute) % 5 7 9
Minimum Gradient % 0.5 0.5 0.5
Maximum Super-elevation % 8 8 8
Min. Crest Vertical Curve -K m/% 23 10 5
Min. Sag Vertical Curve – K
m/% 11 7 4
Comfort criterion
Min. Sag Vertical Curve - K
m/% 22 14 9
Headlights criterion
(100)
Table 7-17: Design Standards H4-T4-U
Design Element Unit Flat Rolling Mountain
Design Speed km/h 60 50 40
g = 0% m 85 65 45
Minimum.
Stopping Sight g = 5% m 95 70 47
Distance (2)
g = 10% m 105 75 50
Minimum SE = 4% m 150 95 55
Horizontal SE = 6% m 135 85 50
Curve Radius(3)
SE = 8% m 120 80 50
Transition Curves Required Yes Yes Yes
(101)
Table 7-18: Design Standards for Unpaved H3-T3 and H3-T4 Rural
Design Element Unit Flat Rolling Mountain Escarp’t
Notes
(102)
Table 7-19: Design Standards for Unpaved H3-T3 and H3-T4 Urban
Design Element Unit Flat Rolling Mountain Escarp’t
Notes
1 If the number of CEFs is high the width should be increased to 10.0 m.
2 On hairpin bends the minimum radius may be reduced to a minimum of 15m.
3 Cross-fall can be reduced to 4% where warranted (e.g. poor gravel - for safety,
low rainfall).
4 In some circumstances in very flat terrain this can be reduced to 0.3%.
(103)
Table 7-20: Design Standards for Unpaved H4-T4 Rural and Urban
Design Element Unit Flat Rolling Mountain
Design Speed km/h 60 50 40
g = 0% m 85 65 45
Minimum.
Stopping Sight g = 5% m 95 70 47
Distance (2)
g = 10% m 105 75 50
Minimum SE = 4% m 150 95 55
Horizontal SE = 6% m 135 85 50
Curve Radius(3)
SE = 8% m 120 80 50
Transition Curves Required Yes Yes Yes
(104)
8 Phasing of Horizontal and Vertical Alignments
Phasing of the vertical and horizontal curves of a road implies their coordination so
that the line of the road appears to a driver to flow smoothly, avoiding the creation of
hazards and visual defects. It is particularly important in the design of high-speed
roads on which a driver must be able to anticipate changes in both horizontal and
vertical alignment well within the safe stopping distance. It becomes more important
with small radius curves than with large.
Defects may arise if an alignment is mis-phased. Defects may be purely visual and do
no more than present the driver with an aesthetically displeasing impression of the
road. Such defects often occur on sag curves. When these defects are severe, they
may create a psychological obstacle and cause some drivers to reduce speed
suddenly. In other cases, the defects may endanger the safety of the user by
concealing hazards on the road ahead. A horizontal curve hidden by a crest curve is an
example of this kind of defect.
(105)
Hidden Dip (Roller Coaster) Profile
8.3 Crest and Sag Curve Have a Common Beginning and End
Where a crest curve and a succeeding sag curve have a common beginning and end,
the visual effect created is that the road has suddenly dropped away. In the reverse
case, the illusion of a hump is created. Either effect is removed by inserting a short
length of straight grade between the two curves. Typically, 60 m to 100 m is adequate
for this purpose.
(106)
Figure 8-2 illustrates the appearance of ‘humps’ when short crests and sags are
included on a long horizontal curve. These should be avoided. Maintaining a constant
grade is the preferred option.
(107)
component. Eliminating the crest curve in advance improves the appearance, as
shown in Figure 8-3.
Eliminating the Crest Curves in Advance and Following the Sag Curve.
(108)
8.5 Distorted Alignment
A common fault is illustrated in Figure 8-4. The roadway is often unnaturally curved to
cross a small stream at right angles. The advantages in the aesthetics alignment of a
skew crossing often far outweigh the savings deriving from a square crossing.
(109)
8.6 Broken Back Curves
Figure 8-5 illustrates a broken-back curve which is two curves in the same direction
separated by a short tangent. Such a combination is unacceptable. Also a ‘broken
plank’ grade line, where two long grades are connected by a short sag curve, is
equally unacceptable.
The advantages of using a single radius curve throughout are illustrated in Figure 8-5.
Broken-back Curve
(110)
8.7 Sag curve at the start of a Horizontal Curve
A sag curve at the start of a horizontal curve has the effect of enhancing the sharp
angle appearance as shown in Figure 8-6, and should be avoided. Raising the
preceding grade will move the sag curve downstream. A longer radius on the
horizontal curve would cause it to start earlier. Applying both remedial measures
should result in a better phasing of the horizontal and vertical alignments.
(111)
8.9 Start of Horizontal Curves not Visible
Figure 8-8 shows the effect when the start of a horizontal curve is hidden by an
intervening crest and the continuation of the curve is visible in the distance. The road
appears disjointed.
(112)
change of direction is consequently greater. If a vertical sag curve overlaps a
horizontal curve, an apparent kink may be produced.
The defect may be corrected in both cases by completely separating the curves. If this
is uneconomic, the curves must be adjusted so that if the horizontal curve is of short
radius, they are coincident at both ends, or if the horizontal curve is of longer radius
they need be coincident at only one end.
8.12 Both Ends of the Vertical Curve Lie on the Horizontal Curve
If both ends of a crest curve lie on a sharp horizontal curve, the radius of the
horizontal curve may appear to the driver to decrease abruptly over the length of the
crest curve. If the vertical curve is a sag curve, the radius of the horizontal curve may
appear to increase. The corrective action is to make both ends of the curves
coincident, or to separate them.
(113)
Figure 8-9: Well-coordinated Crest and Horizontal Curves
(114)
clearance of up to 0.1 m may be provided. Light superstructures (e.g. timber, steel
trusses, steel girders, etc) over roadways should have a clearance height of at least
5.3 m. See ANE’s Bridge Design Manual for further reference.
Underpasses for pedestrians and bicycles should not be less than 2.4 m. For cattle and
wildlife, underpasses must be designed as the normal height of the actual animal plus
0.5 m, and for horse-riding the clear height must be not less than 3.4 m. Bridges
above railways must have a clearance height of at least 6.1 m - if not otherwise stated
- to facilitate possible future electrification.
Over existing pipe culverts and box culverts, the roadway elevation cannot be less
than as indicated in the Drainage Design Manual, 2017.
(115)
9 Design of At-Grade Intersections
9.1 Introduction
An intersection, or junction, is the area where two or more roads join. There are five
main types of intersection distinguished by the amount of traffic that they can carry
satisfactorily and by the method and degree of control of the traffic that they embody
(Table 9-1 and Table 9-2).
Once designed and constructed, almost all will be unique. This chapter deals with basic
principles and examples of some of the popular options.
The principal characteristics of intersections are that vehicles, pedestrians and non-
motorised traffic travelling in many directions must share a common area, often at the
same time. The mitigation of the resulting conflicts is therefore a major objective of
intersection design.
Good intersection design allows through movement and transitions from one route to
another with minimum delay and maximum safety. Thus, the layout and operation of
the intersection should be obvious to vehicle drivers, with good visibility between
conflicting movements.
Intersections for the higher traffic levels are expensive and, like bridges and other
major structures, should be designed for at least 30 years. Therefore, a careful
assessment of likely future traffic flows is required to ensure that a structure will
perform satisfactorily in future.
(116)
Junction islands shaped and located to direct traffic
movement (Figure 9-4 and Figure 9-5).
An at-grade junction of two roads, at which the
Skew or Y minor road approaches the major road at an
junction oblique angle and terminates at the junction
(Figure 9-6).
For low to They provide minimum delays at lower flows and
medium traffic are safer than priority junctions. They require
flows, primarily attention to pedestrian movements and the
Roundabouts.
for urban and accommodation of slow-moving traffic.
metropolitan Roundabouts are discussed in Chapter 10.
conditions
Intersections As for priority As for priority junctions but for higher traffic flows
where traffic is intersections and more complex conditions such as additional
controlled by routes
traffic signals
Grade separated interchanges are expensive and
used only for high flows, but they result in
Grade-
minimum delays. Pedestrian movements need
Separation
special consideration. These interchanges are
dealt with in Chapter 11.
(117)
At existing rural and urban junctions upgrading a simple junction to provide a right
turning facility should always be considered where the minor road flow exceeds 500
vehicles 2-way AADT, a right turning accident problem is evident, or where vehicles
waiting on the major road to turn right inhibit the through flow and create a hazard. A
right turn from the main road is a dangerous manoeuvre hence different junction
designs are used to cater for increasing traffic levels. The use of partial channelisation,
full channelisation, ghost islands, single lane duelling and traffic signal control are all
techniques used to provide safe right turn facilities for increasing traffic flows. These
are illustrated in Figure 9-2, Figure 9-3, Figure 9-5 and Figure 9-6.
Where the flow levels are not large enough to justify the provision of a right turning
facility, and a right turning problem remains, a nearside passing bay should allow
through vehicles to pass the vehicles waiting to turn right, albeit at a reduced speed.
Intersections with more than four arms are not recommended. Where more complex
layouts involving the intersection of four or more roads are encountered, these should
be simplified by redesign to two junctions, or a roundabout should be used.
Experience in some countries has shown that converting crossroads into roundabouts
can reduce accident costs by more than 80 per cent.
T-intersections include the staggered T-intersection (Figure 9-4 and Figure 9-5), which
caters for cross-traffic. Staggered T-intersections are often the result of a realignment
of the minor route to improve the angle of the skew of the crossing.
When traffic on the main road is quite high and a staggered T-intersection is required,
there are two options namely the ‘turn left then turn right’ stagger and the ‘turn right
then turn left’ stagger. Both options have two conflict locations where a vehicle must
merge with one stream and cross the other stream at the same location (i.e. the
driver must identify two gaps at the same time) but the ‘turn right then turn left
stagger’ is preferred because the ‘turn left then turn right’ stagger might require an
auxiliary lane in the main road to store vehicles before they can turn across the
opposite stream of the main road into the minor road. In the case of the ‘right turn
then left turn’ option any required storage occurs in the minor roads.
The basic designs are modified for higher traffic flows and for higher traffic speeds.
Additional lanes are provided and traffic control by means of additional channelisation
and/or traffic signals (Figure 9-7) are added.
(118)
Figure 9-2: Partly Channelised T-Intersection with Ghost Islands
(119)
Figure 9-5: Partly Channelised Staggered Intersection with Ghost Islands
(120)
Figure 9-6: Skew or Y Intersection with Ghost and Channelising Islands.
9.2.3 Roundabouts
The key feature of roundabouts is that traffic entering the roundabout must give way
to circulating traffic already on the roundabout. Ideally the minor road incoming traffic
should be at least 10-15% of the total incoming traffic. Roundabouts are discussed in
Chapter 10.
(121)
geometrical layout of an intersection is based and greatly affects the safety and
efficiency of the intersection and the construction cost. For safety reasons, it should
never be less than 20 km/h lower than the average design speed for the major road
(122)
9.4 Factors Affecting Selection of Intersection Type and Design
9.4.1.1 Visible
i) Intersections should not be located on horizontal curves with radii less than
those indicated in Table 9-3;
ii) Intersections should not be located on gradients steeper than 3%. The
gradient is more critical on the minor road than on the major road because
all vehicles on the minor road have to stop or yield;
iii) In a collision between vehicles, either or both may leave the road. Therefore
intersections should not be located on high fills;
iv) The intersection should be sited so that the major road approaches are
readily visible;
v) Early widening of the intersection approaches;
vi) Provision of visibility splays which ensure unobstructed sight lines to the left
and right along the major road;
vii) Use of traffic islands in the minor road to emphasize a ‘yield’ or ‘stop’
requirement;
viii) Use of medians;
ix) Use of early and eye-catching traffic signs;
x) Optical guidance by landscaping and the use of road furniture, especially
where an intersection must be located on a crest curve;
xi) Suitable pavement tapers and transitions;
xii) The angle of intersection of the major and minor roads should be between
70 and 110 degrees;
xiii) The use of single lane approaches is preferred on the minor road in order to
avoid mutual sight obstruction from two vehicles waiting next to each other
to turn or cross the major road.
9.4.1.2 Comprehensible
i) The right of way should follow naturally and logically from the intersection
layout;
ii) The types of intersections used throughout the whole road network should be
as similar as possible;
iii) The provision of optical guidance by the use of clearly visible kerbs, traffic
islands, road markings, road signs and other road furniture.
(123)
9.4.1.3 Providing easy manoeuvrability
(i) All traffic lanes should be of adequate width for the appropriate vehicle
turning characteristics. To accommodate truck traffic, turning radii shall be
at least 15 m. In restricted urban areas this could be reduced to an
absolute minimum of 12m;
(ii) The edges of traffic lanes should be clearly indicated by road markings;
(iii) Traffic islands and kerbs should not conflict with the natural vehicle paths.
(124)
• Multiple approaches • Addition of exclusive turn lanes
• Poor lighting • Installation or improvement of lighting
• Narrow lanes • Use of channelisation
• Poor drainage • Improved drainage paths
• Low surface friction • Improved surface skid resistance
• Steep grades at intersections • Avoid building on a gradient greater
than 3 % (stopping sight distances
increase quickly as down gradient
increases)
(125)
It may be necessary to modify the alignment of either the major or the minor road, or
both, to ensure that adequate sight distances are available. If this is not possible, the
options available to the designer are to:
• Relocate the intersection;
• Provide appropriate Stop control; or
• Provide a Jug-handle (also called a Quarter link) interchange, as shown in
Figure 11-4.
9.4.4 Capacity
Figure 9.8 illustrates the relationship between recommended intersection type and
traffic on the major and minor roads and traffic speed on the major road based on
safety considerations. Traffic is expressed as AADT. Figure 9-8a (design speed
50km/h) is primarily for urban interchanges, Figure 9-8b (80km/h) is for metropolitan
or rural interchanges and Figure 9-8c (100km/h) is for rural interchanges.
The traffic flows are not constant throughout the day. Significant peaks occur at
certain times and interchange design must cater for peak flows to prevent congestion
and minimise traffic delays.
50 km/h
7000
6000
Minor Road Approaching AADT
5000
Select a controlled intersection
4000
Consider using a
3000 controlled
intersection
2000
1000
Select a priority intersection
0
0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000 11000 12000 13000
9-8(a)
(126)
80 km/h
4000
3500
1500
1000
0
0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000 11000 12000 13000
9-8(b)
100 km/h
3500
3000
Minor Road Approaching AADT
2500
1500
Consider using a
1000
controlled intersection
500
Select priority intersection
0
0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000 11000 12000
Major Road
Approaching AADT (total both directions)
9-8(c)
(127)
The desired level refers to a degree of saturation (actual traffic flow/capacity) of 0.5.
The acceptable level refers to a degree of saturation of 0.7.
Measuring and forecasting traffic flows and capacity analysis for major intersections is
a specialised subject and designers should refer to the Highway Capacity Manual for
details.
(128)
Figure 9-9 (c)
Ca = s x g/c
where
Ca = capacity (PCU/h)
s = saturated flow rate (PCU/h)
g/c = the ratio of useful green time to signal cycle time.
(129)
• On-street parking.
• Pedestrian activity.
• Type and phasing of signals.
The critical factors are the total number of lanes and the need for exclusive turning
lanes at each approach.
Examples of signal-controlled intersections are shown in Figure 9-10 and Figure 9-11.
Note the pedestrian crossings.
(130)
Figure 9-11: Signal-Controlled Crossroads with a Staggered Pedestrian
Crossing and Refuge.
(131)
9.4.6 Design Speed
The Intersection Design Speed, which is the principal design parameter upon which
the geometrical layout and capacity of an intersection is based, is the design speed of
the major road in the vicinity of the intersection. This speed is not the design speed of
the road because drivers tend to slow down when approaching intersections, even
when they are travelling on the major road. The selection of the Intersection Design
Speed greatly affects both the safety and efficiency of the intersection and the
construction cost. For safety reasons, the Intersection Design Speed should never be
less than 20 km/h lower than the design speed for the major road.
The time available to carry out a manoeuvre depends on the speed of traffic in the
lanes to be crossed. Models have been developed for carrying out these calculations
but require many assumptions and they are not reliable. The best information is
obtained from empirical data.
(132)
9.4.7.2 Sight Triangles
Each quadrant of an intersection should contain a triangular area free of obstructions
that might block an approaching driver’s view of potentially conflicting vehicles. These
specified areas are known as clear sight triangles. The dimensions of the legs of the
sight triangles depend on the design speeds of the intersecting roadways and the type
of traffic control used at the intersection. Two different forms of sight triangle are
required. The approach triangle must have sides with sufficient lengths on both
intersecting roadways such that drivers can see any potentially conflicting vehicle in
sufficient time to slow, or to stop if need be, before entering the intersection. For the
departure sight triangle, the line of sight described by the hypotenuse of the sight
triangle should be such that a vehicle just coming into view on the major road will, at
the design speed of this road, have a travel time to the intersection corresponding to
the gap acceptable to the driver of the vehicle on the minor road. Details of sight
triangles for different situations are described in Appendix C.
Practical sight distances are summarised in Table 9-8 and Table 9-9. They are more
conservative than the values obtained using Appendix C which are based on NCHRP
Report 383. However, when the gradients on any of the legs exceed 3% and when
multiple lanes are involved (i.e priority junctions only), prudent use of Appendix C
should be made, and conservative options should be used.
9.4.9 Functionality
The functionality of the road is the key to identifying the most appropriate designs.
Table 1.2 defines over 60 design standards covering many aspects of functionality but
additional considerations concerning traffic composition are also included in Chapter 3.
Thus, design of intersections must be flexible, and compromises must be made in
many circumstances.
9.4.10 Economy
The cost of interchanges is always an important factor. Provided that safety is not
compromised the lowest cost option may be acceptable but it should be born in mind
that interchanges, especially the large ones and those constructed in urban areas
where space is restricted, need to be designed for long design lives (at least 30 years)
and for future traffic that may not be easy to predict accurately. A long-term transport
plan is required if the network is to develop logically and economically.
(133)
9.5 Selection of Intersection Type
(134)
Table 9-10: Intersection Selection Based on Traffic Flow (1000 vpd)
Type of Intersection
Traffic
Flow on Traffic Flow on Minor Road
Major Road
(<) (<) (>)
Range
Less than Less than Greater than
Roundabout/ Grade
Simple Priority
or Signalised Separation
<10 1.2
<10 1.2 - 7.0
10 - 12 7.0 7.0 - 12 >12
12 - 14 6.5 6.5 - 11 11
14 - 16 5.0 5.0 - 10 10
16 - 18 4.0 4.0 – 9.5 9.5
18 - 20 3.5 3.5 – 9.0 9.0
20 - 22 3.5 3.5 – 8.0 8.0
22 - 24 3.0 3.0 – 7.5 7.5
24 - 26 2.5 2.5 – 6.5 6.5
26 - 28 2.5 2.5 – 6.0 6.0
28 - 30 2.0 2.0 – 5.0 5.0
30 - 32 2.0 2.0 – 4.5 4.5
32 - 34 2.0 2.0 – 4.0 4.0
34 - 36 2.0 2.0 – 3.0 3.0
36 - 38 2.0 2.0
38 - 40 2.0 2.0
(135)
7 Assemble design elements
8 Assess key geometric parameters
Checking that it offers adequate safety and capacity for the
9 predicted traffic manoeuvres. If not review a different
intersection type
10 Determine requirements for connecting roads
11 Check that an effective signing system can be provided
12 Carry forward to appraisal stage
(136)
• channelisation can be used to restrict turning movements.
LoS and driver perception are both affected by the spacing of intersections. In certain
cases, it may be necessary to limit the number of intersections for reasons of safety
and serviceability.
(137)
9.7.1 Horizontal and Vertical Alignment
The horizontal and vertical alignments through and approaching an intersection are
critical features. Simple alignment design should enable early recognition of the
intersection and timely focus on the intersecting traffic and manoeuvres that must be
prepared. The following are specific operational requirements at intersections:
• The alignments should not restrict the required sight distance;
• The alignments should allow for the frequent braking and turning associated
with intersections; and
• The alignments should not require a driver’s attention to be detracted from the
intersection manoeuvres and conflict avoidance .
The intersection should not be over a crest, in a sag or on a curve. If there is no
choice, the horizontal curve radii at intersections should not be less than the radii
shown in Table 9-3. For high-speed roads with design speeds in excess of 80 km/h,
approach gradients should not be greater than -3 %. For low-speed roads in an urban
environment this can be increased to -6 %.
(138)
carriageway roads where very little extra construction cost is involved. Examples are
illustrated in the Figure 9-2, Figure 9-5, and Figure 9-6.
9.7.5 Channelisation
A traffic island is a defined area between traffic lanes for the control of vehicle
movements. Traffic islands are used for ‘channelling’ traffic to manage the conflicts
that are inherent in any intersection by guiding vehicles safely through the intersection
area from an approach leg to the selected departure leg.
There are various aspects of good channelisation:
• Traffic streams should cross at close to right angles and merge at flat angles.
• The islands provide refuges for pedestrians and the handicapped where
appropriate.
• High priority flows should have the greater degree of freedom to manoeuvre.
(139)
prevent overtaking and excessive speeds through the conflict zones. It is formed by
widening the major road to provide a central reservation, a right turning lane and
space for vehicles waiting to turn right from the major road into the minor road. A
limiting factor is the left-hand sideways visibility from the driver's seat, which can be
very restricted in some cabs and leaves the driver with no option but to make the
manoeuvre in one stage. It usually has a traffic island in the minor road. In urban
areas this would normally be kerbed to provide a refuge for pedestrians.
Typical island shapes are illustrated in Figure 9-14. (Note traffic control signals are
not shown in the Figures).
(140)
Drivers tend to find an archipelago of small islands confusing and are liable to select
an incorrect path through the intersection area. As a general design principle, a few
large islands are preferred to several small islands.
The designer should bear in mind that islands are hazards and should be less
hazardous than whatever they are replacing. Islands should not be less than 5 m2
in area to ensure that they are easily visible to approaching drivers and, where
necessary, additional guidance should be given by carriageway markings in
advance of the nose supplemented, if necessary, by speed humps.
Islands may be kerbed, painted (see Ghost Islands Section 9.6.3) or simply non-
paved. Kerbed islands provide the most positive traffic delineation and are normally
used in urban areas to provide some degree of protection to pedestrians and traffic
control devices. The island kerbs should be offset a minimum of 0.3 m from the edge
of through-traffic lanes even if they are mountable. Painted islands are usually used in
suburban areas where speeds are low (in the range of 50 km/h to 70 km/h) and space
is limited.
Traffic islands bordered by raised kerbs should not be used in the major road. In rural
areas, kerbs are not common and, at the speeds prevailing in these areas, typically
100 km/h or more, they are a potential hazard. If it is necessary to employ kerbing at
a rural intersection, the use of mountable kerbing should be considered.
As an additional safety measure, a kerbed island should always be preceded by a
painted island with oblique parallel line (chevrons) markings limited by continuous
longitudinal lines.
Non-paved islands are defined by the pavement edges and are usually used for large
islands at rural intersections. These islands may have delineators on posts and may be
landscaped.
A typical triangular island is illustrated in Figure 9-15. The approach ends of the island
usually have a radius of about 0.6 m as shown and the offset between the island and
the edge of the travelled way is typically 0.6 m to 1.0 m to allow for the effect of
kerbing on the lateral placement of moving vehicles. Where the major road has
shoulders, the nose of the island is offset about 1.0 m from the edge of the usable
shoulder. The side adjacent to the through lane is tapered back to terminate at the
edge of the usable shoulder, thus offering some guidance and redirection. A kerbed
cross-section on the major road suggests that the nose of the island should be offset
by about 1.6 m from the edge of the travelled way, with the side adjacent to the
through lane being tapered back to terminate 0.6 m from the edge of the through
lane.
(141)
Figure 9-15: Typical Triangular Island
Generally, two basic layouts for traffic islands and minor road widening will be used
but each junction should be carefully checked to ensure that adequate clearance is
given for the types of vehicles expected to use the junction.
9.7.6 Medians
Median islands are discussed in detail in Section 3.11. The general layout of median
openings at intersections is normally dictated by wheel-track templates. However,
median openings should not be shorter than:
• The surfaced width of the crossing road plus its shoulders.
• The surfaced width of the crossing road plus 2.5 m (if kerbing is provided).
• 12.4 m.
A further control on the layout of the median opening is the volume and distribution of
traffic passing through the intersection area. If the median is wide enough to
accommodate them, it may be advisable to make provision for speed-change and
storage lanes. The additional lanes reduce the width of the median at the point where
the opening is to be provided and thus influence the median end treatment.
The median end treatment is determined by the width of the median. Where the
median is 3 m wide or less, a simple semicircle is adequate. For wider medians, a
bullet nose end treatment is recommended. The bullet nose is formed by arcs dictated
by the wheel paths of turning vehicles and an assumed nose radius of 0.6 to 1.0 m.
This results in less intersection pavement area and a shorter length of opening than
the semi-circular end.
Above a median width of 5 m, the width of the minor road controls the length of the
opening. A flattened bullet nose, using the arcs as for the conventional bullet nose but
with a flat end as dictated by the width of the crossing road, is recommended. These
end treatments are illustrated in Figure 9-16.
(142)
The bullet nose and the flattened bullet nose have the advantage over the semi-
circular end treatment that the driver of a turning vehicle has a better guide for the
manoeuvre for most of the turning path. Furthermore, these end treatments result in
an elongated median, which provides a better refuge area for pedestrians crossing the
dual carriageway road.
(143)
the centreline of the minor road. For the sake of consistency, the radius of the nose
should be of the order of 0.6 m.
The balance of the shape of the island is defined by the turning paths of vehicles
turning both from the minor road to the major road and from the major road to the
minor.
Notes:
1. RC = Central radius dependent upon vehicle turning characteristics (minimum turning
radius) recommended value: 15m.
2. The ratio R1:R2:R3 to be 2:1:3 and the recommended value for R2 is 12.0m.
3. W1 is equal to the minor road lane width but shall not be less than 3.0m.
4. W2 is 5.5m (excluding offsets to raise kerbs)
5. For detail of major road widening, see Section 9.7.9
(144)
Notes:
1. RC = Central radius dependent upon vehicle turning characteristics.
2. The ratio R1:R2:R3 to be 2:1:3 and R2 will be dependent on vehicles turning characteristics
and proportion of large vehicles. Recommended range for R2 is 8.0-12.0m.
3. W1 is equal to the minor road lane width.
4. W2 is dependent upon vehicle turning characteristics.
(145)
If the intersection is located on a crest or in a horizontal curve it is advisable to
lengthen the island because this will make the intersection more visible to approaching
traffic.
Excessive intersection widths should be avoided in order to discourage high speeds
and overtaking.
Where intersecting roadways have shoulders or sidewalks, the shoulder of the main
road should be continued through the intersection. Lane widths should be 3.7 m for
through lanes and 3.6 m for turning lanes. Where conditions are severely constrained,
lane widths as low as 3.3 m can be considered provided that approach speeds are
below 80 km/h. In constricted urban conditions on low speed-roadways, lane widths of
3.0 m should be the minimum adopted.
All traffic lanes should be of adequate width and radius for the appropriate vehicle
turning characteristics. To accommodate truck traffic, turn radii must be a minimum of
12 m.
Offsets from the edge of a turning roadway to kerb lines should be 0.6 to 1.0 m.
The edges of traffic lanes should be clearly indicated by road markings.
(146)
Figure 9-19: Conditions Requiring a Right Turn Lane
The length of the left turn lane including the taper, measured as shown in the Figure,
is related to design speed as indicated in Table 9-13. On up-hill gradients these
distances are shorter and on down-hill grades they are longer. The increase or
decrease in length is linear and is 5% for every 1% change in grade. Thus, for
example, for a down-hill grade of 4 % the length should be increased by 20%.
(147)
Table 9-13: Length of Left Turn Lane
Main Length of deceleration section (LD)
Length of
road
diverging Exit control speed (km/hr)
design
(taper)
speed
(LT) (m) 0 40 50 60 70 80 90 100
(km/hr)
60 65 70 40 25 - - - - -
70 75 95 60 50 25 - - - -
80 80 125 90 75 55 30 - - -
90 85 155 125 110 85 60 30 - -
100 90 190 160 145 125 100 70 35 -
110 100 235 200 190 165 140 110 75 40
120 110 280 245 230 210 180 155 120 85
130 115 325 290 275 255 230 200 170 135
The actual entrance or exit lane from the major road to the minor road can take the
form of a taper or a parallel lane. A taper is preferred. Table 9-14 indicates the taper
rates for exit lanes.
The width of the major approach lane must be the same as the width of the traffic
lanes.
(148)
acceleration lanes for different speed differentials are as shown in Table 9-15.
Acceleration also takes place on the taper, which is thus included in the overall length
of the acceleration lane.
The designs are incorporated into the Standard Detailed Drawings for all intersections
on trunk and link roads.
Provision of right turn lanes can be made for the major road. On single carriageway
roads a painted central reserve must always be used, and traffic control is also
necessary (not shown in the Figure). In order to accommodate a right turn lane, the
carriageway must be widened to provide the required width (Section 9.7.9). The
widening must be designed so that the through lanes are given smooth and optically
pleasing alignments. The width of the through lanes at the intersection must be the
same as the approach lanes.
The widening must be provided by the deviation of both through lanes from the
centreline. This should be achieved by introducing a taper of 100 m length at the
beginning and end of the widening or by introducing a horizontal curve of large radius
as described in Section 9.7.9.
(149)
Figure 9-21: Layout for Right Turn Lane, Single Carriageway
(150)
(a) Simple parallel merge with offside lane drop showing typical lengths
(151)
Three traffic conditions must also be considered:
The lengths of turning roadways at intersections are normally short, so that design for
Case 1 operation is sufficient. Even in the absence of traffic counts, there will usually
be enough trucks in the traffic stream to warrant consideration hence Condition B is
normally adopted for design purposes. Widths of turning roadway for the various cases
and conditions are shown in Table 9-17. The radii in the Table refer to the inner edge
of the pavement. The values supersede any value quoted elsewhere that do not
include provision for large semi-trailers.
Figure 9-24 shows the design of a typical cross road intersection illustrating turning
sections, channelisation islands, deceleration lanes, tapers, medians and mountable
kerbs.
(152)
Figure 9-24: Typical Cross-road Intersection showing all Elements
(153)
Figure 9-25: Typical Access
(154)
Stage 1 2 3
The signal control can work on fixed or vehicle-actuated timings which adapt to traffic
conditions by means of vehicle detectors. Vehicle actuated (i.e. demand-responsive)
signals are much more efficient and drivers are more likely to comply with them.
On a vehicle-actuated system each stage has a minimum and maximum green time.
There should always be an inter-green period (i.e. a short period when no green
signals are showing) between conflicting stages to allow for safe stage changes. The
length of the inter-green period depends on the size of the intersection, the speed
limit and whether pedestrians and cyclists are being accommodated. For details of
traffic signal management, the reader should consult FHWA (2008), Traffic Signal
Timing Manual, Report HOP-08-024.
(155)
Table 9-18: Criteria for Traffic Signalisation of Cross Walks
Pedestrians/Cyclists
Speed Limit Traffic Volume
(Number in maximum
(km/h) (ADT)
hour)
5000 – 8000 >30
30
>8000 >20
5000 – 8000 >20
40
>8000 >10
5000 – 8000 >20
50
>8000 >10
60 2000 >20
70 1500 >20
The capacity analysis should be based on expected traffic volumes during the design
hour, normally both morning and evening peaks.
9.8.2 Visibility
Each traffic lane must have clear vision of at least one primary signal head associated
with its particular movement from the desirable stopping sight distance (70m at 50
km/h and 110m at 70 km/h). It is also important that the desirable stopping sight
distance is available to all traffic entering the queue estimated from the capacity and
traffic flow calculations. Warning sign for traffic signals must be used where the
visibility is impaired.
The intersection inter-visibility zone is defined as the area bounded by measurements
from a distance of 2.5 m behind the stop-line extending the full carriageway width for
each arm, as indicated in Figure 9-27. Designers should aim to achieve the greatest
level of inter-visibility within this zone to permit manoeuvres to be completed safely
once drivers, cyclists and pedestrians have entered the zone.
Signalisation may be an appropriate accident countermeasure for higher volume
intersections with restricted sight distance and a history of sight-distance related
accidents. However, traffic signals may fail from time to time. Furthermore, traffic
signals at an intersection are sometimes placed on two-way flashing operation under
off-peak or night time conditions. To allow for either of these eventualities, the
appropriate departure sight triangles as set out for Case B in Appendix C, should be
provided for the minor-road approaches to ensure a minimum level of safety when the
signals are out of order.
(156)
Figure 9-27: Inter-visibility Zone without Pedestrian Crossing
Minimum design measurements for a right turn with a ghost island are shown in
Figure 9-29.
(157)
7.5 m 1
direct 10
taper ghost island taper
Filter lanes for left turning vehicles can be signalised or uncontrolled (i.e. give way
signs and markings). They can be used when left turn manoeuvres for large vehicles
are required (Figure 9-30). Uncontrolled left turn lanes improve the efficiency of the
traffic signal control, as inter-greens can be decreased, especially at high left turn
volumes. Uncontrolled traffic should be separated with a triangular separation island.
taper
set back
Figure 9-30: Left Turn Filter Lane with Taper to Facilitate Large Vehicles
If left turn filter lanes are used, a consistent design approach should be adopted for
ease of understanding. Uncontrolled filter lanes can be confusing for pedestrians.
Uncontrolled and controlled pedestrian crossings should not be mixed within the same
intersection.
The number of straight-ahead entry and exit lanes should be balanced in order to
reduce conflicts caused by traffic merging or diverging within the intersection (Figure
9-31). Lane drops should take place beyond the visibility zone over a distance of at
least 100 m for a single lane reduction. The lane drop may be carried out on either the
nearside or offside dependant on traffic condition
(158)
Figure 9-31: Lane Drop Design Principles
Minor Minor
road road
1
T
R
Major A
T road R
Major
1
road
B
R T A B
Urban 10 5 30 30
Rural* 15 10 25 25
It is also essential to ensure that adequate turning radii are provided for the swept
paths of all types of vehicles using the intersection as shown in Figure 9-33. Swept
paths must be checked for all permitted turning movements to control locations of
traffic islands, signals etc. The example on the left of the Figure indicates that there is
an unnecessary taper; the example on the right indicates that the stop-line must be
set back.
(159)
Simple swept path templates, if available at the correct scale, can be used for
checking whether semi-trailers can negotiate intersections, but the use of specialist
computer software gives a more accurate simulation.
Nosings of central reserves and pedestrian refuges should be set back a minimum of
1.5 m, measured from a line extended from the edge of the intersecting roads.
Minimum clearances should be provided and must be controlled if the super-elevation
is over 2.5 %.
9.8.5 Signals
There should be at least two signals visible from each approach, usually comprising a
primary and a secondary signal, and stop-lines (Figure 9-34) (see SATCC Road Traffic
Signs Manual). Where separate signalling of turning movements is used this advice
applies to the approach lane(s) associated with each turning movement. One signal
post can display information for more than one turning movement.
The primary signal should be located to the left of the approach a minimum of 1 m
beyond the stop line and in advance of crossing marks for pedestrians, if any. The
secondary signal should be located within a 30-degree angle on a maximum distance
of 50 m with priorities as shown in Figure 9-34.
(160)
Figure 9-34: Signal Location Advice
The following alternative designs may be used where there are approaches with three
or more traffic lanes and protected right turns. The primary right turn arrow is
mounted on the exit separation island, Figure 9-35a, or on an extra separation island
in the approach, Figure 9-35b.
ALT 1 ALT 2
(161)
The standard traffic signal head width is 300 mm (with 450 mm as oversize), which
results in island width requirements, including clearances, of 0.3 to 0.6 m or from 0.9
m to 1.65 m. Wider islands can be needed if they are also to serve as pedestrian
refuges.
(162)
9.9 Checklist for Intersection Design
The following is a checklist of factors that need to be considered in the design of
intersections.
❑ Will the intersection be able to carry the expected/future traffic levels without
becoming overloaded and congested?
❑ Have the traffic and safety performance of alternative intersection designs been
considered?
❑ Is the route through the intersection as simple and clear to all users as
possible?
❑ Is the presence of the intersection clearly evident at the decision sight distance
to approaching vehicles from all directions?
❑ Are warning and information signs placed sufficiently in advance of the
intersection for a driver to take appropriate and safe action given the design
speeds on the road?
❑ Are warning and information signs visible and readable at the operational
speed?
❑ On the approach to the intersection, is the driver clearly aware of the actions
necessary to negotiate the intersection safely?
❑ Are turning movements segregated as required for the design standard?
❑ Are drainage features sufficient to avoid the presence of standing water?
❑ Is the level of lighting adequate for the intersection, location, pedestrians, and
the design standard?
❑ Are the warning signs and markings sufficient, particularly at night?
❑ Have the needs of pedestrian and non-motorised vehicles been met?
❑ Are sight lines sufficient and clear of obstructions including parked and stopped
vehicles?
❑ Are accesses prohibited a safe distance away from the intersection?
❑ Have adequate facilities such as footpaths, refuges, and crossings, been
provided for pedestrians?
❑ Do the design, road marking and signing clearly identify the designated
passage ways and priorities?
❑ Is the design of the intersection consistent with road types and adjacent
intersections?
❑ Are the turning lanes and tapers where required of sufficient length for speeds
and storage?
(163)
10 Roundabouts
10.1 Introduction
A roundabout is a one-way circulatory system around a central island, entry to which
is controlled by markings and signs. Priority is given to traffic already on the
roundabout. Roundabouts thus operate by deflecting the vehicle paths to slow the
traffic and promote yielding.
Roundabouts provide relatively high capacity and minimum delay. They also have a
good safety record largely because traffic speeds are low and the number of potential
traffic conflicts is greatly reduced, typically by 75%, for example, from 32 at a cross-
roads to just 8 at an equivalent four-legged roundabout.
The key elements of a roundabout are:
• Entries and exits.
• Splitter islands
• The circulatory roadway.
• The central island.
• Sight distances.
The main types of roundabout are mini, compact, normal, signalised and grade
separated.
(164)
Figure 10-1: Basic Roundabout Showing Key Features
(165)
Figure 10-2: A Compact Roundabout
(166)
e) Where semi-trailers and/or abnormal vehicles are a significant proportion of the
total traffic passing through the intersection and where there is insufficient
space to provide the required layout; and
f) Where traffic congestion downstream (e.g. from a signalised intersection)
causes a queue to back up through the roundabout.
Roundabouts generally take more land than fully channelised intersections. The
additional land acquisition costs for roundabouts should be balanced with the
increased capacity offered and less maintenance cost.
Roundabouts are usually more difficult for pedestrians to cross than normal
intersections hence arrangements should be made to provide adequate facilities.
(167)
Figure 10-3: Vehicle Path through Roundabout
(168)
10.3.4 Visibility and Sight Distances
Roundabouts should be located where approaching drivers can have a good overview
of the roundabout with its entries, exits and circulating carriageway. Roundabouts
should therefore not be located on crest curves. Stopping sight distances must be
provided at every point within the roundabout and on all approaches.
The visibility splays shown in Figure 10-4 must be provided to allow drivers to judge
whether it is safe to enter the roundabout. It must be possible to see vehicles at the
preceding entry and the following exit as well as the nearest parts of the circulating
carriageway. However, drivers should not be able to see the preceding entry from
more than 15m before the ‘give way’ line, as this might encourage excessive approach
speeds.
shrubs possible
60m
>=50m
5m
Figure 10-4: Required visibility towards approaching vehicles from the right
and required visibility forwards to the left
Once within the roundabout, drivers must be able to see the area shown in Figure
10-5. Signs and landscaping on the centre island should be designed and located so
that they do not obstruct the view more than absolutely necessary, as illustrated.
Stopping sight
(169)
10.4 Dimensions of Roundabouts
The dimensions of roundabouts are defined by the radii and widths shown in Figure
10-6 and Table 10-1 :
(170)
Table 10-1 Roundabouts Dimensions
The inscribed circle diameter (f) of the roundabout is the diameter of the largest circle
that can be fitted into the junction outline (Figure 10-6). The inscribed circle diameter
of a Normal Roundabout should not exceed 100m. Large inscribed circle diameters can
lead to vehicles exceeding 50 km/h on the circulatory carriageway. The minimum
value of the inscribed circle diameter for a Normal or Compact Roundabout is the
smallest roundabout that can accommodate the swept path of the Design Vehicle.
If the inscribed circle diameter lies between 28m and 36m, a Compact Roundabout
should be considered if the traffic flows can be accommodated.
The circulatory carriageway of Normal or Compact Roundabouts should generally be
circular and of constant width. The width of the circulatory carriageway must be
between 1.0 and 1.2 times the maximum entry width.
A suitable Design Vehicle is an articulated vehicle with a single axle at the rear of the
trailer, of length 15.5 metres. The turning space requirements of this vehicle on a
roundabout with an inscribed circle diameter of between 28 m and 36 m are shown in
Figure 10-6. The turning requirements of such a vehicle are greater than those for all
other vehicles within the normal maximum dimensions permitted. The requirements
for other vehicles including an 11 m long rigid vehicle, 12m long coach, 15 m bus,
17.9m, 18.35 m drawbar-trailer combination, and a 16.5 m articulated vehicle are less
onerous.
A mountable area or apron may be added to the central island to accommodate
occasional Large Heavy Vehicles and to allow the circulatory width to be reduced to
9.5 m. The apron should have crossfall steeper than that of the circulatory road,
principally to discourage passenger vehicles from driving on it, and a crossfall of 4 to
5% is recommended.
(171)
two-lane roundabouts are designed for an articulated vehicle and a passenger car.
Figure 10-7 shows the minimum width of circulating carriageway after determining the
design vehicle and the inscribe diameter (outer diameter).
At Normal and Grade Separated Roundabouts, the width of the circulatory carriageway
should not exceed 15 m. At Compact Roundabouts, it should not exceed 6 m, although
an additional overrun area may be required for small values of inscribed circle
diameter, depending on the types of vehicles using the roundabout.
For normal one-lane roundabouts (central island radius 10 m or greater) and two-lane
roundabouts, the central island radius, the edge of carriageway radius and the width
of the circulating carriageway are determined by the graphs in Figure 10-7 and Figure
10-8.
The designer should check that the circulating carriageway is no more than about 1.2
x the maximum entry width. Very wide carriageways encourage unsafe speeds.
The circulatory roadway should be sufficiently wide to allow a stalled vehicle to be
passed. The minimum roadway width for single-lane operation is therefore about 6.5
m between kerbs. Two-lane operation requires a roadway width of about 8.5 m. If
trucks are present in the traffic stream in sufficient numbers, the circulatory road
width should be increased by 3 m both in the single-lane and in the two-lane situation.
A significant proportion of semi-trailers would require the width of the circulatory road
to be increased even more to 13 m and 16 m in the single-lane and the two-lane
situation respectively.
The width should be constant throughout the circle. Drivers tend to position their
vehicles close to the outside kerbs on entering and exiting the roundabout but close to
the central island between these two points. The vehicle path, being the path of a
point at the centre of the vehicle, should thus have an adequate offset to the outside
and inside kerbs. For a vehicle with an overall width of 2.6 m, the offset should be not
less than 1.6 m, with 2.0 m being preferred.
A circulatory road width of 13 m makes it possible for passenger cars to traverse the
roundabout on relatively large radius curves and at correspondingly high speeds. To
avoid this possibility, the central island should be modified as discussed below.
(172)
The cross-slope on the roadway should be away from the central island and equal to
the camber on the approaches to the intersection.
Figure 10-8: Radius of Central Island and Circulating Carriageway for Normal
Roundabouts.
(173)
light vehicles) and be edged with a mountable kerb. The intention is that light
vehicles will go around the outside of the traversable area, thus forcing the drivers to
travel slowly. Drivers of long vehicles will be able to negotiate the roundabout by
letting the rear wheels cross the traversable area. Guidance on the selection of central
island radii and traversable area are given in Figure 10-9.
10.5 Entries
(174)
The need for two lanes must be checked for each entry and circulating flows during
the design hour. If two lanes are necessary for one entry, the whole roundabout
should be designed with two lanes.
(175)
hatching, the measurement should be taken between markings rather than kerb to
kerb.
(176)
For highway improvement schemes on trunk roads, it is usual to consider design year
flows sometime after opening. This can result in roundabout entries with too many
lanes for initial flows, subsequently leading to operational problems. A layout based on
projected flows will determine the eventual land requirements for the roundabout, but
for the early years it may be necessary for the designer to consider an interim stage.
This approach can result in reduced entry widths and entry lanes.
The entry widths in Table 10-2 should normally be used for one and two-lane
roundabouts respectively. The transition to normal lane width should be at least 30
metres long.
Figure 10-13: Example Showing an Arc Projected Forwards from the Splitter Island
and Tangential to the Central Island.
(177)
10.5.5 Entry Flaring
Entry flaring is localised widening at the point of entry. Normal Roundabouts usually
have flared entries with the addition of one or two lanes at the give way line to
increase capacity. Single lane entries e.g. those at Compact Roundabouts, should be
slightly flared to accommodate large goods vehicles. Even a small increase in entry
width may increase capacity.
The effective flare length, l’, is the length over which the entry widens. It is the length
of the curve CF', shown in Figure 10-14.
1. AB = entry width.
2. GH = v (approach half width at point G which is the best estimate of the start of the
flare).
3. GD is parallel to AH and distance v from AH (v is measured along a line perpendicular
to both AH and GD.
4. CF' is parallel to BG and distance ½ BD from the kerb line BG.
The total length of the entry widening (BG) will be about twice the average effective
flare length.
The capacity of an entry can be improved by increasing the average effective flare
length. However, effective flare lengths greater than 25 m may improve the geometric
layout but have little effect in increasing capacity. A minimum length of about 5m in
urban areas and 25 m in rural areas is desirable.
The entry width and the flare length are related. The capacity of a wide entry
combined with a short flare can be similar to that of a narrow entry combined with a
long flare.
(178)
the left before joining the circulatory carriageway (Figure 10-15). It is the most
important determinant of safety at roundabouts because it governs the speed of
vehicles through the junction and whether drivers are likely to give way to circulating
vehicles.
The entry path radius must not exceed 70 m at Compact Roundabouts in urban areas
(where the speed limit and the design speed within 100 m of the give way line on any
approach do not exceed 70 kph. At all other roundabout types, the entry path radius
must not exceed 100 m.
a. Entry path radius should be measured over the smallest best fit circular curve over
a distance of 25m occurring along the approach entry path in the vicinity of the
give way line, but not more than 50m in advance of it.
b. Commencement point 50m from the give way line and at least 1m from the
nearside kerb or centre line (or edge of central reserve).
(179)
R3
R2
R2
R3
R1 R1
A method for creating entry deflection at a Normal Roundabout is to stagger the arms
as shown in Figure 10-18. This will:
• reduce the size of the roundabout;
• minimise land acquisition;
• help to provide a clear exit route with sufficient width to avoid conflicts.
(180)
Figure 10-18: Staggering of East-West Arms to Increase Deflection
(181)
Figure 10-19: Typical Single Carriageway Exit at a Normal Roundabout with a
Long Splitter Island
(182)
Figure 10-20: Example of a Signalised Roundabout
The capacity of roundabouts has been the subject of much study and has led to
comparatively simple relationships which have proved remarkably robust. Of the
significant variables, three are of particular importance namely entry width, approach
width and flare length. The remaining geometries have lesser effects.
Typical values are an entry capacity of 2000 pcu/h when the circulating flow is 1000
pcu/h and no pedestrian facilities, decreasing to 1700 pcu/h when pedestrian crossing
facilities are required.
More detailed information is available from TD 16, TD 50 and TD 54(see references).
>6m
Give Way Line
Alt. 1 Alt. 2
Figure 10-21: Location of pedestrian crossings
(183)
In alternative 1 the give way line is placed after the pedestrian crossing. In alternative
2 it is placed before the pedestrian crossing.
With a sufficient distance between the crossing and the ‘give way’ line (alternative 1),
vehicles can yield separately for the pedestrian crossing and the roundabout. This
improves capacity but safety might be compromised. An exiting vehicle can also give
way to a pedestrian without blocking the roundabout with obvious capacity
advantages.
A disadvantage is that the traffic island may have to be extended and widened to
accommodate pedestrians and cyclists. Another disadvantage is that pedestrians have
to make an extra detour.
(184)
11 Grade Separated Interchanges
11.1 Scope
Grade-separated interchanges are divided into two functional classes, referred to as
‘access’ interchanges (minor interchanges or merely grade separated interchanges),
and ‘systems’ (or major) grade separated interchanges.
Access interchanges are between freeways and roads on which at-grade interchanges
occur. They serve local areas by providing access to freeways. Systems interchanges
are the nodes of the freeway network itself, linking the individual freeways into a
cohesive unit. These two fundamentally different applications require different types of
interchange layout.
The fundamental difference between a freeway and any other road is that it is subject
to rigid control of access. Entrance and exit to and from a freeway may take place only
at specified points, typically remote from each other, and then only at very flat angles
of merging and diverging. A freeway is characterised by the fact that all interchanges
along its length are interchanges.
This manual does not deal in detail with the design of major grade-separated
interchanges between restricted access freeways (motorways) although the topic is
introduced sufficiently for some of the simpler designs to be carried out. More
comprehensive design guidelines for this topic are contained in the Geometric Design
Guidelines published by the South African National Roads Authority Limited, Pretoria,
RSA, and the Code of Practice for the Geometric Design of Trunk Roads published by
the Southern African Transport and Communications Commission (SATCC). More
detailed design information is available in the Advice Notes of the UKs Highways
Agency listed in the References that are freely available on the internet.
11.2 General
Systems interchanges have ramps with free-flowing terminals at both ends. The
volume of turning movements is high so there is a need for high design speeds on the
ramps. They provide uninterrupted movement for vehicles moving from one main
route to another by the use of connector roads with a succession of diverging and
merging manoeuvres. All turning movements are separated, and, ideally, weaving in
the interchanges is reduced to a minimum. The layout of these interchanges is
invariably complex, involving a substantial area and possibly more than one structure
constructed on two or more levels.
The most efficient form of grade separation is that which presents drivers with the
minimum number of clear unambiguous decision points as they drive through the
interchange and in merging and diverging. Additionally, on a motorway or an all-
purpose road that is generally grade separated, consistency of design for successive
interchanges is an important consideration involving the adoption of the same design
speed. This need for consistency also applies to signing and road markings.
At any road interchange, the flow of traffic, expressed in terms of a level of service,
can be enhanced by an interchange. The circumstances in which the use of a grade
separated interchange is warranted are usually as follows:
• Where roads cross freeways/motorways.
• Insufficient capacity of an at-grade junction. An interchange is then
justified economically from the savings in traffic delays and accident costs.
• Grade separation is cheaper on account of topography or on the grounds
that expensive land appropriation can be avoided by its construction.
(185)
• Reduction in accident rates. Some at-grade interchanges exhibit high
accident rates that cannot be lowered by improvements to the geometry or
the use of control devices. Such situations are often found at heavily
travelled urban interchanges.
Accident rates also tend to be high at the interchanges on heavily travelled rural
arterials where there is a proliferation of ribbon development. A third area of high
accident rates is at interchanges on lightly travelled low volume rural locations where
speeds tend to be high. In these cases, low-cost interchanges may be a suitable
solution.
Closely spaced successive off-ramps are often a source of confusion to the driver
leading to erratic responses and manoeuvres. Thus, an interchange should have only a
single exit for each direction of flow and exits should be located in advance of the
interchange structure. Directing traffic to alternative destinations on either side of the
freeway should then take place clear of the freeway itself. Thus, drivers are required
to make two separate decisions. First, to leave the freeway or not and, if not, to
decide which route to take for their next destination. This spreads the workload and
simplifies the decision process, hence improving the operational efficiency and safety
of the entire facility.
Single entrances are also preferred. Merging manoeuvres by vehicles entering the
freeway are a perturbation to the free flow of traffic in the left lane. Closely spaced
entrances exacerbate the problem and could influence the adjacent lanes as well.
There are several advantages in carrying the minor crossing road over the freeway
rather than under it. These are:
• Exit ramps on up-grades assist deceleration and the corresponding entrance
ramps on downgrades assist acceleration.
• Rising exit ramps are highly visible to drivers and provide advanced warning of
the interchange ahead requiring a decision from the driver whether to stay on
the freeway or to depart from it.
• Placing the freeway into cut reduces noise levels to surrounding communities
and also reduces visual intrusion.
(186)
iii) Congestion control.
iv) Trip lengths (travel distance).
v) Size of urban areas.
(187)
Table 11-1: Characteristics of some common Grade Separated Interchanges
Type of
Basic Properties Considerations
interchange
The movements associated with the missing
leg are channelled to another location and this
A is only appropriate if the traffic volumes on the
missing leg are low and capable of being
Grade separation of only served by an at-grade junction.
one traffic stream This configuration is appropriate for traffic
volumes of up to 30,000 AADT on the four-lane
B major road (3,000 vehicles per hour). With a
single loop lane, it is appropriate for loop
traffic of 1,000 vehicles per hour.
Layout C shows the ‘half clover leaf’ type of
C The simplest for major/ junction which has the advantage of being
minor road junctions that easily adapted to meet difficult site conditions.
both transfer the major Layout D shows the normal ‘diamond’ junction
traffic conflicts to the which requires the least land appropriation.
D minor road. The choice between these options is generally
dependent on land requirements.
Layouts E and F show the
two basic layouts for use
where high traffic flows
make the simpler layouts
Layout E shows a ‘full clover leaf’ junction
unsatisfactory. They are
E involving only one bridge but requiring a large
appropriate for traffic
land appropriation.
volumes on both crossing
roads of between 10,000
and 30,000 AADT (3,000
vehicles per hour).
Layout F shows a typical
roundabout interchange. It
is only suitable if the
secondary road containing
Layout F shows a typical roundabout
F the roundabout is of a
interchange involving two bridges.
relatively low design speed
but carries a
comparatively high volume
of traffic.
(188)
The Y-interchange may also be a part of a phased construction, for example, if the
freeway which currently ends at the interchange, is planned to continue at some time
in the future. In such a case the alignment of the freeway should be in the final
position, or as near to it as possible, to minimise future construction work, and the
bridges should be built in their final position, so that the future extension can make
use of them.
LAYOUT A LAYOUT B
(189)
conventional priority interchanges with stop signs or traffic lights. This form of
interchange is very common, particularly in rural areas
The diamond interchange uses less space than most types of freeway interchange and
avoids the interweaving traffic flows that occur in interchanges such as the cloverleaf.
Thus, diamond interchanges are most effective in areas where traffic is light and a
more expensive interchange type is not needed. But where traffic volumes are higher
additional traffic control measures such as traffic lights and extra lanes dedicated to
turning traffic are required.
The ramp intersections with the minor road can be configured as a pair of
roundabouts. This is the ‘dumbell’ layout shown in Figure 11-2. The advantages are
that it can be adapted to fit either a diamond or half cloverleaf; it has increased
junction capacity and reduced land take compared with the diamond.
Roundabouts can generally handle traffic with fewer approach lanes than other
intersection types therefore this configuration allows other roads to form approach
legs to the roundabouts and also allows easy U-turns.
(190)
the radius of the left turn ramps have to be as well, thus the overall size of the
interchange area also increases.
There are two (relatively minor) disadvantages of the cloverleaf. Firstly, the low
radius, and consequent low design speed, of the loops, restricts them to being single
lane thereby limiting their capacity. Secondly the requirement to turn left first in order
to turn right is not intuitive to a driver. The advantage of the cloverleaf interchange is
that it can handle large volumes of traffic and, unless the traffic on one ramp becomes
very high, can serve most situations adequately.
Interchanges with loops in all four quadrants are referred to as full cloverleafs and all
others are referred to as partial cloverleafs. A full cloverleaf may not be warranted at
major-minor crossings where, with the provision of only two loops, freedom of
movement for traffic on the major roadway can be maintained by confining the direct
at-grade left turns to the minor roadway.
Layout F (Figure 11-1) shows an interchange involving two bridges. This layout is
suitable if the secondary road containing the minor circulating roadway is of a
relatively low design speed but carries a comparatively high volume of traffic. If high
speeds on the circulating roadway occur, it can lead to problems for joining traffic
hence the dimensions of the circulating roadway need to be selected to avoid this or
traffic control can be used to alleviate this problem.
(191)
• are extremely expensive.
The need for this type of interchange, although unlikely to be required on rural roads
in Mozambique for some time, can often be reduced by changes in the major road
alignments (which will simplify the traffic pattern) to a combination of the simpler and
more economic layouts described above.
(192)
the middle of the loop or ramp will have a restrictive effect on the capacity of the
ramp and is therefore unacceptable.
Where a dual carriageway intersects with another dual carriageway (a major
interchange), the interchange between the facilities must be designed so that the
linking ramps do not entail any significant reduction in the design speeds of the
crossing carriageways. That is, a sufficient deceleration to cause discomfort to vehicle
occupants (Section 9.7.10).
Deceleration and acceleration lanes must also be provided on the freeway.
The maximum up gradient should be 5% and the maximum down gradient should be
7%.
(193)
11.7.6 Clearances
The required vertical and horizontal clearances must be in accordance with those
described in this manual for principal roads.
11.7.7 Capacity
Grade-separated junctions are generally designed using traffic volumes given in terms
of the Daily High Volume (DHV) rather than Annual Average Daily Traffic (AADTs). A
detailed traffic study and analysis can be made to determine these values. In the
absence of such a study, it can be assumed that the DHV in an urban area is 10% of
AADT and 15% in rural areas. The capacity of each traffic lane, in DHV, is normally
about 1000 vehicles per hour.
Thus, for example, Table 1-1indicates a design traffic flow of 10,000 to 15,000 AADT
for design standard H1. The expected DHV is therefore 1000 to 1500. The capacity of
this facility would be exceeded at more than 1000 vehicles per hour per lane, which
equates to 4,000 vehicles per hour for all four lanes, hence capacity will not be
exceeded at 15,000 AADT.
These DHV values are necessary in choosing the number of lanes for the ramps
corresponding to the junction.
(194)
Basic lanes and lane balance are brought into harmony with each other by building on
the basic lanes, adding or removing auxiliary lanes as required. The principle of lane
balance should always be applied in the use of auxiliary lanes. Operational problems
on existing roadways can be directly attributed to a lack of lane balance and failure to
maintain route continuity. The application of lane balance and coordination with basic
number of lanes is illustrated in Figure 11-5
(195)
the use of long speed-change lanes and compound curves but also the choice of
types of interchange which do not result in abrupt changes in vehicle speeds.
2. Weaving between lanes on the main roadway within the interchange is undesirable
and can be avoided by arranging for diverging points to precede merging points.
3. On a road with many grade-separated interchanges, a consistent design speed is
desirable for ramps. This speed must be not less than 65% of the speed of the
adjoining major road.
4. As a general rule, right-turning movements that are grade separated should be
made through a left-hand loop.
5. Unexpected prohibited traffic movements, especially where traffic is light, are
difficult to enforce and cause danger. If possible, the geometric layout should be
designed to make prohibited movements difficult, for example on one-way ramps,
entry contrary to the one way movement can be restricted by the use of suitably
shaped traffic islands to supplement the traffic signs.
(196)
• Noise and air quality
• Visual impact
B) Engineering Constraints:
• Condition of existing structures
• Topography
• Geology
• Existing traffic flows
• Existing interchange layout
• Ability to manage traffic during construction
• Ability to manage traffic during maintenance.
(197)
Step 11 Appraisal Process
In many cases the scale and effect of the works required will necessitate preparation
of a full environmental appraisal either for the interchange works alone or in
conjunction with adjacent motorway widening or construction proposals.
The Public Consultation type framework for the comparison of several options provides
a suitable basis for the assessment. This will therefore ensure that consideration is
given to:
• The effects on travellers
• The effects on occupiers of property
• The effects on users of facilities
• Conservation policies
• Development and transport policies
• Costs
The effects on travellers will include an appraisal of the complexity and safety of the
proposed interchange layouts. Where there are significant differences between the
times and/or distances involved in negotiating the interchange, economic assessments
of operating costs and time savings or delays should be carried out.
Driver stress and driver comprehension of the layout will depend on the number and
timing of decisions and manoeuvres required. These will be affected by the speed of
traffic and its density which may mean short gaps for manoeuvres and increased
stress when weaving.
Travellers will also be affected by delays during construction and the economic
assessment must take account of these costs. Solutions that result in the best final
arrangement may cause the greatest disturbance to traffic during construction. It is
therefore important that consideration is given to the provision of temporary works.
Such measures, while increasing construction costs, can significantly reduce the cost
of delays. It is also important that the costs of future maintenance, including traffic
delay costs, are taken into account.
Safety of both motorway users and construction personnel is of prime importance in
the design of major interchange improvement schemes. It is essential that designers
consider the safety implications of the construction methods and traffic management
measures necessary for execution of the work.
It will also be necessary to establish the importance given to the feasibility of
providing additional capacity at a future date for each option.
Environmental factors are likely to be significant. There will often be limitations on the
land available for new highway works and amelioration measures due to the presence
of development along some parts of the motorway boundaries. The use of long lengths
of elevated carriageway or the provision of additional levels over existing interchanges
is likely to be environmentally intrusive.
(198)
12 Additional Safety and Miscellaneous Design Items
Road user safety has economic consequences in terms of property damage, loss of
earnings or production and hospital costs resulting from physical injury, in addition to
the emotional consequences of pain, suffering and death. Safety and economy are the
foundations on which competent design rests. Inadequate consideration of either will
automatically result in inadequate design.
It is difficult to correct many safety defects at a later stage without major
reconstruction hence designing for safety should occur at the very beginning of a road
project. Road safety audits by an independent person or team should be undertaken
during each stage of the design and a system for doing so has been under
development (H J S Lotter (2011) Interim Road Safety Audit Procedures).
Good geometric design of roads has an important part to play in reducing the number
and severity of road accidents. Road safety aspects have been highlighted throughout
this manual:
• Human factors have been addressed in the design process;
• Road and shoulder widths have been increased to accommodate pedestrians,
NMT, and intermediate forms of transport (IMT);
• Moderate design speeds have been used for elements of road alignment;
• Parking places and lay-bys for buses have been included in populated areas;
• Account has been taken of reduced friction on unpaved roads;
• Adequate sight distances have been provided.
Indeed, many aspects of geometric design that have been described in previous
chapters are dictated by road safety requirements. The scope of this chapter is to
introduce the design and specifications of other important safety features that have
not been covered in detail in earlier chapters. However, some of the principles, for
example, the effects of human factors, are given additional emphasis.
Miscellaneous design items in this chapter include bus lay-bys and parking bays,
parking lanes, safety barriers, emergency escape ramps, brake check areas, safety
rest areas and scenic overlooks, public utilities, and railway grade crossings.
12.1.1 Pedestrians
In Africa about 38 % of all road fatalities are pedestrians. Methods and designs that
improve the safety of pedestrians are therefore vital.
• Pedestrian actions are less predictable than those of motorists. They tend to
select paths that are the shortest distance between two points and avoid using
underpasses or overpasses that are not convenient. As a consequence, they
frequently take risks that vehicle drivers have difficulty anticipating.
(199)
• Walking speeds vary from 1.0 m/s to 1.8 m/s, with an average of 1.4 m/s. For
design purposes 1.0 m/s is recommended because of the aging population.
• In urban areas it is necessary to make provision for boarding and alighting
public transport passengers (Section 3.13), disabled persons and other non-
vehicular users of the facility in addition to accommodating pedestrians and
cyclists
• Pedestrian safety is enhanced by the provision of median refuge islands of
sufficient width at wide intersections (Section 3.14), and lighting at complex
locations.
• In urban areas, the presence of large numbers of pedestrians will require
adequate sidewalk widths (Section 3.15).
• On rural roads, speeds are high so that accidents involving pedestrians are
inevitably fatal. Provision should be made for protecting pedestrians on rural
roads, even though their numbers may be low (Section 3.16).
• As implied above, age is an important factor that may explain behaviour that
leads to collisions. It is recommended that older pedestrians be
accommodated, not only by assuming lower design speeds as stated above,
but also by using simple designs that minimize crossing widths. Where complex
elements such as channelisation and separate turning lanes are featured, the
designer should assess alternatives that will assist older pedestrians.
12.1.2 Cyclists
Bicycle use is increasing and should be considered in the road design process.
Improvements such as:
• Wider paved shoulders;
• bicycle-safe drainage gratings (flat metal grids to prevent unwanted debris
from entering a drain underneath but with transverse bars and slots which
cannot snag bicycle wheels);
• maintaining a smooth, clean riding surface.
Cyclists can often be accommodated on the normal travelled lanes but, when the
number of cyclists increases, it may be necessary to widen these lanes or to provide
cycle paths adjacent to or, for preference, away from the travelled lane. At certain
locations it may be appropriate to supplement the existing road system by providing
specifically designated cycle paths.
A checklist of engineering design features that affect road safety is given in Figure
12-1. Many of these have been discussed in the appropriate chapters of this manual
but for more detail the TRL publication ‘Towards Safer Roads’ is recommended.
(200)
Figure 12-1: Engineering Design Features Affecting Road Safety
(201)
12.3 Traffic Calming
The seriousness of road accidents increases dramatically with speed and hence very
significant improvements to road safety are possible if traffic can be slowed down. This
process is called traffic calming. All such methods have both advantages and
disadvantages and the effectiveness of the methods also depends on aspects of driver
behaviour that can vary considerably from country to country. Therefore, research
needs to be carried out in Mozambique to identify the most cost effective approaches.
The likely effect of any traffic calming measure on all the road users should be
reviewed before they are installed. Some are unsuitable if large buses are part of the
traffic stream; some are very harsh on bicycles, motorcycles and motor cycle taxis;
and some are totally unsuitable when there is any animal-drawn transport.
The most common methods are:
i) Chicanes;
ii) Rumble strips and other textured surfacings;
iii) Speed reduction humps and cushions;
iv) Roundabouts;
v) Horizontal deflection of a straight road when approaching a roundabout or
junction;
vi) Narrowing the width of the carriageway by, for example, channelising;
vii) Road markings such as painted chevrons, ghost islands, go slow signs, speed
limit signs etc.;
viii) Gateways for the entrance to a village area;
ix) Prohibition of certain vehicle types by physical width or height restrictions or
signs (but with enforcement);
x) Adding crossing facilities for pedestrians and cyclists.
The effectiveness of these methods is very variable but those that require a physical
intervention rather than merely a text warning are the most effective and those that
directly affect speed for 100 % of the time such as the first four in the list (i.e. not
dependent on the presence of third parties, are the most effective of all.
12.3.1 Chicanes
These are designed to produce minor turning movements along straight streets in
established urban areas by reducing the width of the road to one lane for a very short
distance (3-5 m) at intervals (typically 300 m) along it. They are usually built on
alternate sides of the road. They cause drivers to slow down provided that the traffic
level is high enough to make it very probable that they will meet an oncoming vehicle.
The method is obviously unacceptable if traffic flow is high because the congestion
that it causes will be severe. For safety, they must be illuminated at night.
(202)
hence they are effective in providing moderate slowing down of the traffic. They do
not need to be illuminated at night.
Flat-topped road humps are an alternative to the circular road humps but are longer
and with a flattened top, used to give pedestrians a level crossing between footways.
They can especially be useful where there are a lot of pedestrians. Normally,
pedestrian crossings should only be installed at busy crossing points. Where it is
necessary to use traffic calming measures to reduce speed, the most suitable
arrangement is to install circular road humps a short distance from the pedestrian
crossing. If it is necessary to provide a hump at the crossing, a flat-topped hump
(203)
should be used, which is easier for pedestrians. It should however be noted that flat-
topped humps cause more discomfort to bus passengers, so they should not be
installed on busy bus routes.
The standard size in usually 8.4 m long and 100 mm high as shown in Figure 12-3.
Based on a similar principle to the speed hump, speed reducing cushions are more
versatile. They are essentially very similar to the speed hump, but the hump is not
continuous across the road. The width of a two-lane road is usually covered by two or
three cushions with gaps between them of 750 – 1200 mm. The idea is that large
heavy vehicles will not be able to pass without at least one wheel running over one of
the humps, but bicycles and motorcycles can pass between them without interference.
If suitably designed the wheels of animal drawn carts can also avoid the humps.
(204)
Specific measures include calming traffic with speed humps, rumble strips, road
narrowing, pedestrian crossings and specially demarcated low speed zones.
However, the functional characteristics of the through road will dictate to some
extent the kind of safety measures that are acceptable.
The objective of the village treatment approach to traffic calming is to develop a
perception that the village is a low-speed environment and to encourage drivers to
reduce speed as a result of this perception. To this end, the road through the village is
divided in three zones, namely:
(i) The approach zone.
(ii) The transition zone.
(iii) The core zone.
The Approach Zone is the section of road prior to entry into the village where the driver
needs to be made aware that the open road speed is no longer appropriate. This is the
section of road where speed should be reduced typically from above 60/70 km/h down
to 50 km/h before entering the village. The village entry should be marked by an
obvious Gateway that marks the beginning of the village. Drivers should be clearly
informed that they are entering a section, typically a village, where they are required
to drive more slowly and carefully, and this can best be done by installing a gate or
gateway at the point where the built-up area begins. The gateway sign shall be
double-sided and combines the speed limit sign with a panel showing the place name.
Gates are likely to achieve greater speed reductions if they incorporate traffic islands
that prevent the driver from continuing straight ahead - some typical designs are
shown in Figure 12-4. However, to avoid the islands becoming a hazard, especially at
night, they must be very clearly marked with reflective markings and road studs and
they should be designed so that, if errant vehicles hit them, the consequences are not
severe.
The gate should preferably be designed such that the toughest vehicle path for a
passenger car through the gate or portal should have an entry radius below 100 m for
50 km/h speed control and 50 m for 30 km/h speed control. Curves that follow should
have a radius greater than or equal to the entry radius. The gate could be one-sided
with speed control only in the entry direction or two-sided with speed control also in
the exit direction. The design can be tapered or smoothed with curves as shown in
Figure 12-4
(205)
Figure 12-4: Village Gateway Designs
The Transition Zone is the section of road between the village entrance, or Gateway,
and the core zone of the village. The target speed, and posted speed limit in this zone
should be maintained at typically 50 km/h. The first road hump or humps in a series of
humps should be sited in this zone. In this context, with adequate advance warning
provided by the approach zone and Gateway, properly designed road humps should be
quite safe.
The Core Zone is the section identified as being in the centre of the village where most of
vehicle/pedestrian conflicts are expected to take place. This would normally be where the
majority of shops, bus-bays or other pedestrian generating activities are located. This is
the section where pedestrian crossing facilities are most likely to be established and
where the target speed, and posted speed limit, should be reduced to 40 km/h or lower.
Road humps should be provided within this zone with advisory speed limits in order to
enforce the lower speed environment required.
(206)
12.4 Brake Check Areas
Brake check areas for trucks are areas set aside before a steep descent. They provide
opportunity for cooling the brakes system and they ensure that drivers begin the
descent at low speed and in a low gear that may make the difference between
controlled and out-of-control operation on the downgrade. They also provide an
opportunity to display information about the grade ahead, escape ramp locations and
maximum safe recommended descent speeds. They should be provided on routes that
have long, steep downgrades and commercial vehicle numbers of around 500 per day,
especially on National Roads and principal traffic routes. They need to be large enough
to store several semi-trailers, the actual numbers depending on volume and predicted
arrival rate. Their location requires good visibility and acceleration and deceleration
tapers. Adequate signage should be provided to advise drivers in advance of the
facilities.
(207)
Drivers of heavy or wide vehicles may be unwilling to reverse long distances hence
where trucks are travelling in both directions, it may be necessary to reduce the
passing point spacing.
After determining the spacing and location of passing points, the length and width
should be set. The length is primarily dependent on the traffic volume. If the traffic
volume is high, the passing point should be long enough to accommodate several
vehicles waiting for oncoming traffic to pass.
A suitable width depends upon the width of the road itself. The criterion is to provide
enough overall width for two design vehicles to pass each other safely at low speed
hence a total trafficable minimum width of 5.5 m is required. Allowing for vehicle
overhang when entering the passing bay, a total width of 6.5 m is suitable.
12.8.1 General
Many accidents on high-speed roads involve vehicles leaving the road and coming into
collision with hazardous obstacles such as trees, bridge supports, or simply rolling
down a high embankment. Similarly, a vehicle leaving a lane on a dual carriageway
runs the risk of collision with an oncoming vehicle.
The design of a safe roadside requires the identification of the dangerous obstacles
that are present. Once identified, it is possible to establish strategies or measures
necessary to protect the traffic from them.
Two classes of dangerous objects are defined: point obstacles and linear obstacles.
These two classes correspond to different procedures for the selection of mitigation
measures. However, the general strategy to be applied to both classes is common and
consists of the following steps:
1) Assessment of dangerous obstacles;
(208)
2) If possible, removal of the dangerous obstacle out of the free zone;
3) When removal is not possible, assess the possibility of modification of the
dangerous obstacle;
4) If these options are not possible, protect the traffic with a vehicle restraint
system.
(209)
should always seek advice from experts; a safety barrier can be ineffective and even
dangerous if not properly designed and installed. The components of safety barrier
should always be purchased from a specialist manufacturer and their advice obtained.
If possible, arrangements should be made for them to install it, or supervise the
installation.
Source: NPRA
(210)
Table 12-4: Containment Level – Requirement of Design of Safety Barriers
Theoretical
Impact Impact
Containment Total mass Type of kinetic
speed angle
Level Kg vehicle energy
(km/h) (degree °)
KNm
When a safety barrier is hit by a vehicle, it will deform. The deformation of safety
barriers during impact tests is characterised by the working width. The barrier’s
working width (W) is the maximum horizontal distance between the front edge of the
barrier before deformation and the rear edge after. If the vehicle body deforms around
the road safety barrier, so that the latter cannot be used for the purpose of measuring
the working width, the maximum lateral position of any part of the vehicle shall be
taken as an alternative. The barrier’s dynamic deformation or width of deformation, D,
is the horizontal distance between the front edge of the barrier before deformation
and after (Figure 12-5).
The safety barrier including parapet shall contain the vehicle without complete
breakage of any of its principal longitudinal elements. Elements of the safety barrier
including parapets shall not penetrate the passenger compartment of the vehicle.
Deformations of the passenger compartment that can cause serious injuries shall not
be permitted.
The vehicle shall not spin and/or roll over (including rollover of the vehicle onto its
side) during or after impact.
(211)
SATCC has developed general criteria for installation of guardrails. These are shown in
Figure 12-6 and should be used as a general guideline and starting point for
determining need.
In addition to installing safety barriers when the fill is high and the side slopes are
steep, there is a substantial risk caused by obstacles within the clear zone area. Such
obstacles include:
• Bridge piers, abutments and culverts walls.
• None yielding light columns, gantries and trees with diameter > 18 cm.
• Concrete bumpers, solid concrete elements, culvert outlets, end of retaining
walls.
• Solid stones or rock outcrops which have a top more than 20 cm above the
terrain or steep rock slopes where protruding parts should be less than 30 cm.
• Solid installations.
Such dangerous roadside obstacles should be removed, replaced with yielding road
furniture or protected with a safety barrier. If, however, a back slope is built in front of
the obstacles in the clear zone, safety barriers are not necessary if the following
criteria are satisfied, i.e.:
• When the gradient of the back slope is 1:2, the height of the slope measured
from the adjacent road surface shall be minimum 1.8 m.
• When the gradient of the back slope is 1:1.5 the height of the slope measured
from the adjacent road surface can be reduced to 1.4 m.
(212)
the road just beyond the tangent point. Any gaps through which vehicles may fall
should always be closed.
The set-back shall normally be 50 cm beyond the edge line of the road to the face of
the barrier. With roads having AADT of 12,000 and above and a speed limit greater
than 80km/h, the set-back shall be 75cm.
Note that this is the starting point for estimating the need. Engineering judgement
is required to determine the precise length for specific situations
(213)
When an out-of-control vehicle hits the barrier the beam flattens, the posts are
pushed backwards, and the tension in the beam builds up to slow the vehicle and
redirect it back onto the road. That is, if it performs successfully. The speed, mass and
angle of the vehicle is critical to success. With heavy vehicles, high angles of impact
and very high speeds the barrier may be torn apart or crushed. The containment
capability can however be increased by using two beams, one mounted above the
other.
(214)
together (one nested inside the other) and using extra-large concrete
foundations;
h) When installed on top of an embankment there must be at least 600 mm
between the back of the post and the break of slope in order to have
sufficient ground support for the post - where this is not possible, much
longer posts must be used;
i) The guardrail should not be installed behind a kerb, because when a vehicle
hits the kerb it will be pushed upwards and so will hit the guardrail too high
- with a risk that the vehicle will go over the guardrail;
j) The guardrail shall be set back from the shoulder edge (or carriageway
edge if there is no shoulder) by at least 600 mm - putting it at the edge of
the shoulder reduces the effective width of the shoulder and increases the
risk of minor damage.
(215)
• If the cable is snapped due to an impact, the entire length of guardrail can
become ineffective.
• The cable can be stolen.
(216)
Figure 12-10: Different Types of Median Barrier
Median barriers often take the form of two guardrail beams mounted back to back on
one post. These are not suitable where the median is narrower than 2.0 m because
they deflect too much on impact. A mono rail barrier with a box rail on top of the posts
can sometimes be a good solution.
Concrete can be preferred in situation where higher performance is needed. Concrete
barrier can be made in situ casted or by elements mounted together so it acts as a
continuous barrier.
As always with safety barriers it is a problem to terminate them safely. If possible, the
barrier should be terminated at points where speeds are low, such as at roundabouts.
Failing this, the guardrail beams should be flared and ramped down, or at least be
capped with a protective end-piece (bull-nose end treatment). Concrete barriers
should be ramped down.
12.8.14 Terminals
The approach and departure ends of a steel beam guardrail are its most dangerous
features, therefore they shall be constructed with leading and trailing terminal
sections. Also, short (<80m) gaps should not be left in guardrails; instead they should
be made continuous.
There is no wholly safe way of terminating guardrail, but the general advice is to:
• stiffen the end section by installing the posts at 1905 mm spacing, and
(217)
• flare the end section of the guardrail away from the edge of the shoulder
until it is offset by at least 1m - use a flare rate of at least 1 in 10 - this
reduces the risk of a direct impact; and
• use a special impact-absorbing terminal piece or ramp the beam down
sharply into the ground.
With both treatments the post spacing is halved over the first three to five lengths, as
shown in Figure 12-11.
On a two-way road both the upstream and downstream ends of the guardrail will need
to be terminated in this way. One of the problems of ramped ends is that they can
launch out-of-control vehicles into the air, with disastrous consequences. This problem
can be reduced by ramping the beam down sharply. Flaring is an effective way of
reducing the risk of impact, but this can be difficult to achieve in some situations, such
as on narrow embankments.
(218)
12.8.15 Transition from Guardrail to Bridge Parapets and Concrete
Barriers
Collisions with the ends of bridge parapets and concrete barriers are usually very
severe. It is essential that these obstacles are shielded so that out-of-control vehicles
are redirected along the face of the parapet or concrete barrier. This is best done by
installing a semi-rigid steel beam guardrail on the approach, normally at least 30 m
long. It must line up with the face of the parapet/barrier and be strongly connected to
it. The guardrail must be progressively stiffened so that deflection is reduced to zero
as the parapet/barrier is reached. This is called a transition section. The stiffening is
achieved by putting in extra posts, putting two beams together (one nested inside the
other) and using extra-large concrete foundations (Figure 12-12). A steel connecting
piece is used to bolt the end of the guardrail to the parapet or barrier - the design of
this will vary to suit the design of the parapet/barrier.
(219)
• Pedestrian crossings, underpasses’, footbridges – barrier helps channel
pedestrians to the crossing facility; and,
• Medians – barrier can be used to deter pedestrians from using the median to
cross the road, though barriers on the footways are more likely to be effective.
Pedestrian parapets are designed to safeguard pedestrians but are not intended to
contain vehicles. These are used where there is a safety barrier between the vehicle
lanes and the footway. Figure 12-13 shows a typical design for a lightweight steel
parapet.
The requirements are:
1) The minimum height for parapets is 1.2 m, but this should be increased to
1400 mm for cycleway, and 1500 mm for bridges over railways and other
bridges where containment is essential;
2) Metal parapets should have no openings wider than 100mm. If necessary
the parapet should be faced with wire mesh panels. When the bridge has no
facilities for pedestrians, the openings could be increased to 300 mm.
(220)
12.8.17 Summary - Use and Placement of Barriers
The use of barriers is questionable for several reasons:
• In addition to the construction cost of the guardrail itself, there are other
related costs. These include the need to construct a wider roadway to provide a
platform for the construction of the barrier or guardrail. This is necessary,
particularly in mountainous terrain and in rock cuts, and adds more to the
construction costs than the cost of the barrier itself.
• When traffic volumes are low a cost/benefit analysis will often show that they
are not cost effective.
• Where mountainous terrain with steep side slopes is encountered, the
conscientious driver will automatically adjust his behaviour to compensate for
the safety hazards anticipated with the terrain, minimising the need for the
guidance provided by the guardrail.
• Guidelines rather than ‘standards’ usually govern the placement (or non-
placement) of guardrails. Thus, they are not an essential requirement.
• The above factors can create problems with liability. Liability is minimised when
guardrail placement is not a requirement. Conversely, if guardrails are placed
but not maintained, the chances of problems associated with liability are much
greater.
(221)
• Where guardrails are employed they need to be maintained. The responsible
authority cannot be held liable for not installing guardrails, but could be held
liable for an accident due to an un-maintained portion of guardrail.
12.9.1 Types
There are four types of emergency escape ramps. The first is a sand pile, the others
are arrester beds, classified by grade (descending grade, horizontal grade, and
ascending grade). They are illustrated in Figure 12-14. All function by application of
the decelerating effect of loose material.
Sand piles, composed of loose, dry sand dumped at the ramp site are usually no more
than 120 m in length. The influence of gravity is dependent on the slope of the
surface. The increase in rolling resistance is supplied by the loose sand. Deceleration
characteristics of sand piles are usually severe, and the sand can be affected by
weather. Because of these characteristics, the sand pile is less desirable than the
arrester bed. However, at locations where inadequate space exists for another type of
ramp, the sand pile may be appropriate because of its compact dimensions.
Escape ramps are constructed adjacent to the carriageway. The use of loose material
in the arrester bed increases the rolling resistance to slow the vehicle. Descending
ramps can be rather lengthy because gravitational effects are not acting to help
reduce the speed of the vehicle.
(222)
SAND PILE
DESCENDING GRADE
HORIZONTAL GRADE
ASCENDING GRADE
The preferred type of escape ramp is the ascending type with an arrester bed. Ramps
of this type use gradient resistance to advantage, supplementing the effects of the
aggregate in the arrester bed, and generally reducing the length of ramp necessary to
stop the vehicle. The loose material in the arresting bed increases the rolling
resistance, and also serves to hold the vehicle in place on the ramp grade after it has
come to a safe stop.
Each one of the ramp types is applicable to a particular situation and must be
compatible with location and topographic controls at possible sites.
(223)
3. The width of the ramp should be adequate to accommodate large heavy
vehicles. Widths of ramps range from 3.6 to 12 m.
4. The in-fill material used in the arrester bed should be clean, not easily
compacted, and have a high coefficient of rolling resistance. In-fill material
should be single-sized natural or crushed coarse granular material or sand.
Such material will maximize the percentage of voids, thereby providing
optimum drainage and minimising compaction. The use of single-size aggregate
also minimises maintenance, which must be performed by scarifying when the
material is prone to compaction. Loose gravel or sand can also be used. A
maximum particle size of 40 mm is recommended.
5. Contamination of in-fill material can reduce the effectiveness of the arrester
bed by creating a hard surface layer at the bottom of the bed. Therefore, an
aggregate depth up to 1.0m is recommended. To assist in decelerating the
vehicle smoothly, the depth of the bed should be tapered from a minimum of
75 mm at the entry point to the full depth of aggregate in the initial 30 to 60 m
of the bed.
6. A positive method of draining the arrester bed should be provided to avoid
contamination of the arrester bed material. This can be accomplished by
grading the base to drain, intercepting water prior to entering the bed or by
edge drains. Geotextiles can be used between the sub-base and the bed
materials to prevent infiltration of fines.
7. The entrance to the ramp must be designed so that a vehicle travelling at high
speed can enter safely. Sight distance preceding the ramp should be provided
and the full length of ramp should be visible. The angle of a departure for the
ramp should be small. The main roadway surfacing should be extended to a
point at the bed entrance such that both front wheels of the out-of-control
vehicle will enter the arrester bed simultaneously.
8. Advance warning signs and markings are required to inform a driver of the
existence of an escape ramp and to prepare him well in advance so that he will
have enough time to decide whether or not to use the escape ramp. It should
indicate whether the ramp is occupied or not. Regulatory signs near the
entrance should be used to discourage stopping or parking at the ramp.
V2
L=
254(R G ) / 100
Where:
L = distance to stop (i.e. the length of the arrester bed), m,
V = entering velocity, km/h,
G = % gradient of ramp,
R = rolling resistance expressed as equivalent % gradient
For example, assume that topographic conditions at a site selected for an emergency
escape ramp limit the gradient of an ascending ramp to 10 %. The arrester bed is to
be constructed with loose gravel for an entering speed of 140 km/h. Using Table 12-6,
R is also determined to be 10 %. The length necessary is determined from the above
equation. For this case the length of the arrester bed is about 385 m.
(224)
Table 12-6: Rolling Resistance of Roadway Surfacing Materials
Rolling
Equivalent
Surfacing Material Resistance
Grade (%)1
(kg/100 kg GVM)
Crushed aggregate, loose 50 5
Gravel, loose 100 10
Sand 150 15
Pea gravel 250 25
Note 1 Rolling resistance expressed as equivalent gradient.
A plan and profile of an emergency escape ramp with typical appurtenances is shown
in the Standard Detail Drawings.
Where a full-length ramp is to be provided with full deceleration capability for the
design speed, a ‘last chance’ device should be considered when the consequences of
leaving the end of the ramp are serious. The use of a ramp end treatment should be
designed with care to ensure that the advantages outweigh the disadvantages.
Mounds of in-fill material between 0.6 and 1.5 m high with 1:1.5 slopes have been
used at the end of ramps in several instances as the ‘last chance’ device.
12.9.3 Maintenance
After each incident the in-fill materials should be reinstated. The arrester beds should
be inspected periodically, and the in-fill materials replaced as necessary.
(225)
Underground utilities include:
a) Buried telephone lines.
b) Gas pipelines.
c) Power transmission cables.
d) Storm drains and sewers
The following factors should be considered in the location and design of utility
installations.
1) Utility lines should be located to minimise the need for later adjustment, to
accommodate future highway improvements, and to permit servicing such
lines with minimum interference to traffic.
2) Longitudinal installation should be located on a uniform alignment as near as
practicable to the road reserve to provide a safe environment for traffic
operation and preserve space for future highway or street improvements of
other utility installations.
3) To the extent feasible and practicable, utility line crossings of the highway
should cross on a line generally at a right angle (90 degrees) to the highway
alignment. Those utility crossings that are more likely to require future
servicing should be encased or installed in tunnels to permit servicing without
disrupting the traffic flow.
4) The horizontal and vertical location of utility lines within the highway road
reserve should conform to the clear roadside policies and specific conditions
for the particular section involved. Safety of the travelling public should be a
prime consideration in the location and design of utility facilities on highway
reserve.
5) Sometimes attachment of utility facilities to highway structures, such as
bridges, is a practical arrangement and may be authorized. Electric and
Telephone Cables and water main placing in one trench should be done
according to Figure 12-15 unless otherwise stated by the concerned
institutions.
6) All utility installations on, over, or under the highway reserve and attached
structures should be of durable materials designed for long service-life
expectancy, relatively free from routine servicing and maintenance, and meet
or exceed the requirements of the applicable industry codes or specifications.
7) On new construction in road locations no utility should be situated under any
part of the road, except where it must cross the highway.
8) Utility poles and other above ground utility appurtenances that would
constitute hazards to errant vehicles should not be permitted within the
highway clear zone. The only exceptions permitted would be where the
appurtenance is breakaway or could be installed behind a traffic barrier
erected to protect errant vehicles from some other hazard.
(226)
12.11.2 Direcção Nacional de Aguas (DNA)
The placement of water and sewerage pipes, as per the Water and Sewerage
Authority, is given in the Appendix E.
(227)
curvature may inhibit a driver's view down the tracks from both a stopped position at
the crossing and on the approach to the crossings.
Where highways that are parallel with main tracks intersect highways that cross the
tracks there should be sufficient distance between the tracks and the highway
intersections to enable highway traffic in all directions to move expeditiously and
safely.
It is desirable that the intersection of the highway and railroad be made as level as
possible from the standpoint of sight distance, ride quality, braking and acceleration
distances as in Figure 12-17. Vertical curves should be of sufficient length to ensure
an adequate view of the crossing, and crest and sag curves are the same as for the
roadway design. The sight distance requirements down the tracks are similar to those
for a roadway junction.
It is necessary to install signing to provide a safe crossing. Traffic control devices for
railroad-highway grade crossings consist of signs and pavement markings. Standards
for design and placement of these devices are covered in the Standard Detail
Drawings.
(228)
13 Road Signs, Road Markings and Road Furniture
Elements addressed herein include road signs, road markings, traffic signals, and
lighting.
Traffic signs provide essential information to drivers for their safe and efficient
manoeuvring on the road. Road markings delineate the pavement edges and thereby
clarify the paths that vehicles are to follow. Traffic signals are key elements for the
efficient functioning of many urban roads and for some rural junctions. Finally, lighting
is provided to improve the night time safety of a road.
Traffic signs, road markings, and marker posts must conform to National Standards.
Standards for traffic signs and road markings and their placement are provided in the
Standard Detail Drawings.
(229)
13.3 Road Studs
Road studs are manufactured plastic objects incorporating reflectorised patches.
Hybrid markings consisting of both reflective road markings and reflective studs can
be useful for night-time driving in unlit areas. They are generally placed along the
centreline of the road, in the middle of the ‘broken-line’ portion of the marking, for
added demarcation. The studs can also be used to give an audible and tactile warning
of crossing any line that incorporates them, such as a pedestrian crossing.
The configuration for road markings is shown in the Standard Detail Drawings.
All permanent pavement and object markings must be formed in thermoplastic
materials and must be reflectorized.
Kilometre posts are a requirement for all trunk and link roads. The kilometre posts
must be numbered beginning at Maputo or beginning at the trunk road-link road
intercepts. Kilometre posts must be placed every 1 km, past the edge of the shoulder.
Marker posts must be constructed from either concrete or plastic. Plastic marker posts
may have the following advantages:
i) Lower initial costs.
ii) Lower maintenance cost due to their ability to absorb an impact and remain
intact.
iii) Minimal damage to impacting vehicle.
iv) Safer highway environment.
v) Unlikely to be removed by local population for alternative use.
The incorporation of reflective panels into the marker post greatly improves their
visibility at night.
(230)
junctions. The phasing of the signals at each road junction should be integrated to
achieve optimum efficiency. In designing the road, careful consideration should be
given to the junction location and geometry with respect to the visibility of traffic
signals and pedestrian requirements.
The layout of traffic lanes at signal-controlled junctions determines the functioning of
the junction. Adequate provision should be made for right and left turning lanes and
signals must be phased accordingly. Consideration should also be given to the
provision of pedestrian signals at major junctions.
13.6 Lighting
Lighting is provided to improve the safety of a road. Statistics indicate that the night-
time accident rate is higher than during daylight hours, which, to a large degree, may
be attributed to impaired visibility. In urban areas, where there are concentrations of
pedestrians and junctions, fixed source lighting tends to reduce accidents. However,
lighting of rural highways is seldom justified except at junctions, intersections, and
railway level crossings, narrow or long bridges, tunnels, sharp curves, and areas
where there is activity adjacent to the road (e.g. markets). Options that reduce
lighting costs, such as the use of solar power, should be considered as first priority.
To minimise the effect of glare and to provide the most economical lighting
installation, luminaries should be mounted at a height of at least 9 m. High mounted
luminaries provide greater uniformity of lighting and mounting heights of 10 to 15 m
are frequently used. High mast lighting (special luminaries on masts of 30 m) is used
to illuminate large areas such as intersections. This type of lighting gives a uniform
distribution of light over the whole area and thus illuminates the layout of the
intersection.
Lighting columns (poles) should be placed behind vertical kerbs whenever practical.
The appropriate distance is 0.5 m behind the kerb for roads with a design speed of 50
km/h or less, and 1.2 m or greater for roads with a design speed of 80 km/h or
greater. Where poles are located within the clear zone, regardless of distances from
the edge of the carriageway, they should be designed to include a frangible impact
attenuation feature. However, these types of poles should not be used on roads in
densely populated areas, particularly with footways. When struck, these poles may
collapse and cause injury to pedestrians or damage adjacent property. Because of
lower speeds and parked vehicles on urban roads, there is much less chance of
injuries to vehicle occupants from striking fixed poles compared to higher speed roads.
On dual carriageways, lighting may be located either in the median or on the left-hand
side of each carriageway. However, with median installation the cost is generally
lower, and illumination is higher on the high-speed outer lanes. On median
installations, dual mast arms should be used, for which 12-15 m mounting heights are
favoured. These should be protected with a suitable safety barrier. On narrow
medians, it is preferable to place the lighting poles so that they are integral with the
median barrier.
When it is intended to install highway lighting in the future, providing the necessary
conduits/ducts as part of the initial road construction can give rise to considerable
savings.
(231)
14 Departures from Standards
14.1 Procedure
Where the designer departs from a standard, written approval must be obtained from
the Director, ANE. The Designer should submit the following information to ANE:
1) The number, name, and description of the road section;
2) The design parameter for which a Departure from Standards is desired;
3) A description of the standard, including normal value, and the value of the
Departure from Standards;
4) The reason for the Departure from Standards, and
5) Any mitigation to be applied in the interests of safety.
6) Justification for departure
The Designer must submit all major and minor Departures from Standards to the
respective regional directorate for evaluation. If the proposed Departures from
Standards are acceptable, the Departures from Standards will be submitted to the
Quality Assurance, Road Inspection and Safety Directorate for final approval.
An appropriate proforma is shown below based on the proposed modifications to the
appropriate part of the manual or specifications that, if approved, will allow the project
to proceed. At this stage this is not a permanent change but merely a temporary one
for the affected project.
(232)
DEPARTURE FROM STANDARDS – APPROVAL FORM
Project Name:
1. Description of issue/challenge/problem:
4. Impact if any (including quality, cost, design life, safety) and mitigations,
environmental, social etc:
No Impact Mitigation
5. Submitted by:
Name:____________________________________Designation:________________
(233)
Email:________________________________________date:___________________
Signature Date
Signature date
Signature date
(234)
15 References
American Association of State Highway and Transportation Officials (2011).
A Policy on Geometric Design of Highways and Streets. 6th Edition, AASHTO,
Washington, D.C.
Austroads (2003). Guide to the Geometric Design of Rural Roads. Sydney, Australia.
Austroads (2016). Guide to Road Design Part 3: Geometric Design (2016 Edition)
Sydney, Australia.
Austroads (2016). Supplement to Austroads Guide to Road Design. Part 3:
Geometric Design. Sydney, Australia.
Committee of State Road Authorities (1988). TRH 17: Geometric Design of Rural
Roads. Pretoria, South Africa.
Committee of Land Transport Officials (1999). South African Road Safety Manual.
Pretoria, RSA.
(235)
Institution of Highways and Transportation (1990). Highway Safety Guidelines -
Accident Reduction and Prevention. International edition. Institution of Highways and
Transportation, UK.
SATCC (1998). Code of Practice for the Geometric Design of Trunk Roads.
CSIR/Transportek Report CR-97/049, Pretoria, RSA.
South African National Road Agency (2003). Geometric Design Guidelines. RSA.
The Highway Agency (1997). Design Manual for Roads and Bridges. London, UK.
A series of technical notes from the Design Manual for Roads and Bridges available on
the internet.
Geometric Design of Roundabouts. TD 16.
Layout of Grade Separated Junctions. TD 22.
Junctions and Accesses: Determination of Size of Roundabouts and Major/Minor
Junctions. TA 23.
Choice between Options for Trunk Road Schemes. TA 30.
The Design of Major Interchanges. TD 39.
The Layout of Compact Grade Separated Junctions. TD 40.
Geometric Design of Major/Minor Priority Junctions. TD 42.
Layout of Grade Separated Junctions. TA 48.
Geometric Layout of Signal Controlled Junctions and Signalised Roundabouts. TD
50.
Design of Mini-roundabouts. TD 54
The Layout of Large Signalised Junction. TA 86.
Geometric Design of Pedestrian, Cyclist and Equestrian Routes. TA 90.
Provision for Non-Motorised Users. TA 91.
TRL (1994). Towards Safer Roads: A Guide for Planners and Engineers. TRL Limited,
Crowthorne, UK.
TRL (1988). A Guide to Geometric Design. Overseas Road Note No 6. TRL Limited,
Crowthorne, UK.
(236)
TRL (1988). A Guide to Geometric Design. Overseas Road Note 6. TRL, Crowthorne,
UK.
TRL (1994). Towards Safer Roads: A Guide for Planners and Engineers. TRL Limited,
Crowthorne, UK.
United Nations Economic Commission for Africa (1990). Road Safety Manual on
Low Cost Engineering Countermeasures. United Nations Economic Commission for
Africa, Addis Ababa, Ethiopia.
World Road Association (PIARC) (2016). Human Factors Guidelines for a Safer
Man-Road Interface. Technical Committee C3.2 Design and Operation of Safer Road
Infrastructure. World Road Association (PIARC) Paris.
Yang, G, H. Xu, Z. Wang and Z Tia, (2016). Truck acceleration behavior study and
acceleration lane length recommendations for metered on-ramps. International
Journal of Transportation Science and Technology. Tongji University Press. Publishing
Services by Elsevier B.V. Shanghai, China.
(237)
Appendix A Estimating Design Traffic (Example)
Consider a road that currently carries the following traffic and corresponding growth
rates. The road is in a rural area but links two townships. It is to be designed to class
H2.
Table A-1 Traffic Information for Estimating Design Traffic for the Example
Vehicle growth
Current AADT Vehicle growth
rate from year
Vehicle Classification (Number of rate up to end of
6 to year 20
vehicles/day) year 5 (%)
(%)
Pedestrians 200 8 8
Bicycles 80 3 2
Motorcycles 40 8 6
Car 220 5 5
Pick-up/4-wheel drive 90 5 5
Small bus 85 5 5
Bus/coach 20 5 5
Small truck (2 axle) 97 7 5
Truck (3 or 4 axle) 118 7 5
The design life for the road is 20 years. The geometric design is required.
Step 1
First convert pedestrians, bicycles and motorcycles into equivalent cars using the car
equivalency factors from the Table A-2 (Section 2.4.1). This gives the results shown.
The numbers of pedestrians, bicycles and motorcycles (converted to CEF) are used
only to determine if the cross-section design needs modifying for high values of NMTs.
Step 2
The AADT at 20 years is then computed first by computing the vehicle numbers for the
first growth period to year 5, then by computing the vehicle numbers for the second
growth period from year 6 to year 20 inclusive.
The formula for computing the number of vehicles at end of any given year is:
AADTx = AADT0*(1+i/100)x
where:
(238)
AADTx is the AADT for a given vehicle class in year x,
i is the growth rate for a given vehicle class,
x is the number of years from the time at which the traffic count was
conducted to the year being considered.
Step 3
Determine the design class (Section 2.4.5).
The total design AADT is 1728 at the end of year 20. The cross-section design class is
therefore T3.
Since the number of non-motorised traffic and motorcycles converted to equivalent
cars is not greater than 300, there is no need to adjust carriageway or shoulder
widths.
Therefore, the design class is H2 T3 R in Table 1-2 and Table 7-8.
(239)
Appendix B Measuring Sight Distance on Plans
By determining, graphically, the sight distances on the plans and recording them at
frequent intervals, the designer can appraise the overall layout and provide a more
balanced design by minor adjustments in the horizontal and vertical profiles. Once the
horizontal and vertical alignments are tentatively established, the practical means of
examining sight distances along the proposed highway is by direct scaling on the
plans. Methods for scaling sight distances are demonstrated in Figure B-1. The figure
also shows a typical sight distance record that could be shown on the final plans.
Because the view of the highway ahead may change rapidly in a short distance, it is
desirable to measure and record sight distance for both directions of travel at each
station. Both horizontal and vertical sight distances should be measured, and the
shorter lengths recorded. In the case of two-lane highways, passing sight distance in
addition to stopping sight distance should be measured and recorded.
Horizontal sight distance on the inside of a curve is limited by obstructions such as
buildings, hedges, wooded areas, noise barriers, high ground, or other topographic
features. These generally are plotted on the plans. Horizontal sight is measured with a
straightedge, as indicated at the upper left in Figure B-1. The cut slope obstruction is
shown on the worksheets by a line representing the proposed excavation slope at a
point 600 mm (approximate average of 1050 mm and 200 mm) above the road
surface for stopping sight distance and at a point about 1300 mm above the road
surface for passing sight distance. The position of this line with respect to the
centerline may be scaled from the plotted highway cross sections. Preferably, the
stopping sight distance should be measured between points on the one traffic lane and
passing sight distance from the middle of one lane to the middle of the other lane.
Such refinement on two-lane highways is not necessary and measurement to the
centerline or edge of the traveled way is suitable. Where there are changes of grade
coincident with horizontal curves that have sight-limiting cut slopes on the inside, the
line-of-sight intercepts the slope at a level either lower or higher than the assumed
average height. In measuring sight distance, the error in the assumed 600-or 1300-
mm height can usually be ignored.
Vertical sight distance may be scaled from a plotted profile by the method illustrated
at the right centre of Figure B-1. A transparent strip with parallel edge 1300 mm apart
and with scratched lines 600 mm and 1050 mm from the upper edge, in accordance
with the vertical scale, is a useful tool. The 1050-mm line is placed on the station from
which the vertical sight distance is desired, and the strip is pivoted about this point
until the upper edge is tangent to the profile. The distance between the initial station
and the station on the profile intersected by the 600 mm line is the stopping sight
distance. The distance between the initial station and the station on the profile
intersected by the lower edge of the strip is the passing sight distance.
A simple sight distance record is shown in the lower part of Figure B-1. Sight distances
in both directions are indicated by arrows and figures at each station on the plan and
profile sheet of the proposed highway. Sight distance less than 500 m may be scaled
to the nearest 10 m and those greater than 500 m to the nearest 50 m. Sight
distances can easily be determined also where alignments are drawn using computer-
aided design and drafting systems (CADD), although such programs presently do not
automatically make this determination.
Sight distance records for two-lane highways may be used to advantage to tentatively
determine the marking of no-passing zones. No-passing zones thus established serve
as a guide for markings when the highway is completed. The zone so determined
should be checked and adjusted by field measurements before actual markings are
placed.
(240)
Figure B-1 Scaling and Recording Sight Distances on Plans
(241)
Appendix C Sight Distances at Intersections
Sight Triangles
The distances shown in this Appendix are derived from research into gap acceptance
as reported in SANRAL (2003) adopted from NCHRP Report 383 Intersection Sight
Distance.
(242)
Figure 1(a): Approach Sight Triangles
• The recommended dimensions of the clear sight triangles vary with the type of
traffic control used at an intersection because different types of control impose
different legal constraints on drivers resulting in different driver behaviour.
(243)
Sight distance policies for intersections with the following types of traffic
control are shown below:
A. Intersections with no control;
B. Intersections with ‘Stop’ control on the minor road;
Case B1: Right turn from the minor road;
Case B2 Left turn from the minor road;
Case B3 Crossing manoeuvre from the minor road;
C. Intersections with ‘Yield’ control on the minor road;
Case C1 Crossing manoeuvre from the minor road;
Case C2 Left or right turn from the minor road;
D. Intersections with traffic signal control;
E. Intersections with all-way Stop control.
(244)
Table C-1 Case A: Recommended Sight Distances for Intersections
with no Traffic Control
(245)
• For minor-road approaches from which substantial volumes of heavy vehicles
enter the major road, the values for single-unit trucks or semitrailers should be
applied. Table C-2 includes adjustments to the acceptable gaps for the number
of lanes on the major road and for the approach gradient of the minor road.
The adjustment for the gradient of the minor-road approach need be made
only if the rear wheels of the design vehicle would be on an upgrade steeper
than 3 % when the vehicle is at the stop line of the minor-road approach.
• The length of the sight triangle along the major road (distance ‘b’ in Figure 1)
is the product of the design speed of the major road in m/sec and the critical
gap in seconds as listed in Table C-2. If these sight distances along the major
road (including the appropriate adjustments) cannot be provided, consideration
should be given to the installation of advisory speed signs on the major-road
approaches.
• Dimension ‘a’ in Figure 1 depends on the context within which the intersection
is being designed. In urban areas drivers tend to stop their vehicles
immediately behind the Stop line, which may be located virtually in line with
the edge of the major road. A car driver would, therefore, be located about 2.4
m away from the Stop line. In rural areas, vehicles usually stop at the edge of
the shoulder of the major road. In the case of a 3-m wide shoulder, for
example, the driver would be approximately 5.4 m away from the edge of the
travelled way.
Table C-2 Travel Times Used to Determine the Leg of the Departure Triangle
along the Major Road for Right and Left Turns from Stop-controlled
Approaches
Travel Time (seconds) at Design
Vehicle
Speed of the Major Road
Passenger car 7.5
Single unit truck 9.5
Semi-trailer 11.5
Multi-lane highways.
For right turns onto 2-way highways with more than 2 lanes, add 0.5 seconds for
cars and 0.7 seconds for trucks for each additional lane (in excess of one) to be
crossed by the turning vehicle. No adjustment is necessary for left turns.
Adjustment for gradients.
If the approach gradient on the minor road exceeds 3% add 0.1 second per
gradient for right turns and 0.2 seconds per gradient for left turns
• Where the major road is a dual carriageway, two departure sight triangles have
to be considered: a sight triangle to the right, as for the crossing movement
and one using the acceptable gap as listed in Table C-2for vehicles approaching
from the left. This presupposes that the width of the median is sufficient to
provide a refuge for the vehicle turning from the minor road. If the median
width is inadequate, the adjustment in Table C-2for multilane major roads
should be applied with the median being counted as an additional lane. The
departure sight triangle should be checked for various possible design vehicles
because the width of the median may be adequate for one vehicle type and not
for another so that two different situations have to be evaluated.
(246)
Case B2: Left turn from the minor road.
• A departure sight triangle for traffic approaching from the right, as shown in
Figure C-1should be provided for left turns from the minor road. The lengths of
the legs of the departure sight triangle for left turns should generally be the
same as those for the length of the leg of the departure sight triangle
(dimension ‘b’) along the major road and should be based on the travel times
in Table C-2, including appropriate adjustment factors.
• Dimension ‘a’ depends on the context of the design and can vary from 2.4 m to
5.4 m. Where sight distances along the major road based on the travel times
from Table .2 cannot be provided, it should be kept in mind that field
observations indicate that, in making left turns, drivers generally accept gaps
that are slightly shorter than those accepted in making right turns. The travel
times in Table C-2 can be decreased by 1.0 to 1.5 seconds for left turn
manoeuvres, where necessary, without undue interference with major-road
traffic. When the recommended sight distance for a left-turn manoeuvre cannot
be provided, even with this reduction, consideration should be given to the
installation of advisory speed signs and warning devices on the major road
approaches.
• Table C-3presents travel times and appropriate adjustment factors that can be
used to determine the length of the leg of the sight triangle along the major
road to accommodate crossing manoeuvres. At divided highway intersections,
depending on the width of the median and the length of the design vehicle,
sight distance may be needed for crossing both roadways of the divided
highway or for crossing the near lanes only and stopping in the median before
proceeding.
Table C-3 Travel Times Used to Determine the Leg of the Departure Triangle
along the Major Road for Crossing Manoeuvres from Stop-controlled
Approaches
Travel Time (seconds) at Design
Vehicle
Speed of the Major Road
Passenger car 6.5
Single unit truck 8.5
Semi-trailer 10.5
Multi-lane highways.
(247)
For left turns onto 2-way highways with more than 2 lanes, add 0.5
seconds for cars and 0.7 seconds for trucks for each additional lane (in
excess of one) to be crossed. In the case of dual carriageways with
inadequate median width for refuge, count the median as another lane to
be crossed.
Adjustment for gradients.
If the approach gradient on the minor road exceeds 3% add 0.2 second
per % gradient in excess of 3%.
Notes: 1. For minor-road approach gradients that exceed +3 %, increase by
the same factor as in Table C-1.
2 Travel time applies to a vehicle that slows before crossing the
intersection but does not stop.
(248)
Table C-4 Leg of Approach Sight Triangle Along the Minor Road to
Accommodate Crossing Manoeuvres from Yield-controlled Approaches
Travel time (ta) from
Design speed (minor Distance along
decision point to
road). (km/h) minor road (m)
major road(1)(2)
30 30 3.4
40 40 3.7
50 50 4.1
60 65 4.7
70 85 5.3
80 110 6.1
90 140 6.8
100 165 7.3
110 190 7.8
120 230 8.6
Notes 1 For minor-road approach gradients that exceed +3 %, increase by
the same factor as in Table 1.
2 Travel time applies to a vehicle that slows before crossing the
intersection but does not stop
• The length of the leg of the approach sight triangle along the major road to
accommodate the crossing manoeuvre (distance ‘b’ in Figure 1) should be
calculated using the following equations:
tc = ta + (w + La)/(0.167.vminor)
b = 0.278.tc.vmajor
where:
tc = travel time to reach and clear the major road in a crossing
manoeuvre (seconds)
b = length of leg of sight triangle along the major road (m)
ta = travel time to reach the major road from the decision point for a
vehicle that does not stop (sec) (use appropriate value for the
minor road design speed from Table 1, adjusted for approach
grade, where appropriate)
w = width of intersection to be crossed (m)
La = length of design vehicle (m)
vminor = design speed of minor road (km/h)
vmajor = design speed of major road (km/h)
• These equations provide sufficient travel time for the major road vehicle during
which the minor-road vehicle can:
▪ Travel from the decision point to the intersection, while decelerating at
the rate of 1.5 m/s² to 60 % of the minor-road design speed; and then
(249)
▪ Cross and clear the intersection at the same speed.
• Field observations did not provide a clear indication of the size of the gap
acceptable to the driver of a vehicle located at the decision point on the minor
road. If the required gap is longer than that indicated by the above equations,
the driver would probably, bring the vehicle to a stop and then select a gap on
the basis of Case B. If the acceptable gap is shorter than that indicated by the
above equations, the sight distance provided would, at least, provide a margin
of safety.
• If the major road is a divided highway with a median wide enough to store the
design vehicle for the crossing manoeuvre, then only crossing of the near lanes
need be considered and a departure sight triangle for accelerating from a
stopped position in the median should be provided, based on Case C1.
(250)
be an option to consider where the sight distance for other types of control
cannot be achieved. This is particularly the case if signals are not warranted.
Table C-5 Travel Times Used to Determine the Sight Distance along the Major
Road to Accommodate Right Turns from the Major Road (Case F)
Travel Time (seconds) at Design
Vehicle
Speed of the Major Road
Passenger car 5.5
Single unit truck 6.5
Semi-trailer 7.5
Multi-lane highways.
For right turns that have to cross more than one opposing lane add 0.5 seconds
for cars and 0.7 seconds for trucks for each additional lane (in excess of one) to
be crossed. In the case of dual carriageways where the median is not sufficiently
wide to provide refuge for the turning vehicle, the median should be regarded as
another lane to be crossed.
• If stopping sight distance has been provided continuously along the major road
and if sight distance for Case B (Stop control) or Case C (Yield control) has
been provided for each minor-road approach, sight distance should generally
be adequate for left turns from the major road. However, at intersections or
driveways located on or near horizontal or vertical curves on the major road,
the availability of adequate sight distance for left turns from the major road
should be checked. In the case of dual carriageways, the presence of sight
obstructions in the median should also be checked.
• At four-legged intersections, opposing vehicles turning right can block a
driver's view of oncoming traffic. If right-turn lanes are provided, off-setting
them to the right, to be directly opposite one other will provide right-turning
drivers with a better view of oncoming traffic.
(251)
as described above. At skew intersections, the length of the travel paths for crossing
manoeuvres will be increased. The actual path length for a crossing manoeuvre can be
calculated by dividing the total width of the lanes (plus the median width, where
appropriate) to be crossed by the sine of the intersection angle and adding the length
of the design vehicle. The actual path length divided by the lane width applied to the
major road cross-section gives the equivalent number of lanes to be crossed. This is
an indication of the number of additional lanes to be applied to the adjustment factor
shown in Table C-3 for Case B3.
The sight distances shown for Case B can, regardless of the form of control, also
accommodate turning movements from the minor road to the major road at skew
intersections. In the obtuse angle, drivers can easily see the full sight triangle and, in
addition, often accelerate from the minor road at a higher rate than when they have to
negotiate a ninety-degree change of direction. In the acute-angle quadrant, drivers
are often required to turn their heads considerably to see across the entire clear sight
triangle. For this reason, it is suggested that Case A should not be applied to oblique-
angle intersections. Stop or Yield control should be applied and the sight distances
appropriate to either Case B or Case C provided. Even in a skew intersection it is
usually possible for drivers to position their vehicles at approximately 90o to the major
road at the Stop line, offering added support for the application of Case B for skew
intersections. When driving through a deflection angle greater than 120 o, the right
turn to the minor road may be undertaken at crawl speeds. Allowance could be made
for this by adding the time, equivalent to that required for crossing an additional lane,
to the acceptable gap.
(252)
Appendix D Road Friction
Coefficient of Friction
Coefficient of friction is the ratio of the frictional force on the vehicle and the
component of the weight of the vehicle perpendicular to the frictional force.
The longitudinal coefficients of friction, as determined by various authors, are shown
in Figure D-1. The purpose of showing this Figure is primarily to illustrate the very
wide range of values that are obtained. Longitudinal friction coefficients depend on
vehicle speed; type, condition and texture of roadway surface; weather conditions;
and type and condition of tyres. Its value decreases as speed increases. The
coefficient of friction values chosen for use in this manual are shown in Figure D-1 and
Table 4-3 using the lowest results of friction tests. The values allow a reasonable
safety factor to cater for the wide range of conditions.
Coefficient of friction
Figure D-1 Longitudinal Friction for Various Tyre and Pavement Conditions
(253)
Side friction coefficients are also dependent on vehicle speed, type, condition and
texture of roadway surface, weather conditions, and type and condition of tyres.
Figure D-2 illustrates some values obtained by various researchers.
Coefficient of friction
(254)
Appendix E Utilities
E1 Electricidade de Moçambique (EDM)
The EDM Manual shows the minimum vertical clearance of wires above roads.
The manual generally gives no guidance on the placement of the utility within the road
reserve. A drawing shows that street lighting is to be placed 1 m behind a curb on a
main road. The manual does not state placement for un-curbed roads, and such
placement should not be allowed. Similarly, power poles are placed 60 cm behind
curbs; in rural areas, the poles must be placed at least 15 m from the center of the
road.
For underground cables crossing the road, unprotected cables are placed 80 cm below
a gravel road; or cables encased with concrete pipe are placed 100 cm below an
asphalt road or paved sidewalk. The EDM shows vertical clearances as per Table E-1.
Table E-1 Minimum Vertical Clearance of Wires above Road Surface (in
centimetres)
Open-Supply Wires, Voltage to
Guys, Ground
Type of Location Messengers,
etc. 750 to 15,000 to
0 to 750
15,000 50,000
When crossing above:
Railroads 820 820 850 910
Streets, alleys, and
roadways 550 550 610 670
Private driveways 310 310 610 670
Walkways for pedestrians
only 240 460 460 520
When wires are along:
Streets or alleys 550 550 610 670
Roads in rural districts 430 460 550 610
Note: The designer should always refer to the most up to date manuals for the values
in stated in Table E-1.
For pipes up to 150 mm diameter, pipes are laid at a depth as indicated in Table E-2.
For larger pipes, the depth is generally greater than 1.5 m.
(255)
Table E-2 Trench Dimensions for Water and Sewerage Pipe Culverts
Diameter Depth Width Bedding thickness
(mm) (cm) cm) (cm)
150 85 70 10
125 72.5 70 10
100 70 50 10
75 57.5 40 -
50 55 40 -
(256)
Appendix F Compact Grade-Separated Interchanges
Alternative layouts for 4-arm junctions are shown in Figure F-1to Figure F-3and an
example of a layout for a 3-arm junction is shown in Figure F-4. Schematic
representations of other layouts are shown in Figures Figure F-4 to Figure F-8. Figure
F-9 shows two method of incorporating a compact grade separation into a section of
carriageway which has a series of priority junctions in close proximity.
Figure F-1 Grade Separation for a 4-Arm Junction Showing Merge and Diverge
Tapers
.
Grade separation for a 4-arm junction showing merge and diverge tapers
and free flow on the minor carriageway. (For intersections where minor
road traffic movement is primarily straight across).
Figure F-2 Grade Separation for 4-Arm Junction Without Merge and Diverge
Tapers
(257)
Grade separation for 4-arm junction without merge and diverge tapers and
free flow on the minor carriageway. (For junctions where minor road traffic
movement is primarily straight across).
Figure F-3 Grade Separation for 4-Arm Junction with Compact Connector
Road
Grade separation for 4-arm junction with compact connector road forming a
loop (for junctions where minor road traffic movement is primarily turning
onto and off the major carriageway).
Figure F-4 Grade separation for 3-arm junction with compact connector roads
showing merge and diverge tapers
(258)
Figure F-5 A selection of schematic layouts indicating 4-arm compact grade
separations on dual all-purpose carriageways.
(259)
Figure F-6 A selection of schematic layouts indicating 4-arm compact grade
separations on single all-purpose carriageways.
(260)
Figure F-9 Schematic example of compact grade separation and restricted
junctions.
(261)
Appendix G Passing Sight Distance
The minimum sight distance required by a vehicle to overtake or pass another vehicle
safely on a two-lane single carriageway road is the distance, which will enable the
overtaking driver to pass a slower vehicle without causing an oncoming vehicle to slow
below the design speed. The manoeuvre is one of the most complex but important
driving tasks. It is also relatively difficult to quantify for design purposes because of
the various stages involved, the large number of relative speeds of vehicles that are
possible, and the lengthy section of road needed to complete the manoeuvre. As a
result, there are numerous models which have been developed and a variety of design
solutions that have been used throughout the world. NCHRP Report 605 by Harwood
et al. (2008) is a comprehensive review the conclusions of which are summarised
below.
The PSD is determined by a formula with four components (Figure G1), as follows:
d1 = distance traversed during perception and reaction time and during the
initial acceleration to the point of encroachment on the left lane.
d2 = distance traveled while the passing vehicle occupies the right lane.
d3 = distance between the passing vehicle at the end of its maneuver and the
opposing vehicle
d4 = distance traversed by the opposing vehicle for two-thirds of the time the
passing vehicle occupies the right lane, or 2/3 of d2 above. The formulae
for these components are as indicated below:
d1 = 0.278 t1 (v – m + a.t1/2)
Where
t1 = time of initial manoeuvre, s
a = average acceleration, km/h/s
v = average speed of passing vehicle, km/h
m = difference in speed of passed vehicle and passing vehicle, km/h
d2 = 0.278 v.t2.
Where
t2 = time passing vehicle occupies right lane, s
v = average speed of passing vehicle, km/h
d3 = safe clearance distance between vehicles at the end of the manoeuvre -
dependent on ambient speeds as per Table G1.
d4 = distance traversed by the opposing vehicle, which is approximately equal to
d2 minus the portion of d2 whereby the passing vehicle is entering the right
lane, estimated as:
d4 = 2d2/3
(262)
Figure G-1 Passing Sight Distance
The minimum Passing Sight Distance (PSD) for design is calculated from:
PSD = d1 + d2 + d3 + d4
Two-lane highways can be designed safely with any set of PSD criteria equal to or
greater than the PSD criteria currently used in marking passing and no-passing zones
presented in the Manual on Uniform Traffic Control Devices (MUTCD). The longer PSD
criteria currently presented in the AASHTO Green Book provide improved traffic
operational efficiency but are so long that they are considered to be impractical.
A driver finding that he has insufficient distance after initiating the passing manoeuvre
can choose to abort the manoeuvre (see Figure 4-3). The Minimum Passing Sight
Distance is then the sight distance required on a two-lane road to enable the passing
manoeuvre to be aborted. The recommended minimum PSDs are as indicated in Table
4-8 and Table G-2. The range of values used worldwide occurs because of different
underlying assumptions in their derivation.
A method of measuring and recording sight distances are given in Appendix B.
(263)
Table G-2 Passing Sight Distances
30 115 195
40 135 275
50 155 345
60 180 420
70 210 485
80 240 550
90 275 615
100 310 670
110 350 730
120 395 780
130 440 830
Note 1 Manual on Uniform Traffic Control Devices (MUTCD) and NCHRP Report
605 by Harwood et al. (2008).
(264)
Appendix H Elements of a Circular Curve
The elements of circular curves are shown in Figure H-1.
Example:
A curve has a deflection angle of = 23o 18’ 02”, and a radius of 1432.6 m. The Point
of Intersection (PI) is 5+053.87. Calculate the tangent distance (T), external distance
(E), curve length (L), Point of Curvature (PC), and Point of Tangent (PT).
(265)
∆ 230 18′ 02"
𝑇 = 𝑅𝑡𝑎𝑛 = (1432.6) (𝑡𝑎𝑛 ) = 1432.6(0.2026) = 295𝑚
2 2
1432.6 × 2 × 3.142
𝐿 = ∆ × = 23.3 ( ) = 582𝑚
360
∆ 1
𝐸 = 𝑅 (𝑠𝑒𝑐 − 1) = 1432.6 (( ) − 1) = 1432.6(0.021) = 30𝑚
2 ∆
𝑐𝑜𝑠 2
(266)